QUESTIONS_AND_ANSWERS_SET_10.doc

DOC document 24 KB Posted

Attached to
Truck Inspection Station
Solicitation number
W912GY18R0015
Issued by

View the file

Other files

File Type Posted
QUESTIONS_AND_ANSWERS_TRUCK_INSPECTION_FACILITY_SET_9.doc DOC document
Grading-2018-05-09(2_trucks).pdf PDF
W912GY18R00150002.pdf PDF
QUESTIONS_AND_ANSWERS_SET_8_REVISED.doc DOC document
Grading-2018-05-07(2_trucks).pdf PDF
Questions_and_Answers_Set_8.pdf PDF
W912GY18R00150001.pdf PDF
Questions_and_Answers_Set_7.doc DOC document
Site_Visit_Sign_Sheet.pdf PDF
Questions_and_Answers_3-6.doc DOC document
Questions_and_Answers_Set_2.doc DOC document
Questions_and_Answers_Set_1.doc DOC document
Drawings_Pass_&_ID_-_2017-10-05_(2_trucks).pdf PDF
W912GY18R0015.pdf PDF
Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS SET 10

Q&A set number 1 question 6:

6. What is the source of power and will this be the responsibility of the contractor to bring power to the facility?

ANSWER: Contractor needs to supply own power.

1. There is no 120/240 power wiring in the in ground pull box near the new guard shack location. Are we to set the relocated guard shack transformer adjacent to the existing Building 106 transformer or are we to set the relocated transformer adjacent to the guard shack? For clarification purposes Sierra Plumas usually installs the wiring and makes the final connections to the distribution (utility) side of the transformer. Will this be the case for this job?

ANSWER: Yes, the power supply will be provided.