AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of the amendment is to:

1. Extend the proposal due dates (see Summary of Changes)

2. Make changes to the Proposal Submission Requirements and Instructions (see Summary of Changes)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 11-Sep-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HP-14-R-0012

X 9B. DATED (SEE ITEM 11)

20-Feb-2014

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

11-Sep-2015

CODE

US ARMY CORPS OF ENGINEERS, CHARLESTON

69-A HAGOOD AVENUE

CHARLESTON SC 29403

W912HP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912HP-14-R-0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

ISSUE AMENDMENT 9

NOTICE: Proposal Due Dates has changed to the following:

Volume 1 Non Price – Proposal due 2:00 PM EST, 16 September 2015 Volume 2 Price – Proposal due 2:00 PM EST, 18 September 2015

SECTION 00 100 (Phase 2 Seed Project) – PROPOSAL SUBMISSION REQUIREMENTS AND INSTRUCTIONS

1. Section 00 100 – Proposal Submission Requirements and Instructions, paragraph E.2.a Proposed Contract Duration:

DELETE the second sentence: “The Government will evaluate the contract duration, as proposed by the Firm in the Contract Line Item Schedule, not to exceed the maximum allowed duration specified in specification section 00 73 10.”

And REPLACE with: “The Government will evaluate the contract duration, as proposed by the Firm in the Contract Line Item Schedule, not to exceed the maximum allowed duration specified in specification section 01 08 10.”

SECTION 00 01 10 – TABLE OF CONTENTS TASK ORDER

2. Section 00 01 10 – REQUEST FOR PROPOSAL Building 2270 Renovation & New Construction Fort Jackson:

DELETE page 3 of 5 SECTION 00 11 00 CLIN CONTRACT LINE ITEM SCHEDULE

And REPLACE with attached page 3 of 5 SECTION 00 11 00 CLIN CONTRACT LINE ITEM

SCHEDULE.

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time 20-Mar-2015 02:00 PM has been deleted.

(End of Summary of Changes)

SEED PROJECT: Building 2270

SECTION 00 11 00 CLIN

CONTRACT LINE ITEM SCHEDULE

Item No. Description Quantity Unit Amount

BASE PROPOSAL

0001 Design Costs

0001AA Bldg 2270 1 Job $_________________

0001AB Bldg 2280 1 Job $_________________

0001AC New building, including site work 1 Job $_________________

Subtotal Item 0001 $_________________

0002 Non-Design Costs

0002AA Bldg 2270 1 Job $_________________

0002AB Bldg 2280 1 Job $_________________

0002AC New building, including site work 1 Job $_________________ (Not to exceed $900,000 New Construction Cost Limitation)

Subtotal Item 0002 $_________________

TOTAL BASE PROPOSAL $_________________

0003 Option Design Costs access drive 1 Job $_________________

0004 Option Non-Design Costs access drive 1 Job $_________________

Subtotal Option 1, Items 0003, 0004 $_________________

TOTAL BASE OFFER (Items 0001-0002) $____________________

TOTAL OPTION OFFER (Items 0003-0004) $____________________

TOTAL OFFER BASE + OPTIONS (Items 0001-0004) $____________________

Enter Proposed Contract Duration in Calendar Days, after NTP is received: DAYS **NOTE: Contract duration for all work shall NOT exceed the duration specified in Section 01 08 10 TASK ORDER REQUIREMENTS (FAR 52.211-10). See Note 8.

SECTION 00 11 00 CLIN

BASE PROPOSAL

0001 Design Costs

0001AC New building, including site work 1 Job $_________________

0002 Non-Design Costs

0002AC New building, including site work 1 Job $_________________

Enter Proposed Contract Duration in Calendar Days, after NTP is received: DAYS

**NOTE: Contract duration for all work shall NOT exceed the duration specified in Section 01 08 10 TASK ORDER REQUIREMENTS (FAR 52.211-10). See Note 8.