C1_Preliminary-Abstract-W912HY19B0003-Freeport_HFPP.pdf
PDF 220 KB Posted
- Solicitation number
- W912HY19B0003
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNIT
PRICE TOTAL
1 JB SUM $202,821.00
150 CY $1,029.24 $154,386.00
27,000 TON $121.32 $3,275,640.00
6,200 TON $62.74 $388,988.00
650 TON $119.48 $77,662.00
450 TON $62.60 $28,170.00
200 SY $5.41 $1,082.00
300 CY $27.66 $8,298.00
2,000 TON $62.00 $124,000.00
$4,261,047.00
SCHEDULE NO. 1ITEM
DESCRIPTION QUANTITY
TOTAL SCHEDULE NO. 1
0005 Riprap Type 2
CURTIS COLE, JR.
CONTRACTING OFFICER
ABSTRACT OF OFFERS Page 1 of 3
Solicitation No.: W912HY19B0003 Date Issued: 23 May 19 Date Opened: 16 Jul 19 Issuing Office: USAED-Galveston Project Title: 100% Small Business Set-Aside for Freeport, Texas, Hurricane Flood Protection in Brazoria County, Texas, Emergency Erosion Repairs.
Mobilization and Demobilization
Semi-Compacted Fill
Bedding Stone Type 2
Number of Amendments Issued: 0001 thru 0005
Government Estimate (Without Profit)
NO.
* The apparent low bidder, Pontchartrain Partners, LLC is 24.23% below the Government's Estimate.
I CERTIFY THAT I HAVE OPENED, READ, AND RECORDED ON THIS ABSTRACT ALL OFFERS RECEIVED IN RESPONSE TO THIS SOLICITATION.
Riprap Type 1
Bedding Stone Type 1
Sod
Excavation of Fill
Debris and Riprap Removal
UNIT
PRICE TOTAL
1 JB SUM $2,150,000.00
150 CY $200.00 $30,000.00
27,000 TON $125.00 $3,375,000.00
6,200 TON $125.00 $775,000.00
650 TON $125.00 $81,250.00
450 TON $125.00 $56,250.00
200 SY $400.00 $80,000.00
300 CY $125.00 $37,500.00
2,000 TON $150.00 $300,000.00
$6,885,000.00
UNIT
PRICE TOTAL
1 JB SUM $657,000.00
150 CY $68.00 $10,200.00
27,000 TON $127.00 $3,429,000.00
6,200 TON $125.00 $775,000.00
650 TON $319.00 $207,350.00
450 TON $222.00 $99,900.00
200 SY $28.00 $5,600.00
300 CY $120.00 $36,000.00
2,000 TON $87.00 $174,000.00
$5,394,050.00
UNIT
PRICE TOTAL
1 JB SUM $2,755,083.42
150 CY $386.38 $57,957.00
27,000 TON $229.31 $6,191,370.00
6,200 TON $109.19 $676,978.00
650 TON $251.14 $163,241.00
450 TON $136.49 $61,420.50
200 SY $108.00 $21,600.00
300 CY $54.84 $16,452.00
2,000 TON $27.82 $55,640.00
$9,999,741.92
UNIT
PRICE TOTAL
1 JB SUM $541,376.77
150 CY $554.72 $83,208.00
27,000 TON $164.58 $4,443,660.00
6,200 TON $117.86 $730,732.00
650 TON $302.25 $196,462.50
450 TON $294.72 $132,624.00
200 SY $92.20 $18,440.00
300 CY $150.79 $45,237.00
2,000 TON $48.47 $96,940.00
$6,288,680.27
0009 Debris and Riprap Removal
TOTAL SCHEDULE NO. 1
Offeror: #4 - Relyant Global, LLC, 335 High Street, Maryville, TN 37804 Business Size: Unknown NAICS 237990 not listed in SAM
QUANTITY
0006 Bedding Stone Type 2
0007 Sod
0008 Excavation of Fill
0009 Debris and Riprap Removal
TOTAL SCHEDULE NO. 1
0007 Sod
0001 Mobilization and Demobilization
0002 Semi-Compacted Fill
0003 Riprap Type 1
0004 Bedding Stone Type 1
0005 Riprap Type 2
0006 Bedding Stone Type 2
0007 Sod
Offeror: #3 - JSR, Inc., 8835 Greaves Lane, Schertz, TX 78154
ITEM SCHEDULE NO. 1
Solicitation No.: W912HY19B0003 Date Issued: 23 May 19 Date Opened: 16 Jul 19
0004 Bedding Stone Type 1
Bedding Stone Type 2
0002 Semi-Compacted Fill
TOTAL SCHEDULE NO. 1
NO.
Project Title: 100% Small Business Set-Aside for Freeport, Texas, Hurricane Flood Protection in Brazoria County, Texas, Emergency Erosion Repairs.
ABSTRACT OF OFFERS (CONT'D) Page 2 of 3
Offeror: #1 - Trade West Construction Inc., 300 W. Hafen Lane, Mesquite, NV 89027 Business Size: SB/WO
QUANTITY
Bedding Stone Type 1
Semi-Compacted Fill
Business Size: Unknown NAICS 237990 not listed in SAM
NO. DESCRIPTION QUANTITY
0008 Excavation of Fill
0009 Debris and Riprap Removal
TOTAL SCHEDULE NO. 1
Business Size: SB
QUANTITY
Offeror: #2 - Cayo, LLC, 1400 Everman Pkwy, Suite 116, Fort Worth, TX 76140
0007 Sod
Riprap Type 2
NO.
0001 Mobilization and Demobilization
DESCRIPTION
Riprap Type 1
ITEM
0005 Riprap Type 2
NO. DESCRIPTION
0001 Mobilization and Demobilization
0002 Semi-Compacted Fill
0003 Riprap Type 1
0004 Bedding Stone Type 1
0008 Excavation of Fill
SCHEDULE NO. 1
Bedding Stone Type 2
Riprap Type 2
0003 Riprap Type 1
ITEM SCHEDULE NO. 1
0008 Excavation of Fill
Debris and Riprap Removal
Mobilization and Demobilization
SCHEDULE NO. 1
DESCRIPTION
ITEM
1 JB SUM $650,000.00
150 CY $203.00 $30,450.00
27,000 TON $75.00 $2,025,000.00
6,200 TON $70.00 $434,000.00
650 TON $89.00 $57,850.00
450 TON $82.00 $36,900.00
200 SY $20.00 $4,000.00
300 CY $41.00 $12,300.00
2,000 TON $32.00 $64,000.00
$3,314,500.00
UNIT
PRICE TOTAL
1 JB SUM $375,500.00
150 CY $30.00 $4,500.00
27,000 TON $83.00 $2,241,000.00
6,200 TON $74.00 $458,800.00
650 TON $88.00 $57,200.00
450 TON $76.00 $34,200.00
200 SY $20.00 $4,000.00
300 CY $25.00 $7,500.00
2,000 TON $23.00 $46,000.00
$3,228,700.00
0009 Debris and Riprap Removal
TOTAL SCHEDULE NO. 1
Project Title: 100% Small Business Set-Aside for Freeport, Texas, Hurricane Flood Protection in Brazoria County, Texas, Emergency Erosion Repairs.
Offeror: #5 - Midwest Construction Company, PO Box 610, Nebraska City, NE 68410 Business Size: SB/WO
0004 Bedding Stone Type 1
0005 Riprap Type 2
0006 Bedding Stone Type 2
0007 Sod
0008 Excavation of Fill
NO. DESCRIPTION QUANTITY
0001 Mobilization and Demobilization
0002 Semi-Compacted Fill
0003 Riprap Type 1
0009 Debris and Riprap Removal
TOTAL SCHEDULE NO. 1
ABSTRACT OF OFFERS (CONT'D) Page 3 of 3
Offeror: #6 - Pontchartrain Partners, LLC, 739 S. Clark St., New Orleans, lA 70119 (Apparent Low) Business Size: SB/SDB/SDVO/HZ
ITEM SCHEDULE NO. 1
0004 Bedding Stone Type 1
0005 Riprap Type 2
0006 Bedding Stone Type 2
0007 Sod
0008 Excavation of Fill
0001 Mobilization and Demobilization
0002 Semi-Compacted Fill
0003 Riprap Type 1
Solicitation No.: W912HY19B0003 Date Issued: 23 May 19 Date Opened: 16 Jul 19
File details come from the government source that posted it.