CORRECTED NEW_Phasing Calendar Days.pdf

PDF 498 KB Posted

Attached to
INDUSTRY DAY EVENT for FY19 LXEZ 194643 Improve Military Family Housing, Stearley Heights, Kadena Air Base, Okinawa, Japan
Solicitation number
W912HV-21-Z-0006
Issued by

About this file

This notice announces an industry day event for a design-build-bid construction project to improve military family housing at Stearley Heights located on Kadena Air Force Base in Okinawa, Japan. The U.S. Army Corps of Engineers, Japan District will hold an in-person industry day on February 25, 2021 to provide information on the project to local construction firms, answer questions, and receive feedback. Eligible firms must be physically located and authorized to perform construction work in Japan. The project scope includes interior and exterior renovation of 130 single-family homes and has an estimated value between $25-100 million. A firm-fixed price invitation for bid is anticipated in fiscal year 2021 with a 60 month period of performance. Responses to a market survey are requested by February 17, 2021 to facilitate acquisition planning for the project.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT PHASES

Phasing

Phase I-III (Base) Phase IV (Options)

SECTION 00 70 00 CONDITIONS OF THE CONTRACT

52.211-10 COMMENCEMENT, PROSECUTION, AND

COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed (NTP), (b) prosecute the work diligently, and (c) complete the Phase I work ready for use not later than 546 calendar days after receipt of the NTP (d) complete Phase II work ready for use not later than 790 calendar days after receipt of the

NTP,

SECTION 00 70 00 CONDITIONS OF THE CONTRACT

52.211-10 COMMENCEMENT, PROSECUTION, AND

COMPLETION OF WORK (APR 1984)

(e) complete Phase III work ready for use not later than 1,034 calendar days after receipt of the NTP, and (f) complete Option Items 1 thru 7 (if any or all exercised) work ready for use not later than 1,307 calendar days after the date the contractor receives the notice to proceed. The time stated for completion shall include final cleanup of the premises.

CONSTRUCTION

(a) Commence work within 15 Calendar Days

(b) Prosecute work diligently

NTP

540 CD

790 CD

1,034 CD

(c) From NTP (Phase I):

(d) From NTP (Phase II)

(e) From NTP (Phase III)

(f) Any or All Options 1,307 CD

PROJECT phases
SECtion 00 70 00 conditions of the contract
SECtion 00 70 00 conditions of the contract
CONSTRUCTION

File details come from the government source that posted it. Updated .