W912ES26QA014 - Amendment 0001 Scope of Work.pdf

PDF 2 MB Posted

Attached to
Guttenberg Ponds Rock Supply Federal contract opportunity
Solicitation number
W912ES26QA014
Issued by
Department of the Army Corps of Engineers Engineering District St Paul

About this file

This is a Scope of Work for a federal contract to supply riprap (quarried stone) materials for bank protection along the Upper Mississippi River near Pool 11 Guttenberg Ponds. The Contractor must furnish and deliver 2,000 tons of riprap materials to a stockpile location, with loading operations to occur between River Miles 605 to 640 of the Upper Mississippi River, roughly between Prairie Du Chien, Wisconsin and Cassville, Wisconsin. The contract is managed by the U.S. Army Corps of Engineers with a Contracting Officer's Representative assigned at contract award. Delivery is anticipated between March 1, 2026 and May 1, 2026, occurring Monday through Thursday between 8:00 a.m. and 4:30 p.m. local time, with delivery rates varying between 100 and 800 tons per day as designated by the Contracting Officer.

Riprap material must be durable quarried stone meeting strict specifications: specific gravity between 2.55 and 2.75, maximum aspect ratio of 3:1, reasonably well-graded within specified limits, and free from cracks, blast fractures, bedding, seams, soil, quarry fines, and refuse. The Contractor must submit material sources for approval within 7 calendar days of award and perform gradation testing using Method A (weighing individual stones) or Method B (separating stones into weight classes) with minimum sample weight of 5,500 pounds. One satisfactory test is required before delivery and one additional test during delivery. Material will be measured by ton through certified scales meeting NIST HB 44 standards with 0.2 percent sensitivity. Approved quarry sources are listed in Attachment 1, including operations in Iowa and Wisconsin. The Contractor must provide at least two pieces of heavy equipment to serve as anchoring points for barges, use straight-line end dump trucks for delivery, and employ a loading method (such as a long reach excavator) that limits rock drops to no more than two feet onto Government barge decks. All work must comply with OSHA and U.S. Army Corps of Engineers Safety Manual EM 385-1-1, and the Contractor must establish quality control procedures with documentation provided to the Government.

View the file

Other files for this federal contract opportunity

Other files attached to Guttenberg Ponds Rock Supply, newest first.
File Type Posted
Solicitation Amendment W912ES26QA0140001 SF 30.pdf PDF
Vendor Questions and Responses 01-27-2026.docx DOCX document
W912ES26QA014 Scope of Work.pdf PDF
Solicitation - W912ES26QA014 Professional Appearance.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

TABLE OF CONTENTS

PARAGRAPH DESCRIPTION

PART 1 GENERAL

1.1 SCOPE

1.2 APPLICABLE PUBLICATIONS

1.3 SUBMITTALS

1.4 RIPRAP MEASUREMENT AND PAYMENT

PART 2 RIPRAP

2.1 MATERIALS

2.2 DOCUMENTATION

2.3 SOURCES AND EVALUATION

2.4 TESTS FOR ACCEPTABILITY OF ALTERNATIVE SOURCE MATERIAL

2.5 RIPRAP GRADATION TESTING

PART 3 EXECUTION

3.1 SCHEDULE FOR MATERIAL DELIVERY

3.2 COORDINATION

3.3 DELIVERY LOCATION

3.4 DELIVERY

3.5 QUALITY CONTROL

3.6 SAFETY

1. GENERAL.

1.1 SCOPE. The Contractor will provide all plant, labor, and material necessary to furnish and deliver 2,000 tons of riprap materials to the stockpile location in accordance with this scope of work.

The loading of riprap will take place between River Miles 640 to 605 of the Upper Mississippi River, roughly between Prairie Du Chien, WI and Cassville, WI.

1.2 APPLICABLE PUBLICATIONS. The publications listed below form a part of this scope of work to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. Army Corps of Engineers, Engineer Manual (EM).

EM 385-1-1 Safety and Health Requirements Manual, (15 March 2024).

Iowa Department of Transportation (IADOT)

IADOT Standard Specifications for Construction (2023)

Wisconsin Department of Transportation (WDOT)

WDOT Standard Specifications (2025)

National Institute of Standards and Technology (NIST)

NIST HB 44 Specifications, Tolerances, and Other Technical Requirements for Weighing and Measuring Devices.

1.3 CONTRACTING OFFICER’S REPRESENTATIVE. A Contracting Officer’s Representative (COR) will be assigned to this contract and designated in writing by the Contracting Officer at the time of contract award.

1.4 SUBMITTALS

1.4.1 General. The Contractor will submit the following as required. Approval of submittals will not relieve the Contractor of responsibility to furnish materials as required. In order to make the submittal process as efficient as possible, the Contracting Officer’s Representative may give verbal responses to a submittal followed by the written response at a later date. In this case, the submittal response date will be the date that the verbal response was given.

a. Material Source for Riprap as specified in PARAGRAPH: SOURCES AND EVALUATION

b. Method of Processing Riprap as specified in PARAGRAPH: Riprap Gradation Processing

c. Gradation Test Results as specified in PARAGRAPH: RIPRAP GRADATION TESTING

d. Weighing Operations as specified in PARAGRAPH: Riprap Measurement

e. Delivery Tickets for Riprap as specified in PARAGRAPH: Riprap Measurement

f. Scale Accuracy Certification as specified in PARAGRAPH: Riprap Measurement

g. Daily Delivery Report as specified in PARAGRAPH: Riprap Measurement

h. Delivery Location as specified in PARAGRAPH: DELIVERY LOCATION

i. Method of Transferring Rock as specified in PARAGRAPH: Schedule for Material Delivery

j. Schedule of Delivery as specified in PARAGRAPH: Schedule for Material Delivery

1.4.2 Submission of Submittals. Submittals will be submitted in ample time to secure approval prior to the time the items covered are to be delivered to the site. ENG Form 4025-R (Attachment 5) will be used for the transmittal of submittals. One electronic copy of all submittals will be provided. Hard copies of submittals are generally not required unless specifically noted. The Government will require at least ten working days to review a submittal.

1.4.3 Submittal Control. Within 7 calendar days after contract award date, the Contractor will submit to the Contracting Officer for review and approval, a submittal control document (ENG Form 4288) in electronic format listing and scheduling all items required to be furnished for review by the Government. A copy of the submittal register is included in Attachment 4. Primary responsibility for submittals will rest with the Contractor. Omissions from the attached sample submittal register will not relieve the Contractor from providing all required submittals. In addition to those items listed in the sample register, the Contractor will furnish submittals for all deviations from the specifications.

1.5 RIPRAP MEASUREMENT AND PAYMENT.

1.5.1 Riprap Measurement. Riprap will be measured by the ton by weighing each truck load of material on an approved scale. Scales will be of sufficient length to permit simultaneous weighing of all axle loads and will be sensitive to a change in load of 0.2 percent throughout the range of the scale. The scale's accuracy will conform to the applicable requirements of the most current publication of NIST HB 44 and will be certified by a scale servicing company or by an inspector of the State Inspection Bureau. Each load will be accompanied by a delivery ticket certified by the weighmaster. As a minimum, each ticket will contain the following information:

a. Date and Time.

b. Vehicle Number.

c. Gross Weight.

d. Vehicle Tare Weight.

e. Net Weight of Riprap.

f. Material weighed (Description of Load Contents).

g. Signature of Weighmaster.

The Government will collect a copy of the delivery ticket from each truck for each material type as it arrives on site.

The Contractor will submit a daily report at the close of each day’s hauling operations detailing the number of trucks that made deliveries to the site as well as an overall quantity of material delivered to the site that day for each material type.

1.5.2 A plan indicating the location and proposed schedule of weighing operations will be submitted for approval in accordance with PARAGRAPH 1.4: Submittals.

1.5.3 Riprap Payment. Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary for delivering Riprap to locations as shown and specified.

2 RIPRAP

2.1 MATERIALS.

2.1.1 General. Riprap material will be durable quarried stone of suitable quality to ensure permanence in the Upper Mississippi River environment. Stone will be free from cracks, blast fractures, bedding, seams, and other defects that would tend to increase its deterioration from natural causes. A crack is considered to be detrimental if it is more than 4 mil wide and is continuous for one-third the dimension of at least two sides of the stone.

The stone will be clean and reasonably free from soil, quarry fines, and contain no refuse.

2.1.2 Specific Gravity. All Stone will have a specific gravity of not less than 2.55 and not more than 2.75.

2.1.3 Riprap Shape. The maximum aspect ratio (greatest dimension: least dimension) of any piece of stone for size ranges will be not greater than 3:1 when measured across mutually perpendicular axis. ASTM D4791 will be used as a guide to perform the test.

2.1.4 Riprap Gradation. Riprap will be reasonably well graded within the specified limits shown on the riprap gradation plot contained in Attachment 2 to permit construction of relatively dense riprap sections. Inclusion of objectionable quantities of dirt, sand, clay, rock fines, or other deleterious materials will not be allowed or measured for payment.

2.1.5 Riprap Gradation Processing. On the same date the Contractor provides the submittal for material sources, they will also submit their method of processing riprap at the quarry for approval. The method will preclude the inclusion of objectionable amounts of fine material and organic matter. All riprap will be processed in accordance with the approved method.

Quarry-run riprap material will not be accepted. All rock designated for use as riprap will be processed over a vibratory grizzly or by an approved method to unsure the exclusion of poor-quality rock.

2.2 DOCUMENTATION: Documentation in the form of load tickets will be provided from the material supplier for each load of riprap delivered to the site verifying that the material meets the requirements for riprap as specified.

2.3 SOURCES AND EVALUATION.

2.3.1 Approved material sources are provided in Attachment 1. The Contractor may elect to furnish rock from another source or sources not listed in Attachment 1, provided the source is approved by the Contracting Officer and meets the conditions hereinafter stated.

If the Contractor proposes to furnish materials from a source not listed, a Government Geologist will make such investigations and evaluations as necessary to determine if materials meeting the requirements of this contract can be produced from the proposed source. The Contractor will be responsible for making its own investigations for sources of suitable materials and for making its own arrangements with the owners of the quarries or land for procuring the required quantities of suitable materials.

2.3.1.1 Within 7 calendar days after award of the contract, the Contractor will designate and submit for approval only one source or combination of sources from which it proposes to furnish the materials specified. If the Contractor proposes to furnish materials from a source or from sources not listed in Attachment 1, it may designate only a single source or a single combination of sources from which to furnish the material specified. Samples for acceptability testing will be provided as required by the PARAGRAPH 2.4: Tests for Acceptability. If a source for materials so designated by the Contractor is not approved for use by the Contacting Officer, the Contractor will not submit for approval other sources but will furnish the materials from approved sources selected from the list in Attachment 1, at no additional cost to the Government.

2.3.1.2 Approval of a source of material is not to be construed as approval of all material from that source. The right is reserved by the Government to reject materials from certain localized areas, zones, strata, or channels when such materials are unsuitable as determined by the Government Geologist. Materials produced from an approved source will meet all the requirements of this specification.

2.4 TESTS FOR ACCEPTABILITY OF ALTERNATIVE SOURCE MATERIAL.

2.4.1 Quality tests and service records will be used to determine the acceptability of stone materials. In the event suitable test reports and satisfactory service records are not available, as in the case of newly operated sources, the materials will be tested to determine acceptability. Tests to which the materials may be subjected to include petrographic analysis, specific gravity, soundness, abrasion, absorption, freezing and thawing, and other tests considered necessary to demonstrate acceptability. Tests will be made by, or under the supervision of, the Government and at the Government’s expense.

2.4.2 Samples. When directed by the Contracting Officer, suitable samples of materials will be submitted for approval prior to delivery of materials to the work site. Samples will be obtained by the Contractor, in the presence of the Contracting Officer or its designated representative and delivered at the Contractor’s expense to a point designated by the Contracting Officer, at least 15 days in advance of the date that the material is required to be delivered.

2.5 RIPRAP GRADATION TESTING.

2.5.1 General Requirements. Gradation tests will be performed by the methods and frequency listed below. Testing listed herein will be completed by and at the expense of the Contractor. Gradation testing results, including failed tests, will be submitted utilizing the gradation plot for the required riprap gradation and the WORKSHEET FOR GRADATION ANALYSIS OF RIPRAP. The worksheets for methods A and B discussed in detail below are included in Attachment 3. (gradation plots and blank copies of the worksheet are included in the attachments section). The Contracting Officer will direct the time and location of sampling, unless waived. The Contracting Officer will be informed 24 hours before each test is to be performed. The Contracting Officer will be informed immediately of test results and draft copies of test results will be submitted at the Contracting Officers request. Tests performed on material that does not meet gradation and shape requirements will not be counted as part of the tests required.

2.5.2 Test Method A. Test method A will consist of weighing all stones larger than 5 pounds in a sample. Five to seven weight classes will be selected within the range of stone sizes.

Each stone will be weighed and recorded on the worksheet for method A and the calculations on the worksheet will be performed and recorded. The weight of stones will be summed for each weight class; after which calculations and a plot of the gradation will be completed in accordance with accepted practice for soil and aggregate gradations.

2.5.3 Test Method B. Test method B will consist of separating the stones into 5 to 7 piles, ordered by size. The sample will be separated on a clean, hard surface that is free of smaller stones that could become mixed with the sample. The stones will be visually screened to place them into appropriate piles. All stones will be separated and placed into a pile before weighing. After separating, the smallest and the largest rock in each pile will be weighed and recorded. The stones will be adjusted as necessary so that the weight classes do not overlap. After adjustment is adequate and weight classes have been established, each pile of stone will be weighed and recorded on the worksheet for method B. Calculations and a plot of the gradation will be completed in accordance with accepted practice for soil and aggregate gradations.

2.5.4 Scales. Accuracy of scales will be as required in PARAGRAPH: Riprap Measurement.

2.5.5 Testing. A sample will be obtained from each approved material source or combination of sources for the gradation required and tested in accordance with either method A or B. A satisfactory test will be obtained from each source or combination of sources for each gradation prior to hauling any riprap from that quarry. All samples will have a minimum gross weight of 5,500 pounds.

2.5.6 Testing Frequency. One satisfactory gradation test will be required prior to bringing materials on site. One additional satisfactory gradational test will be required during riprap delivery. The Contracting Officer will notify the Contractor when to conduct this second test. Tests that do not meet gradation requirements will not be counted.

2.5.7 Corrective Action. If materials fail to meet gradation or shape requirements, the

Contractor will adjust their operations and verify with necessary tests that acceptable materials are being produced, or it will propose another source and verify, with necessary tests, that acceptable material can be produced from that source.

3 EXECUTION.

3.1 SCHEDULE FOR MATERIAL DELIVERY. Within 7 calendar days after award of the contract, the

Contractor will designate and submit for approval the method the contractor plans to load rock on barges. Whether loading with machine or driving truck or end loader on to barge.

The Contracting Officer will notify the Contractor 15 calendar days in advance of when delivery is to commence. The Contractor will provide the riprap gradation submittals for approval no later than 7 calendar days prior to delivery of materials to the specified delivery location. It is anticipated that delivery will occur between 01 March 2026 and 1 May 2026. Delivery will commence no later than 15 calendar days following the Contracting Officer’s notification and will continue on consecutive workdays until completed, unless directed otherwise by the Contracting Officer. The delivery period will be between the hours of 8:00 a.m. and 4:30 p.m. (local time), Monday through Thursday. No deliveries will be made on weekends or on Federal holidays.

3.2 COORDINATION. The Contractor will not block access to the loading docks or access routes at the delivery site for extended periods of time and will coordinate access routes with the following:

Mr. Christopher Stai Chief, Maintenance and Repair

651.290.5144 (office) 612.790.2675(mobile) Christopher.J.Stai@usace.army.mil

3.3 DELIVERY LOCATION. Within 7 calendar days after award of the contract, the Contractor will designate and submit for approval the delivery location. All riprap material required under mailto:Christopher.J.Stai@usace.army.mil this contract will be delivered on existing roads. The loading of riprap will take place between River Miles 605 to 640 of the Upper Mississippi River. The Contractor will provide the Contracting Officer with the proposed loading site and method of loading of barges as a part of bid submission which will be reviewed prior to contract award. Proposed load site may be in Wisconsin or Iowa. Site must have adequate river depths which will allow access for USACE fleet and allow for safe mooring of Government barges. At no time will the load site selected by the contractor impede or otherwise interfere with the normal navigation of commercial barge traffic. It is intended that material is directly loaded onto USACE material barges.

3.4 DELIVERY. Delivery of riprap by the Contractor will include placing material directly from the delivery trucks onto USACE material barges. Rock will be required to be placed on Government barges by a method that does not allow rock to fall greater than two feet onto the barge deck surface. This will minimize damage to Government barges due to rock impact. Regardless of the delivery method, rock must be uniformly distributed on Government barges to load at approximately 120-500 tons per barge load. The Government will be able to supply 3 to 4 barges to be filled at a time. It will not be acceptable to simply dump rock directly on the barge surface without a method of full and even distribution. It is recommended that the Contractor utilize a long reach excavator or material handler to safety load and arrange rock onto barges. Specifications of the Government barges will be between 110 – 120 feet long by 26 – 30 feet wide. Load amounts of rock per barge may vary between 120 -500 tons depending on the loading arrangement, placement site water depth, and/or ramp configuration.

Contractor must provide at least two (2) pieces of heavy equipment (ie, bulldozers, wheel loaders, etc.) to serve as anchoring points for (1) USACE barge to be loaded at a time if mooring cells or davits arc not available at load site. USACE towing vessels will bring and retrieve (1) barge at a time to/from loading site. Equipment must be fully operational and capable of adjusting the position of barges, as needed. Contractor must provide bank wires or lines to secure barges.

Delays by the Government to ensure a safe work environment may occur due to equipment maintenance, breakdowns, water levels, or any number of river or weather conditions that may arise during the course of deliveries. Additionally, the Government may need to temporary halt the receiving of rock in event of forementioned events.

3.4.1 Load Restrictions. Delivery trucks used by the Contractor will meet load restrictions for all roadways used to deliver the riprap.

3.4.2 Delivery Truck Requirements. Delivery trucks used by the Contractor for placing riprap into stockpiles will be straight-line end dump trucks. Use of articulated end-dump trailers, side dump, or belly dump trailers will not be allowed.

3.4.3 Delivery Rate. The riprap material delivery rates will vary between 100 tons and

800 tons per day, as designated by the Contracting Officer. The Contractor will be required to increase or decrease the delivery rate within the above stated delivery rate range daily until the required quantity of material is met.

3.4.4 Crane option. If barges are loaded mechanically with excavator or crane, the Government would be able to load up to 1,500/tons/day; the Government would be able to utilize larger material barges and more barges.

3.5 QUALITY CONTROL. The Contractor will establish and maintain quality control and will maintain records of the quality control for work under this section to ensure compliance with contract requirements. A copy of inspections and tests, as well as corrective actions taken, will be furnished to the Government.

3.6 SAFETY. The Contractor will comply with all state and Federal OSHA requirements as well as all pertinent provisions of the latest version of the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 as they pertain to the work required in this scope of work. If a conflict exists between the guidance provided between the sources listed above, the Contractor will follow the most stringent standard given.

ATTACHMENTS

ATTACHMENT 1: MATERIAL SOURCES

ATTACHMENT 2: RIPRAP GRADATION PLOT

ATTACHMENT 3: WORK SHEETS FOR GRADATION ANALYSIS OF RIPRAP

(METHODS A AND B)

ATTACHMENT 4: SUBMITTAL REGISTER

ATTACHMENT 5: ENG FORM 4025-R

ATTACHMENT 1: MATERIAL SOURCES

NOTES:

1. Systematic blasting must be performed in order to minimize deleterious cracks in the final product.

2. At a minimum, material must be vigorously processed over a vibrating grizzly.

3. All materials produced from this quarry must be restricted to the unweathered portion of the Stewartville Member of the Wise Lake Formation

4. All materials produced from this quarry must be restricted to the top ~100 feet of dolomite. Rock on the lower half of the quarry is not acceptable for this bank protection project.

5. All materials produced from this part of the quarry must be restricted to the unweathered portion of the Oneota Formation

6. All material produced from this quarry must be restricted to the unweathered portions of the Oneota Formation and Sherwood, Mortimer, and Fairplay members (Beds G2 through G4) of the Dunleith Formation.

POOL 11 GUTTENBERG PONDS – UPPER MISSISSIPPI RIVER RESTORATION

APPROVED MATERIAL SOURCES FOR RIPRAP AND BEDDING STONE

1. The sources listed below are capable of producing rock fill and riprap products. Gradations will need to be evaluated in the f ield to pass all the specif ications once the products are produced.

QUARRY NAME AND OPERATOR QUARRY LOCATION NOTES

Barnhart Quarry T95N, R4W, Sec. 34, SE ¼, (1,2,3) Bruening Rock Products Inc. Clayton County, IA Elkader, IA 52043

(563) 380-3300

Frenchtown Quarry T93N, R3W, Sec. 12, SE ¼ (1,2,6) Pattison Company T93N, R3W,Sec 7 Garnavillo, IA T93N, R3W, Sec12, SE ¼

(563) 964-2860 ext. 131 Clayton County, IA

Moyna Quarry T93N, R5W, Sec. 13, SE ¼ (1,2,3) Moyna Materials Clayton County, IA

24412 HWY 13

Elkader, IA 52043

(563) 880-7625

Osterdock Quarry T91N, R3W, Sec. 2, S ½ (1,2,3) Bard Materials Clayton County, IA Colesburg, IA 52035

(563) 599-6756

Slama Quarry T7N, R6W, Sec. 18, NW ¼ (1,2,4) Prairie Sand and Gravel Crawford County, WI 34592 Co Rd K.

Prairie Du Chien, WI 53821

(608) 326-6471

Sny Magil Quarry T94N, R3W, Sec. 22, SE ¼ (1,2,5) Moyna Materials Clayton County, IA

24412 HWY 13

Elkader, IA 52043

(563) 880-7625

ATTACHMENT 2: RIPRAP GRADATION PLOT

2.65

PROJECT

AREA

DATE

Percent Passing Lower Bound Upper Bound TEST # 1 2 3 4 5 100 90 205 50 45 85 30 24.02 15 15 40 5 8 35

WEIGHT OF STONES IN POUNDS

SPECIFIC GRAVITY OF STONE =

MVP Standard Riprap Gradation Pool 11 Rock Supply

R45 Developed March 2014, Applied 12/9/2025

Specification

ENG FORM 4055 (COMPUTER GENERATED)

110100100010000

P E

R C

E N

T C

O A

R S

E R

B Y

W E

IG

H

T

P E

R C

E N

T F

IN

E

R B

Y W

E

IG

H T

3 9 8

2.65

WEIGHT OF STONES IN POUNDS

(ASSUMING STONE SHAPE MIDWAY BETWEEN A SPHERE AND CUBE)

SPECIFIED GRADATION ASSUMES A SPECIFIC

GRAVITY OF STONE EQUAL TO 2.65

3457 6

PROJECT ___________________________________

AREA ______________________________________

DATE

RIPRAP/ROCKFILL GRADATION CURVE

SIZE OF STONE IN INCHES

SPECIFIC GRAVITY OF STONE = 2.65

MVP Standard Riprap Gradation

R45

March 2014

ATTACHMENT 3: WORK SHEETS FOR GRADATION ANALYSIS OF RIPRAP

(METHODS A AND B)

ATTACHMENT 4: SUBMITTAL REGISTER

SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 1 PAGES

POOL 11 ROCK SUPPLY CONTRACT

SUBMITTAL REGISTER

CONTRACT NO.

TITLE AND LOCATION CONTRACTOR

CONTRACTOR:

SCHEDULE DATES

CONTRACTOR

ACTION

APPROVING AUTHORITY

A C T I V I T Y

N O

T R A N S M I T T A L

N O

S P E C

S E C T

DESCRIPTION

ITEM SUBMITTED

P A R A G R A P H

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W

R SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

MATERIAL SOURCE FOR RIPRAP

METHOD OF PROCESSING RIPRAP

WEIGHING OPERATIONS

SCALE ACCURACY CERTIFICATION

G

G

G

G

FIO

G

G

FIO = FOR INFORMATION ONLY

G = GOVERNMENT APPROVAL REQUIRED

DAILY DELIVERY REPORT FIO

DELIVERY TICKETS FOR RIPRAP

GRADATION TEST RESULTS

METHOD OF TRANSFERING ROCK

G

DELIVERY SCHEDULE

G

DELIVERY LOCATION

ATTACHMENT 5: ENG FORM 4025-R