abstract 9-23-09.xls

XLS spreadsheet 2 MB Posted

Attached to
Recovery - Z - Bank Protection, Disposal Area 14B
Solicitation number
W912HN-09-B-0026
Issued by

About this file

Bid Abstract

View the file

Other files

File Type Posted
D-08 SITE PLAN AREA 14B1 STA 0 00 TO 13 75.pdf PDF
amd 0004.pdf PDF
amd 0004 conform.pdf PDF
amd 0003.pdf PDF
amd 0003 conform.pdf PDF
amd 0002 conform.pdf PDF
amd 0002.pdf PDF
amd 0001 conform _2_.pdf PDF
14B_RockRevet_Plans_amd1.pdf PDF
amdt001_09-B-26DisposalArea14B_.pdf PDF
SAS_14BRockRev_Plans.pdf PDF
SPECIFICATIONS.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOTAL 0001-0018

IFB NO: W912HN-09-B-0026BID ABSTRACT
Bid Opening Date: 23 Sep 2009 10:00 a.m. / PROJECT: Disposal Area 14B, Rock Revetment, Jasper County, SCGRANDCOREY
IGECONSTRUCTIONICES-CAROLINASENTERPRISESASHRIDGE, INCWECC, INC
ITEM NOSUPPLIES/SERVICESEST QTYEST QTYEST QTYEST QTYEST QTYEST QTYEST QTYEST QTYITEM NOSUPPLIES/SERVICESU/PTOTALU/PTOTALU/PTOTAL
0001Site 14B-1 Deliver, Stockpile, and Place Armor Stone0001Site 14B-1 Deliver, Stockpile, and Place Armor Stone
0001AADeliver and Stockpile Armor Stone, First 3,480 tons3,480ton$ 50.00$ 174,000.00$ 53.00$ 184,440.00$ 64.92$ 225,921.600001AADeliver and Stockpile Armor Stone, First 3,480 tons$88.60$308,328.00$43.12$150,057.60$86.00$299,280.00
0001ABDeliver and Stockpile Armor Stone, All over 3,480 tons350ton$ 50.00$ 17,500.00$ 53.00$ 18,550.00$ 64.92$ 22,722.000001ABDeliver and Stockpile Armor Stone, All over 3,480 tons$88.60$31,010.00$43.12$15,092.00$86.00$30,100.00
0001BAArmor Stone Template Placement, First 3,480 tons3,480ton$ 59.00$ 205,320.00$ 57.00$ 198,360.00$ 69.91$ 243,286.800001BAArmor Stone Template Placement, First 3,480 tons$20.40$70,992.00$25.00$87,000.00$37.00$128,760.00
0001BBArmor Stone Template Placement, All over 3,480 tons350ton$ 59.00$ 20,650.00$ 57.00$ 19,950.00$ 69.91$ 24,468.500001BBArmor Stone Template Placement, All over 3,480 tons$20.40$7,140.00$1.00$350.00$46.00$16,100.00
0002Site 14B-1 Deliver, Stockpile, and Place Type 1 Riprap0002Site 14B-1 Deliver, Stockpile, and Place Type 1 Riprap$0.00$0.00
0002AADeliver & Stockpile Type 1 Riprap Underlayer, First 780 tons780ton$ 50.00$ 39,000.00$ 47.00$ 36,660.00$ 57.72$ 45,021.600002AADeliver & Stockpile Type 1 Riprap Underlayer, First 780 tons$83.70$65,286.00$38.37$29,928.60$75.00$58,500.00
0002ABDeliver & Stockpile Type 1 Riprap Underlayer, All over 780 tons80ton$ 50.00$ 4,000.00$ 47.00$ 3,760.00$ 57.72$ 4,617.600002ABDeliver & Stockpile Type 1 Riprap Underlayer, All over 780 tons$83.70$6,696.00$38.37$3,069.60$76.00$6,080.00
0002BAType 1 Riprap Template Placement, First 780 tons780ton$ 48.00$ 37,440.00$ 57.00$ 44,460.00$ 69.91$ 54,529.800002BAType 1 Riprap Template Placement, First 780 tons$22.20$17,316.00$35.00$27,300.00$39.00$30,420.00
0002BBType 1 Riprap Template Placement, All over 780 tons80ton$ 48.00$ 3,840.00$ 57.00$ 4,560.00$ 69.91$ 5,592.800002BBType 1 Riprap Template Placement, All over 780 tons$22.20$1,776.00$1.00$80.00$40.00$3,200.00
0003Site 14B-1 Deliver, Stockpile, and Place GADOT #40003Site 14B-1 Deliver, Stockpile, and Place GADOT #4$0.00
0003AADeliver & Stockpile GADOT#4 Bedding Stone, First 550 tons550ton$ 44.00$ 24,200.00$ 33.00$ 18,150.00$ 41.10$ 22,605.000003AADeliver & Stockpile GADOT#4 Bedding Stone, First 550 tons$67.90$37,345.00$28.62$15,741.00$52.00$28,600.00
0003ABDeliver & Stockpile GADOT#4 Bedding Stone, All over 550 tons85ton$ 44.00$ 3,740.00$ 33.00$ 2,805.00$ 41.10$ 3,493.500003ABDeliver & Stockpile GADOT#4 Bedding Stone, All over 550 tons$67.90$5,771.50$28.62$2,432.70$52.00$4,420.00
0003BAGADOT #4 Bedding Stone Template Placement, First 550 tons550ton$ 31.00$ 17,050.00$ 57.00$ 31,350.00$ 69.91$ 38,450.500003BAGADOT #4 Bedding Stone Template Placement, First 550 tons$20.70$11,385.00$35.00$19,250.00$31.00$17,050.00
0003BBGADOT #4 Bedding Stone Template Placement, All over 550 tons85ton$ 31.00$ 2,635.00$ 57.00$ 4,845.00$ 69.91$ 5,942.350003BBGADOT #4 Bedding Stone Template Placement, All over 550 tons$20.70$1,759.50$1.00$85.00$52.00$4,420.00
0004Site 14B-1 Deliver, Stockpile, and Place GADOT #4 Top of Slope0004Site 14B-1 Deliver, Stockpile, and Place GADOT #4 Top of Slope$0.00
0004AADeliver & Stockpile GADOT #4 Filter Stone, First 150 tons150ton$ 44.00$ 6,600.00$ 33.00$ 4,950.00$ 41.10$ 6,165.000004AADeliver & Stockpile GADOT #4 Filter Stone, First 150 tons$77.90$11,685.00$28.62$4,293.00$52.00$7,800.00
0004ABDelivery & Stockpile GADOT #4 Filter Stone, All over 150 tons15ton$ 44.00$ 660.00$ 33.00$ 495.00$ 41.10$ 616.500004ABDelivery & Stockpile GADOT #4 Filter Stone, All over 150 tons$77.90$1,168.50$28.62$429.30$52.00$780.00
0004BAGADOT #4 Filter Stone Template Placement, First 150 tons150ton$ 31.00$ 4,650.00$ 57.00$ 8,550.00$ 69.91$ 10,486.500004BAGADOT #4 Filter Stone Template Placement, First 150 tons$20.70$3,105.00$35.00$5,250.00$31.00$4,650.00
0004BBGADOT #3 Filter Stone Template Placement, All over 150 tons15ton$ 31.00$ 465.00$ 57.00$ 855.00$ 69.91$ 1,048.650004BBGADOT #3 Filter Stone Template Placement, All over 150 tons$20.70$310.50$1.00$15.00$31.00$465.00
0005Site 14B-1 Install SCDOT Type A Silt Fencing0005Site 14B-1 Install SCDOT Type A Silt Fencing$0.00
0005AASilt Fence Type A, First 300 linear feet300LF$ 3.30$ 990.00$ 6.00$ 1,800.00$ 1.38$ 414.000005AASilt Fence Type A, First 300 linear feet$2.75$825.00$2.00$600.00$2.00$600.00
0005ABSilt Fence Type A, All over 300 linear feet45LF$ 3.40$ 153.00$ 6.00$ 270.00$ 1.38$ 62.100005ABSilt Fence Type A, All over 300 linear feet$2.75$123.75$2.00$90.00$2.00$90.00
0006Grassing Site 14B-11AC$ 2,535.00$ 2,535.00$ 2,660.00$ 2,660.00$ 1,154.50$ 1,154.500006Grassing Site 14B-1$4,750.00$4,750.00$1,450.00$1,450.00$1,947.00$1,947.00
0007Agricultural Lime Site 14B-13tz$ 110.00$ 330.00$ 320.00$ 960.00$ 785.00$ 2,355.000007Agricultural Lime Site 14B-1$55.00$165.00$65.00$195.00$87.00$261.00
0008Fertilizer, Nitrogen Site 14B-10.1ton$ 830.00$ 83.00$ 8,600.00$ 860.00$ 923.50$ 92.350008Fertilizer, Nitrogen Site 14B-1$770.00$77.00$380.00$38.00$818.00$81.80
0009Fertilizer, Mixed Grade Site 14B-10.6ton$ 740.00$ 444.00$ 1,600.00$ 960.00$ 808.00$ 484.800009Fertilizer, Mixed Grade Site 14B-1$880.00$528.00$500.00$300.00$818.00$490.80
0010Site 14B-2 Deliver, Stockpile, and Place Armor Stone0010Site 14B-2 Deliver, Stockpile, and Place Armor Stone
0010AADeliver & Stockpile Armor Stone, First 86,240 tons86,240ton$ 50.00$ 4,312,000.00$ 53.00$ 4,570,720.00$ 64.92$ 5,598,700.800010AADeliver & Stockpile Armor Stone, First 86,240 tons$88.60$7,640,864.00$42.00$3,622,080.00$81.00$6,985,440.00
0010ABDeliver & Stockpile Armor Stone, All over 86,240 tons8,630ton$ 50.00$ 431,500.00$ 53.00$ 457,390.00$ 64.92$ 560,259.600010ABDeliver & Stockpile Armor Stone, All over 86,240 tons$88.60$764,618.00$42.00$362,460.00$81.00$699,030.00
0010BAArmor Stone Template Placement, First 86,240 tons86,240ton$ 64.00$ 5,519,360.00$ 57.00$ 4,915,680.00$ 69.91$ 6,029,038.400010BAArmor Stone Template Placement, First 86,240 tons$20.40$1,759,296.00$24.00$2,069,760.00$36.00$3,104,640.00
0010BBArmor Stone Template Placement, All over 86,240 tons8,630ton$ 64.00$ 552,320.00$ 57.00$ 491,910.00$ 69.91$ 603,323.300010BBArmor Stone Template Placement, All over 86,240 tons$20.40$176,052.00$0.00$0.00$36.00$310,680.00
0011Site 14B-2 Deliver, Stockpile, and Place Type 1 Riprap0011Site 14B-2 Deliver, Stockpile, and Place Type 1 Riprap
0011AADeliver & Stockpile Type 1 Riprap Underlayer, First 19,340 tons19,340ton$ 50.00$ 967,000.00$ 47.00$ 908,980.00$ 57.72$ 1,116,304.800011AADeliver & Stockpile Type 1 Riprap Underlayer, First 19,340 tons$83.70$1,618,758.00$38.37$742,075.80$69.00$1,334,460.00
0011ABDeliver & Stockpile Type 1 Riprap Underlayer, All over 19,340 tons1,940ton$ 50.00$ 97,000.00$ 47.00$ 91,180.00$ 57.72$ 111,976.800011ABDeliver & Stockpile Type 1 Riprap Underlayer, All over 19,340 tons$83.70$162,378.00$38.37$74,437.80$69.00$133,860.00
0011BAType 1 Riprap Template Placement, First 19,340 tons19,340ton$ 53.00$ 1,025,020.00$ 57.00$ 1,102,380.00$ 69.91$ 1,352,059.400011BAType 1 Riprap Template Placement, First 19,340 tons$22.20$429,348.00$25.00$483,500.00$34.00$657,560.00
0011BBType 1 Riprap Template Placement, All over 19,340 tons1,940ton$ 53.00$ 102,820.00$ 57.00$ 110,580.00$ 69.91$ 135,625.400011BBType 1 Riprap Template Placement, All over 19,340 tons$22.20$43,068.00$25.00$48,500.00$34.00$65,960.00
0012Site 14B-2 Deliver, Stockpile, and Place GADOT #40012Site 14B-2 Deliver, Stockpile, and Place GADOT #4$0.00
0012AADeliver & Stockpile GADOT #4 Bedding Stone, First 16,170 tons16,170ton$ 44.00$ 711,480.00$ 33.00$ 533,610.00$ 41.10$ 664,587.000012AADeliver & Stockpile GADOT #4 Bedding Stone, First 16,170 tons$67.90$1,097,943.00$27.62$446,615.40$51.00$824,670.00
0012ABDeliver & Stockpile GADOT #4 Bedding Stone, All over 16,170 tons2,430ton$ 44.00$ 106,920.00$ 33.00$ 80,190.00$ 41.10$ 99,873.000012ABDeliver & Stockpile GADOT #4 Bedding Stone, All over 16,170 tons$67.90$164,997.00$27.62$67,116.60$51.00$123,930.00
0012BAGADOT #4 Bedding Stone Template Placement, First 16,170 tons16,170ton$ 37.00$ 598,290.00$ 57.00$ 921,690.00$ 69.91$ 1,130,444.700012BAGADOT #4 Bedding Stone Template Placement, First 16,170 tons$20.70$334,719.00$25.00$404,250.00$30.00$485,100.00
0012BBGADOT #4 Bedding Stone Template Placement, All over 16,170 tons2,430ton$ 37.00$ 89,910.00$ 57.00$ 138,510.00$ 69.91$ 169,881.300012BBGADOT #4 Bedding Stone Template Placement, All over 16,170 tons$20.70$50,301.00$1.00$2,430.00$30.00$72,900.00
0013Site 14B-2 Deliver, Stockpile, and Place GADOT #4 Top of Slope0013Site 14B-2 Deliver, Stockpile, and Place GADOT #4 Top of Slope
0013AADeliver & Stockpile GADOT #4 Filter Stone, First 4,070 tons4,070ton$ 44.00$ 179,080.00$ 33.00$ 134,310.00$ 41.10$ 167,277.000013AADeliver & Stockpile GADOT #4 Filter Stone, First 4,070 tons$77.90$317,053.00$27.62$112,413.40$54.00$219,780.00
0013ABDeliver & Stockpile GADOT #4 Filter Stone, All over 4,070 tons410ton$ 44.00$ 18,040.00$ 33.00$ 13,530.00$ 41.10$ 16,851.000013ABDeliver & Stockpile GADOT #4 Filter Stone, All over 4,070 tons$77.90$31,939.00$28.62$11,734.20$52.00$21,320.00
0013BATemplate Placement GADOT #4 Filter Stone, First 4,070 tons4,070ton$ 37.00$ 150,590.00$ 57.00$ 231,990.00$ 69.91$ 284,533.700013BATemplate Placement GADOT #4 Filter Stone, First 4,070 tons$20.70$84,249.00$35.00$142,450.00$43.00$175,010.00
0013BBTemplate Placement GADOT #4 Filter Stone, All over 4,070 tons410ton$ 37.00$ 15,170.00$ 57.00$ 23,370.00$ 69.91$ 28,663.100013BBTemplate Placement GADOT #4 Filter Stone, All over 4,070 tons$20.70$8,487.00$1.00$410.00$31.00$12,710.00
0014Site 14B-2 Install SC DOT Silt Fencing0014Site 14B-2 Install SC DOT Silt Fencing
0014AASilt Fence, First 6,500 linear feet6,500LF$ 3.30$ 21,450.00$ 3.00$ 19,500.00$ 1.38$ 8,970.000014AASilt Fence, First 6,500 linear feet$2.75$17,875.00$2.00$13,000.00$2.00$13,000.00
0014ABSilt Fence, All over 6,500 linear feet975LF$ 3.40$ 3,315.00$ 3.00$ 2,925.00$ 1.38$ 1,345.500014ABSilt Fence, All over 6,500 linear feet$2.75$2,681.25$2.00$1,950.00$2.00$1,950.00
0015Grassing Site 14B-212AC$ 2,535.00$ 30,420.00$ 1,474.00$ 17,688.00$ 1,154.50$ 13,854.000015Grassing Site 14B-2$4,750.00$57,000.00$1,450.00$17,400.00$1,620.00$19,440.00
0016Agricultural Lime Site 14B-236ton$ 110.00$ 3,960.00$ 86.00$ 3,096.00$ 785.00$ 28,260.000016Agricultural Lime Site 14B-2$65.00$2,340.00$65.00$2,340.00$87.00$3,132.00
0017Fertilizer, Nitrogen Site 14B-21.2ton$ 830.00$ 996.00$ 800.00$ 960.00$ 923.50$ 1,108.200017Fertilizer, Nitrogen Site 14B-2$380.00$456.00$380.00$456.00$818.00$981.60
0018Fertilizer, Mixed Grade Site 14B-27.2ton$ 740.00$ 5,328.00$ 800.00$ 5,760.00$ 785.00$ 5,652.000018Fertilizer, Mixed Grade Site 14B-2$500.00$3,600.00$500.00$3,600.00$818.00$5,889.60
TOTAL$ 15,508,254.00$ 15,366,199.00$ 18,848,120.45$ 15,355,565.00$ 8,992,026.00$15,915,538.80
Difference between IGE and bidder-0.92%21.54%-0.98%-42.02%2.63%