B.08.03 W912GB23R0044_0001 Modifications Document_Hassi Ehel Ahmed Bichna School.pdf
PDF 366 KB Posted
- Solicitation number
- W912GB23R0044
- Issued by
-
Department of the Army European Command
About this file
This is a contract modification document for solicitation number W912GB23R0044 from the Department of the Army European Command. The modification updates the table of contents and attachments for a project to construct the Hassi Ehel Ahmed Bichna School in Mauritania. It adds a new pre-qualification questionnaire as attachment 16 and extends the response deadline from August 8, 2023 to August 28, 2023. The opportunity is for the construction of a new school facility in Mauritania to support educational services for local communities. Interested offerors must submit responses by the new deadline of August 28, 2023.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IAF-23-0009
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Add B.08.02 Att 16_PPQ based on feedback from ProjNet.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 27-Jul-2023
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912GB23R0044
X 9B. DATED (SEE ITEM 11)
25-Jul-2023
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
27-Jul-2023
CODE
CONTRACTING DIVISION
US ARMY CORPS OF ENGINEERS
KONRAD ADENAUER RING 39
D-65187 WIESBADEN GERMANY
WIESBADEN 65187
W912GB 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912GB23R0044
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 01 10 - TABLE OF CONTENTS
The Table of Contents has changed from:
Section 00 10 00 – Price Schedule Section 00 21 00 – Instructions to Offerors Section 00 22 00 – Evaluation Factors for Award Section 00 70 00 – Conditions of the Contract Section 00 73 00 – Supplementary Conditions
ATTACHMENTS (Incorporated herein by reference)
1. B.08.02 _Statement of Work (SOW) 27APR23
2. B.08.02 Att 1_Project Location Map
3. B.08.02 Att 2_Conceptual Site Plan NEW
4. B.08.02 Att 3_Dedication Plaque
5. B.08.02 Att 4_Existing Conditions Photographs
6. B.08.02 Att 5_Construction Drawings (Previous contract for reference only)
7. B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM
8. B.08.02 Att 7_Swing Gate
9. B.08.02 Att 8_TAG13 The Design of VIP Latrines
10. B.08.02 Att 9 Price Schedule
11. B.08.02 Att 10 Price and Payment Procedures
12. B.08.02 Att 11 Site Visit Attendee Worksheet
13. B.08.02 Att 12 SOFA Agreement
14. B.08.02 Att 13 Specs Binder IAF-23-0009
15. B.08.02 Att 14 Bank Letter of Assurance Sample
16. B.08.02 Att 15 Bank Letter of Guarantee Sample to:
Section 00 10 00 – Price Schedule Section 00 21 00 – Instructions to Offerors Section 00 22 00 – Evaluation Factors for Award Section 00 70 00 – Conditions of the Contract Section 00 73 00 – Supplementary Conditions
ATTACHMENTS (Incorporated herein by reference)
17. B.08.02 _Statement of Work (SOW) 27APR23
18. B.08.02 Att 1_Project Location Map
19. B.08.02 Att 2_Conceptual Site Plan NEW
20. B.08.02 Att 3_Dedication Plaque
21. B.08.02 Att 4_Existing Conditions Photographs
22. B.08.02 Att 5_Construction Drawings (Previous contract for reference only)
23. B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM
24. B.08.02 Att 7_Swing Gate
25. B.08.02 Att 8_TAG13 The Design of VIP Latrines
26. B.08.02 Att 9 Price Schedule
27. B.08.02 Att 10 Price and Payment Procedures
W912GB23R0044
28. B.08.02 Att 11 Site Visit Attendee Worksheet
29. B.08.02 Att 12 SOFA Agreement
30. B.08.02 Att 13 Specs Binder IAF-23-0009
31. B.08.02 Att 14 Bank Letter of Assurance Sample
32. B.08.02 Att 15 Bank Letter of Guarantee Sample
33. B.08.02 Att 16_PPQ based on feedback from ProjNet.
The following have been modified:
TABLE OF CONTENTS
Section 00 10 00 – Price Schedule Section 00 21 00 – Instructions to Offerors Section 00 22 00 – Evaluation Factors for Award Section 00 70 00 – Conditions of the Contract Section 00 73 00 – Supplementary Conditions
ATTACHMENTS (Incorporated herein by reference)
34. B.08.02 _Statement of Work (SOW) 27APR23
35. B.08.02 Att 1_Project Location Map
36. B.08.02 Att 2_Conceptual Site Plan NEW
37. B.08.02 Att 3_Dedication Plaque
38. B.08.02 Att 4_Existing Conditions Photographs
39. B.08.02 Att 5_Construction Drawings (Previous contract for reference only)
40. B.08.02 Att 6_Structural Calculations Guidelines_ AOR AFRICOM
41. B.08.02 Att 7_Swing Gate
42. B.08.02 Att 8_TAG13 The Design of VIP Latrines
43. B.08.02 Att 9 Price Schedule
44. B.08.02 Att 10 Price and Payment Procedures
45. B.08.02 Att 11 Site Visit Attendee Worksheet
46. B.08.02 Att 12 SOFA Agreement
47. B.08.02 Att 13 Specs Binder IAF-23-0009
48. B.08.02 Att 14 Bank Letter of Assurance Sample
49. B.08.02 Att 15 Bank Letter of Guarantee Sample
50. B.08.02 Att 16_PPQ based on feedback from ProjNet.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 08-Aug-2023 10:00 AM to 28-Aug-
2023 10:00 AM.
(End of Summary of Changes)