QUESTIONS_AND_ANSWERS_SET_10.doc
DOC document 24 KB Posted
- Attached to
- Truck Inspection Station
- Solicitation number
- W912GY18R0015
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QUESTIONS_AND_ANSWERS_TRUCK_INSPECTION_FACILITY_SET_9.doc | DOC document | |
| Grading-2018-05-09(2_trucks).pdf | ||
| W912GY18R00150002.pdf | ||
| QUESTIONS_AND_ANSWERS_SET_8_REVISED.doc | DOC document | |
| Grading-2018-05-07(2_trucks).pdf | ||
| Questions_and_Answers_Set_8.pdf | ||
| W912GY18R00150001.pdf | ||
| Questions_and_Answers_Set_7.doc | DOC document | |
| Site_Visit_Sign_Sheet.pdf | ||
| Questions_and_Answers_3-6.doc | DOC document | |
| Questions_and_Answers_Set_2.doc | DOC document | |
| Questions_and_Answers_Set_1.doc | DOC document | |
| Drawings_Pass_&_ID_-_2017-10-05_(2_trucks).pdf | ||
| W912GY18R0015.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS AND ANSWERS SET 10
Q&A set number 1 question 6:
6. What is the source of power and will this be the responsibility of the contractor to bring power to the facility?
ANSWER: Contractor needs to supply own power.
1. There is no 120/240 power wiring in the in ground pull box near the new guard shack location. Are we to set the relocated guard shack transformer adjacent to the existing Building 106 transformer or are we to set the relocated transformer adjacent to the guard shack? For clarification purposes Sierra Plumas usually installs the wiring and makes the final connections to the distribution (utility) side of the transformer. Will this be the case for this job?
ANSWER: Yes, the power supply will be provided.