This is a contract modification document for solicitation number W912GB23R0044 from the Department of the Army European Command. The modification updates the table of contents and attachments for a project to construct the Hassi Ehel Ahmed Bichna School in Mauritania. It adds a new pre-qualification questionnaire as attachment 16 and extends the response deadline from August 8, 2023 to August 28, 2023. The opportunity is for the construction of a new school facility in Mauritania to support educational services for local communities. Interested offerors must submit responses by the new deadline of August 28, 2023.

View the file

Other files

File Type Posted
B.08.03 Att 18 ProjNet Inquiry Report.pdf PDF
B.08.03 W912GB23R0044_0002 Conformed_Hassi Ehel Ahmed Bichna School.pdf PDF
B.08.03 W912GB23R0044_0002 Modifications Document_Hassi Ehel Ahmed Bichna School.pdf PDF
B.08.03 Att 17 Commitment Letters.docx DOCX document
B.08.03 W912GB23R0044_0001 Conformed_Hassi Ehel Ahmed Bichna School.pdf PDF
B.08.03 Att 16_PPQ.pdf PDF
B.08.02 Att 2_Conceptual Site Plan NEW.pdf PDF
B.08.02 W912GB23R0044_Hassi Ehel Ahmed Bichna School.pdf PDF
B.08.02 Att 8_TAG13 The Design of VIP Latrines.pdf PDF
B.08.02 Att 1_Project Location Map.pdf PDF
B.08.02 Att 4_Existing Conditions Photographs.pdf PDF
B.08.02 Att 14 Bank Letter of Assurance Sample.docx DOCX document
B.08.02 Att 15 Bank Letter of Guarantee Sample.docx DOCX document
B.08.02 Att 9 Price Schedule.docx DOCX document
B.08.02 Att 11 Site Visit Attendee Worksheet.xlsx XLSX spreadsheet
B.08.02 Att 13 Specs Binder IAF-23-0009.pdf PDF
B.08.02 Att 12 SOFA Agreement.pdf PDF
B.08.02 Att 5_Construction Drawings (Previous contract for reference only).pdf PDF
B.08.02 _Statement of Work (SOW) 27APR23.pdf PDF
B.08.02 Att 3_Dedication Plaque.pdf PDF
B.08.02 Att 10 Price and Payment Procedures.docx DOCX document
B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM.pdf PDF
B.08.02 Att 7_Swing Gate.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IAF-23-0009

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Add B.08.02 Att 16_PPQ based on feedback from ProjNet.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jul-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912GB23R0044

X 9B. DATED (SEE ITEM 11)

25-Jul-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jul-2023

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

KONRAD ADENAUER RING 39

D-65187 WIESBADEN GERMANY

WIESBADEN 65187

W912GB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912GB23R0044

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 01 10 - TABLE OF CONTENTS

The Table of Contents has changed from:

Section 00 10 00 – Price Schedule Section 00 21 00 – Instructions to Offerors Section 00 22 00 – Evaluation Factors for Award Section 00 70 00 – Conditions of the Contract Section 00 73 00 – Supplementary Conditions

ATTACHMENTS (Incorporated herein by reference)

1. B.08.02 _Statement of Work (SOW) 27APR23

2. B.08.02 Att 1_Project Location Map

3. B.08.02 Att 2_Conceptual Site Plan NEW

4. B.08.02 Att 3_Dedication Plaque

5. B.08.02 Att 4_Existing Conditions Photographs

6. B.08.02 Att 5_Construction Drawings (Previous contract for reference only)

7. B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM

8. B.08.02 Att 7_Swing Gate

9. B.08.02 Att 8_TAG13 The Design of VIP Latrines

10. B.08.02 Att 9 Price Schedule

11. B.08.02 Att 10 Price and Payment Procedures

12. B.08.02 Att 11 Site Visit Attendee Worksheet

13. B.08.02 Att 12 SOFA Agreement

14. B.08.02 Att 13 Specs Binder IAF-23-0009

15. B.08.02 Att 14 Bank Letter of Assurance Sample

16. B.08.02 Att 15 Bank Letter of Guarantee Sample to:

Section 00 10 00 – Price Schedule Section 00 21 00 – Instructions to Offerors Section 00 22 00 – Evaluation Factors for Award Section 00 70 00 – Conditions of the Contract Section 00 73 00 – Supplementary Conditions

ATTACHMENTS (Incorporated herein by reference)

17. B.08.02 _Statement of Work (SOW) 27APR23

18. B.08.02 Att 1_Project Location Map

19. B.08.02 Att 2_Conceptual Site Plan NEW

20. B.08.02 Att 3_Dedication Plaque

21. B.08.02 Att 4_Existing Conditions Photographs

22. B.08.02 Att 5_Construction Drawings (Previous contract for reference only)

23. B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM

24. B.08.02 Att 7_Swing Gate

25. B.08.02 Att 8_TAG13 The Design of VIP Latrines

26. B.08.02 Att 9 Price Schedule

27. B.08.02 Att 10 Price and Payment Procedures

W912GB23R0044

28. B.08.02 Att 11 Site Visit Attendee Worksheet

29. B.08.02 Att 12 SOFA Agreement

30. B.08.02 Att 13 Specs Binder IAF-23-0009

31. B.08.02 Att 14 Bank Letter of Assurance Sample

32. B.08.02 Att 15 Bank Letter of Guarantee Sample

33. B.08.02 Att 16_PPQ based on feedback from ProjNet.

The following have been modified:

TABLE OF CONTENTS

Section 00 10 00 – Price Schedule Section 00 21 00 – Instructions to Offerors Section 00 22 00 – Evaluation Factors for Award Section 00 70 00 – Conditions of the Contract Section 00 73 00 – Supplementary Conditions

ATTACHMENTS (Incorporated herein by reference)

34. B.08.02 _Statement of Work (SOW) 27APR23

35. B.08.02 Att 1_Project Location Map

36. B.08.02 Att 2_Conceptual Site Plan NEW

37. B.08.02 Att 3_Dedication Plaque

38. B.08.02 Att 4_Existing Conditions Photographs

39. B.08.02 Att 5_Construction Drawings (Previous contract for reference only)

40. B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM

41. B.08.02 Att 7_Swing Gate

42. B.08.02 Att 8_TAG13 The Design of VIP Latrines

43. B.08.02 Att 9 Price Schedule

44. B.08.02 Att 10 Price and Payment Procedures

45. B.08.02 Att 11 Site Visit Attendee Worksheet

46. B.08.02 Att 12 SOFA Agreement

47. B.08.02 Att 13 Specs Binder IAF-23-0009

48. B.08.02 Att 14 Bank Letter of Assurance Sample

49. B.08.02 Att 15 Bank Letter of Guarantee Sample

50. B.08.02 Att 16_PPQ based on feedback from ProjNet.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 08-Aug-2023 10:00 AM to 28-Aug-

2023 10:00 AM.

(End of Summary of Changes)