Questions and Answers- 22 Sep 26.pdf

PDF 501 KB Posted

Attached to
Full Start-Up Commissioning of Data Center Cooling Infrastructure and UPS battery
Solicitation number
W912HQ26S0077
Issued by

About this file

This is a Questions and Answers (Q&A) document clarifying requirements for a federal contract involving startup, commissioning, and controls correction work at a facility.

Equipment and Testing Requirements: The contract requires two Eaton PW9390-160 UPS systems with a total of 80 batteries. UPS battery testing must utilize the system's internal battery test cycle without requiring an external load bank. Startup and testing activities for Liebert/Vertiv, Multistack, and Eaton equipment may be performed by qualified technicians in accordance with OEM requirements rather than requiring OEM-authorized service technicians. TAB (Testing, Adjusting, and Balancing) verification is not required; system digital readings will suffice for required airflow measurements. Any defective components or repairs identified during startup/commissioning that fall outside the specific scope of work (including the CRV top fan) will be addressed separately by the Government and are not included in the contractor's firm-fixed price.

Controls and Past Performance: The facility currently operates a Tridium Niagara V4.13.3.48 controls system supported by Smart Building Solutions. The contractor must correct controls programming to match the as-built sequence of operation and clear all error codes without requiring integration with Liebert or Multistack equipment. The contractor must furnish all required controls software, licensing, credentials, and network access. For past performance evaluation, the Government will consider relevant experience of major subcontractors and OEM service providers when reviewing the two required same/similar project references performed within the last two years.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. UPS Quantity: The SOW 3.1 states “one (2) Eaton PW9390-160 UPS system.”

Please confirm whether the requirement involves one or two UPS systems.

A: (2) Two UPS with a total of 80 batteries.

2. OEM Authorization: Are the Liebert/Vertiv, Multistack, and Eaton startup/testing activities required to be performed by OEM-authorized service technicians, or may qualified technicians perform the work in accordance with OEM requirements?

A: Qualified technicians perform the work in accordance with OEM requirements

3. TAB Requirements: Is an independent certified TAB contractor required for the CRV airflow and hydronic/glycol system verification? If so, is NEBB, AABC, or another certification required?

A: System digital reading will suffice for require airflow.

4. Discovered Deficiencies: If startup/commissioning identifies defective components or repairs beyond the specifically identified CRV top fan, should those repairs/replacement parts be included in the contractor's firm-fixed price, or will they be addressed separately by the Government?

A: Any findings outside of SOW will be addressed separately by the Government.

5. UPS Testing: Please confirm the required battery discharge-test methodology/duration and whether an external load bank is required.

A: No load bank require, system will need to be cycle through it internal battery test.

6. Past Performance: For the two required same/similar project references performed within the last two years, will the Government consider relevant past performance of major subcontractors/OEM service providers?

A: Yes

1. Please identify the existing controls/BAS system manufacturer and platform currently installed at the facility.

Tridium Niagara V4.13.3.48

2. Is the intent to utilize and integrate with the existing controls system, or is a new controls system/controller installation required?

Current system is running on Niagara system.

3. Please identify the controls contractor/vendor currently supporting the existing system, if applicable.

Smart Building Solutions

4. Please clarify the required controls scope, including programming, network integration, point-to-point verification, graphics, sequence modifications, and functional testing.

Requirement is to correct control to as-built sequence of operation and clear any errors code.

5. Please confirm whether controls software, licensing, credentials, and network access required to perform the work will be Government-furnished or Contractor-furnished.

Contractor furnished

6. Please identify any required communication protocols/interfaces between the Liebert equipment, Multistack equipment, and the facility BAS.

N/A