General Planning Services
W912HY-09-R-0021
Section B
Section B - Supplies or Services and Prices
INFORMATION TO OFFERORS
SECTION B – SUPPLIES OR SERVICES AND PRICES/COST
General Planning Services as needed for the U.S. Army Engineer District, Galveston, Texas and Louisiana, all in accordance with the Descriptions/Specifications/Work Statement (Section C), Contract Clauses (Section I), and subsequent task orders for a one (1) year period starting on the date of award with the option, at the Government’s discretion, to renew for four (4) additional one (1) year periods.
NOTES TO OFFERORS:
A. Offerors must bid on all line items unless specifically stated in this price schedule. Failure to submit an offer on all items will result in an incomplete offer, and the offer will be rejected.
B. Rates for labor categories above shall include all fringe benefits, overhead, G&A overhead, and profit.
C. Lodging and subsistence will be paid in accordance with the Government Joint Travel Regulation (JTR). The number of days will be negotiated for each task order.
D. Airfares will be paid at the lowest commercial rates in effect at the time of negotiations for each task order. The contractor may be required to furnish documentation of the airfare cost at the time of negotiations.
E. Costs for travel, per diem, misc. reproduction, and misc. vehicles and equipment, and misc. office and laboratory supplies will be submitted for individual task order and negotiated on a per job basis.
F. Task Orders. Services will be ordered by the Government in accordance with Section I, Contract Clause entitled "Ordering". All services shall be charged at the unit prices set forth in this Section B, supplies or Services and Prices/Costs. The quantities listed below are estimated only. The extended amount will be used by the Government for proposal evaluation purposes, only. Award will be made based upon the Total Estimated Amount. Quantities stated in Section B do not represent an upper or lower limit to the contract.
G. Central Contractor Registration (CCR). Offerors must be registered in the CCR database prior to award, during performance, and through final payment of any contract resulting from this solicitation. SEE SECTION L.
H. Where "TBN" (To Be Negotiated) occurs in the Unit Price column, the offeror is not required to provide a price at this time. Because costs for these items cannot be determined in advance with any certainty, prices for these items will be negotiated for each task order in which they are used.
I. For purposes of price evaluation, the price will be evaluated combining the base plus all option years.
J. The maximum amount to be awarded for all combined task orders, base and all option years included, will not exceed $11,500,000.
CONTRACT SUMMARY
Total Estimated Base Year (Dates)
(1 Nov 2009 through 31 Oct 2010) $_____________________
Total Estimated Option Year 1 (Dates)
(1 Nov 2009 through 31 Oct 2011)
Total Estimated Option Year 2 (Dates)
(1 Nov 2009 through 31 Oct 2012)
Total Estimated Option Year 3 (Dates)
(1 Nov 2009 through 31 Oct 2013)
Total Estimated Option Year 4 (Dates)
(1 Nov 2009 through 31 Oct 2014)
Total Estimated Contract Amount
BID SCHEDULE
SUPPLIES OR SERVICES AND PRICES/COSTS
SECTION B
NOTE 1: Offeror shall submit a price on all line items unless specifically stated in this price schedule.
NOTE 2: The quantities listed below are estimated only. The extended amount will be used by the Government for proposal evaluation purposes.
Quantities stated in the Bid Schedule do not represent an upper or lower limit to the contract.
General Planning Services for the U. S. Army Engineer District, Corps of Engineers, Galveston, Texas, in accordance with the Descriptions/Specifications/Work Statement (Section C), Contract Clauses (Section I) and subsequent Task Orders for a one (1) year period from date of contact award with the option at the Government's discretion to renew for for four (4) additional one year periods. NOTE: The entire Maximum Limitation of approximately $11.500,000.00 may be utilized within the base year or any option year.
TOTAL ESTIMATED BASE YEAR FOR ITEM NO. 0001 THRU
ITEM NO. 0032 FOR A ONE YEAR PERIOD
$2,300,000.00
TOTAL ESTIMATED OPTION YEAR 1 FOR ITEM NO. 0001
THRU ITEM NO. 0032
$2,300,000.00
TOTAL ESTIMATED OPTION YEAR 2 FOR ITEM NO. 0001
THRU ITEM NO. 0032
$2,300,000.00
TOTAL ESTIMATED OPTION YEAR 3 FOR ITEM NO. 0001
THRU ITEM NO. 0032
$2,300,000.00
TOTAL ESTIMATED OPTION YEAR 4 FOR ITEM NO. 0001
THRU ITEM NO. 0032
$2,300,000.00
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
FFP
General Planning
Performance period is 1 Nov 2009 through 31 Oct 2010 for General Planning Services as needed for US Army Engineer District, Galveston, Texas, and Louisiana, in accordance with the terms of the contract which includes the Scope of Work.
FOB: Destination
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
FFP
General Planning
Performance period is 1 Nov 2009 through 31 Oct 2011 for General Planning Services as needed for US Army Engineer District, Galveston, Texas, and Louisiana, in accordance with the terms of the contract which includes the Scope of Work.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
FFP
General Planning
Performance period is 1 Nov 2011 through 31 Oct 2012 for General Planning Services as needed for US Army Engineer District, Galveston, Texas, and Louisiana, in accordance with the terms of the contract which includes the Scope of Work.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
FFP
General Planning
Performance period is 1 Nov 2012 through 31 Oct 2013 for General Planning Services as needed for US Army Engineer District, Galveston, Texas, and Louisiana, in accordance with the terms of the contract which includes the Scope of Work.
NET AMT
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
FFP
General Planning
Performance period is 1 Nov 2013 through 31 Oct 2014 for General Planning Services as needed for US Army Engineer District, Galveston, Texas, and Louisiana, in accordance with the terms of the contract which includes the Scope of Work.
NET AMT
Base Year
| Item |
| Est Qnty |
| Unit |
| Rate |
| Item Cost |
| Senior Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Recreation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Financial Analyst |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Economist |
| 10 |
| day |
| $_________ |
| $____________ |
| Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Assistant Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Senior Statistician |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Coastal Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Coastal Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Sociologist |
| 1 |
| day |
| $_________ |
| $____________ |
| Staff Sociologist |
| 5 |
| day |
| $_________ |
| $____________ |
| Senior Transportation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Transportation Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Public Involvement Specialist |
| 5 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Technician |
| 5 |
| day |
| $_________ |
| $____________ |
| Editor |
| 1 |
| day |
| $_________ |
| $____________ |
| Word Processor |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Civil Engineer |
| 1 |
| day |
| $_________ |
| $____________ |
| Civil Engineer |
| 5 |
| day |
| $_________ |
| $____________ |
| Miscellaneous Reproduction |
| 1 |
| job |
| TBN |
| Equipment, Materials, Supplies |
| 1 |
| job |
| TBN |
Estimated Total Basic Year
Option Year 1
| Item |
| Est Qnty |
| Unit |
| Rate |
| Item Cost |
| Senior Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Recreation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Financial Analyst |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Economist |
| 10 |
| day |
| $_________ |
| $____________ |
| Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Assistant Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Senior Statistician |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Coastal Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Coastal Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Sociologist |
| 1 |
| day |
| $_________ |
| $____________ |
| Staff Sociologist |
| 5 |
| day |
| $_________ |
| $____________ |
| Senior Transportation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Transportation Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Public Involvement Specialist |
| 5 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Technician |
| 5 |
| day |
| $_________ |
| $____________ |
| Editor |
| 1 |
| day |
| $_________ |
| $____________ |
| Word Processor |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Civil Engineer |
| 1 |
| day |
| $_________ |
| $____________ |
| Civil Engineer |
| 5 |
| day |
| $_________ |
| $____________ |
| Miscellaneous Reproduction |
| 1 |
| job |
| TBN |
| Equipment, Materials, Supplies |
| 1 |
| job |
| TBN |
Estimated Total Option Year 1
Option Year 2
| Item |
| Est Qnty |
| Unit |
| Rate |
| Item Cost |
| Senior Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Recreation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Financial Analyst |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Economist |
| 10 |
| day |
| $_________ |
| $____________ |
| Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Assistant Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Senior Statistician |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Coastal Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Coastal Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Sociologist |
| 1 |
| day |
| $_________ |
| $____________ |
| Staff Sociologist |
| 5 |
| day |
| $_________ |
| $____________ |
| Senior Transportation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Transportation Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Public Involvement Specialist |
| 5 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Technician |
| 5 |
| day |
| $_________ |
| $____________ |
| Editor |
| 1 |
| day |
| $_________ |
| $____________ |
| Word Processor |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Civil Engineer |
| 1 |
| day |
| $_________ |
| $____________ |
| Civil Engineer |
| 5 |
| day |
| $_________ |
| $____________ |
| Miscellaneous Reproduction |
| 1 |
| job |
| TBN |
| Equipment, Materials, Supplies |
| 1 |
| job |
| TBN |
Estimated Total Option Year 2
Option Year 3
| Item |
| Est Qnty |
| Unit |
| Rate |
| Item Cost |
| Senior Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Recreation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Financial Analyst |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Economist |
| 10 |
| day |
| $_________ |
| $____________ |
| Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Assistant Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Senior Statistician |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Coastal Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Coastal Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Sociologist |
| 1 |
| day |
| $_________ |
| $____________ |
| Staff Sociologist |
| 5 |
| day |
| $_________ |
| $____________ |
| Senior Transportation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Transportation Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Public Involvement Specialist |
| 5 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Technician |
| 5 |
| day |
| $_________ |
| $____________ |
| Editor |
| 1 |
| day |
| $_________ |
| $____________ |
| Word Processor |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Civil Engineer |
| 1 |
| day |
| $_________ |
| $____________ |
| Civil Engineer |
| 5 |
| day |
| $_________ |
| $____________ |
| Miscellaneous Reproduction |
| 1 |
| job |
| TBN |
| Equipment, Materials, Supplies |
| 1 |
| job |
| TBN |
Estimated Total Option Year 3
Option Year 4
| Item |
| Est Qnty |
| Unit |
| Rate |
| Item Cost |
| Senior Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Water Resources Planner |
| 25 |
| day |
| $_________ |
| $____________ |
| Recreation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Financial Analyst |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Economist |
| 10 |
| day |
| $_________ |
| $____________ |
| Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Assistant Economist |
| 25 |
| day |
| $_________ |
| $____________ |
| Senior Statistician |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Coastal Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Coastal Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Sociologist |
| 1 |
| day |
| $_________ |
| $____________ |
| Staff Sociologist |
| 5 |
| day |
| $_________ |
| $____________ |
| Senior Transportation Planner |
| 5 |
| day |
| $_________ |
| $____________ |
| Transportation Planner |
| 10 |
| day |
| $_________ |
| $____________ |
| Public Involvement Specialist |
| 5 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| GIS/CADD Technician |
| 5 |
| day |
| $_________ |
| $____________ |
| Editor |
| 1 |
| day |
| $_________ |
| $____________ |
| Word Processor |
| 10 |
| day |
| $_________ |
| $____________ |
| Senior Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Environmental Specialist |
| 1 |
| day |
| $_________ |
| $____________ |
| Senior Civil Engineer |
| 1 |
| day |
| $_________ |
| $____________ |
| Civil Engineer |
| 5 |
| day |
| $_________ |
| $____________ |
| Miscellaneous Reproduction |
| 1 |
| job |
| TBN |
| Equipment, Materials, Supplies |
| 1 |
| job |
| TBN |
Estimated Total Option Year 4
A0006-1