This document is Amendment 0001 to the specifications for Solicitation W912ES23B0015, which is for the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-4 in Clay County, Minnesota. The amendment modifies Section 01 14 00.00 13 of the specifications, providing details on roadway closures, access requirements, and environmental restrictions. Key changes include:

The document specifies that 140th Ave S and 150th Ave S may be closed concurrently, but not at the same time as 3rd St, 130th Ave S, Clay County Road 2, or 180th Ave S. It also states that the permanent closure of 170th Ave S may be completed concurrently with the temporary closure of 140th Ave S and 150th Ave S, but not with other specified road closures. The contractor must maintain access to affected properties during construction by providing temporary access roads. Additionally, the amendment outlines scheduled access needs for the Red River Structure Contractor and environmental restrictions on work below the ordinary high water mark of the Red River and Wolverton Creek during specified timeframes.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

23B0015

AMEND 0001

The following modification is made to SECTION 01 14 00.00 13:

SECTION 01 14 00.00 13

a. PAGE 4. Delete Section 01 14 00.00 13 Page 4 in its entirety, and substitute therefor revised Section 01 14 00.00 13 Page 4, Amendment 0001, dated 24 April 2024.

ATTACHMENTS: Section 01 14 00.00 13 Page 4

Solicitation No. W912ES23B0015

140th Ave S and 150th Ave S may be closed concurrently to construct the roadway crossings of the Southern Embankment but must not be closed concurrently with the closure of 3rd St, 130th Ave S and Clay County Road 2 and 180th Ave S. The permanent closure of 170th Ave S may be completed concurrently with the temporary closure of 140th Ave S and 150th Ave S but not concurrently with the temporary closure of 3rd St, 130th Ave S, Clay County 2 (160th Ave S) or 180th Ave S.

Construction activities will eliminate current access to properties adjacent to and within the work limits. (See the Reference Drawings for additional information on potentially impacted parcels). Maintain access to affected properties during construction activities by providing temporary access or by sequencing work to ensure property owners have access and emergency services can be provided. The temporary access must be completed prior to disrupting access for the adjacent properties.

Temporary access roads must be 24 feet wide with 4 inches of gravel surfacing. Maintain access roads in a condition that is free of dips, rutting, and potholes. Remove temporary access features and restore the area to preconstruction condition.

All work associated with the placement of stockpiles in Staging Area South as well as work on 180th Ave S must be completed per the interim completion date and released to the Government on that interim completion date.

3.5 RED RIVER STRUCTURE ACCESS

Provide the Red River Structure Contractor access to their work site from 3rd St S as tentatively detailed below. This is the responsibility of the Contractor to work with the Red River Structures contractor in regard to scheduled access needs.

a. May 1, 2024 - October 15, 2024 - No access needed by Red River Structure Contractor.

b. October 15, 2024 - March 31, 2025 - Full access needed by Red River Structure Contractor.

c. March 31, 2025 - May 15, 2025 - No access needed by Red River Structure Contractor.

d. May 15, 2025 - December 31, 2025 - Full access needed by Red River Structure Contractor.

3.6 ENVIRONMENTAL RESTRICTIONS

To avoid impacts to fish during the spawning season, perform no work below the ordinary high water mark in the follow waterways during the periods defined:

a. Red River of the North: March 15 to July 1

b. Wolverton Creek: March 15 to June 15

-- End of Section --

SECTION 01 14 00.00 13 Page 4 AMEND. 0001

24 APR 2024

NARRATIVE PAGE
SECTION 01 14 00.00 13
Page 4