18R3007vol1.PDF
PDF 9 MB Posted
- Attached to
- Construct Tanker Truck Delivery System
- Solicitation number
- W912HN18R3007
About this file
SPECS Vol 1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amd8.pdf | ||
| 18R3007vol3.PDF | ||
| amd7.pdf | ||
| 18R3007vol1.PDF | ||
| W912HN-18-R-3007_AMD7.PDF | ||
| 18R3007vol1.PDF | ||
| amd6.pdf | ||
| 18R3007vol1.PDF | ||
| amd4.pdf | ||
| 18R3007vol2.PDF | ||
| 18R3007vol3.PDF | ||
| W912HN-18-R-3007_AMD2.pdf | ||
| amd2.pdf | ||
| 18R3007vol1.PDF | ||
| amd1.pdf | ||
| 18R3007vol1.PDF | ||
| 18R3007vol3.PDF | ||
| 18R3007vol2.PDF | ||
| W912HN-18-R-3007.PDF |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Seymour Johnson AFB, North Carolina
Solicitation Number
W912HN-18-R-3007
Construct tanker Truck Delivery System Volume 1 of 3: Procurement and Contracting Requirements and Specification Divisions 01 - 04
PN DESC1801
June 2018
U.S. ARMY ENGINEER DISTRICT, SAVANNAH
CORPS OF ENGINEERS
100 WEST OGLETHORPE AVENUE
SAVANNAH, GEORGIA 31401-3640
US Army Corps of Engineers Savannah District
Const r uct Tanker Tr uck Del i ver y Syst em 18R3007 Seymour Johnson AFB, NC
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 32 01. 00 10 PROJECT SCHEDULE
01 33 00 SUBMI TTAL PROCEDURES
01 33 29 SUSTAI NABI LI TY REPORTI NG
01 35 26 GOVERNMENTAL SAFETY REQUI REMENTS
01 35 29. 13 HEALTH, AND SAFETY, AND EMERGENCY RESPONSE PROCEDURES FOR
CONTAMI NATED SI TES SOI L EXCAVATI ON
01 42 00 SOURCES FOR REFERENCE PUBLI CATI ONS
01 45 00. 00 10 QUALI TY CONTROL
01 45 00. 15 10 RESI DENT MANAGEMENT SYSTEM CONTRACTOR MODE( RMS CM)
01 45 35 SPECI AL I NSPECTI ONS
01 50 00 TEMPORARY CONSTRUCTI ON FACI LI TI ES AND CONTROLS
01 57 19 ENVI RONMENTAL PROTECTI ON
01 57 23 TEMPORARY STORM WATER POLLUTI ON CONTROL
01 74 19 CONSTRUCTI ON AND DEMOLI TI ON WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMI TTALS
01 78 23 OPERATI ON AND MAI NTENANCE DATA
01 78 23. 33 OPERATI ON AND MAI NTENANCE MANUALS FOR AVI ATI ON FUEL
SYSTEMS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 DEMOLITION
02 61 13 EXCAVATI ON AND HANDLI NG OF CONTAMI NATED MATERI AL
02 81 00 TRANSPORTATI ON AND DI SPOSAL OF HAZARDOUS MATERI ALS
02 82 13. 00 10 ASBESTOS ABATEMENT
02 83 13. 00 20 LEAD I N CONSTRUCTI ON
DI VI SI ON 03 - CONCRETE
03 11 13. 00 10 STRUCTURAL CAST- I N- PLACE CONCRETE FORMI NG
03 15 00. 00 10 CONCRETE ACCESSORI ES
03 20 00. 00 10 CONCRETE REI NFORCI NG
03 30 00. 00 10 CAST- I N- PLACE CONCRETE
03 35 00. 00 10 CONCRETE FI NI SHI NG
03 39 00. 00 10 CONCRETE CURI NG
03 42 13. 00 10 PLANT- PRECAST CONCRETE PRODUCTS FOR BELOW GRADE
CONSTRUCTION
DI VI SI ON 04 - MASONRY
04 20 00 MASONRY
DI VI SI ON 05 - METALS
05 12 00 STRUCTURAL STEEL
05 21 19 OPEN WEB STEEL JOI ST FRAMI NG
05 30 00 STEEL DECKS
05 50 13 MI SCELLANEOUS METAL FABRI CATI ONS
05 51 33 METAL LADDERS
05 59 10 ROLLI NG COVER FOR AVI ATI ON REFUELI NG VAULTS
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 ROUGH CARPENTRY
PROJECT TABLE OF CONTENTS Page 1
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 21 13 BOARD AND BLOCK I NSULATI ON
07 22 00 ROOF AND DECK I NSULATI ON
07 27 26 FLUI D- APPLI ED MEMBRANE AI R BARRI ERS
07 52 00 MODI FI ED BI TUMI NOUS MEMBRANE ROOFI NG
07 60 00 FLASHI NG AND SHEET METAL
07 61 14. 00 20 STEEL STANDI NG SEAM ROOFI NG
07 84 00 FIRESTOPPING
07 92 00 JOI NT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 STEEL DOORS AND FRAMES
08 51 13 ALUMI NUM WI NDOWS
08 51 23 STEEL WI NDOWS
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 SUPPORTS FOR GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 51 00 ACOUSTI CAL CEI LI NGS
09 65 00 RESI LI ENT FLOORI NG
09 90 00 PAI NTS AND COATI NGS
09 97 13. 17 THREE COAT EPOXY I NTERI OR COATI NG OF WELDED STEEL
PETROLEUM FUEL TANKS
09 97 13. 27 EXTERI OR COATI NG OF STEEL STRUCTURES
DI VI SI ON 10 - SPECI ALTI ES
10 44 16 FI RE EXTI NGUI SHERS
DI VI SI ON 12 - FURNI SHI NGS
12 21 00 WI NDOW BLI NDS
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 34 19 METAL BUI LDI NG SYSTEMS ( PUMP SHELTER)
13 34 20 METAL BUI LDI NG SYSTEMS ( CANOPI ES)
DI VI SI ON 22 - PLUMBI NG
22 00 00 PLUMBI NG, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 00 00 AI R SUPPLY, DI STRI BUTI ON, VENTI LATI ON, AND EXHAUST SYSTEMS
23 05 93 TESTI NG, ADJUSTI NG, AND BALANCI NG FOR HVAC
23 07 00 THERMAL I NSULATI ON FOR MECHANI CAL SYSTEMS
23 08 00. 00 10 COMMI SSI ONI NG OF HVAC SYSTEMS
23 81 00. 00 20 UNI TARY AI R CONDI TI ONI NG EQUI PMENT
23 82 46. 00 40 ELECTRI C UNI T HEATERS
DI VI SI ON 26 - ELECTRI CAL
PROJECT TABLE OF CONTENTS Page 2
26 00 00. 00 20 BASI C ELECTRI CAL MATERI ALS AND METHODS
26 08 00 APPARATUS I NSPECTI ON AND TESTI NG
26 12 19. 10 THREE- PHASE PAD- MOUNTED TRANSFORMERS
26 20 00 I NTERI OR DI STRI BUTI ON SYSTEM
26 23 00 LOW- VOLTAGE SWI TCHGEAR
26 28 01. 00 10 COORDI NATED POWER SYSTEM PROTECTI ON
26 32 15. 00 10 DI ESEL- GENERATOR SET STATI ONARY 100- 2500 KW, WI TH
AUXILIARIES
26 41 00 LI GHTNI NG PROTECTI ON SYSTEM
26 42 14. 00 10 CATHODI C PROTECTI ON SYSTEM ( SACRI FI CI AL ANODE)
26 42 17. 00 10 CATHODI C PROTECTI ON SYSTEM ( I MPRESSED CURRENT)
26 51 00 I NTERI OR LI GHTI NG
26 56 00 EXTERI OR LI GHTI NG
DI VI SI ON 27 - COMMUNI CATI ONS
27 10 00 BUI LDI NG TELECOMMUNI CATI ONS CABLI NG SYSTEM
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 64. 00 10 FI RE DETECTI ON AND ALARM SYSTEM, ADDRESSABLE
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 31 16. 13 CHEMI CAL TERMI TE CONTROL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 01 19 FI ELD MOLDED SEALANTS FOR SEALI NG JOI NTS I N RI GI D
PAVEMENTS
32 11 20 BASE COURSE FOR RI GI D AND SUBBASES FOR FLEXI BLE PAVI NG
32 11 23 AGGREGATE BASE COURSES
32 12 16 HOT- MI X ASPHALT ( HMA) FOR ROADS
32 13 13. 06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SI TE
FACILITIES
32 16 13 CONCRETE SI DEWALKS AND CURBS AND GUTTERS
32 17 23 PAVEMENT MARKI NGS
32 92 23 SODDING
DI VI SI ON 33 - UTI LI TI ES
33 01 50. 01 CLEANI NG FUEL STORAGE TANKS
33 08 53 AVI ATI ON FUEL DI STRI BUTI ON SYSTEM START- UP
33 09 53 AVI ATI ON FUEL PUMP CONTROL AND ANNUNCI ATI ON SYSTEM
33 11 00 WATER UTI LI TY DI STRI BUTI ON PI PI NG
33 30 00 SANI TARY SEWERS
33 32 13. 10 24 DROP TANK VAULT SUBMERSI BLE PUMP
33 34 00 DROP TANK VAULT FORCE MAI N
33 40 00 STORM DRAI NAGE UTI LI TI ES
33 52 43. 11 AVI ATI ON FUEL MECHANI CAL EQUI PMENT
33 52 43. 12 AVI ATI ON FUEL PANTOGRAPHS
33 52 43. 13 AVI ATI ON FUEL PI PI NG
33 52 43. 14 AVI ATI ON FUEL CONTROL VALVES
33 52 43. 23 AVI ATI ON FUEL PUMPS
33 52 43. 28 FI LTER SEPARATOR, AVI ATI ON FUELI NG SYSTEM
33 56 10 FACTORY- FABRI CATED FUEL STORAGE DROP TANKS
33 56 13. 13 STEEL TANKS WI TH FI XED ROOFS
33 56 19 FUEL I MPERMEABLE LI NER SYSTEM
PROJECT TABLE OF CONTENTS Page 3
33 58 00 LEAK DETECTI ON FOR FUELI NG SYSTEMS
33 71 02 UNDERGROUND ELECTRI CAL DI STRI BUTI ON
33 82 00 TELECOMMUNI CATI ONS OUTSI DE PLANT ( OSP)
DI VI SI ON 41 - MATERI AL PROCESSI NG AND HANDLI NG EQUI PMENT
41 22 13. 24 BRI DGE CRANES, OVERHEAD HAND OPERATED, UNDER RUNNI NG
- - End of Pr oj ect Tabl e of Cont ent s - -
PROJECT TABLE OF CONTENTS Page 4
(RFP)
(Include area code) (NO COLLECT CALLS)
(See _________________________
(If "YES," indicate within how many calendar days after award in Item 12B.)
(date).
(Construction, Alteration, or Repair)
(Title, identifying no., date):
(hour)
(If Other Than Item 7)
(Construction, Alteration, or Repair) the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
(Type or print)
(To be completed by Government)
(4 copies unless otherwise specified)
(Insert any number equal to or greater than
(Include ZIP Code) (Include area code)
(Include only if different than Item 14)
(Contractor is not required to sign this document.)
document and return _______ copies to issuing office.)
31A. NAME OF CONTRACTING OFFICER (Type or print)
(Type or print)
TEL: EMAIL:
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this
(M ust be fully completed by offeror) to include all modifications, if applicable
Please provide details such as similar equipment, requirements, conditions, etc.
ADJECTIVE RATINGS AND DEFINITIONS TO BE USED TO BEST REFLECT
YOUR EVALUATION OF THE CONTRACTOR’S PERFORMANCE
(If liquidated damages were assessed or the schedule was not met, please address below)
If no, please explain in Remarks section.
Indicate if show cause or cure notices were issued, or any default action in comment section below.
If yes, please explain below.
(explain if specific issues)
(If no, please explain below) if applicable
(please attach additional pages if necessary)
ATTACHMENT 1 TO SECTION 00 73 00
LIST OF ATTACHMENTS
Attachment 1 - 1
Army Project Sign
Project Sign Legend Defined
Project Sign Erection Detail
Safety Performance Sign
Corps of Engineers Logo
Minimum Basic Outline for Accident Prevention Plans (EM 385-1-1, App A)
Construction Quality Control Report
Small Business Subcontracting Plan
Weekly Temporary Electrical Inspection
Minimum Standard for Temporary Electrical Service (Ref. FAR 52.236-14)
SAS Form 9 - Activity Hazard Analysis
SAD Form 1666a-R - Safety Checklist for Crawler, Truck & Wheel Mounted Cranes
SAD Form 1666d-R Safety Checklist for Control of Hazardous Energy
(Lockout/Tagout)
SAD Form 1666d-R Safety Checklist for Motor Vehicles, Trailers, and Trucks
SAD Form 1666d-R Safety Checklist for Safe Access and Fall Protection
SAD Form 1666d-R Safety Checklist for Scaffolds - Other Types
SAD Form 1666e-R Safety Checklist for Crawler Tractors and Dozers
SAD Form 1666e-R Safety Checklist for Cutting/Welding Operations
SAD Form 1666e-R Safety Checklist for Demolition Operations
SAD Form 1666e-R Safety Checklist for Forms, Falsework, and Concrete
Operations
SAD Form 1666e-R Safety Checklist for Permit Required Confined Spaces (PRCS)
SAD Form 1666e-R Safety Checklist for Personal Protective Equipment
SAD Form 1666e-R Safety Checklist for Portable Ladders
SAD Form 1666e-R- Safety Checklist for Portal, Tower, and Pillar Cranes
SAD Form 1666e-R Safety Checklist for Rigging
SAD Form 1666e-R Safety Checklist for Sanitation/Housekeeping
SAD Form 1666e-R Safety Checklist for Scaffolds - Metal Frame
ATTACHMENT 1 TO SECTION 00 73 00
LIST OF ATTACHMENTS
Attachment 1 - 2
SAD Form 1666f-R - Safety Checklist for Scrapers, Motor Graders, and Other Mobile Equipment
SAD Form 1666e-R Safety Checklist for Structural Steel Erection
SAD Form 1666e-R Safety Checklist for Tree Work, Maintenance, or Removal
Operations
SAD Form 1666e-R Safety Checklist for Trenching and Excavation Competent
Person
SAD Form 1666e-R Safety Checklist for Trenching and Excavation Operations
SAD Form 1666f-R Safety Checklist for Crane Inspections
SAD Form 1666g-R - Safety Checklist for Material Hoists
SAD Form 1666h-R - Safety Checklist for Earth Drilling Equipment
SAD FL 198 – Report of Safety Meeting
DA Form 5418-R - Cost Estimate Analysis
DD Form 1354 - Transfer and Acceptance of Military Real Property
DD Form 1532 - Pest Management Report
DD Form 1532 - Pest Management Maintenance Record
DHS Form I-9 - Employment Eligibility Verification
ENG Form 2454 - Construction Progress Chart
ENG Form 3394 – Accident Investigation Report
ENG Form 4025 - Transmittal of Shop Drawings, Equipment Data, Material
Samples, or Manufacturer's Certificates of Compliance
Real Property Inventory and BIS Worksheet
Landfill Permit Application
Standard Form LLL-A - Disclosure of Lobbying Activities
AF3952 - Contractor HazMat Authorization, Inventory, and Usage Form
Contractor-Furnished Spoil, Disposal Areas
PROJECT SIGN LEGEND DEFINED
Legend Group 1: The words:
"Construction or "Design and Construction Supervised by:" Supervised by:"
shall be placed on two lines using black, 1.25" Helvetica regular typeface.
Maximum line length is 19".
10.5" Reverse Signature: The Corps symbol shall be a 10.5" white reverse signature using a 6" castle on a red background. The castle and surrounding border lines shall be white. The castle windows, door, and logo background are to be red. The words "U.S. Army Corps of Engineers" shall be black.
Legend Group 2: The words:
"Savannah District South Atlantic Division" shall be placed on two lines below the 10.5" reverse signature, using black, 1.25" Helvetica regular typeface.
Legend Group 3: The "Name of Project" shall be placed on one to three lines using white 3" Helvetica bold typeface. Maximum line length is 42".
Legend Group 4: The "Army Installation" shall be a one or two line identification of the facility or name of the sponsoring department.
Lettering is to be white, 1.5" Helvetica regular typeface. Maximum line length is 42".
NOTE: Cross-align the first line of legend group 4 with the first line of the Corps signature (U.S. Army Corps) as shown.
Legend Group 5a: The words:
"Architects:" or "Engineers:" or "Architect-Engineers:"
shall be a one to five line identification of the prime architect or engineering corporate or firm name, city, and State. Lettering shall be white, 1.25" Helvetica regular typeface. Maximum line length is 21".
Legend Group 5b: The "Contractor:" shall be a one to five line identification of the prime Contractor corporate or firm name, city, and State. Include type of Contractor, i.e. General Contractor, etc. Lettering shall be white, 1.25" Helvetica regular typeface. Maximum line length is 21".
NOTE: All typography shall be flush left and rag right, upper and lower case with initial capitals only as shown.
Safety Performance Sign EP 310-1-6a 01 Jun 06
16-3
Each contractor’s safety record is to be posted on Corps managed or supervised construction projects and mounted with the Construction Project Identification sign specified on page 16-2.
The graphic format, color, size and type-faces used on the sign are to be repro-duced exactly as specified below. The title with First Aid logo in the top section of the sign, and the performance record captions are standard for all signs of this type. Legend groups 2 and 3 below identify the project and the contractor and are to be placed on the sign as shown.
Safety record numbers are mounted on individual metal plates and are screw-mounted to the background to allow for daily revisions to posted safety perfor-mance record.
Special applications or situations not covered in these guidelines should be referred to the district Sign Program Manager.
Legend Group 1: Standard two-line title “Safety is a Job Requirement” with 8” (outside diameter) Safety Green first aid logo.
Color: To match Pantone system 347 Typeface: 3" Helvetica Bold Color: Black
Legend Group 2: One- to two-line project title legend describes the work being done under this contract and name of host project.
Color: Black Typeface: 1.5" Helvetica Regular Maximum line length: 42"
Legend Group 3: One- to two-line identifica-tion: name of prime contractor and city, state address. Color: Black Typeface: 1.5" Helvetica Regular Maximum line length: 42"
Legend Group 4: Standard safety record captions as shown.
Color: Black Typeface: 1.25” Helvetica Regular
Replaceable numbers are to be mounted on white .060 aluminum plates and screw-mounted to background.
Color: Black Typeface: 3" Helvetica Regular Plate size: 2.5" x 4.5"
All typography is flush left and rag right, upper and lower case with initial capitals only as shown. Letter- and word-spacing to follow Corps standards as specified in Appendix D.
3” 33.030” eq. 8” eq.
6”
4.5”
10.5”
2.25” 3”
2.25” 3”
4.875”
4.875”
6.75”
4.875” .75” 4.875”
4.5”
3”
3” 42” 3”
2.25” 2.25” 2.25” 2.25”
.75”
3”
.75”
Sign Legend Panel Post Specification Mounting Color Type Size (A) Size Size Code Height Bkg/Lgd
CID-02 various 4’x4’ 4”x4” HDO-3 48” WH/BK-SG
CORPS OF ENGINEERS LOGO
HALF SIZE
EM 385-1-1
30 Nov 14
A-1
APPENDIX A
Minimum Basic Outline for Accident Prevention Plans
1. Accident Prevention Plan (APP) - General. An APP is a safety and health policy and program document that is contract- or job- specific. It is an integral part of the planning process. > See Section 01 and 01.A.12.
a. The APP shall interface with the employer’s overall safety and health program. Any portions of the overall safety and health program that are referenced in the APP shall be included as appropriate.
b. The APP shall be submitted to the GDA for acceptance prior to work starting.
(1) Understanding that the APP is submitted prior to work starting and that some project-specific information is not yet known (e.g., subcontractors to be used, type of fall protection to be used at a certain point in time, specific cranes or other load handling equipment (LHE) to be brought on site, etc.), the known information shall be provided and additional information added at each preparatory phase/meeting along with the appropriate Activity Hazard Analyses (AHAs).
(2) A copy of the contractor’s project-specific, accepted APP shall be available on the work site. > See ANSI/ASSE A10.38 for programmatic issues.
2. Abbreviated APP. In lieu of a fully-developed APP, for Limited-Scope Service, Supply and R&D Contracts (e.g. grass mowing, park attendant, rest room cleaning, etc.), the Contracting Officer (KO) and local Safety and Occupational Health Office (SOHO) may allow an Abbreviated APP to be developed and submitted for acceptance.
a. The non-mandatory Abbreviated APP Form, Form A-1 (or similar) may be used to insure each area of required information has been provided.
b. This APP is a short-version APP that can be used on low-risk, limited-scope contracts. > See 01.A.12.e, and Appendix A, paragraph 3.k.
c. Each sub-contractor shall be provided a copy of the APP by the prime contractor and be required to comply with it.
A-2
3. APP Format. The following areas are typically addressed in an APP, but besides being job-specific, the APP shall also address any unusual or unique aspects of the contract or job for which it is written. The non-mandatory Accident Prevention Plan (APP) Checklist, Form A-2 (or similar), may be used to insure each area of required information has been provided. > See ANSI A10.33 for multi-employer projects.
a. Signature Sheet: Include title, signature, and phone number of the following:
(1) Plan preparer (Qualified Person (QP), Competent Person (CP), Corporate safety staff person, QC) and their qualifications;
(2) Plan must be approved by company/corporate officers authorized to obligate the company;
(3) Plan concurrence (e.g., Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project QC). Contractors shall provide concurrence of other applicable corporate and project personnel.
b. Background Information. List the following:
(1) Contractor;
(2) Contract number;
(3) Project name;
(4) Brief project description, description of work to be performed, location (map), equipment to be used, anticipated high risk activities, and
(5) Major phases of work anticipated.
(6) Within these major phases of work identified, activities [includes Definable features of Work (DFOWs) and tasks] to be performed that will require an AHA shall be specifically highlighted. This information can then be used by QC, QA and Safety personnel to track AHA submittals. The AHAs for these activities, tasks of DFOWs are NOT submitted at this time (AHAs created/submitted at this time would not be activity-specific as they are intended to be). > See Sections 01.A.14 and 01.A.15.
c. Statement of Safety and Health Policy. Provide a copy of current corporate/company Safety and Health Policy Statement, detailing commitment to providing a safe and healthful workplace for all employees. The Contractor’s written safety program goals, objectives, and accident experience goals for this contract shall also be provided.
A-3
d. Responsibilities and Lines of Authority. Provide the following:
(1) A statement of the employer’s ultimate responsibility for the implementation of his SOH program for his own employees, all sub-contractors and all others on the worksite (includes the strict enforcement of the program).
(2) Identification and accountability of personnel responsible for safety at both corporate and project level. Contracts specifically requiring safety or industrial hygiene personnel shall include a copy of their resumes. Qualifications shall be in accordance with Section 01.A.17.
Note: Only official OSHA 30-Hour cards will be accepted or, if equivalent training is provided, appropriate instructor qualifications. > See also Section 01.A.17.i, Exception 2.
(3) If equivalent training to the OSHA 30-hour classes is being presented as qualification, the training shall have covered the following areas:
(a) OSH Act/General Duty Clause;
(b) 29 CFR 1904, Recordkeeping;
(c) Subparts C, CC, D, E, F, K and M of OSHA;
(d) Rigging, load handling equipment (LHE), welding and cutting, scaffolding, excavations, concrete and masonry, demolition, health hazards in construction, materials handling, storage and disposal, hand and power tools, motor vehicles, mechanized equipment, marine operations, steel erection, stairways and ladders, confined spaces or any others that are applicable to the work being performed;
(4) The names of CP(s) and/or QP(s) and proof of competency/qualification to meet specific OSHA CP/QP requirements must be attached. The local SOHO will review the qualifications for acceptance;
(5) Requirements and details of the employer’s Risk Management Process;
Note: USACE uses the Activity Hazard Analysis (AHA) as part of a total risk management process. Contractors and other individual employer’s may use the AHAs or their own version [Job Safety Analyses (JSAs), Job Hazard Analyses (JHAs), or similar Risk Management assessment tools]. These documents are considered equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA.
(6) Requirements for initial activity-specific AHAs to be submitted and accepted at preparatory meetings, prior to work being performed;
A-4
(7) Requirements that no work by the Contractor shall be performed unless a designated CP/SSHO is present on the job site;
(8) Policies and procedures regarding non-compliance with safety requirements (to include disciplinary actions for violation of safety requirements) should be identified;
(9) Lines of authority;
(10) Provide written company procedures for holding managers and supervisors accountable for safety.
e. Subcontractors and Suppliers. If applicable, provide procedures for coordinating SOH activities with other employers on the job site:
(1) Identification of subcontractors and suppliers. If not known at the time of initial APP submittal, the contractor shall include the following statement in their initial APP: “The subcontractors for the following DFOWs/activities are not known at this time, but additional information will be submitted to the APP for acceptance prior to the start of any activities listed”;
(2) Safety responsibilities of subcontractors and suppliers.
f. Training.
(1) Requirements for new hire SOH orientation training at the time of initial hire of each new employee.
(2) Requirements for mandatory training and certifications that are applicable to this project (e.g. explosive actuated tools, confined space entry, crane operator, underwater diver, vehicle operator, HAZWOPER training and certification, PPE, etc.) and any requirements for periodic retraining/recertification.
(3) Procedures for periodic safety and health training for supervisors and employees.
(4) Requirements for emergency response training.
g. Safety and Health Inspections.
(1) Specific assignment of responsibilities for a minimum daily jobsite SOH inspection during periods of work activity: Who will conduct (e.g., SSHO, PM, QC, supervisors, employees – depends on level of technical proficiency needed to perform said inspections), proof of inspector’s training/qualifications, when inspections will be conducted, procedures for documentation, deficiency tracking system, and follow-up procedures;
A-5
(2) Any external inspections/certifications that may be required (e.g. USCG).
h. Mishap Reporting and Investigation. The Contractor shall identify means to provide the following:
(1) Exposure data (man-hours worked);
(2) Mishap reports, investigations, and documentation. Report all accidents per the requirements covered in Section 01.D. Mishaps shall be reported as soon as possible but not more than 24 hours afterwards to the KO/COR. The contractor shall report, thoroughly investigate, and analyze all mishaps occurring incidentally to an operation, project or facility for which this manual is applicable. Implement corrective actions as soon as reasonably possible and provide notice to the KO/COR when corrective actions are completed;
i. Plans, Programs and Procedures, required by this manual. Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable SOH risks and associated compliance plans.
(1) Include a project-specific compliance plan, as applicable to the work being performed, and as identified below. The plans shall incorporate project-wide procedures to control hazards to which the employees of all project employers may be exposed.
(2) These procedures shall be coordinated with all project employers and shall include project-specific, project-wide emergency response and evacuation procedures, PPE requirements, recordkeeping and reporting requirements, and training requirements.
(3) The plans shall be prepared prior to the start of any work activities on the job site (as much as the information can be known at that point in time). The plans shall be updated throughout the life of the project to include changes in personnel, equipment, conditions, etc. Additional revisions shall be incorporated as necessary to reflect changing site conditions, construction methods, personnel roles and responsibilities and construction schedules.
(4) No activity (DFOW) shall be started on site until the APP is revised and submitted to the GDA for acceptance, with the site-specific plans, programs and procedures required to complete the project. Using the EM 385-1-1 as a guide, plans, programs, procedures (assessments and evaluations) may include but not be limited to:
Fatigue Management Plan (01.A.20);
Emergency Plans (01.E);
Site Sanitation/Housekeeping Plan (02.B);
A-6
Medical Support Agreement (03.A.01; 03.A.03);
Blood-Borne Pathogen Program (03.A.05);
Exposure Control Plan (03.A.05);
Automatic External Defibrillator (AED) Program (03.B.04);
Site Layout Plan (04.A);
Access/Haul Road Plan (04.B);
Hearing Conservation Program (05.C);
Respiratory Protection Plan (05.G);
Health Hazard Control Program (06.A);
Hazard Communication Program (06.B.01);
Process Safety Management Program (06.B.04);
Lead Compliance Plan (06.C.02 & specifications);
Asbestos Abatement Plan (06.C.03 & specifications);
Radiation Safety Program (06.F);
Abrasive Blasting Procedures (06.I.01);
Heat Stress Monitoring Plan (HSMP) (06.J.02);
Cold Stress Monitoring Plan (CSMP) (06.J.04)
Indoor Air Quality Management (06.L);
Mold Remediation Plan (06.L.04);
Chromium (VI) Exposure Evaluation (06.M);
Crystalline Silica Evaluation (06.N.02);
Lighting Plan for Night Operations (07.A.06);
Traffic Control Plan (08.C.05);
A-7
Fire Prevention Plan (09.A.01);
Wild Land Fire Management Plan (09.L);
Arc Flash Hazard Analysis (11.B);
Assured Equipment Grounding Control Program (AEGCP) (11.D.05, Appendix E);
Hazardous Energy Control Program & Procedures (12.A.01);
Standard Pre-Lift Plan – Load Handling Equipment (16.A.03);
Critical Lift Plan – Load Handling Equipment (16.H);
Naval Architectural Analysis – Load Handling Equipment (Floating) (16.L);
Floating Plant Inspection and Certification (19.A.01);
Severe Weather Plan for Marine Activities (19.A.03);
Emergency Plan for Marine Activities (19.A.04);
Man Overboard/Abandon Ship Procedures (19.A.04);
Float Plan for Launches, Motorboats, and Skiffs (19.F.04);
Fall Protection and Prevention Plan (21.D);
Demolition/Renovation Plan (to include engineering survey) (23.A);
Rope Access Work Plan (24.H);
Excavation/Trenching Plan (25.A.01);
Fire Prevention and Protection Plan for Underground Construction (26.D.01);
Compressed Air Work Plan for Underground Construction (26.I.01);
Erection and Removal Plan for Formwork and Shoring (27.C);
Precast Concrete Plan (27.D.01);
Lift-Slab Plans (27.E);
Masonry Bracing Plan (27.F.01);
A-8
Steel Erection Plan (28.B);
Explosives Safety Site Plan (ESSP) (29.A);
Blasting Plan (29.A; 26.J);
Dive Operations Plan (30.A.14, 30.A.16);
Safe Practices Manual for Diving Activities (30.A.15)
Emergency Management Plan for Diving (30.A.18)
Tree Felling and Maintenance Program (31.A.01);
Aircraft/Airfield Construction Safety & Phasing Plan (CSPP) (32.A.02);
Aircraft/Airfield Safety Plan Compliance Document (SPCD) (32.A.02);
Site Safety and Health Plan for HTRW (33.B);
Confined Space Entry Procedures (34.A.05);
Confined Space Program (34.A.06).
j. Risk Management Process (AHAs). Detailed project-specific hazards and controls shall be provided by AHAs for each activity (DFOW). No work will begin on an activity (DFOW) until the initial AHA has been accepted by the GDA addressing the project-specific hazards. > See Section 01.A.14 and 01.A.15.
Note: USACE uses the Activity Hazard Analysis (AHA) as part of a total risk management process. Contractors and other individual employer’s may use the AHAs or their own version [Job Safety Analyses (JSAs), Job Hazard Analyses (JHAs), or similar Risk Management assessment tools]. These documents are considered equivalent to, and acceptable substitutes for, the USACE’s AHA provided the data collected is the same as that required by the AHA.
(1) The AHA defines the work sequence, anticipated hazards, conditions, equipment, materials, personnel and the control measures to be implemented to eliminate or reduce each hazard to an acceptable level of risk, and the Risk Assessment Code for each step.
(2) Once this process has occurred, an overall RAC shall be assigned to the activity, based on the highest RAC assigned to an individual step.
A-9
(3) Acceptance of risk. The residual risk is that which remains after controls have been applied. This residual risk must be communicated to the proper authority for acceptance in order to proceed with the activity.
(4) Before beginning each work activity/DFOW, the Contractor performing that work activity shall prepare the initial AHA, which will include a RAC for that activity.
(5) No work will begin on the activity until the initial AHA has been accepted by the GDA addressing the activity-specific hazards.
(6) AHA’s are intended to be created by the contractor field crews/workers performing the work, with the assistance of others (SSHO, QC, Superintendent, etc) as needed. They are living documents and are intended to be created in the field and updated (by the workers) as needed.
(7) The AHA shall be reviewed and modified as necessary to address changing site conditions, operations, or change of CP(s)/QP(s).
(a) If a new CP/QP (not on the original list) is added, the list shall be updated (an administrative action not requiring an updated AHA). The new person shall acknowledge in writing that he or she has reviewed the AHA and is familiar with current site safety issues.
(b) If the initial RAC increases due to a change made to the AHA by the workers, the AHA shall be resubmitted to GDA for acceptance prior to work proceeding.
(c) Changes to or updates of an AHA that do not increase the RAC are not required to be resubmitted for acceptance by the GDA.
(8) Workers/crews shall have in their possession the current AHA that reflects current site conditions, personnel, equipment, control measures, etc while the work is being performed.
(9) The AHA shall be used by the contractor and USACE personnel to assure work is being performed consistent with the AHA. In the event that the work is not being conducted in a safe manner, the contractor and/or the USACE shall stop the unsafe work being conducted until it is in compliance with this manual, APP and the AHA or the APP/ AHA is revised and accepted by the GDA, if necessary. > See Section 01.A.14.
(10) Once the activity has been completed, the AHA shall be available and kept on file on site for the length of the contract.
A-10
k. Abbreviated APP for Limited-Scope Service, Supply and R&D Contracts. If service, supply and R&D contracts with limited-scopes are awarded, the contractor may submit an abbreviated APP in lieu of a full APP. The abbreviated APP shall address the following areas at a minimum. If other areas of the EM 385-1-1 are pertinent to the contract, the contractor must assure these areas are addressed as well. The non-mandatory Abbreviated APP Form, Form A-01 (or similar) may be used to insure each area of required information has been provided.
(1) Title, signature, and phone number of the plan preparer.
(2) Background Information to include:
(a) Contractor;
(b) Contract number;
(c) Project name;
(d) Brief project description, Note: The project description shall provide a means to evaluate the work being done (see AHA requirements in 01.A.14), associated hazards involved and a RAC assigned to each. The overall RAC for the activity must be determined (based on highest task RAC) and accepted at the appropriate level in order for work to proceed.
(e) Description of work to be performed, and
(f) Location of work being performed, to include a map.
(3) Statement of Safety and Health Policy detailing their commitment to providing a safe and healthful workplace for all employees.
(4) Responsibilities and Lines of Authorities – to include a statement of the employer’s ultimate responsibility for the implementation of his SOH program; Identification and accountability of personnel responsible for safety at all levels to include designated site safety and health officer (SSHO) and associated qualifications. The District SOHO will be asked to review the qualifications for acceptance.
(5) Training - new hire SOH orientation training at the time of initial hire of each new employee and any periodic retraining/recertification requirements.
(6) Procedures for job site inspections - assignment of responsibilities and frequency.
A-11
(7) Procedures for reporting man-hours worked and reporting and investigating any mishaps required by Section 01.D.
(8) Emergency Planning. Employees working alone shall be provided an effective means of emergency communication. This may be cellular phone, two-way radio or other acceptable means. The selected means of communication must be readily available and must be in working condition.
(9) Drinking Water provisions, toilet and washing facilities.
(10) First Aid and CPR training (at least two employees on each shift shall be qualified/certified to administer first aid and CPR) and provision of first aid kits (types/size).
(11) Personal Protective Equipment (PPE).
(a) Work Clothing - Minimum Requirements. Employees shall wear clothing suitable for the weather however minimum requirements for work shall be short-sleeve shirt, long pants (excessively long or baggy pants are prohibited) and leather work shoes. If analysis determines that safety-toed (or other protective) footwear is necessary (i.e., mowing, weedeating, chainsaw use, etc), they shall be worn.
(b) Eye and Face Protection. Eye and face protection shall be worn as determined by an analysis of the operations being performed, however, all involved in chainsaw use, chipping, stump grinding, pruning operations, grass mowing, weedeating and blowing operations shall be provided safety eyewear (Z87.1) as a minimum.
(c) Hearing Protection. Hearing protection must be worn by all those exposed to high noise activities (to include grass mowing and trimming, chainsaw operations, tree chipping, stump grinding and pruning).
(d) Head Protection. Hard hats shall comply with ANSI Z89.1 and shall be worn by all workers when a head hazard exists, per Section 05.D.
(e) High Visibility Apparel shall comply with ANSI/ISEA 107, Class 2 requirements at a minimum and shall be worn by all workers exposed to vehicular or equipment traffic.
(f) Protective Leg chaps shall be worn by all chainsaw operators.
(g) Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.
(h) If work is being performed around water and drowning is a hazard, PFDs must be provided and worn as appropriate.
A-12
(12) Machine Guards and safety devices. Power tools/equipment must have appropriate guards and safety devices in place and operational.
(13) Hazardous Substances. When any hazardous substances are procured, used, stored or disposed, a Hazard Communication Program must be in place and MSDSs (SDSs) shall be available at the worksite. Employees shall have received training in hazardous substances being used. When the eyes or body of any person may be exposed to corrosives, irritants or toxic chemicals, suitable facilities for quick drenching or flushing of the eyes and body shall be provided within 10 seconds of the worksite.
(14) Traffic control shall be accomplished in accordance with DOT’s MUTCD.
(15) Control of Hazardous Energy (Lockout/Tagout). Before an employee performs any servicing or maintenance on any equipment where the unexpected energizing or startup of the equipment could occur, procedures must be in place to ensure adequate control of this energy. > See Section 12.
(16) High hazard activities should not be encountered on these types of jobs. If they are (i.e., driving/operating equipment on slopes, working from/in boats, etc), a determination shall be made by the KO and local SOH Office as to whether an abbreviated APP is applicable. If so, they shall be fully addressed in the APP. AHAs are required on work activities which include high hazard activities.
A-13
THIS PAGE INTENTIONALLY LEFT BLANK
Item Description Yes No N/A
(Qualmed person, corporate safety staff person, owner, company president, regional vice presiden
U.S.Army Corps of Engineers Safety Inspection Checklist
Abbreviated Accident Prevention Plan
Remarks (Any NO or N/A Item) of
U.S.Army Corps of Engineers Safety Inspection Checklist
Remarks (Any NO or N/A item)
Item Description Yes No N/A Remarks (Any NO or N/A Item)
U.S.Army Corps of Engineers Safety Inspection Checklist
1. Signature sheet
a. Includes the name, signature, and title of the Plan Preparer (Qualified person, i.e. corporate safety staff person, QC )
b. Includes the name, signature, and title of the Plan Approver (e.g. owner, company president, regional vice president ) (HTRW activities require approval of a Certified Industrial Hygienist, a Certified Safety Professional may approve the plan for operations involving UST removal where contaminants are known to be petroleum, oils, or lubricants).
c. Includes the name(s), signature(s), and title(s) for Plan Concurrence (provide concurrence of other applicable corporate and project personnel (contractor)) (e.g. Chief of Operations, Corporate Chief of Safety, Corporate Industrial Hygienist, project manager or superintendent, project safety professional, project
QC. )
2. Background information
a. Includes the Contractor Name.
b. Includes the Contract Number.
c. Includes the Project Name.
d. Includes the Brief Project Description.
e. Includes the Location of the Project (map).
f. Includes the Contractor Accident Experience (Copy of OSHA
g. Includes the Listing of Phases of Work and Hazardous Activities Requiring an Activity Hazard Analyses (AHA).
3. Statement of Safety and Health Policy. Includes a copy of the corporate safety policy. (In addition to the corporate policy statement, a copy of the corporate safety program may provide a portion of the information required by the accident prevention
4. Responsibilities and Lines of Authorities
a. Includes the identification and job responsibilities of personnel responsible for safety - at both corporate and project level – including their resumes.
b. Includes the lines of authority.
CESO Form A-02 Sep 13
Remarks (Any NO or N/A item)
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist
Date of Inspection
Location (Plant or Facility) Contract Number
Contractor Name Project Name
Inspector Name (Print) Inspector Signature
This checklist serves as a guide only, it does not replace or eliminate the need to comply with the requirements set forth in Engineering Manual 385-1-1, Safety and Health Requirements Manual, dated XX Sept 2014. The references included in this checklist correspond to the applicable sections of EM 385-1-1.
5. Training
a. Includes the list of subjects to be discussed with employees at safety indoctrination.
b. Includes the list of mandatory training and certifications applicable to this project (e.g., explosive actuated tools, confined space entry, crane operator, diver, vehicle operator, HAZWOPER training and certification, PPE ) and any requirements for periodic retraining / recertification.
c. Includes the identity requirements for emergency response training.
d. Includes the outline requirements (who attends, when given, who will conduct, etc. ) for supervisory and employee safety
6. Safety and Health Inspections
a. Includes the name(s) of individual(s) responsible for conducting safety inspections. (e.g., PM, safety professional, QC, supervisors, employees )
b. Includes proof of inspector's training / qualifications.
c. Indicates when inspections will be conducted.
d. Furnished sample forms upon which inspections will be recorded.
e. Indicates deficiency tracking system and follow-up procedures.
f. Includes the names of competent and / or qualified person(s) and proof of competency / qualification to meet specific OSHA competent / qualified person(s) requirements.
g. Includes any external inspections / certifications which may be required. (e.g., US Coast Guard )
7. Safety and Health Expectations, Incentive Programs, and Compliance
a. Includes the company's written safety program goals, objectives, and accident experience goals.
b. Includes a brief description of the company's safety incentive programs (if any ).
c. Includes the policies and procedures regarding noncompliance with safety requirements (to include disciplinary actions for violation of safety requirements).
d. Includes the written company procedures for holding managers and supervisors accountable for safety.
8. Mishap Reporting
a. The plan identifies how, when, and who shall complete the Exposure data (man-hours worked).
b. The plan identifies how, when, and who shall complete mishap investigations, reports, and logs.
c. The plan identifies how, when, and who shall make immediate notification of major mishaps.
CESO Form A-02 Sep 13
Remarks (Any NO or N/A item)
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist (cont’d)
Date of Inspection
9. Plans (Programs, Procedures) required by the Safety Manual
a. Fatigue Management Plan (01.A.20)
b. Emergency response plans:
(1) Procedures & Test (01.E.01)
(2) Spill Plans (01.E.01, 06.A.02)
(3) Fire Fighting Plan (01.E.01; 19.A)
(4) Posting of Emergency Telephone Numbers (01.E.05)
(5) Man overboard/abandon ship (19.A.04)
(6) Medical Support. Outline on-site medical support and off-site medical arrangements including rescue and medical duties for those employees who are to perform them, and the name(s) of on-site Contractor personnel trained in first aid and CPR. A minimum of two employees shall be certified in CPR and first-aid per shift/site (Section 03.A; 03.D)
c. Plan for prevention of alcohol and drug abuse (01.C.02)
d. Site Sanitation Plan (Section 02.B)
e. Medical Support Plan, (03.A.01; 03.A.06; 03.D)
f. Bloodborne Pathogen Plan (03.A.05)
g. Exposure Control Plan (03.A.05)
h. Site Layout Plan (04.A)
i. Access/Haul road Plan (04.B)
j. Hearing Conservation Program (05.C)
k. Respiratory Protection Plan (05.G)
l. Health Hazard Control Program (06.A)
m. Process Safety Management Plan (06.B.04)
n. Lead Abatement Plan (06.C & Specs)
o. Asbestos Abatement Plan (06.C & Specs)
p. Radiation Safety Program (06.F)
q. Abrasive Blasting Plan (06.I)
r. Heat/Cold Stress Monitoring Plan (06.J)
s. Indoor Air Quality Management Plan (06.L)
t. Mole Remediation Plan (06.L.04)
u. Chromium (VI) Exposure Evaluation (06.M)
v. Crystalline Silica Assessment (06.N)
w. Lighting Evaluation (07.A)
x. Lighting Plan for Night Operations (07.A.09) CESO Form A-02 Sep 13
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist (cont’d)
Date of Inspection
Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans. Using the EM 385-1-1 as a guide, plans may include but not be limited to:
9. Plans (Programs, Procedures) continued.
y. Traffic Control Plan (08.C.05)
z. Fire Prevention Plan (09.A.01)
aa. Wild Land Fire Management Plan (09.L)
bb. Arc Flash Hazard Analysis (11.B)
cc. Assured Equipment Grounding Control Program (AEGCP), (11.D.05, App D)
dd. Hazardous Energy Control Plan, (12.A.01)
ee. Standard Pre-Lift Plan (LHE) (16.A.03, 16.L.15)
ff. Critical Lift Plan – LHE (16.H)
gg. Naval Architectural Analysis (16.L)
hh. Contingency Plan for Severe Weather (19.A.03)
ii. Man Overboard/Abandon Ship (19.A.04)
jj. Float Plan (19.F.04)
kk. Fall Protection Program, (21.D);
ll. Demolition/Renovation Plan (to include engineering survey), (23.A.02)
mm. Rope Access Program, (24.H.02)
nn. Excavation/Trenching Plan, (25.A.01)
oo. Underground construction fire prevention and protection Plan, (26.D.01)
pp. Compressed Air Plan, (26.I.01)
qq. Formwork and Shoring Erection and Removal plan, (27.C)
rr. PreCast Concrete Plan, (27.D) ss Lift. slab plans, (27.E)
tt. Masonry Bracing Plan, (27.F.01)
uu. Steel Erection Plan, (28.B)
vv. Explosives Safety Site Plan (ESSP) (29.A)
ww. Blasting Plan, (29.A; 26.J)
xx. Underwater Dive Operations Plan, (30.A.14, 16, )
yy. Tree Felling/Maintenance Program, (31.A)
zz. Aircraft/Airfield Construction Safety & Phasing Plan, (32.A.02) aaa. Site Safety and Health Plan (HTRW), (33.B) bbb. Confined Space Entry Program, (34.A.06, 07)
10. Risk Management Processes. Detailed project-specific hazards shall be identified and controls provided via Activity Hazard CESO Form A-02 Sep 13
Form A-02 U.S. Army Corps of Engineers
Accident Prevention Plan Checklist (cont’d)
Date of Inspection
Based on a risk assessment of contracted activities and on mandatory OSHA compliance programs, the Contractor shall address all applicable occupational risks and compliance plans. Using the EM 385-1-1 as a guide, plans may include but not be limited to:
Other Remarks:
CESO Form A-02 Sep 13
CONTRACTOR'S NAME
(Address)
DAILY CONTRACTOR QUALITY CONTROL REPORT
Date: ______________ Report No. _____
Contract No. _____________________________
Description and Location of Work: ___________________________________________
Weather: (Clear) (P. Cloudy) (Cloudy); Temperature: ___ Min. ___ Max; ___
Rainfall ______ inches
Contractor/Subcontractors and Area of Responsibility
1. Work Performed Today: (Indicate location and description of work performed. Refer to work performed by prime and/or subcontractors by letter in table above.)
2. Results of Surveillance: (Include satisfactory work completed, or deficiencies with action to be taken.)
3. Tests required by Plans and/or Specifications Performed and Results of tests:
4. Verbal Instructions Received: (List any instructions given by Government personnel on construction deficiencies, retesting required, etc., with action to be taken.)
5. Remarks: (Cover delays and any conflicts in plans, specifications, or instructions.)
6. Safety Inspection: (Report violations noted; corrective instructions given; and corrective actions taken.)
7. Equipment Data: (Indicate items of construction equipment, other than hand tools, at jobsite, and whether or not used.)
CONTRACTOR'S VERIFICATION: The above report is complete and correct and all material and equipment used and work performed during this reporting period are in compliance with the contract plans and specifications except as noted above.
Contractor's Approved Authorized Representative
SMALL BUSINESS SUBCONTRACTING
PLAN
I. IDENTIFICATION DATA:
Company Name:
Address:
Date Prepared: Solicitation Number:
Description:
Estimated Contract Dollar Value:
Our firm has established a policy to afford Small Business concerns (SB), Small Disadvantaged Business concerns (SDB), Women-Owned Small Business concerns (WOSB), Veteran-Owned Small Business concerns (VOSB), Service Disabled Veteran-Owned Small Business concerns (SDVOSB), Historically Black Colleges and Universities/Minority Institutions (HBCU/MI) and HUBZone Small Business (HSB) concerns opportunities to participate in all contracts with the Department of Defense or other entities, both public and private. In most instances, HBCU/MI are not applicable to construction contracts, but will be included throughout this plan with the intent to involve them whenever possible. The following, together with any attachments, is hereby submitted as a Small Business Subcontracting Plan to satisfy the applicable requirements of Public Law 95-507, Public Law 99661, Section 1207, and Public Law 100-180, Section 806.
II. TYPE OF PLAN (circle one)
A. Individual Plan (All elements developed specifically for this contract and applicable for the full term of this contract, including any option periods.)
B. Master Plan (Goals developed for this contract; all other elements standard; must be renewed every three years)
C. Commercial Plan Commercial products/service plan, including goals, covers the offeror’s fiscal year and applies to the entire production of commercial items or delivery of services sold by either the entire company or a portion thereof (e.g., division, plant, or product line); this includes planned subcontracting for both commercial and Government business. In accordance with FAR 19.704(d), “A commercial plan (as defined in FAR 19.701) is the preferred type of subcontracting plan for contractors furnishing commercial items.”(Contractor sells large quantities of off-the-shelf commodities to many Government agencies. Plans/goals negotiated by a lead agency on a company-wide basis rather than for individual contracts. Plan effective only during the year for which it is approved. The contractor must provide a copy of the lead agency approval.)
III. GOALS:
State separate dollar and percentage goals, expressed in terms of percentages of total subcontracting dollars, for the use of Large Business, Small Business, Veteran-Owned Small Business, Service Disabled Veteran-Owned Small Business, HUBZone Small Business, Small Disadvantaged Business, Woman-Owned Small Business, and Historically Black Colleges and Universities/Minority Institutions concerns as subcontractors.