FY17_AIWW_-_Bid_Schedule_and_Statement_REV_A.pdf
PDF 20 KB Posted
- Attached to
- AIWW CHARLESTON HARBOR- PORT ROYAL DREDGING
- Solicitation number
- W912HP-17-B-0005
About this file
Bid Schedule
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FY17 Atlantic Intracoastal Waterway Charleston Harbor to W912HP-B-17-0005 Port Royal Maintenance Dredging
Section 00010 Page 2
SECTION 00010
BIDDING SCHEDULE
ITEM
NO. DESCRIPTION ESTIMATED
QUANTITY U/I
UNIT PRICE AMOUNT
BASE
0001 MOBILIZATION AND DEMOBILIZATION
MAINTENANCE DREDGING BASE SHOALS
1 - 7
1 JA JOB $_________
0002 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 1 - RANTOWLES
32,000 CY $_________ $_________
0003 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 2 - UPPER DAWHOO
154,000 CY $_________ $_________
0004 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 3 - LOWER DAWHOO
28,000 CY $_________ $_________
0005 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 4 - WATTS CUT
282,000 CY $_________ $_________
0006 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 5 - FENWICK CUT
14,000 CY $_________ $_________
0007 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 6 - ROCK CREEK
44,000 CY $_________ $_________
0008 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 7 - ASHEPOO COOSAW CUTOFF
250,000 CY $_________ $_________
TOTAL (COMBINATION OF BASE BID
ITEMS 0001-0008)
OPTION
0009 MOBILIZATION AND DEMOBILIZATION
MAINTENANCE DREDGING OPTIONAL
SHOAL 8
1 JA JOB $_________
0010 DREDGING OF UNCLASSIFIED MATERIAL
SHOAL 8- BRICKYARD CREEK
35,000 CY $_________ $_________
TOTAL (COMBINATION OF OPTIONAL
BID ITEMS 0009-0010)
TOTAL (COMBINATION OF ALL BID
ITEMS 0001-0010)
FY17 Atlantic Intracoastal Waterway Charleston Harbor to W912HP-B-17-0005 Port Royal Maintenance Dredging
Section 00010 Page 3
STATEMENT
Enter prices where space is provided for ALL items. Failure to follow this instruction may render the bid non-responsive and the bid will not be considered for award.
All bidders are advised materially unbalanced bids may be rejected as non-responsive.
Quantities indicated are comprised of material within the required channel prism including the maximum optional pay slope material and allowable overdepth as described on the contract drawings.
File details come from the government source that posted it. Updated .