Attachment 6 Statement of Work Svencionys

View the file

Other files

File Type Posted
B.08.03.01_W912GB19R0048_Amendment_0001.pdf PDF
B.07.01_W912GB19R0048_PPC_Slides_2019.07.15.pdf PDF
B.07.01_Sign_In_Sheet.pdf PDF
B.08.03.01_W912GB19R0048_Amendment_0001_Conformed_Solicitation.pdf PDF
B.08.02.06.06_Att_6_Existing_Utility_Information.pdf PDF
H.08.04_Specifications.pdf PDF
B.08.02.07.03_Att_3_Floor_Plans.pdf PDF
B.08.02.04_Attachment_4_M_P_-_Salcininkai_Svencionys_Fire_Station_Renovations.pdf PDF
B.08.02.00_Site_Visit_Sign_in_sheet.pdf PDF
B.08.02.07.01_Att_1_Project_Location_Map.pdf PDF
B.08.02.05_Attachment_5_VAT_law_of_the_Republic_of_Lithuania.pdf PDF
B.08.02.06.04_Att_4_Structural_Calculations_Guideline.pdf PDF
B.08.02.01_Attachment_1(a)_PastPerformanceQuestionnaire.docx DOCX document
B.08.02.03_Attachment_3_BLG_Template.docx DOCX document
B.08.02.07.02_Att_2_Conceptual_Site_Plan.pdf PDF
B.08.02.06.03_Att_3_Annotated_Drawings.pdf PDF
B.08.02.07.04_Att_4_Structural_Calculations_Guideline.pdf PDF
B.08.02_W912GB19R0048.pdf PDF
B.08.02.06.01_Att_1_Project_Location_Map.pdf PDF
B.08.02.06.02_Att_2_Conceptual_Site_Plan.pdf PDF
B.08.02.07.06_Att_6_Existing_Utility_Information.pdf PDF
B.08.02.07_SECTION_011010_Statement_of_Work_Salcininkai,_Lithuania.pdf PDF
B.08.02.02_Attachment_2_BLA_Template.docx DOCX document
B.08.02.06.05_Att_5_Dedication_Plaque.pdf PDF
B.08.02.01_Attachment__1_ExperienceInfoSheet.docx DOCX document
B.08.02.07.05_Att_5_Dedication_Plaque.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Army Corps of Engineers

Europe District

APO AE 09049

li09

Statement of Work

Project Number: OHASIS 34818

Renovation of Fire and Rescue Station, Svencionys, Lithuania

Prepared by:

Design Section

Engineering Branch

2 May, 2019

01 10 10 Statement of Work Svencionys, Lithuania

2-May-19 Page 2 of 39

SECTION 01 10 10

STATEMENT OF WORK

SECTION TABLE OF CONTENTS:

1 GENERAL

2 CIVIL AND GEOTECHNICAL

3 ARCHITECTURAL

4 STRUCTURAL

5 ELECTRICAL & COMMUNICATIONS

6 MECHANICAL

ATTACHMENTS

Att. # 1 Location Map

Att. # 2 Conceptual Site Plan

Att. # 3 Annotated drawings

Att. # 4 Structural Calculations Guideline

Att. # 5 Dedication Plaque

Att. # 6 Existing Utility Information

1.0 GENERAL

1.1 PROJECT DESCRIPTION

The Request for Proposal (RFP) provides parameters for a design-build project for

Renovation of Fire and Rescue Station.

The Švenčionys Fire and Rescue Station is located in the south-eastern region of

Lithuania. The facility was constructed in the 19th Century as a horse carriage barn. The original building was renovated in 1940 and has had multiple additions and modifications since. The main vehicle garage was added in 1994 along with a small one-story multi-purpose space. An additional two-story office space was added in 1996. Since that time, there has not been significant modernization or rehabilitation of the facility or major building components. The facility is inadequate compared to modern day standards and the current condition hinders the response capabilities and resiliency of the Fire and Rescue Service.

The walls, roof, and windows are minimally insulated. It is estimated that they allow four times as much heat loss as current code allows. The vehicle garage doors are uninsulated and do not have proper weather seals installed. Cold winter winds quickly remove heat from the garage area. The attics are insulated with wood fiber cellulose that has become damp, uneven, and begun to deteriorate. The existing asbestos roof tiles have become brittle and damaged, allowing water infiltration that accelerates the rot of organic insulations.

The project includes the following general items of work, detailed requirements are contained elsewhere in this Statement of Work:

a. Replace roof covering and attic insulation;

b. Replace vehicle garage windows and doors;

c. Insulate exterior walls;

d. Provide a perimeter rainwater management system;

e. Replace vehicle garage exhaust system (;

f. Refurbish vehicle garage slab approx. 201m2);

g. Provide new high-efficiency lighting throughout vehicle garage;

h. Replace interior doors; and

i. Provide minor interior space reconfigurations.

1.2 GENERAL REQUIREMENTS

The Contractor must deliver fully functional, turnkey type facilities (without furniture) as described in this document. The work includes - but is not limited

2-May-19 Page 3 of 39 to - design, demolition, fabrication, delivery, installation, construction, and site work. The facility and the installed equipment must be permanent construction.

The facility in this project must be complete and usable to meet codes and technical and functional requirements per this Statement of Work (SOW). The proposal price must include all design, calculations, approvals, certificates, fees, labor, material, equipment, direct overhead, indirect overhead, general and administrative expenses (G&A) and general conditions to complete this project as described in the SOW.

These design and product requirements are minimum requisites. Compliance with the provisions of this section by subcontractors is the responsibility of the

Contractor.

1.2.1 BASE BID ITEMS AND OPTIONAL BID ITEMS

This Statement of Work addresses the technical requirements necessary to complete all work associated with this project. For information and requirements regarding the allocation of pricing between elements of the work, refer to the Bid Schedule included as a separate document. The Bid Schedule identifies the breakdown between the individual base bid and optional items for all work identified in this

Statement of Work, associated drawings, and attachments. All work as described in these documents is included in either the Base Bid or Optional Items: consider all items not specifically identified in the Optional Items as part of the Base Bid

Items.

1.3 SUBMITTALS

Government approval is required for submittals with “G” designation; submittals not having a “G” are for Contractor Quality approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-05 Design Data

65% Pre-Final Design; G, DO

95% Final Design; G, DO

100% Corrected Final Design; G, DO

1.3.1 DESIGN SUBMITTALS

Provide a complete design package at each milestone, as described in Specification

Section 01 33 16 DESIGN AFTER AWARD. The milestones for this project are indicated above in Section 1.4 SUBMITTALS. The specific requirements of each milestone are described in each discipline-specific section of this Specification.

Submit all documents in electronic format (.pdf for text and calculations, .pdf and .dwg (AutoCAD, latest version) for drawings). See Specification 01 33 00

SUBMITTAL PROCEDURES for additional information.

Coordinate the delivery locations for each remaining set of documents with the COR prior to each submittal. See Specification 01 33 00 SUBMITTAL PROCEDURES for additional information.

1.4 MATERIALS AND EQUIPMENT

Materials and products used must be durable, heavy duty, industry standard. The equipment must be the manufacturer’s standard quality and must be compatible with all other equipment and materials within the system or assembly. Equipment and materials must include all connections and accessories necessary to ensure operability and correct installation according to manufacturer’s requirements.

2-May-19 Page 4 of 39

Provide a nameplate secured to each major piece of equipment. Each nameplate must have the manufacturer’s name, address, contact information, type or style, model or serial number, and catalog number. The definition of a “major piece of equipment” is at the discretion of the COR.

1.4.1 LIFE-SPAN

Construction must have an expected life span of 25 years.

1.4.2 MAINTAINABILITY

Provide low maintenance materials and systems appropriate for the project climate and location.

1.4.3 OPERABILITY

Systems (including but not limited to architectural, electrical, communications, and mechanical systems) must be simple to operate and easy to maintain.

1.4.4 STANDARDIZATION

Provide standardized materials, products, equipment, and systems to minimize the requirements for replacement parts, storage facilities, and service requirements.

1.5 DESIGN DIMENSIONS

Develop the design using the metric system.

1.6 DESIGN CRITERIA

Project design, site facilities, utility systems and material standards must be in accordance with the latest editions of the Host Nation building codes. In the absence of Host Nation building codes, use the International Building Code (IBC) and codes, technical standards, and regulations referenced in this RFP.

While this RFP references various source standards and specifications, all design documents must meet Host Nation codes and requirements. It is the designer's responsibility to demonstrate that the Host Nation standard is equal to the cited standard or specifications being supplanted. Apply the more restrictive standards when conflicts arise between the requirements of this RFP and any referenced or other applicable codes, standards or regulations. If equivalency cannot be met, use the more stringent requirement and quote both codes verbatim in correspondence to the COR. The designer is responsible to determine the required material and execution standards where specific standards are not indicated.

Provide an electronic copy of the local Host Nation standards and building codes in their original language as related to facility design and construction.

1.7 DESIGN CONFERENCES AND MEETINGS

The Contractor and the entire design team are required to participate in a design review conference for each design submittal. The Contractor may request a review conference, but the Government is under no obligation to conduct or participate in a review conference unless specifically identified in the contract documents. The

Contractor must bring the personnel that developed the design submittal to any review conference.

All design review conferences must be held via teleconference or be reviewed and comments resolved via email.

The Contractor is responsible for taking meeting minutes during each design review conference and submitting to the COR for information and approval.

The Contractor is responsible for evaluating all Government comments prior to each design review conference. The Contractor is responsible for resolving all

2-May-19 Page 5 of 39

Government comments from each design phase. The Contractor must provide annotated responses to each design review comment with the subsequent design submittal packages. Construction may not begin until all Government comments from all design phases have been resolved.

1.8 SPECIAL CONSTRUCTION REQUIREMENTS

1.8.1 THIRD PARTY INSPECTION SERVICES

Furnish independent 3rd party inspection services to inspect the electrical and structural construction features of the project. The 3rd party must not be the same company responsible for the electrical or structural installation. This is in addition to the Contractor Site Personnel Requirements contained in 01 45 05

CONTRACTOR SITE PERSONNEL REQUIREMENTS. All testing is at the expense of the

Contractor. Submit a plan for third party services to the COR. The inspection plan must be approved by the COR prior to construction.

1.8.1.1 GENERAL REQUIREMENTS

3rd Party inspectors must submit professional reports directly to the COR, without coordination with the Contractor, within 48 hours of the actual inspection. The report must contain the following at a minimum: names of all persons present for activity, listing and approval of all related materials, description of observed activity, and 10 photos (minimum resolution: 1504x1000) of the observed activity.

1.8.1.2 THIRD PARTY ELECTRICAL INSPECTOR REQUIREMENTS

The electrical inspector must be a certified Master electrician or licensed degreed Electrical Engineer and have a minimum of 10 years' experience, 5 years in the country where the project work is performed. Submit the inspector’s CV

(Resume) to the COR for Government approval.

The following inspections must be conducted at a minimum: all outlets, off-cover inspection of all panels, verify that GFCI is present on all panels, municipal power connections, lightning protection installations, and generator installations.

Submit a plan and schedule to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.

1.8.1.3 THIRD PARTY STRUCTURAL ENGINEER INSPECTOR REQUIREMENTS

The structural inspector must be a licensed graduate engineer with 10 years of experience, 5 years in the country where the project work is performed. Required experience includes, but is not limited to, inspecting concrete moment frame, concrete foundations, roof system and rebar and form work. Submit the inspector’s

CV (Resume) to the COR for Government approval.

Submit an inspection plan and schedule of inspections to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the inspection plan and timing.

The following inspections must be conducted at a minimum: Bearing capacity of foundation soils, formwork and rebar of foundations, concrete placement of foundations. Formwork, rebar and concrete pour of moment frame. No concrete may be placed in forms without a preceding rebar inspection report and verification of functioning vibration equipment.

The inspector must review concrete test results and sign off on strength approvals.

1.8.2 PROTECTION OF WORK AREA

1.8.2.1 DUST AND DEBRIS CONTAINMNET

Seal the project area with construction barriers and dust partitions in order to contain construction dust and debris and maintain a clean environment outside of

2-May-19 Page 6 of 39 the work area. In addition to protections within the work area, provide temporary protection for all finishes from the entrance of the facility to each area of work. Patch and repairing any damage caused during construction. Coordinate the locations of barriers with the COR prior to the start of work.

1.8.2.2 PROTECTION OF FURNITURE, FIXTURES, AND EQUIPMENT

Protect all existing furniture, fixtures, and equipment that remain within the work area. Coordinate with the COR and the User for any special protection measures required for sensitive equipment. The Contractor is responsible for repairing or replacing any damage caused during construction. Either the

Contractor or the COR may request to conduct a preconstruction survey of furniture, fixtures, and equipment with both the Contractor and Government representative present.

1.8.2.3 NOISE AND VIBRATION CONTROL

Employ demolition and construction methods that minimize the production of sound and vibration. Coordinate the schedule of especially loud or disruptive activities with the COR prior to the start of work.

1.8.2.4 PROTECTION OF EGRESS AND LIFE SAFETY

The Contractor must not take actions that hinder existing egress paths or disrupt operation of life safety systems without prior coordination with the COR and all applicable authorities having jurisdiction (AHJ). The Contractor is responsible for supplying signage or other protective measures as required by the COR or AHJ prior to impeding the egress path or life safety system.

1.9.3 CONSTRUCTION PHASING

The Fire and Rescue Station must remain fully operational during construction.

Submit detailed Phasing Plan – including a construction schedule – to the COR for approval prior to the start of construction activities. Construction on the vehicle garage can only occur during the spring/summer when freezing temperatures and snow are not expected so that the vehicles can be operational if parked outside. The Contractor must inform the COR of any variances in the schedule during construction.

END OF SECTION

2-May-19 Page 7 of 39

2.0 CIVIL AND GEOTECHNICAL

Provide and perform civil engineering design and construction services as required to provide a complete, accessible, functional and usable project. The Contractor is required to extensively coordinate civil design and construction work with the scope of the other disciplines described in this SOW.

2.1 SCOPE SUMMARY

Civil works for this project include, but are not limited to, site survey, site layout, demolition, earthwork, and storm system. Refer to the bid schedule for which of these are base bid or optional.

2.2 EXISTING CONDITIONS

The project site is located in the city of Svencionys, Lithuania. The GPS coordinates are 55°08’01.0”N 26°09’46.5”E. The site is 85 km from Vilnius, the capital city of

Lithuania. The site is within 5 km of the Belarusian border.

2.2.1 TOPOGRAPHY

There is no known topographic survey for the project site. The existing site contains buildings, pavement, fences, a small amount of grass, and utilities. There is very little vegetation and no apparent slope to the site. The existing information shown on Att. #2 - Conceptual Site Plan was compiled from google earth and site photos.

2.2.2 UTILITIES

The building is connected to municipal electrical, potable water supply, telephone, and sanitary utilities. A local municipal storm sewer exists but the building is not connected to it. An existing utility map is available in Att. #6 – Existing

Utility Information.

2.2.3 GEOTECHNICAL

There is no geotechnical information provided for the project site.

2.2.4 ENVIRONMENTAL

There are no known environmental protection areas or archeological preservation areas on the project site. There is no prior knowledge of any hazardous or contaminated materials in the site’s soil or pavement. Apparent environmental hazards include high winds, heavy snow, and flooding due to heavy rains.

2.2.5 EXISTING CONDITIONS INVESTIGATION

Prior to bid, investigate the general and local conditions which can affect the work and/or its cost, including but not limited to:

a. Weather, river stages, or similar physical conditions at the site;

b. Existing depth of groundwater and drainage characteristics of the existing soil;

c. Surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site and due diligence research of as-built drawings, geotechnical reports, environmental reports, and publicly available information on the site.

d. Determination of the existing laundry room drainage channel and/or piping source and discharge.

e. Mobilization and staging constraints.

2.3 DESIGN SUBMITTALS

Provide civil design submittals in accordance with RFP Section 01 33 16, DESIGN

AFTER AWARD and SOW Section 1.0 – GENERAL. The submittals required for this project are stated in SOW Section 1.0 – GENERAL. Below are the contents required for each submittal:

65% Design Submittal:

a. Pre-Final Design Analysis of civil features.

2-May-19 Page 8 of 39

b. Final Site Survey (include in the Design Analysis).

c. Final Existing Conditions Plan.

d. Pre-Final Demolition Plan.

e. Pre-Final Utility Plans, Profiles, Cross Sections, and Details (Storm).

f. Pre-Final Civil Specifications.

95% Design Submittal:

a. Update all items from the previous Design Submittal to 95% (Final) Design.

Incorporate all previous design comments.

100% Submittal:

The 100% Submittal provides a complete and final set of contract documents ready for construction. Update all Final submittals from 95% to a corrected Final submittal.

Address all previous government review comments before submitting.

2.3.1 DESIGN ANALYSIS

Provide a Design Analysis for all Civil features that documents significant design choices and substantiates design compliance with contract requirements, applicable codes and standards. Documentation includes narrative, calculations, photographs, sketches, and catalog cut sheets. Reference all applicable regulations, standards, and criteria for the design. Reference sources are subject to Government approval.

Provide design assumptions. For design choices, discuss alternative systems considered, and provide rationale for the selected alternative.

The Design Analysis includes but is not limited to:

a. Discussion of Storm system constraints and design decisions. Provide a hydrologic and hydraulic analysis of the storm system, including offsite areas that contribute to and influence the project’s storm system. Provide drainage basin map(s), rainfall data, and coefficients used. For each section of pipe, include analyses indicating pipe size, friction factor, length, elevations at each end of pipe, slope, design flow (Q), maximum flow capacity, design depth of flow, design percentage full, and design flow velocity. Use the Rational

Method or TR-55 for analysis and design. In the absence of Host Nation requirements, use a minimum 10-year storm frequency for analysis and design.

Provide calculations on the pipe’s structural capacity if the pipe is shallower than required in section 2.10-Utilities. Include pertinent geotechnical information that affects the storm system. Confirm that the existing receiving system has adequate capacity to receive the additional storm water flow generated by the project.

b. Site Survey as an appendix.

2.3.2 DESIGN DRAWINGS

Provide civil design drawings of sufficient detail to address the requirements of each design submittal. Civil drawings include plans, profiles, cross sections, and details of civil features for the project. Design drawings include all necessary information (labeling, dimensioning, legend, details, notes, etc.) to allow for complete understanding and constructability of all proposed features. Provide comprehensible differentiation between features that are proposed, existing, future, or proposed to be demolished by use of appropriate choice of line styles, line weights, and/or colors. In the absence of the Host Nation’s drafting requirements, reference USACE A/E/C Graphics Standard for graphic requirements.

2.3.3 SPECIFICATIONS

Provide Civil specifications of sufficient detail to address the requirements of each design submittal. Specifications, when combined with the design drawings, allow for complete understanding and constructability of all proposed Civil features.

Specifications may be notes on the civil design drawings as an alternative to a separate specifications document.

2-May-19 Page 9 of 39

2.4 DESIGN CRITERIA

Provide civil design in accordance with Host Nation codes. In the absence of Host

Nation codes, use the latest release of the International Building Code (IBC), SOW

Section 1.0-GENERAL, and the following codes and technical standards:

a. Uniform Facility Criteria (UFC) 3-201-01, Civil Engineering

b. UFC 3-220-01, Geotechnical Engineering

c. USACE A/E/C Graphics Standard (ERDC/ITL TR-12-1)

2.5 GEOTECHNICAL INVESTIGATION AND REPORT

The Contractor is not required to perform a geotechnical investigation for this project. The Contractor may perform geotechnical investigative activities if desired to improve the design. Provide any geotechnical information or assumptions in the

Design Analysis to support design decisions.

For Construction, perform field and laboratory geotechnical work required for utility installation and/or trench backfill (i.e. compaction tests).

2.5.1 DESIGN DRAWINGS AND SPECIFICATIONS

On the design drawings and/or specifications, include geotechnical information that is pertinent to the design of the project.

2.6 TOPOGRAPHIC SURVEY

Provide a topographic survey from a licensed surveyor that includes all existing site information needed to design and construct the project. Include x, y, and z coordinates to the nearest 0.005 meters, dimensions, material, and basic characteristics of all features within the project site limits, as well as all features outside of the project site limits that will affect the design and construction of the project. Research record drawings to obtain utility and pavement information that is not visible from the surface. Provide notes indicating the sources and any limitations or assumptions of the data. Provide a copy of the survey in CAD, in addition to the paper/electronic requirements of the Design Analysis.

Locate and show on the topographic survey the following information:

a. Property boundary, public right of way, and easements. Include the address numbers, street names, and easement records.

b. Survey monuments and benchmarks. Include description.

c. Spot elevations covering the entire survey limits showing high points, low points, grade changes, and at sufficient intervals to represent the general character of the terrain.

d. Contours in intervals of 0.10 meters.

e. Buildings and other miscellaneous structures. Provide finish floor elevation.

f. Pavements. Include pavement type, thicknesses, joint patterns, and pavement markings. Include top of curb and gutter elevations.

g. Surface Drainage Features.

h. Utility lines and structures. Include rim elevations and invert elevations for utility structures; identification of lines as underground or aboveground;

pipe sizes and materials.

i. Signs. Include sign text.

j. Trees: For tree removal, identify trees per Host Nation permitting requirements.

Where selective clearing will be proposed, locate trees over 150 millimeter diameter at chest height, and include tree species, diameter at chest height, and dripline diameter.

k. Locate environmentally sensitive areas (determined and marked by others).

l. North arrow and scale of drawing.

m. Legend depicting the symbols and abbreviations used on the drawing.

n. Horizontal and vertical coordinate systems, date of survey, licensed surveyor name and license number.

2-May-19 Page 10 of 39

Site information provided to the Contractor by the Government is not to be considered accurate Site Survey information. Utility field locates and as-built research are the responsibility of the Contractor.

Reference UFC 3-201-01, Civil Engineering, Section 2-2.2-SURVEYING for survey requirements. In the absence of the Host Nation’s horizontal and vertical coordinate system, use the Universal Transverse Mercator (UTM) coordinate system, and base vertical coordinates on sea level.

2.7 SITE LAYOUT

Locate the proposed utilities indicated on Att. #2 – Conceptual Site Plan. Amend the site layout as determined by site-specific constraints, code requirements, the owner’s preferences, and future expansion.

Locate proposed utility mains a minimum of 3 meters away from existing buildings.

The Contractor is responsible for all aspects of the project whether they are shown on the conceptual plan or not.

2.8 DEMOLITION

Remove existing pavement and other features to construct the proposed improvements.

Provide straight, neat sawcuts at limits of pavement removal. Any contaminated soils discovered will require special testing and disposal per Host Nation requirements. Reference RFP Section 00 74 00-SPECIAL CONDITIONS and 01 30 00-GENERAL

REQUIREMENTS for additional demolition, protection, and permitting requirements.

2.8.1 CONSTRUCTION LIMITS

Do not disturb any areas past the site’s property line, with the exception of utility trenches. The Contractor is responsible for coordination and permits associated with improvements outside the property boundary. Show demolition work and limits of disturbance in the drawings. Stake-out the limits of disturbance on-site with temporary fencing before beginning construction.

2.8.2 ITEMS TO REMAIN IN PLACE WITHIN CONSTRUCTION LIMITS

Take necessary precautions to avoid damage to existing items to remain in place, to be reused, or to remain the property of the Government. Repair or replace damaged items as approved by the COR. Construct and maintain shoring, bracing, and supports as required. Ensure that structural elements are not overloaded. Provide new supports and reinforcement for existing construction weakened by demolition, deconstruction, or removal work. Repairs, reinforcement, or structural replacement require approval by the COR prior to performing said work.

2.8.3 TREE DEMOLITION

If it cannot be avoided, remove trees with driplines within the footprint of the proposed improvements. Protect trees larger than 150mm diameter at chest height within the project site which might be damaged during construction, with a 1.8 m high fence around the dripline of the tree(s), which is assumed to be the extent of the tree’s roots. Mitigate for tree removal per Host Nation requirements. Tree cutting interrelated processes need to be coordinated with responsible persons and local authorities. This includes, but is not limited to, compensation measures and endangered species studies. The Contractor is responsible for permitting, environmental studies, and coordination with local authorities related to tree and vegetation demolition.

2.8.4 UTILITY DEMOLITION

Any existing utilities encountered within the site boundary that are impacted by this project must be protected, or relocated if protection is not feasible. Relocate existing utility mains outside the structural zone of influence of proposed buildings and structures. Utilities impacted by this project that require decommissioning, https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system https://en.wikipedia.org/wiki/Universal_Transverse_Mercator_coordinate_system

2-May-19 Page 11 of 39 or that are already out of service, must be removed up to the utility main and capped.

2.8.5 DUST, DEBRIS, AND EROSION CONTROL

Prevent the spread of dust, debris, and erosion from the project site. Install erosion control measures before beginning construction. Sweep pavements as often as necessary to control the spread of debris. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, ice, flooding, erosion, or pollution. Remove snow, dust, dirt, and debris from work areas daily.

Remove and transport the debris in a manner that prevents spillage on streets or adjacent areas. Apply Host Nation regulations regarding hauling and disposal.

2.9 EARTHWORK

Perform all earth work necessary for the installation of the proposed improvements.

2.9.1 PLANS AND SPECIFICATIONS

Define earthwork requirements in the plans and specifications. Include requirements for satisfactory material, borrow material, structural fill, topsoil, utility trenches, replacement and improvement of on-site soils, soil compaction (for subgrades of structures, paving, and landscaped areas), compaction for utility trenches, maximum lift depths, density testing frequency, maximum temporary and permanent slopes, and engineered support systems. The earthwork requirements must not conflict with the recommendations in the Contractor-provided Geotechnical Report.

2.9.2 CONTAMINATED SOIL

Inspect and test all soil according to Host Nation requirements. If hazardous materials are discovered, cease excavation, secure the area, and notify the COR for further guidance.

2.9.3 CULTURAL RESOURCES

Cultural resources, such as archaeological remains, are not expected, but may be uncovered during excavation operations. If suspected cultural remains are found, cease excavation, secure the area, and notify the COR for further guidance.

2.9.4 TOPSOIL

Remove and save topsoil (approximately first 20 centimeters of excavation). Separate out subsoil, brush, litter, weeds, roots, stones larger than 25 mm in diameter, and other materials that would interfere with planting and maintenance operations. When restoring the site to finish grade, place topsoil back in excavated areas that do not include proposed paving or structures.

2.9.5 SATISFACTORY MATERIAL

Excavated material, if satisfactory for reuse per the Contractor’s Geotechnical

Engineer, may be used on the project site where fill is required. Unsatisfactory material, and surplus excavated material not required for fill, must be disposed of offsite, and is the responsibility of the Contractor. Borrow material may be required for construction from sources off site. Borrow materials are to be free of hazardous materials and contaminants. Any soil brought in from off-site sources must be certified clean.

2.9.6 BACKFILL COMPACTION

In the absence of Host Nation requirements and geotechnical recommendations, fill and backfill must be placed in layers of 20 centimeters loose thickness and compacted to a minimum 95% of the maximum dry density as determined by Host Nation test method equivalent to ASTM D-1557 (Modified Proctor test). Provide density tests on all lifts at a frequency of 1 test per 40 square meters for foundations and parking, and

1 test per 30 meters of road and utility trench. Round up to nearest whole number

(i.e. a 25 square meter foundation requires one test). The location of all tests must be selected by the Contractor’s geotechnical engineer, and copies of all test

2-May-19 Page 12 of 39 results must be furnished to the COR. Repair earthwork areas as recommended by the

Contractor’s Geotechnical Engineer, and approved by the COR.

2.9.7 ENGINEERED SOIL SUPPORT SYSTEMS

Provide engineered soil support systems (i.e. shoring) as required for the construction of the proposed improvements. The Contractor is responsible for all dewatering necessary for earthwork.

2.9.8 SITE GRADING

Provide site grading that directs storm water runoff away from buildings and structures either by drainage systems or by grading as follows:

a. Finished grades of earth/grass/gravel surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 5% for the first 2 meters.

b. Finished grades of paved surfaces adjacent to buildings and structures must slope away from all exterior edges with a minimum slope of 2% for the first 2 meters.

c. Finished grades must not create stagnating water or ponding anywhere on the project site, nor create ponding on adjacent properties. Provide storm improvements if ponding is unavoidable.

The Contractor must limit proposed landscape slopes to a maximum 4H:1V for grass areas requiring mowing and 2H:1V for non-grass areas, which will a require non-erodible surface (i.e. rock, shrubs with mulch).

2.10 UTILITIES

This section applies to all project underground utilities located outside the building, including but not limited to, sanitary sewer, water supply, storm drainage, electrical, communications, gas, liquid fuel, and heat. See Sections 5.0-ELECTRICAL and Section 6.0-MECHNICAL for additional utility requirements.

In the absence of Host Nation requirements, design utilities per IBC and UFC 3-201-

01, Civil Engineering. Provide utility materials per IBC requirements. Provide utility main alignments outside the structural zone of influence of proposed buildings and structures. Provide utility line depths, bedding, and backfill as required by applicable requirements and geotechnical recommendations. Minimum cover over pipes is 0.6 meters; greater than frost penetration; or sufficient to support imposed dead and live loads for the pipe materials used; whichever is more stringent.

Place plastic warning tape along the route of the buried pipe after installation at a height of 0.3 meters above the pipe.

Coordinate all required installation, relocation, improvement and protection of utilities held by third party (e.g. public or private utility). This includes coordination of any work to be performed by the utility owner. Choice of materials and products for utility installation must be coordinated with the utility owner

(customer or third party) to ensure proper integration and compliance with existing systems and allow for easy maintenance and repair of the utilities in the future.

Provide corrosion protection for utilities that provides the minimum life expectancy specified in GENERAL Section 1.0. Any piping or equipment exposed to sunlight must be coated with protective coatings suitable for UV exposure with a minimum expected coating life of 10 years before recoating.

2.10.1 STORM SYSTEM

Provide a gravity storm drainage system to direct runoff away from improvements, eliminate ponding, and prevent erosion. A pump system is not allowed. An infiltration system is not allowed. Proposed storm improvements include:

a. Perimeter drainage trench around the facility that consists of a minimum 30 cm wide trench with drainage material (gravel) from grade to the depth of the

2-May-19 Page 13 of 39 building footings. Provide perforated drainage pipe in the drainage trench that connects that connects to the municipal storm system with a solid wall pipe.

Provide filter fabric geotextile between drainage trench aggregate and native ground.

b. Connect building downspouts to the municipal storm system in a separate pipe than the perimeter trench drainage system.

c. Route drainage from the existing drainage channel and/or piping through the laundry room to the existing sanitary system. The new drainage system must not allow storm water or sewage backflow into the laundry room.

d. Provide an oil/water separator for washing of fire trucks. Fire trucks are required to be washed following every call, typically 200 times per year.

Provide a bypass into the storm sewer system upstream of the oil/water interceptor designed to divert flows above the capacity of the oil/water interceptor. Use a separator with a completely removable cover.

Allowable storm pipe materials include polyvinyl chloride (PVC), high density polyethylene (HDPE), ductile iron, or reinforced concrete pipe. Storm structures must be concrete, with traffic rated cast iron or ductile iron frames and covers.

Provide metal covers over all drainage collection trenches constructed through existing paved sidewalks, driveways, or parking areas. Trench covers shall be rated for loading from the fire station’s largest truck.

In the absence of Host Nation requirements, design the storm drainage system per the

IBC and UFC 3-201-01, Civil Engineering Chapter 3-Storm Drainage Systems.

After installation, test storm lines and structures for leakage and deflection per

Host Nation codes. Provide test results to the COR. Locate and repair any sections failing to pass the required tests. Repeat the specified tests and inspections on the repaired sections.

2.11 PAVEMENT

Replace existing pavement sections where trenching occurs for utility installation and where pavement is removed for below grade exterior wall waterproofing work.

Sawcut a minimum of 30 cm beyond edge of trench.

2.12 LANDSCAPING

Provide grass seed and 20 centimeters of topsoil in all non-paved disturbed areas.

Seeds must be locally sourced from a certified plant nursery, and native to the area. Provide seed coverage density per manufacturer/supplier’s recommendations.

Provide watering, weeding, and any other necessary care to establish growth. Limit planting to times of the year per Host Nation codes and/or manufacturer/supplier’s recommendations. Replace topsoil and seeds, at Contractor’s expense, in areas which do not have new growth coverage of 75% before the warranty period ends.

Before using chemicals during landscaping work, including for use on plants and on site features, the Contractor must submit to the COR, in the form of brochures, certificates and other technical material, information about the chemicals proposed, including about their environmental compatibility. Their use is only permitted with approval of the COR.

2-May-19 Page 14 of 39

3.0 ARCHITECTURAL

3.1 PROJECT DESCRIPTION

Design and construction work of Svencionys Fire and Rescue Station.

Perform the construction work of two-story, wood and masonry building that will serve as Fire and Rescue Station.

Extensive coordination is required between the architectural work and the civil, geotechnical, structural, mechanical, and electrical requirements of this project.

3.1.1 DESIGN

Provide a design and construction package that uses the space allocations, functional adjacencies, design details, and features given or referenced in this

RFP. The design must incorporate all referenced codes and regulations. The

Contractor is responsible for creating additional details as required to complete a full design. All details must conform to the requirements of this RFP and are subject to the approval of the COR. A schematic design has been attached for reference. The schematic plans are provided for diagrammatic purposes only and do not necessarily represent an approved floor plan or design. The Contractor is responsible for providing a design that meets all requirements of the User and the codes and criteria referenced in this Statement or Work.

3.1.2 DESIGN SUBMITTALS

Provide all architectural submittals after contract award in accordance with

Section 01 33 16 DESIGN AFTER AWARD and Section 01 33 00 SUBMITTAL PROCEDURES.

Prepare and submit the documents listed below at the submittals indicated.

3.1.2.2 65% DESIGN SUBMISSION

Include the following drawings and reports as applicable to the project:

a. Code Summary – Provide a tabular code compliance summary [per UFC 3-600-01].

b. Life Safety Plans – Provide plans depicting smoke/fire resistance ratings, egress routes, dead-end corridors, exits, and other aspects of life safety pertaining to the design.

c. [Demolition Plans – Provide existing floor plans, indicating all demolition required.]

d. Floor Plans – Provide all floor plans, indicating room names, areas, and basic dimensions, scale 1:50.

e. Ceiling Plans – Provide reflected ceiling plans for all rooms, indicating ceiling materials and fixtures, scale 1:50.

f. Building Elevations – Provide all building elevations indicating all exterior materials.

g. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

h. Building Section – Indicate heights of critical building elements.

i. Wall Section - Provide a typical interior and exterior wall section for each building – describe wall materials.

j. Interior Elevations – Provide interior elevations of all bathrooms and built-in casework and kitchenettes, indicate critical heights of surfaces and plumbing fixtures and describe all materials and finishes.

k. Pre-Final Design Analysis – Provide a narrative explaining the design and indicating how the design and materials meet the requirements of this SOW.

l. Pre-Final Specifications – Provide detailed explanations of requirements for all performed work or provide product specific manufacturer information

(brochures, technical information, cut sheets) for all materials and products to be provided/installed.

3.1.2.3 95% DESIGN SUBMISSION

The 95% Submittal provides a complete and final set of contract documents essentially ready for construction by the D/B Contractor. All previous government review comments

2-May-19 Page 15 of 39 must have been addressed. Include the following drawings and reports as applicable to the project:

a. All documents from the 65% submittal updated to incorporate 65% review comments.

b. Floor Plans – Provide all floor plans, indicating room names, areas, and dimensions, scale 1:50.

c. Building Elevations – Provide all building elevations indicating all exterior materials.

d. Roof Plan – Provide a plan of all roof areas, indicating direction of slope and method of drainage.

e. Building Section – Indicate heights.

f. Wall Sections – Provide sufficient wall section(s) to indicate all materials and different conditions.

g. Section and Plan Details – Provide details of critical building intersections.

h. Window and Door Schedule – Provide a schedule of all windows and doors, indicating sizes, hardware, and operation.

i. Stair Section and Details.

j. Finish Schedule – Indicate all proposed finishes.

k. Final Design Analysis – Provide a finalized narrative describing all work to be performed on the project and how it meets the functional and code requirements of the project. Provide product specific manufacturer information (brochures, technical information, cut sheets) for all materials and products to be provided/installed.

l. Final Specifications – Provide line items and detailed descriptions of all work to be performed.

3.1.2.4 100% DESIGN SUBMISSION

The 100% Submittal provides a complete and final set of contract documents ready for construction by the D/B Contractor. All previous government review comments must have been addressed. Include all drawings, specifications and calculations from the

95% Submittal updated to incorporate all previous review comments.

3.2 TECHNICAL CRITERIA AND STANDARDS

Design and construct the project in accordance with the requirements outlined in

Section 1.7 DESIGN CRITERIA.

3.2.1 LIFE SAFETY REQUIREMENTS

The Design must meet all Host Nation and local Fire Suppression System codes and requirements.

In the absence of Host Nation codes and standards, for individual concerns of Life

Safety the Contractor must follow appropriate US codes and standards:

NFPA 101 - Life Safety Code

3.3 GENERAL SCOPE OF WORK

Design the architectural elements of this facility to withstand all site-specific environmental conditions such as wide seasonal temperature swings, local wind, rain, snow and earthquake conditions. All architectural features must be appropriately braced for anticipated seismic activity. The Contractor may propose alternate building materials to meet the facility’s requirements, but final selection of materials is subject to the approval of the COR. Consider economics not only in the initial acquisition, but also in the future maintenance of the materials, when selecting materials and building systems to be incorporated into the project. When requested, the Contractor must provide documentation demonstrating that a chosen alternative material is life cycle cost effective.

3.4 DETAILED SCOPE OF WORK

2-May-19 Page 16 of 39

The Contractor is responsible for the following specific tasks required for the construction of this facility.

3.4.1 DEMOLITION

The Contractor is responsible for all required demolition as indicated in this scope. Demolition work for this project is limited to demolition required under

Section 2.0 CIVIL AND GEOTECHNICAL.

Demolition work includes, but is not limited to, the following items:

a. Demolish and remove existing interior doors;

b. Demolish and remove metal roof sheeting, roof flashing, gutters, downspouts, existing cellulose, attic insulation, fascia boards and soffit.

c. Demolish and remove existing parapet flashing, downspouts, and metal window sills.

d. Demolish and remove existing exterior windows, metal window sills, and garage doors on the vehicle garage. and

e. Demolish and remove existing electrical and lighting systems.

3.4.1.1 DEMOLITION AND DISPOSAL

All demolished materials must be abated and disposed of in accordance with local laws, codes and regulations. The Contractor is responsible for all required testing before, during and after demolitions as well as for all required compliance with safety standards.

Submit a Demolition Plan to be part of the QC Plan or a separate submittal to be tracked via the submittal register, indicating the demolition, abatement, and disposal methods.

3.4.1.2 DEMOLITION AND DISPOSAL OF HAZARDOUS MATERIAL

The local fire and rescue service, as well as Vilnius Fire and Rescue Board have agreed to remove all existing asbestos roof coverings prior to construction.

3.4.2 BUILDING SYSTEM AND MATERIALS

The intent of this RFP is to allow the Contractor the maximum flexibility to design and construct this facility in an economical manner without sacrificing good engineering practices, quality materials and systems. The Government requires low or no maintenance finish materials to the greatest extent possible. Building materials as described herein for roofing, walls, ceilings, doors, windows and floors are minimum requirements and may require revision based on code compliance and criteria.

3.4.2.1 FIRE PROTECTION RATINGS OF INTERIOR FINISHES

All interior finishes must conform to Host Nation fire protection standards/requirements or equivalent US standards/requirements.

3.4.2.2 ACOUSTICAL DESIGN

Doors, walls, floors, and ceilings must meet the minimum sound protection per Host

Nation requirements.

3.4.2.3 THERMAL INSULATION

Provide thermal insulation in accordance with Host Nation and local requirements

(STR 2.01.02:2016 “Design and Certification of Energy Performance of Buildings”).

3.4.3 EXTERIOR CONSTRUCTION WORK

Provide the following exterior architectural systems.

3.4.3.1 EXTERIOR WALLS

Design and construct new exterior walls in accordance with (IAW) the requirements of this SOW. Refer to Section 4.0 STRUCTURAL. Exterior walls must have smoke/fire

2-May-19 Page 17 of 39 resistance ratings as required by Host Nation, and local fire and life safety codes. Provide exterior wall finishes appropriate for the wall structure as required below.

3.4.3.1.1 Install new exterior insulation finish system (EIFS) with new polystyrene thermal insulation, stucco and paint over existing brick façade and building base.

Demolish existing parapet flashing, downspouts, and metal window sills. Remove and set aside existing exterior mechanical units, light fixtures, switches, receptacles, signage, utility connection boxes, loudspeakers, and other miscellaneous accessories on the exterior of the building for reinstallation after the project is complete. Structurally shore existing communications pole and demolish existing structural attachments. Demolish all existing sidings (wood, vinyl, and plaster), fascia, and soffits.

Clean all masonry facades to prepare for installation of new EIFS. Provide new substrate for application of EIFS on all wood construction. Repair any existing structural damage. Protruding bricks of existing façade must be modified to create a flat surface for EIFS application. All exteriors must be cleaned of any sand, dust, dirt, sealers, efflorescence, environmental contaminants and bond breakers that could have negative effects on adhesion. Adhesion tests must be completed to insure that EIFS system will properly adhere to existing brick façade. Install exterior insulation system must consist of insulation boards, to include mineral lightweight plaster, fiberglass reinforcing net and secondary air/weather barrier layer. Additionally dowel/anchor the boards. Thermal insulation boards must be as dense as practicable to provide the greatest resistance to thermal conductivity with the least material thickness. Thermal insulation must meet the requirements of HN building code (STR 2.01.02:2016

“Design and Certification of Energy Performance of Buildings”). Thermal insulation must wrap the corner of all window and door openings and provide the greatest thickness of insulation possible without obscuring frames, hinges, or weep holes.

The work must include all necessary expansion joints, base - and corner rails, diagonal fiberglass-reinforcing fabric at the window and door corners and end flashing at eave. Use products from a single system, by a single manufacturer, which are certified by the manufacturer to be suitable for the purpose. This also applies to the paint. Apply products in accordance with the manufacturer's instructions. The work must include all necessary sealing e.g. at window sills.

Submit a sample of the insulation system along with the manufacturer's catalog data including installation instructions, typical details and product data for

COR's acceptance.

3.4.3.1.1 WALLS BELOW GRADE

Provide fluid-applied monolithic membrane waterproofing on all concrete and masonry walls below grade (at least 10cm above ground level). Waterproofing must be low VOC. Apply liquid proof coating with fabric reinforcement corner strips in accordance with manufacturer guidelines. Provide new continuous rigid insulation and drainage membrane. Thermal insulation must meet the requirements of HN building code (STR 2.01.02:2016 “Design and Certification of Energy Performance of

Buildings”). All materials must be suitable for continuous contact with soil.

3.4.3.2 EXTERIOR DOORS

Provide new exterior doors as indicated on attached drawings.

3.4.3.2.1 EXTERIOR PERSONNEL DOORS

Provide new insulated exterior door to replace door on the existing single-story administrative addition.