L_-_CONSOLIDATED_REPORT_REV_A.pdf

PDF 62 KB Posted

Attached to
AIWW CHARLESTON HARBOR- PORT ROYAL DREDGING
Solicitation number
W912HP-17-B-0005
Issued by

About this file

Consolidated Report

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY17 Atlantic Intracoastal Waterway Charleston Harbor to W912HP-B-17-0005 Port Royal Maintenance Dredging

L-1 ATTACHMENT L

CONSOLIDATED REPORT - DREDGING

TITLE: FY17 ATLANTIC INTRACOASTAL WATERWAY CHARLESTON HARBOR TO PORT ROYAL

MAINTENANCE DREDGING, CHARLESTON, COLLETON, AND BEAUFORT COUNTIES, SOUTH

CAROLINA

IFB NO. W912HP-17-B-0005 CONTRACT NO. W912HP-17-C-0005

DRAWING NO. 9586 (Contract), 9587 (BD), 9588 (AD)

GOVERNMENT INSPECTOR:

CONTRACTOR:

CONTRACTOR'S SUPERINTENDENT:

TYPE EQUIPMENT USED ON JOB:

DREDGE(S): (NAME, SIZE, PUMP HP, BOOSTER, ETC.)

OTHER EQUIPMENT: (DRAGLINES, DOZERS, ETC.)

SUBCONTRACTORS:

DATES:

ADVERTISEMENT: BID OPENING:

AWARD: NOTICE TO PROCEED:

REQUIRED STARTING: ACTUAL STARTING:

REQUIRED COMPLETION DATE: ACTUAL COMPLETION:

NUMBERS DAYS ON JOB (PUMPING):

NUMBERS DAYS ON JOB (TOTAL):

DREDGING QUANTITIES:

REQUIRED PRODUCTION RATE:

ACTUAL PRODUCTION RATE:

CHARACTER OF MATERIALS:

NOTE: HARD MATERIAL OR ANY CHANGE OF CONDITIONS SHOULD BE

NOTED. ANY DEBRIS ENCOUNTERED SHOULD ALSO BE LISTED

WITH EXPLANATION OF HOW IT WAS REMOVED AND WHAT EQUIP

WAS USED FOR REMOVAL.

L-2 ATTACHMENT L

CONSOLIDATED REPORT – DREDGING

ADVERTISED QUANTITIES:

SHOAL

NO. LOCATION

REQUIRED

DREDGING PRISM

CY PL. MEAS. *

ALLOWABLE

OVERDEPTH PRISM

CY PL. MEAS. **

TOTAL CY

PL. MEAS.

BASE

Rantowles (11’+1’) 7398+00 to 7420+00

2 Dawho River 1 (11’+1’) 8284+00 to 8346+00

3 Dawho River 2 (11’+1’) 8372+00 to 8388+00

4 Watts Cut (11’+1’) 8534+00 to 8680+00

5 Fenwick Cut (11’+1’) 9055+00 to 9069+00

6 Rock Creek (11’+1’) 9281+00 to 9302+00

Ashepoo Coosaw Cutoff (11’+1’)

9313+00 to 9400+00

OPTIONS

Brickyard Creek (11’+1’) 9975+00 to 9984+00

2 Dawho River 1 (12’+2’) 8284+00 to 8388+00

Dawhoo River 2 (12’+2’)

TOTALS

L-3 ATTACHMENT L

BEFORE DREDGING QUANTITIES:

SHOAL

NO. LOCATION

REQUIRED

DREDGING PRISM

CY PL. MEAS. *

ALLOWABLE

OVERDEPTH PRISM

CY PL. MEAS. **

TOTAL CY

PL. MEAS.

L-4 ATTACHMENT L

AFTER DREDGING QUANTITIES:

SHOAL

NO. LOCATION

REQUIRED

DREDGING PRISM

CY PL. MEAS. *

ALLOWABLE

OVERDEPTH PRISM

CY PL. MEAS. **

TOTAL CY

PL. MEAS.

L-5 ATTACHMENT L

EFFECTIVE AND NON-EFFECTIVE TIME:

NAME OF

DREDGE

PUMPING:

HANDLING PIPE LINES:

HANDLING SWING LINES:

CLEARING PUMP AND PIPELINES:

CLEARING CUTTER:

CHANGING LOCATION ON JOB:

PASSING VESSELS:

SHORE LINE & SHORE WORK:

MINOR REPAIR:

PREPARATION:

MISCELLANEOUS:

MOBILIZATION AND

DEMOBILIZATION:

PRIVATE WORK:

SUNDAYS AND HOLIDAYS:

MAJOR REPAIRS:

LOST TIME:

LOST TIME NOT CHARGEABLE TO COST AT WORK:

TOTAL TIME:

AVERAGES:

WIDTH OF CUT:

LIFT:

NUMBER OF LOADS PER DAY:

CUBIC YARDS PER LOAD:

CUBIC YARDS PUMPED PER HOUR - CREDIT:

CUBIC YARDS PUMPED PER HOUR - GROSS:

CUBIC YARDS PUMPED PER DAY - CREDIT:

CUBIC YARDS PUMPED PER DAY - GROSS:

PUMPING TIME - HOURS PER DAY

TIME DELAYS AND CAUSES OF SUCH DELAYS:

L-6 ATTACHMENT L

DISPOSAL AREA(S): (FOR EACH DISPOSAL AREA)

DISPOSAL AREA:

TOTAL GROSS CYDS PLACED IN THE DISPOSAL AREA:

LOCATION: (WHAT DISCHARGE POINT)

REMARKS:

DISPOSAL AREA:

TOTAL GROSS CYDS PLACED IN THE DISPOSAL AREA:

LOCATION: (WHAT DISCHARGE POINT)

REMARKS:

WATER QUALITY:

NOTE: DOCUMENTATION SHOULD LIST ALL EFFORTS MADE TO INSURE

WATER QUALITY HAS BEEN MAINTAINED AND ANY PROBLEMS

THAT WERE ENCOUNTERED.

OTHER - EXPLAIN:

REMARKS, COMMENTS, AND LESSONS LEARNED:

L-7 ATTACHMENT L

COSTS/PRICES:

ORIGINAL CONTRACT AWARD AMOUNTS:

ITEM

NO. DESCRIPTION ESTIMATED

QUANTITY U/I

UNIT PRICE AMOUNT

BASE

0001 MOBILIZATION AND

DEMOBILIZATION

MAINTENANCE DREDGING BASE

SHOALS 1-7

1 JA JOB $_________

0002 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 1 - RANTOWLES

32,000 CY $_________ $_________

0003 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 2 - DAWHOO RIVER 1

154,000 CY $_________ $_________

0004 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 3 - DAWHOO RIVER 2

28,000 CY $_________ $_________

0005 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 4 - WATTS CUT

282,000 CY $_________ $_________

0006 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 5 - FENWICK CUT

14,000 CY $_________ $_________

0007 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 6 - ROCK CREEK

44,000 CY $_________ $_________

0008 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 7 - ASHEPOO COOSAW

CUTOFF

250,000 CY $_________ $_________

TOTAL (COMBINATION OF BASE BID

ITEMS 0001-0008)

OPTION

0009 MOBILIZATION AND

DEMOBILIZATION

MAINTENANCE DREDGING OPTIONAL

SHOAL 8 - BRICKYARD CREEK

1 JA JOB $_________

0010 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 8- BRICKYARD CREEK

35,000 CY $_________ $_________

0011 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 2 - DAWHOO RIVER 1 TO

12'+2'

68,000 CY $_________ $_________

0012 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL - 3 DAWHOO RIVER 2 TO

12'+2'

16,000 CY $_________ $_________

L-8 ATTACHMENT L

TOTAL (COMBINATION OF OPTIONAL

BID ITEMS 0009-0012)

TOTAL (COMBINATION OF ALL BID

ITEMS 0001-0012)

L-9 ATTACHMENT L

ACTUAL CONTRACT AMOUNTS:

ITEM

NO. DESCRIPTION ESTIMATED

QUANTITY U/I

UNIT PRICE AMOUNT

BASE

0001 MOBILIZATION AND

DEMOBILIZATION

MAINTENANCE DREDGING BASE

SHOALS 1-7

1 JA JOB $_________

0002 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 1 - RANTOWLES

32,000 CY $_________ $_________

0003 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 2 - DAWHOO RIVER 1

154,000 CY $_________ $_________

0004 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 3 - DAWHOO RIVER 2

28,000 CY $_________ $_________

0005 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 4 - WATTS CUT

282,000 CY $_________ $_________

0006 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 5 - FENWICK CUT

14,000 CY $_________ $_________

0007 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 6 - ROCK CREEK

44,000 CY $_________ $_________

0008 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 7 - ASHEPOO COOSAW

CUTOFF

250,000 CY $_________ $_________

TOTAL (COMBINATION OF BASE BID

ITEMS 0001-0008)

OPTION

0009 MOBILIZATION AND

DEMOBILIZATION

MAINTENANCE DREDGING OPTIONAL

SHOAL 8 - BRICKYARD CREEK

1 JA JOB $_________

0010 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 8- BRICKYARD CREEK

35,000 CY $_________ $_________

0011 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 2 - DAWHOO RIVER 1 TO

12'+2'

68,000 CY $_________ $_________

0012 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL - 3 DAWHOO RIVER 2 TO

12'+2'

16,000 CY $_________ $_________

L-10 ATTACHMENT L

TOTAL (COMBINATION OF OPTIONAL

BID ITEMS 0009-0012)

TOTAL (COMBINATION OF ALL BID

ITEMS 0001-0012)

MODIFICATIONS:

MOD 1: (BRIEF DESCRIPTION) $___________

MOD 2: (BRIEF DESCRIPTION) $___________

CLAIMS:

CLAIM 1: (BRIEF DESCRIPTION) $___________

CLAIM 2: (BRIEF DESCRIPTION) $___________

ADDITIONAL COSTS:

NOTE: INCLUDE ALL OTHER COSTS NOT LISTED ABOVE.

File details come from the government source that posted it. Updated .