This document summarizes an industry day conference for a federal contract opportunity to improve military family housing at Stearley Heights, Kadena Air Base in Okinawa, Japan. The U.S. Army Corps of Engineers, Japan District will renovate 130 single family housing units with interior and exterior modernization work. Interested local contractors are requested to attend the industry day on February 25, 2021 to learn about the project and procurement process. Responses are due by February 17 to provide attendee names and questions. The firm-fixed price design-bid-build contract will be awarded in fiscal year 2021 with an estimated value between $25-100 million. The five-year period of performance involves phased renovations to be completed by January 2027.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRESENTED BY: USACE Japan Engineer District – Okinawa Area Office
DATE: 25 FEB 2021
INDUSTRY DAY CONFERENCE
PROJECT: IMPROVE MILITARY FAMILY HOUSING,
STEARLEY HEIGHTS, KADENA AIR BASE,
OKINAWA, JAPAN
WELCOME & ANNOUNCEMENTS
Introduction of Japan Engineer District (JED) Staff
Administrative info – restrooms, phones, building exits, mask, social distancing, etc.
Sign-in Sheet
Questions/Inquiries shall be submitted in writing to Jack.T.Letscher.civ@usace.army.mil mailto:Jack.T.Letscher.civ@usace.army.mil
AGENDA
9:00 AM Registration
9:20 AM Welcome & Announcements
9:30 AM Procurement Overview – Contracting
10:00 AM Project Overview – Technical Lead
10:30 AM Lessons Learned – Construction
11:00 AM Discussion Items – Open Floor
11:30 AM Question & Answers – Open Floor
12:00-12:30 PM Networking Opportunity
AGENDA
1:00 PM Registration
1:20 PM Welcome & Announcements
1:30 PM Procurement Overview – Contracting
2:00 PM Project Overview – Technical Lead
2:30 AM Lessons Learned – Construction
3:00 AM Discussion Items – Open Floor
3:30 AM Question & Answers – Open Floor
4:00-4:30 PM Networking Opportunity
GROUND RULES
Unofficial and non-binding
Official information to be included in the solicitation
No recording devices permitted
Presented in English.
PURPOSE & GOAL OF INDUSTRY DAY
PURPOSE: Present the proposed construction project & to discuss the contracting, construction phasing, lessons learned in regards to schedule & sequencing, quality assurance, and safety for the proposed project site.
GOAL: Collect feedback from potential bidders to allow USACE to:
Enhance understanding of proposed construction phasing, schedule, sequence, quality assurance of work and site safety Review final construction project based on potential bidder feedback
CONTRACTOR REQUIRED INFORMATION
• SAM: System for Award Management
• Contractors must be registered in SAM
• www.sam.gov
• Certifications & Representations
• BIDDER MAILING LIST
• Construction & Business License
• Joint Venture License(s)
• http://www.poj.usace.army.mil/BusinessWithUs.aspx
• SOLICITATION POSTING
• betaSAM.Gov
• https://www.betaSAM.gov/
• Search “W912HV” http://www.sam.gov/ http://www.poj.usace.army.mil/BusinessWithUs.aspx https://www.betasam.gov/
SAM.GOV
•https://www.beta.SAM.gov
BETA SAM CONTRACT OPPORTUNITIES - WEBSITE
連邦政府 入札案件ウェブサイト https://www.fbo.gov/?s=main&mode=list&tab=list&tabmode=list
BETA SAM CONTRACT OPPORTUNITIES - WEBSITE
https://www.beta.SAM.gov/
W912HV – Army Corps of Engineers https://www.fbo.gov/?s=main&mode=list&tab=list&tabmode=list
• “Solicitation” 入札案内
-Contractual Requirements 契約条件
-Technical Requirements 技術的条件
-Site Visit Information 現場訪問情報
-Requests for Information Process 米側に質問する際の手順情報
-Proposal due date 締切日時など
BETA SAM OPPORTUNITIES - WEBSITE
PROJECT INFORMATION
Title: Improve Military Family Housing, Stearley Heights Description: The project will provide whole-house interior and exterior modernization, renovation, and repair of 130 single family dwelling units (51 D3-53 3-Bedroom (BR), 36 G3-53 3-BR, 1 H4-53 4-BR, 36 L3-53 3-BR, and 6 N3-53 3-
BR.
Location: Kadena Air Base, Okinawa, Japan Projected Construction NTP: October 2021 Program Areas:
Site Improvements Structural Electrical Fire Protection Architectural/Interior Design Mechanical/Plumbing
PROJECT INFORMATION
Phasing Sheet G-008
PROCUREMENT APPROACH
Solicitation: Invitation for Bid (IFB)
Firm Fixed Price (FFP) Contract
Anticipate Releasing IFB: April/May Timeframe
Bid Guarantee / Performance Bond / Revolving Bond
SOLICITATION STANDARD FORM 1442
SECTION 00 10 00 CONTRACT LINE ITEMS
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT
PRICE
AMOUNT
BASE ITEMS
0001 Building Renovation Within Phase I 1 JB - ¥_________
0002 Building Renovation Within Phase II 1 JB - ¥_________
0003 Building Renovation Within Phase III 1 JB - ¥_________
TOTAL BASE CLIN SCHEDULE ¥_________
CONTRACT LINE ITEMS
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT
PRICE
AMOUNT
OPTION ITEMS
Site Work within Phase I – III
(OPTION 1) 1 JB - ¥_________
Renovate Buildings 2200, 2201, 2204, 2206 within Phase IV including sitework (OPTION 2) 1 JB - ¥_________
Renovate Buildings 2120, 2122, 2124, 2126, 2128 within Phase IV including sitework (OPTION 3)
1 JB - ¥_________
Renovate Buildings 2120, 2122, 2124, 2126, 2128 within Phase 1 JB - IV including sitework (OPTION 3)
CONTRACT LINE ITEMS
ITEM NO. DESCRIPTION QUANTITY UNIT UNIT
PRICE
AMOUNT
OPTION ITEMS
Renovate Buildings 2104, 2106, 2108, 2110 within Phase IV including sitework (OPTION 5)
1 JB - ¥_________
Renovate Buildings 1819, 1821, 1823, 1825, 1827, 1829 within Phase IV including sitework (OPTION 6) 1 JB - ¥_________
Renovate Buildings 1831, 1833, 1835, 1837, 1839, 1841, 1843 within Phase IV including sitework
(OPTION 7)
1 JB - ¥_________
TOTAL (BASE + OPTION ITEMS) CLIN SCHEDULE ¥_________
CONTRACT LINE ITEMS NOTES
1. Failure of the offeror to propose prices for all items in the CLIN Schedule may be cause for rejection of the proposal as unacceptable.
2. See Section 01 22 00.00 10, for additional line item description.
3. Any reference to “bid”, “bidder”, or “bidding schedule” shall be construed to mean “offeror” and “CLIN schedule.”
CONTRACT LINE ITEMS NOTES
4. The Government reserves the right to exercise option item(s) by written notice to the Contractor either singularly or in any combination for up to ninety (90) calendar days after award of the Base Schedule, at the prices stated in the CLIN Schedule. Completion of the added option(s) shall continue at the same schedule as the Base Schedule unless otherwise noted in Section 00 70 00, 52.211-10, COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK.
5. LEGEND: JB = Job
INFORMATION PRICE BREAKDOWN BUILDING TYPES
In addition to completing the CLIN Schedule above, Offerors/Bidders are requested to provide a total price breakdown per building type of Base Bid, as identified in the table below. The total proposed price should include any and all associated overhead and profit for each building type. Do not include site work CLIN 0004 (Option 1). This price breakdown will not be evaluated for award.
BUILDING TYPE QUANTITY PRICE
D3-53 Building Renovation. Includes all costs related to the renovation of D3-53 Housing units per the contract documents.
39 ¥_________
G3-53 Building Renovation. Includes all costs related to the renovation of G3-53 Housing units per the contract documents.
27 ¥_________
H4-53 Building Renovation. Includes all costs related to the renovation of H4-53 Housing units per the contract documents.
1 ¥_________
BUILDING TYPE QUANTITY PRICE
L3-53 Building Renovation. Includes all costs related to the renovation of L3-53 Housing units per the contract documents.
1 ¥_________
N3-53 Building Renovation. Includes all costs related to the renovation of N3-53 Housing units per the contract documents.
27 ¥_________
SECTION 00 21 00 INSTRUCTIONS TO BIDDERS
The Public Bid Opening will be held at the following location:
U.S. Army Corps of Engineers, Japan Engineer District Okinawa Area Office (OAO) Building #364, Room # 108 Camp Foster, Okinawa Japan
REQUIRED SUBMITTALS FOR INVITATION FOR BIDS.
Bidders shall include the following documents when submitting a Sealed Bid in response to W912HV21B0003, Improve Family Housing Stearley Heights construction project:
REQUIRED SUBMITTALS FOR INVITATION FOR BIDS.
• SF1442 (pages 1 and 2), including acknowledgment on all SF30 Amendments issued;
• Section 00 10 00, Solicitation, Contract Line Item Number (CLIN) Schedule (completed in its entirety);
• Section 00 45 00, Representations and Certifications (completed in its entirety);
• Bid Guarantee; and
• Joint Venture Agreement (if applicable).
REQUIRED SUBMITTALS FOR INVITATION FOR BIDS.
Failure to submit all required documents may result in the Bid being considered non-responsive. Additionally, failure of the Bidder to propose prices for all items in the CLIN Schedule may be cause for rejection of the Bid as non-responsive.
MAGNITUDE OF THE PROPOSED PROJECT.
Magnitude of the Proposed Project. The estimated price range of this work is between $25,000,000 and $100,000,000 (¥2,500,000,000 and ¥10,000,000,000).
• BIDDER INQUIRIES.
• Prospective Bidders shall submit all questions or requests for information (RFI) through the PrjoNet website https://www.projnet.org/projnet/.
• All questions or RFIs shall be submitted within the ProjNet, Bidder Inquiry Module no later than 4:00 P.M., Japan Standard Time on TBD
• The Bidder Inquiry Key is: TBD https://www.projnet.org/projnet/
THIS SOLICITATION IS FOR LOCAL SOURCES ONLY.
DELIVERY OF BIDS.
CONTRACTOR APPLICATION.
SUBMISSIONS OF BIDS IN JAPANESE YEN.
BID GUARANTEES AND PERFORMANCE BONDS.
BONDING THRESHOLDS.
PERFORMANCE OF WORK BY THE CONTRACTOR –
DEFINED.
SIGNATURE ON BIDS.
JOINT VENTURE.
BIDDER ELIGIBILITY.
JAPANESE CONSUMPTION TAX.
ARITHMETIC DISCREPANCIES.
AMENDMENTS PRIOR TO THE PUBLIC BID OPENING.
SECTION 00 21 00 CONTRACT PROVISIONS
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the options(s).
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(c) The amount of the bid guarantee shall be twenty (20) percent of the bid price or ¥300,000,000, whichever is less.
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) –
ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, bidders are urged and expected to inspect the site where the work will be performed.
• (b) An organized site visit has been scheduled for--
SEC 00 45 00 REPRESENTATIONS & CERTIFICATIONS
52.204-8 ANNUAL REPRESENTATIONS AND
CERTIFICATIONS (DEC 2019)
• (2) If the provision at 52.204-7, System for Award Management, is not included in this solicitation, and the Offeror has an active registration in the System for Award Management (SAM), the Offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation.
52.204-8 ANNUAL REPRESENTATIONS AND
CERTIFICATIONS (DEC 2019)
The Offeror shall indicate which option applies by checking one of the following boxes:
Paragraph (d) applies.
Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.
52.209-7 INFORMATION REGARDING RESPONSIBILITY
MATTERS (OCT 2018)
(b) The offeror ( ) has ( ) does not have current active Federal contracts and grants with total value greater than $10,000,000.
252.204-7007 ALTERNATE A, ANNUAL
REPRESENTATIONS AND CERTIFICATIONS (JUN 2019)
Substitute the following paragraphs (b), (d) and (e) for paragraphs (b) and (d) of the provision at FAR 52.204-8:
(b)(1) If the provision at FAR 52.204-7, System for Award Management, is included in this solicitation, paragraph
(e) of this provision applies.
252.204-7007 ALTERNATE A, ANNUAL
REPRESENTATIONS AND CERTIFICATIONS (JUN 2019)
(e) The offeror has completed the annual representations and certifications electronically via the SAM Web site at https://www.acquisition.gov/.
252.229-7001 TAX RELIEF (SEPT 2014)
(a) Prices set forth in this contract are exclusive of all taxes and duties from which the United States Government is exempt by virtue of tax agreements between the United States Government and the Contractor's government. The following taxes or duties have been excluded from the contract price:
NAME OF TAX: (Offeror Insert) RATE (PERCENTAGE):
(Offeror Insert)
SECTION 00 70 00 CONDITIONS OF THE CONTRACT
52.211-10 COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the Phase I work ready for use not later than 546 calendar days after receipt of the NTP (d) complete Phase II work ready for use not later than 790 calendar days after receipt of the
NTP,
52.211-10 COMMENCEMENT, PROSECUTION, AND
COMPLETION OF WORK (APR 1984)
(e) complete Phase III work ready for use not later than 1,034 calendar days after receipt of the NTP, and (f) complete Option Items 1 thru 7 (if any or all exercised) work ready for use not later than 1,307 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION
(SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ¥191,750 for each calendar day of delay until the work is completed or accepted.
52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS
AND CONDUCT (OCT 2015)
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED
MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS
(MAY 2008)
52.228-1 BID GUARANTEE (SEP 1996)
52.236-1 PERFORMANCE OF WORK BY THE
CONTRACTOR (APR 1984)
52.252-2 CLAUSES INCORPORATED BY REFERENCE
(FEB 1998)
252.225-7043 ANTITERRORISM/FORCE PROTECTION
POLICY FOR DEFENSE CONTRACTORS OUTSIDE THE
UNITED STATES (JUN 2015)
252.225-7045 BALANCE OF PAYMENTS PROGRAM--
CONSTRUCTION MATERIAL UNDER TRADE
AGREEMENTS--BASIC (AUG 2019)
252.236-7001 CONTRACT DRAWINGS AND
SPECIFICATIONS (AUG 2000)
SECTION 00 73 00 SUPPLEMENTARY CONDITIONS
ADMINISTRATIVE CONTRACTING OFFICER.
WORKERS COMPENSATION INSURANCE (DEFENSE
BASE ACT).
BONDING THRESHOLDS.
PERFORMANCE BOND.
PAYMENT BOND NOT REQUIRED.
SECTION 00 73 00 SUPPLEMENTARY CONDITIONS
BID GUARANTEES AND PERFORMANCE BONDS.
JAPANESE CONSUMPTION TAX.
COST BREAKDOWNS - CONTRACT MODIFICATIONS.
BANK TRANSACTION FEES.
QUESTIONS
| �Industry Day conference��Project: Improve Military family housing, stearley heights, kadena air base, Okinawa, Japan | ��� |
| WELCOME & Announcements | |
| Agenda | |
| Agenda | |
| Ground Rules | |
| Purpose & GOAL OF INDUSTRY DAY | |
| Contractor required information | |
| SAM.GOV | |
| Beta sam contract opportunities - website�連邦政府 入札案件ウェブサイト | |
| Beta sam contract opportunities - website�連邦政府 入札案件ウェブサイト | |
| Beta sam opportunities - website�連邦政府 入札案件ウェブサイト | |
| PROJECT INFORMATION | |
| PROJECT INFORMATION | |
| Procurement approach | |
| Solicitation Standard form 1442 | |
| Solicitation Standard form 1442 | |
| Solicitation Standard form 1442 | |
| Solicitation Standard form 1442 | |
| Solicitation Standard form 1442 | |
| Solicitation Standard form 1442 | |
| SECTION 00 10 00 Contract Line Items | |
| Contract Line Items | |
| Contract Line Items | |
| Contract line items notes | |
| Contract line items notes | |
| Information PRICe breakdown building types | |
| Information PRICe breakdown building types | |
| Information PRICe breakdown building types | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 instructions to bidders | |
| SECTIOn 00 21 00 Contract provisions | |
| SECTIOn 00 21 00 Contract provisions | |
| SECTIOn 00 21 00 Contract provisions | |
| SEC 00 45 00 representations & certifications | |
| SEC 00 45 00 representations & certifications | |
| SEC 00 45 00 representations & certifications | |
| SEC 00 45 00 representations & certifications | |
| SEC 00 45 00 representations & certifications | |
| SEC 00 45 00 representations & certifications | |
| SEC 00 45 00 representations & certifications | |
| SECtion 00 70 00 conditions of the contract | |
| SECtion 00 70 00 conditions of the contract | |
| SECtion 00 70 00 conditions of the contract | |
| SECtion 00 70 00 conditions of the contract | |
| SECtion 00 70 00 conditions of the contract | |
| SECtion 00 70 00 conditions of the contract | |
| SECtion 00 73 00 supplementary conditions | |
| SECtion 00 73 00 supplementary conditions | |
| QUESTIONS |