About this file

Amendment 0010

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

THE PURPOSE OF THIS AMENDMENT IS TO:

1. SEE SECTION SF 30 BLOCK 14 CONTINUATION PAGE FOR ADDITIONAL INFORMATION.

2. NOTICE: Submission Instructions and Due Dates for Revised Proposal Volume(s) have changed to the follow ing:

Volume 1 Non Price – Not Required. NOTE: Revised site plans/diagrams/images depicting or narratives explaining the site location of the new building to address changes in this Amendment are not required to be submitted due to time constraints, how ever, the contractor shall acknow ledge all amendments as directed in SECTION 00100 - PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS, paragraph B.3.c. “Volume 2 Price: (i) Section A.”

Volume 2 Price – Required. Due 2:00 PM EST, 26 September 2015

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 23-Sep-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HP-14-R-0012

X 9B. DATED (SEE ITEM 11)

20-Feb-2014

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

23-Sep-2015

CODE

U.S. ARMY CORPS OF ENGINEERS, CHARLESTON

DISTRICT, CONTRACTING DIVISION

69-A HAGOOD AVENUE

CHARLESTON SC 29403

W912HP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HP-14-R-0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

ISSUED AMENDMENT 10

SUMMARY OF CHANGES

1. RFP Building 2270 Renovation & New Construction for the Army Band:

DELETE page 3 of 5 SECTION 00 11 00 CLIN CONTRACT LINE ITEM SCHEDULE

And REPLACE with the attached page 3 of 5 SECTION 00 11 00 CLIN CONTRACT LINE ITEM SCHEDULE bearing the notation “Accompanying Amendment 0010”

2. RFP Building 2270 Renovation & New Construction for the Army Band, Section 01 10 00, paragraph 2.1.1.2

ADD the following after the existing sentence “The new building location shall be coordinated with existing site conditions to avoid impact to existing CEP piping.”:

“See approximate location of CEP lines labeled “HCS line” (includes medium temp hot water piping in trenches and direct buried chilled water piping) on Appendix AA UTILITY DIAGRAM. Contractor shall field verify exact location of all subsurface utilities and determine if lines are still in use prior to the first design submittal. See paragraph 6.11.7 CENTRAL ENERGY PLANT (CEP) CHILLED WATER DISTRIBUTION PIPING for requirements if direct buried chilled water piping will be impacted.“

3. RFP Building 2270 Renovation & New Construction for the Army Band, Appendix AA:

ADD “UTILITIES DIAGRAM” bearing the notation “Accompanying Amendment 0010” to Appendix AA Existing Utilities Base Maps

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time 26-Sep-2015 02:00 PM has been added.

(End of Summary of Changes)

Su mt er Av e

Ma gru de r A ve

Beauregard St

Wh ee ler St

Ferguson Ave

Cheatham St

Patrick Tinneny

(803) 751-1602

UNCLASSIFIED FOUO

Fort Jackson DPW

Ele Utility Point Ele Transformer Bank Point Ele Capacitor Point Ele Junction Point Ele Meter Point Ele Riser Point Ele Switch Point Ele Utility Line Ele Cable Line Ele Ductbank Line Ele Substation Area

Water Fire Connection Point Water Hydrant Point Water Junction Point Water Meter Point Water Pump Point Water Pump Station Point Water Tank Point Water Valve Point Water Line x_coc_hydrants x_water_fill_pt

NG Reg Reducer Point NG Fitting Point NG Junction Point NG Marker Point NG Meter Point NG Tank Point NG Valve Point

WW Grease Trap Point WW Junction Point WW Treat Plant Point WW Pump Ejector Station Point WW Line

SS Inlet Point SS Junction Point SS Oil Water Separator Point SS Line

# HCS Fitting Point # HCS Junction Point # HCS Valve Point

HCS Line NG Line

Installation Area Building Range Area Paved Secondary Firebreak Ramp Highway I-77 Leesburg Rd (HWY 262)

0 125 250 375 500 Feet

Electrical WastewaterNatural GasWater BasemapChilled WaterStorm Sewer

UTILITIES DIAGRAM

This yellow box is not an accurate representation of the building addition size or location.

Section: Appedix AA Accompanying Amendment 0010

Accompanying Amendment 0010 SEED PROJECT: Building 2270

SECTION 00 11 00 CLIN

CONTRACT LINE ITEM SCHEDULE

Item No. Description Quantity Unit Amount

BASE PROPOSAL

0001 Design Costs 0001AA Bldg 2270 1 Job $_________________

0001AB Bldg 2280 1 Job $_________________

0001AC New building, including site work 1 Job $_________________

0001AD Relocate impacted CEP Chilled Water Piping 1 Job $_________________

(reference Section 01 10 00, paragraphs 2.1.1.2 as amended and 6.11.7). If not applicable to your technical approach, enter “$0.00” or “N/A.”

Subtotal Item 0001 $_________________

0002 Non-Design Costs 0002AA Bldg 2270 1 Job $_________________

0002AB Bldg 2280 1 Job $_________________

0002AC New building, including site work 1 Job $_________________ (Not To Exceed $900,000 New Construction Cost Limitation. See “Options Note”.)

0002AD Relocate impacted CEP Chilled Water Piping 1 Job $_________________

(reference Section 01 10 00, paragraphs 2.1.1.2 as amended and 6.11.7). If not applicable to your technical approach, enter “$0.00” or “N/A.”

Subtotal Item 0002 $_________________

TOTAL BASE PROPOSAL $_________________

0003 Option Design Costs, New access drive 1 Job $_________________

0004 Option Non-Design Costs, New access drive 1 Job $_________________

(Options Note: Exercise of options subject to NTE $900,000 New Construction Cost Limitation by combining CLIN 0002AC with Option CLIN 0004)

Subtotal Option 1, Items 0003, 0004 $_________________

TOTAL BASE OFFER (Items 0001-0002) $____________________

TOTAL OPTION OFFER (Items 0003-0004) $____________________

TOTAL OFFER BASE + OPTIONS (Items 0001-0004) $____________________

Enter Proposed Contract Duration in Calendar Days, after NTP is received: DAYS **NOTE: Contract duration for all work shall NOT exceed the duration specified in Section 01 08 10 TASK ORDER REQUIREMENTS (FAR 52.211-10). See Note 8.

SECTION 00 11 00 CLIN

BASE PROPOSAL

0001 Design Costs

0001AC New building, including site work 1 Job $_________________

0002 Non-Design Costs

0002AC New building, including site work 1 Job $_________________

Enter Proposed Contract Duration in Calendar Days, after NTP is received: DAYS

**NOTE: Contract duration for all work shall NOT exceed the duration specified in Section 01 08 10 TASK ORDER REQUIREMENTS (FAR 52.211-10). See Note 8.