This document provides details for an industry day event regarding a federal construction project. The U.S. Army Corps of Engineers, Japan District will hold an event on February 25, 2021 to provide information on Project LXEZ 194643 to improve military family housing at Stearley Heights located on Kadena Air Force Base in Okinawa, Japan. The project scope includes interior and exterior renovation of 130 single-family homes and is estimated between $25 million to $100 million with a 60 month period of performance. Interested contractors are requested to respond to a market survey by February 17th to provide details on their capability and experience, bonding capacity, potential issues with materials, the project phasing, and other questions. The event will include a presentation and Q&A session to further discuss the project and procurement strategy.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT PHASES
Phasing
Phase I-III (Base) Phase IV (Options)
SECTION 00 70 00 CONDITIONS OF THE CONTRACT
52.211-10 COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the Phase I work ready for use not later than 546 calendar days after receipt of the NTP (d) complete Phase II work ready for use not later than 790 calendar days after receipt of the
NTP,
SECTION 00 70 00 CONDITIONS OF THE CONTRACT
52.211-10 COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK (APR 1984)
(e) complete Phase III work ready for use not later than 1,034 calendar days after receipt of the NTP, and (f) complete Option Items 1 thru 7 (if any or all exercised) work ready for use not later than 1,307 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
CONSTRUCTION
(a) Commence work within 15 Calendar Days
(b) Prosecute work diligently
NTP
(c) From NTP (Phase II): 540 CD
(d) From NTP (Phase III) 790 CD
(e) From NTP (Phase III) 1,034 CD
(f) Any or All Options 1,307 CD
| PROJECT phases |
| SECtion 00 70 00 conditions of the contract |
| SECtion 00 70 00 conditions of the contract |
| CONSTRUCTION |