Text version

FY17 Atlantic Intracoastal Waterway Charleston Harbor to W912HP-B-17-0005 Port Royal Maintenance Dredging

Section 00010 Page 2

SECTION 00010

BIDDING SCHEDULE

ITEM

NO. DESCRIPTION ESTIMATED

QUANTITY U/I

UNIT PRICE AMOUNT

BASE

0001 MOBILIZATION AND

DEMOBILIZATION

MAINTENANCE DREDGING BASE

SHOALS 1-7

1 JA JOB $_________

0002 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 1 - RANTOWLES

32,000 CY $_________ $_________

0003 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 2 - DAWHOO RIVER 1

154,000 CY $_________ $_________

0004 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 3 - DAWHOO RIVER 2

28,000 CY $_________ $_________

0005 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 4 - WATTS CUT

282,000 CY $_________ $_________

0006 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 5 - FENWICK CUT

14,000 CY $_________ $_________

0007 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 6 - ROCK CREEK

44,000 CY $_________ $_________

0008 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 7 - ASHEPOO COOSAW

CUTOFF

250,000 CY $_________ $_________

TOTAL (COMBINATION OF BASE BID

ITEMS 0001-0008)

OPTION

0009 MOBILIZATION AND

DEMOBILIZATION

MAINTENANCE DREDGING OPTIONAL

SHOAL 8 - BRICKYARD CREEK

1 JA JOB $_________

0010 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 8- BRICKYARD CREEK

35,000 CY $_________ $_________

0011 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL 2 - DAWHOO RIVER 1 TO

12'+2'

68,000 CY $_________ $_________

0012 DREDGING OF UNCLASSIFIED

MATERIAL

SHOAL - 3 DAWHOO RIVER 2 TO

12'+2'

16,000 CY $_________ $_________

FY17 Atlantic Intracoastal Waterway Charleston Harbor to W912HP-B-17-0005 Port Royal Maintenance Dredging

Section 00010 Page 3

TOTAL (COMBINATION OF OPTIONAL

BID ITEMS 0009-0012)

TOTAL (COMBINATION OF ALL BID

ITEMS 0001-0012)

STATEMENT

Enter prices where space is provided for ALL items. Failure to follow this instruction may render the bid non-responsive and the bid will not be considered for award.

All bidders are advised materially unbalanced bids may be rejected as non-responsive.

Quantities indicated are comprised of material within the required channel prism including the maximum optional pay slope material and allowable overdepth as described on the contract drawings.

File details come from the government source that posted it. Updated .