W912GB21R0013 AMEND 0002 Design-Build of Delnice School Renovation, Croatia
Solicitation number
W912GB21R0013
Issued by

About this file

This solicitation seeks design-build construction services for the renovation of a school in Delnice, Croatia. The work includes partial interior renovation and reconfiguration of existing school areas, as well as new exterior egress stairs. The period of performance is 455 days after contract award. The solicitation was issued by the Department of the Army European Command. Offerors must have the capability to provide design, demolition, construction, and site work services to deliver a fully functional, turnkey school facility. The contractor will be responsible for all design, permitting, construction, and commissioning to complete the project in accordance with the statement of work.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W912GB21R0013

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to provide an updated SOW, section 011010 and AsBuilt Roof Structure draw ings, attachment 13.

Proposal due date remains as 22 February 2021 at 3pm CET.

1. CONTRACT ID CODE PAGE OF PAGES

1 66

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 16-Feb-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912GB21R0013

X 9B. DATED (SEE ITEM 11)

20-Jan-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-Feb-2021

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

KONRAD ADENAUER RING 39

D-65187 WIESBADEN GERMANY

WIESBADEN 65187

W912GB 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

SOW SECTION 011010

US Army Corps of Engineers Europe District

APO AE 09049

co15

Statement of Work Project

Number:

HR-HA-2020-

00039177

Renovation of School

Delnice, Croatia

Prepared by: Design Section

Engineering Branch

08FEB2021

Renovation of School - Delnice, Croatia

01 10 10 Statement of Work

8-Feb-21 Page 4 of 66

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL & PLUMBING

ATTACHMENTS

Attachment # 1 Location Map Attachment # 2 Conceptual Site Plan Attachment # 3 Conceptual Floor Plans Attachment # 4 Sanitary & Storm Sewer As-Builts Attachment # 5 Structural Calculations Guideline Attachment # 6 Dedication Plaque Attachment # 7 Existing Building Photographs Attachment # 8 As-Built Roof Structure

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for renovation of a school in Delnice, Croatia. The GPS coordinates are approximately:

45.39698, 14.803603. (Refer to the attached Location Map.)

The projects includes partial interior renovation and reconfiguration of the existing school.

The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:

a. Clear, grub, and grade the site

b. Provide two additional classrooms, library, and renovated laundry and bathrooms;

c. Construct new exterior exit stairs from the attic;

d. Provide site improvements.

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without mobile furniture) as described in this document. The work includes - but is not limited to - design, demolition, fabrication, delivery, installation, construction, and site work.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the Contractor.

1.2.1 BASE ITEMS AND OPTIONAL ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to Specification

8-Feb-21 Page 5 of 66

Section 01 22 00 PRICE AND PAYMENT PROCEDURES. The Schedule of Items identifies the breakdown between the individual base items and optional items for all work identified in this Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base or Optional Items. Consider all items not specifically identified in the Optional Items as part of the Base Items.

1.3 FUNCTIONAL AREAS

Provide the following functional areas within the facility:

1.3.1 AREA OF RENOVATION - WINGS A AND A1 ATTIC RECONFIGURATION

Room Name Notes Approximate Net

Area (m2)

Wing A

301 OFFICE 13.60

302 OFFICE 13.60

303 CLASSROOM Provide new classroom for 25 students. 41.70 304 CORRIDOR Provide exit door to new exit stairs and maintenance door to unused attic.

13.30

305 CORRIDOR Provide maintenance door to unused attic. 36.90 306 MALE TOILET Provide one sink, one urinal and one toilet. 2.00 307 FEMALE TOIL. Provide one sink and one toilet. 2.00

WING A1

308 TEACHER’S RM Provide maintenance door to unused attic. 41.70

Attic A and A1 area to be reconfigured: 164.70 m2 net.

1.3.2 AREA OF RENOVATION - WING A SECOND FLOOR RECONFIGURATION

Area (m2) 201 CLASSROOM Renovate and convert existing second floor teacher’s office into new classroom.

62.60

202 LIBRARY Renovate and convert existing space of other two offices, restrooms and adjoining small corridor into new library.

61.50

Second floor area to be reconfigured: 124.10 m2 net.

1.3.3 AREA OF RENOVATION - WING D FIRST FLOOR RENOVATION

Area (m2)

110 CHILDREN

BATHROOM

Demolish existing kindergarten children bathroom appliances (5 children WC’s, 1 shower, and 6 sinks) and all interior finishes. Provide 6 children WC’s, 1 shower and 4 sinks.

20.30

First floor Wing D area to be renovated: 20.30 m2 net.

1.3.4 AREA OF RENOVATION - WING C FIRST FLOOR RENOVATION

Area (m2)

8-Feb-21 Page 6 of 66

Demolish existing laundry and restroom (3 washing machines connections, 3 toilet stalls, and 3 sinks) and all interior finishes.

101 Students Toilets

Provide one new restroom with 2 sinks and 2 toilet stalls for students.

6.40

102 Laundry Provide one laundry room with space for linen closet, ironing machine and connections for one washing machine and one dryer.

9.90

103 Employee Toilet

Provide one separate unisex employee restroom with one sink and one toilet.

3.90

First floor Wing C area to be renovated: 20.20 m2 net.

1.4 SUBMITTALS

Designer of Record approval is required for submittals with a “DA” designation.

Government approval is required for submittals with a “G” or “GA” designation.

Submittals having an “FIO” designation are for Contractor Quality Control approval. Submit the following to the Contracting Officer (KO) in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Demolition Plan; G Sequencing Plan; G

SD-05 Design Data

65% Pre-Final Design; DA/GA 95% Final Design; DA/GA 100% Corrected Final Design; DA/GA

SD-06 Test Reports Test Results and Reports; FIO

1.4.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in RFP Section 01 33 16-DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

1.4.2 TEST REPORTS

Provide all test results and reports identified in this SOW to the Government as a submittal in accordance with RFP Section 01 33 00-SUBMITTAL PROCEDURES. Submittals will be considered for information only (FIO) submittals unless specifically identified as a submittal requiring government approval. Coordinate with the KO after award for the specific items to be included in the submittal register.

1.5 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the KO.

8-Feb-21 Page 7 of 66

1.5.1 LIFE-SPAN

The facility and the installed equipment must be permanent construction with an expected lifespan of more than 25 years.

1.5.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.5.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.5.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.6 DESIGN DIMENSIONS

Develop the design using the metric system.

1.7 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with Host Nation building codes (current versions as of the date of RFP, unless otherwise indicated). In the absence of Host Nation building codes, use the International Building Code (IBC) and the codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the KO. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

1.8.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope.

Submit a Demolition Plan to be tracked via the submittal register indicating all demolition, abatement, and disposal methods.

1.8.1.1 ABATEMENT AND DISPOSAL

All demolished materials must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.

1.8.1.2 LOCATION OF HAZARDOUS MATERIAL

The Contractor is responsible to survey the site and determine if hazardous materials exist. If hazardous materials are found to exist, immediately notify the KO and provide the results of the relevant sampling and testing. Provide the hazardous material report no later than 30 days after Notice to Proceed (NTP) for

8-Feb-21 Page 8 of 66 information and approval.

1.8.2 PROTECTION OF WORK AREA

1.8.2.1 DUST AND DEBRIS CONTAINMNET

Seal the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of the work area. In addition to protections within the work area, provide temporary protection for all finishes from the entrance of the facility to each area of work. Patch and repairing any damage caused during construction. Coordinate the locations of barriers with the Government prior to the start of work.

1.8.2.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT

Protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the Government for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction. Either the Contractor or the KO may request to conduct a preconstruction survey of furniture, fixtures, and equipment with both the Contractor and Government representative present.

1.8.2.3 NOISE AND VIBRATION CONTROL

Employ demolition and construction methods that minimize the production of sound and vibration. Coordinate the schedule of especially loud or disruptive activities with the KO prior to the start of work.

1.8.2.4 PROTECTION OF EGRESS AND LIFE SAFETY

The Contractor must not take actions that hinder existing egress paths or disrupt operation of life safety systems without prior coordination with the KO and all applicable authorities having jurisdiction (AHJ). The Contractor is responsible for supplying signage or other protective measures as required by the KO or AHJ prior to impeding the egress path or life safety system.]

1.8.3 SEQUENCING OF CONSTRUCTION WORK

The Contractor must sequence construction to allow the facility to remain occupied during construction. Do not block access to occupied areas during construction.

Utility and communication services must remain functional in all occupied areas.

Some relocation of equipment and/or personnel may be required to comply with this requirement, all restrictions are listed below:

a. Sequencing must allow first and second floors to be occupied at any given time.

Provide a Sequencing Plan with the 95% Final Design Submittal. The Sequencing Plan must describe the proposed performance of construction operations to comply with the stated sequencing requirements. The Sequencing Plan must include a graphical depiction of the sequencing of each work area and mobilization/staging area. The Sequencing Plan is in addition to the requirements of RFP Section 01 32 01-PROJECT SCHEDULE or 01 32 16-SMALL PROJECT PROGRESS SCHEDULES (NOTE: Only one of these specifications applies to this contract, refer to other documents for the section applicable to this project).]

END OF SECTION

8-Feb-21 Page 9 of 66

2.0 CIVIL AND GEOTECHNICAL

Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.

2.1 SCOPE SUMMARY

Civil works for this project include, but are not limited to, site survey, geotechnical investigation, site layout, demolition, earthwork, storm system, sanitary system, water system, pavement, outdoor furnishings, and landscaping.

Refer to the bid schedule for which of these are base bid or optional.

2.2 EXISTING CONDITIONS

2.2.1 TOPOGRAPHY

There is no known topographic survey for the project site. The existing site contains buildings, pavement, utilities, fences, and vegetation as shown on the attached Conceptual Site Plan. The existing information shown on the attached Conceptual Site Plan was compiled from a scope validation report, Google Earth, and site photos.

2.2.2 UTILITIES

There is an existing storm connection located to the west of the site approximately 25 meters away from the existing building. Closer connection manholes that are not on the attached As-Builts may be available.

There is no available information on the water system. However, it is assumed that a water connection to a pressurized water system exists within 100 meters of the existing building.

There is an existing sanitary connection located to the west of the existing buildings approximately 25 meters away. Closer connection manholes that are not on the attached As-Builts may be available.

Power, communications, and an existing pellet heat system are available on site.

Refer to the other sections of this SOW for details of these existing utilities.

There are existing utility connection points near the building as shown on the attached Utility As-builts. Contractor must verify all utility locations (surface and subsurface) in the field prior to the first design submittal.

2.2.3 GEOTECHNICAL

There is no geotechnical information available for the project site.

The Contractor must perform a Geotechnical Investigation and submit a Geotechnical Report as part of the Design Analysis. Refer to other sections of this SOW for the requirements of the Geotechnical Investigations and Report.

2.2.4 ENVIRONMENTAL

There are no known environmental protection areas or archeological preservation areas on the project site.

2.2.5 EXISTING CONDITIONS INVESTIGATION

Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:

a. Weather, river stages, or similar physical conditions at the site.

b. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, 8-Feb-21 Page 10 of 66 environmental reports, and publicly available information on the site.

c. Mobilization and staging constraints.

2.3 DESIGN SUBMITTALS

Provide civil design submittals in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and in compliance with SOW Section 1.0 – GENERAL.

65% Design Submittal:

a. Preliminary Design Analysis of civil features.

b. Final Site Survey (include in the Design Analysis).

c. Final Geotechnical Report (include in the Design Analysis).

d. Final Existing Conditions Plan.

e. Pre-Final Site Layout Plans - Indicate existing and proposed Civil features.

Include other disciplines’ features (faded back) that affect the Civil Design (buildings, mechanical structures, electrical utilities, etc.).

f. Pre-Final Grading Plans, including contours, finish floor elevations, and retaining walls.

g. Pre-Final Grading Profiles, Cross Sections, and Details. Include spot grades and slopes in Grading Plan. Include retaining wall profiles, cross sections, and details. Include erosion control design.

h. Pre-Final Demolition Plan

i. Pre-Final Pavement Plans, Profiles, Cross Sections, and Details

j. Pre-Final Utility (Storm, Sanitary, and Water) Profiles, Plans, Cross

Sections, and Details.

k. Pre-Final Fencing and Outdoor Furnishings Details

l. Preliminary Landscape Plan and Details, including seed mix and seed coverage rate

m. Preliminary Civil Specifications

95% Design Submittal:

Update all items from the 65% Design Submittal to 95% (Final) Design. Incorporate all 65% design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal. Address all previous government review comments before submitting.

As Built Drawing Submittal:

In addition to the as-built requirements discussed in RFP Section 01 78 00- CLOSEOUT SUBMITTALS, provide a topographical survey of the site per requirements of SOW Section 2.6-SITE SURVEY. Include existing utility lines or structures (both modified and unmodified) encountered in the construction footprint that were not located on the original Site Survey.

2.3.1 DESIGN ANALYSIS

Submit a Design Analysis in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD. Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval. Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

The Design Analysis includes but is not limited to:

a. Discussion of Site Layout constraints and design decisions, including but not

8-Feb-21 Page 11 of 66 limited to, land use, vehicle and pedestrian access, orientation of features on-site, setbacks from site features, minimizing utility lengths, minimizing earthwork and tree removal, and future expansion.

b. Discussion of Demolition constraints and design decisions. Include discussion on how access will be provided during construction, and how each utility will be maintained and operated during construction.

c. Discussion of Earthwork constraints and design decisions. Provide cut and fill calculations. Include pertinent geotechnical information that affects earthwork.

d. Discussion of Storm system constraints and design decisions. Provide a hydrologic and hydraulic analysis of the storm system, including offsite areas that contribute to and influence the project’s storm system. Provide drainage basin map(s), rainfall data, and coefficients used. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations for sizing of structures, including detention, infiltration, and LID features. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the storm system. Confirm that the existing receiving system has adequate capacity to receive the additional stormwater flow generated by the project.

e. Discussion of Sanitary system constraints and design decisions. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Provide calculations for sizing of structures. Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the sanitary system. Confirm that the existing receiving system has adequate capacity to receive any additional sanitary flow generated by the project.

f. Discussion of Water system constraints, design decisions and source. Provide calculations to demonstrate water system meets project requirements, including demand, water pipe sizing, design water pressure and flow rates at buildings and fire hydrants. Provide field conducted flow tests from nearest hydrants (or other relevant water structures if hydrants unavailable). Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities.

g. Discussion of Pavement constraints and design decisions. Provide calculations for the pavement section. Include traffic studies (if available). Provide design traffic calculations and assumptions. Include pertinent geotechnical information that affects the pavement design.

h. Discussion of Outdoor Furnishings constraints and design decisions. Provide structural calculations for foundations if the foundation is designed by the Designer of Record. Calculations are not necessary if the foundation design is from an industry standard detail.

i. Discussion of Landscaping constraints and design decisions.

j. Site Survey as an appendix.

k. Geotechnical Investigation and Report as an appendix.

2.3.2 DESIGN DRAWINGS

Provide Civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of Civil features for the project. Civil drawings also include temporary construction plans/methods that affect the design and construction of the project.

These temporary plans include mobilization, traffic control, erosion control, dewatering, shoring, construction sequence, etc. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to

8-Feb-21 Page 12 of 66 allow for complete understanding and constructability of all proposed features.

Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. Reference USACE A/E/C Graphics Standard for graphic requirements.

2.3.3 SPECIFICATIONS

Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.

2.4 DESIGN CRITERIA

Provide civil design in accordance with Host Nation codes. In the absence of Host Nation codes, use the latest release of the International Building Code (IBC) and the following codes and technical standards:

a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering

b. UFC 3-220-01, Geotechnical Engineering

c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)

d. UFC 3-240-01, Wastewater Collection

e. UFC 3-600-01, Fire Protection Engineering for Facilities

f. Architectural Barriers Act (ABA)

2.5 GEOTECHNICAL INVESTIGATION AND REPORT

This project is not expected to add an appreciable amount of load on the foundation under the existing building. There will be some utility installation work. Perform any geotechnical investigations necessary for the design and construction of project features. Provide any geotechnical investigations and reports to the Government that are performed. Provide geotechnical information and assumptions in the Design Analysis to support design decisions. Perform geotechnical work required for construction (i.e. compaction tests, inspection of structure foundation excavations). In the absence of Host Nation standards, perform the geotechnical scope of work per UFC 3-220-01, Geotechnical Engineering and IBC.

Coordinate testing locations with the KO to avoid impact to existing utilities and facility operations. Utility locates, permits, pavement removal and vegetation clearing is the Contractor’s responsibility. Repair disturbed areas with a concrete patch in paved areas, and compacted soil in non-paved areas. The repaired area must be flush with the adjacent surface. Following restoration, stake and flag each of the hole locations with boring identification numbers. In paved areas, use white paint on the paved surface to mark hole locations. Provide a map indicating the borehole and test pit locations.

2.5.1 REPORT

Include, as a minimum, the following information:

a. Description of field work completed and equipment used; names, signatures and stamps of licensed professionals involved; name of drilling company.

b. A description of site subsurface conditions, regional geology, and seismic conditions at the site.

c. Site map of borehole and test pit locations.

d. High resolution color digital photographs of each borehole and test pit location.

e. Test pit logs with classification of all subsurface materials. The logs must distinguish fill materials from native materials, include all in-situ test results, and include groundwater depth information, if groundwater is encountered. Distinguish between bedrock and rock boulders.

8-Feb-21 Page 13 of 66

f. Reports of all the field and laboratory testing.

g. Recommendations for expected settlement.

h. Recommendations for preparation, placement, and compaction of onsite soils, borrow material, soil replacement, soil amendment/treatment, structural fill, topsoil, and trench backfill. Include dewatering and temporary retaining structure needs.

i. Soil Resistivity.

j. Frost Depth.

k. Recommendations for pavement design and construction.

l. Calculations to support conclusions and recommendations.

2.5.2 DESIGN DRAWINGS AND SPECIFICATIONS

On the design drawings and/or specifications, include geotechnical information that affect the design of the project, including but is not limited to, boring locations, boring logs, groundwater and frost depths, and any details that convey requirements for site preparation.

2.6 SITE SURVEY

Conduct and provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Survey must be conducted prior to the first design submittal. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis. Locate and show on the topographic survey the following information:

a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.

b. Survey monuments. Include description.

c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.

d. Contours in intervals of 0.25 meters.

e. Buildings and other miscellaneous structures. Provide finish floor elevation.

f. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.

g. Surface Drainage Features. Indicate normal water level for water bodies.

h. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;

pipe sizes and materials.

i. Signs. Include sign text.

j. Trees/Woods: In wooded areas that trees are to be protected, locate outside drip line of wooded area, include general density and type of trees. For wooded areas with proposed tree removal, identify trees per Host Nation permitting requirements. Where selective clearing will be proposed, locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.

k. Geotechnical boring locations.

l. Locate environmentally sensitive areas (determined and marked by others).

m. North arrow and scale of drawing.

n. Legend depicting the symbols and abbreviations used on the drawing.

o. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.

8-Feb-21 Page 14 of 66

Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.

Upon completion of construction, update the original survey with an As-built survey of the site as constructed, including underground utility locations and depths. Submit the As-built survey to the KO for approval.

Reference UFC 3-201-01, Civil Engineering, Section 2-4.2-SURVEYING for survey requirements.

2.7 SITE LAYOUT

Locate the proposed improvements as indicated on the attached Conceptual Site Plan. Amend the site layout as determined by the site-specific constraints, the owner’s preferences, accessibility, future expansion, and opportunities that are identified and evaluated as part of the Contractor’s scope of work.

The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.

2.8 DEMOLITION

Remove existing structures, utilities, pavement, vegetation, and any other features to construct the proposed improvements. Provide straight, neat sawcuts at limits of pavement removal. All contaminated soils discovered require special testing and disposal per Host Nation requirements.

2.8.1 CONSTRUCTION LIMITS

Do not disturb the project site beyond necessary for installation of proposed construction. Do not disturb any areas past the site’s property line. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as required by the KO. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the KO prior to performing said work.

2.8.3 TREES

Protect trees which might be damaged during construction, with a 1.8 meter high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Trees are defined as larger than 150mm diameter at 1.3 meters above existing grade. Mitigate for tree removal per Host Nation requirements.

2.8.4 UTILITIES

Any existing utilities encountered that are impacted by this project must be protected, or relocated if protection is not feasible. Remove existing and abandoned utilities under or within 3.0 m of the foundation of any proposed facility or building foundation. Reroute existing utilities to remain in accordance with SOW Section 2.10-UTILITIES. Abandoned utilities must be removed up to the utility main (or next utility main junction) and capped. Manholes or underground structures to be abandoned must be removed to a minimum depth of 50 centimeters below finish grade. Fill abandoned manhole or structure per Section 2.9-EARTHWORK requirements.

2.8.5 DUST, DEBRIS, AND EROSION CONTROL

8-Feb-21 Page 15 of 66

Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.

Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply local regulations regarding hauling and disposal.

2.8.6 ADDITIONAL REQUIREMENTS

Reference RFP Section 00 74 01-SPECIAL CONDITIONS and 01 30 00-GENERAL REQUIREMENTS for additional demolition, protection, and permitting requirements.

2.9 EARTHWORK

Perform all earth work necessary for the installation of the proposed improvements.

2.9.1 PLANS AND SPECIFICATIONS

Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided Geotechnical Report.

2.9.2 UNEXPLODED ORDNANCE (UXO) CLEARANCE

UXO survey is not required.

2.9.3 CONTAMINATED SOIL

Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the KO for further guidance.

2.9.4 CULTURAL RESOURCES

Cultural resources, such as archaeological remains, may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the KO for further guidance.

2.9.5 SATISFACTORY MATERIAL

Excavated material (below topsoil), if satisfactory for reuse per the Contractor’s Geotechnical Engineer, may be used on the project site where fill is required.

Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.

2.9.6 BACKFILL COMPACTION

In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and 1 test per 30 meters of road and utility trench. Round up to nearest whole number (i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test results must be furnished to the KO. All structure foundation excavations must be inspected and approved by the Contractor’s

8-Feb-21 Page 16 of 66

Geotechnical Engineer prior to placing concrete. Repair earthwork areas as recommended by the Contractor’s Geotechnical Engineer, and approved by the KO.

2.9.7 ENGINEERED SOIL SUPPORT SYSTEMS

Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.

2.9.8 SITE GRADING

Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading.

Site grading around the building must meet ABA and Host Nation accessibility guidelines.

2.10 UTILITIES

This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, and heat. See Sections 5.0-ELECTRICAL & COMMUNICATIONS, Section 6.0-MECHANICAL, and Section 7.0-FIRE PROTECTION for additional utility requirements.

Provide horizontal and vertical separation between new and existing utilities for rehabilitation, maintenance, repair or replacement. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations. Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent. Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.

Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner (customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.

Provide utility materials per IBC requirements. Provide corrosion protection for utilities that provides the minimum life expectancy specified in Section 1.0- GENERAL. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.

2.10.1 STORM SYSTEM

Retain the connection of existing building downspouts to the existing main storm water system. Collect runoff from other surfaces to the main storm water system.

After installation, test storm lines and structures for leakage and deflection as a result of the renovation per local codes. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.

2.10.2 SANITARY SYSTEM

Provide a sanitary system that connects the building to the nearest existing sanitary system near to the building. A closer connection manhole may exist and is available to connect to if it is in good condition.

8-Feb-21 Page 17 of 66

Allowable sanitary pipe materials include polyvinyl chloride (PVC), high density polyethylene (HDPE), or ductile iron. Sanitary structures must be concrete, with traffic rated cast iron or ductile iron frames and covers. In the absence of Host Nation standards, design the sanitary system per UFC 3-240-01, Wastewater Collection.

After installation, test sanitary lines and structures for leakage and deflection per local codes. Provide test results to the KO. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.

See SOW Section 6.0 – MECHANICAL for indoor sanitary scope.

2.10.3 WATER SYSTEM

See SOW Section 6.0 – MECHANICAL for indoor water scope.

2.11 PAVEMENT

Provide site access to allow operational and maintenance access to the facility.

Proposed pavements for the project include:

a. PCC slabs for the fire escape landing and other proposed outdoor features that serve the proposed facility. Provide medium broom finish on PCC concrete.

b. Replace existing pavement sections where the trenching occurs for utility installation. Sawcut a minimum 30 centimeters beyond edge of trench.

In the absence of Host Nation standards, design pavements per UFC 3-201-01, Civil Engineering.

For asphalt concrete, provide compaction and pavement density tests, as well as thickness and evenness tests, at the frequency listed in Section 2.9 - EARTHWORK.

For PCC, reference SOW Section 4.0 - STRUCTURAL for concrete requirements. Perform subgrade tests for all pavements as described in Section 2.9 - EARTHWORK. The location of all tests must be selected by the Contractor’s Geotechnical Engineer, and copies of all test results must be furnished to the KO.

2.11.1 PAVEMENT MARKINGS

There likely will not be a need to provide pavement markings. If any existing pavement markings are disturbed as a result of this project, replace according to host nation standards. In the absence of Host Nation standards, design pavement markings per SDDCTEA Pamphlet 55-17, Better Military Traffic Engineering-Chapters 6 and 17.

2.12 OUTDOOR FURNISHINGS

2.12.1 BOLLARDS

Provide bollards at the exterior corners of the fire escape slab if it is placed in an area with vehicle traffic.

Bollards must be a minimum 1.22 meter high above ground level, 10 centimeters diameter steel pipe filled with concrete, painted yellow, and embedded in a Portland cement concrete foundation. Steel pipe wall must be minimum 6 millimeter thick. The foundation must not be attached to the building foundation or the slab.

2.12.2 SIGNS

Provide facility signage in accordance with the Installation and Host Nation standards. Size messages and graphics on signs according to the functional viewing distance. Typically, at least 25 millimeter of letter height per 7.62 meters of viewing distance is required for readability.

2.13 LANDSCAPING

8-Feb-21 Page 18 of 66

Provide grass seed and 20 centimeters of topsoil on the site in areas that do not have pavement or a building within the limits of disturbance. Seeds must be locally sourced from a certified plant nursery, and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations. Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per local codes and/or manufacturer/supplier’s recommendations. Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends.

8-Feb-21 Page 19 of 66

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Provide and perform architectural design and construction services to provide a complete, accessible, functional, and usable school in Delnice, Croatia.

Provide partial interior renovation and reconfiguration of the existing school areas and new exterior egress stairs:

(1) Wing A Attic Space Reconfiguration: Reconfigure currently unused attic space into one new classroom for 25 students, one female employee restroom with one sink and one toilet, one male employee restroom with one sink, one urinal and one toilet, one central corridor, and two smaller offices.

Provide one egress corridor with exterior egress stairs.

(2) Wing A1 Attic Space Reconfiguration: Reconfigure currently unused attic space into one new teacher’s room for 35 employees.

(3) Wing A Second Floor Reconfiguration – Renovate and convert existing second floor teacher’s office into new classroom. Renovate and convert existing space of other two offices, restrooms and adjoining small corridor into library. Provide separate new door openings with new wooden doors and door frames for each room from the adjoining corridors.

(4) Wing D - First Floor Kindergarten Bathroom Renovations: Demolish existing kindergarten bathroom appliances (5 children WC’s, 1 shower, and 6 sinks) and all interior finishes. Provide 6 children WC’s, 1 shower and 4 sinks.

(5) Wing C - First Floor Laundry and Restroom Renovations: Demolish existing laundry and restroom (3 washing machines connections, 3 toilet stalls, and 3 sinks) and all interior finishes. Provide one new restroom with 2 sinks and 2 toilet stalls for students, one laundry room with space for linen closet, ironing machine and connections for one washing machine and one dryer; and one separate unisex employee restroom with one sink and one toilet.

Extensive coordination is required between the architectural work and the civil, geotechnical, structural, fire protection, mechanical, and electrical requirements of this project.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this RFP. The design must incorporate all referenced codes and regulations. The Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the KO. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with RFP Section 01 33 16-DESIGN AFTER AWARD and 01 33 00-SUBMITTAL PROCEDURES. Prepare and submit the documents listed below at the submittals indicated.

3.1.2.1 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary indicating Host Nation and/or IBC life safety requirements for all new facilities.

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. Demolition Plans – Provide existing floor plans, indicating all demolition

8-Feb-21 Page 20 of 66 required.

d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

f. Building Elevations – Provide all building elevations indicating all exterior materials.

g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

h. Building Section – Indicate heights of critical building elements.

i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall…