Tuesday, December 8, 2020 11:12:22 AM - Inbox - Jacob.L.Fall@usace.army.mil - Outlook b6ecjlf9 Line b6ecjlf9 Callout Location of the Downstream Sill Beam.
b6ecjlf9 Polygonal Line b6ecjlf9 Callout Staging Area for the Downstream Sill Beam and other downstream concrete placements.
b6ecjlf9 Polygonal Line b6ecjlf9 Polygonal Line b6ecjlf9 Callout Staging Area for the upstream concrete placements.
b6ecjlf9 Callout Staging Area for the concrete placements at mid chamber.