A22 W912ES21B0005 0002 - Solicitation Amendment.pdf
PDF 297 KB Posted
- Attached to
- Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1
- Solicitation number
- W912ES21B0005
About this file
This solicitation amendment provides responses to vendor questions on solicitation W912ES21B0005 for the Fargo Moorhead Metropolitan Area Flood Risk Management Project, Southern Embankment Reach SE-1. The amendment increases the quantity of filter material under CLIN 0035 from 6 cubic yards to 175 cubic yards. The project requires construction of an earth dam embankment with gravel road and topsoiled/seeded slopes, as well as culverts, headwalls, riprap, bedding, and geotextiles. Offerors must submit bids on 34 CLINs by the extended date. The U.S. Army Corps of Engineers, St. Paul District will evaluate bids and make award to the responsible bidder with the lowest price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6702031786
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this solicitation amendment is to answ er vendor submitted questions and change the quantity of CLIN 0035. A corrected Bid Schedule is included w ith this amendment.
All other solicitation terms and conditions remain unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 04-Feb-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES21B0005
X 9B. DATED (SEE ITEM 11)
15-Jan-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
04-Feb-2021
CODE
CONTRACTING DIVISION
USACE - ST PAUL
180 FIFTH STREET EAST
SUITE 700
SAINT PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES21B0005
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
CLIN 0035
The pricing detail quantity has increased by 169.00 from 6.00 to 175.00.
The following have been added by full text:
AMENDMENT 0002
Vendor Questions and Answers:
Q - On Plan page CD301 section D1: the end station numbering is missing, can you please provide it?
A - There is no end station for Section D1 on sheet CD302. There is a smooth transition to adjacent sections (Section A1 on sheet CD302, and Section D6 on sheet CD302).
Q - On Plan page CD303 sections D1, A1, and A6: the end station numbering is missing, can you please provide it?
A - There are no end stations for Sections D1, A1 and A6 on sheet CD303. There is a smooth transition to adjacent sections (for Section D1: Section A6 on sheet CD303, and Section A1 on sheet CD304; for Section A1: Section D6 on sheet CD302; for Section A6: Section A1 on sheet CD303).
Q - Is the filter material for the pipe installation incidental to the pipe? I cannot reconcile CLIN 0035 - Filter Material - 6 CY with details shown on CS501. RESPONSE:
A - The filter material is not incidental to the pipe installation. The filter material will be paid for under CLIN 0035.
The following Bid Schedule incorporates the change in CLIN 0035 and replaces the original Bid Schedule.
CLIN Description Quantity Unit Unit Price Total Price 0001 Performance and Payment Bonds 1 JOB 0002 Demolition 1 JOB 0003 Traffic Control Signs 1 Job 0004 Clearing and Grubbing 1 JOB 0005 Road Removal 6,200 CY 0006 Stripping
0006AA First 60,000 CY 60,000 CY 0006AB Over 60,000 CY 6,000 CY
0007 Inspection Trench 11,000 LF 0008 Subgrade Excavation
0008AA First 5,000 CY 5,000 CY 0008AB Over 5,000 CY 1,000 CY
0009 Excavation
W912ES21B0005
0009AA First 22,000 CY 22,000 CY 0009AB Over 22,000 CY 4,000 CY
0010 Borrow Excavation 0010AA First 95,000 CY 95,000 CY 0010AB Over 95,000 CY 15,000 CY
0011 Geotextile - Type 2 21,000 SY 0012 Aggregate Surface 7,000 TON 0013 Topsoil Respread
0013AA First 30,000 CY 30,000 CY 0013AB Over 30,000 CY 4,000 CY
0014 Seeding 50 AC 0015 Turf Reinforcement Mat (TRM) 9,200 SY 0016 Traffic Gate 2 EA 0017 36" RCP Culvert 177 LF 0018 24" RCP Culvert 138 LF 0019 15" CSP Culvert 115 LF 0020 30" CSP Culvert 42 LF 0021 36" CSP Culvert 43 LF 0022 36" Twin Pipe Headwall 1 EA 0023 36" Single Pipe Headwall 1 EA 0024 24" RCP Flared End Section 4 EA 0025 36" RCP Flared End Section 3 EA 0026 15" CSP Flared End Section 6 EA 0027 30" CSP Flared End Section 2 EA 0028 36" CSP Flared End Section 2 EA 0029 36" Flap Gate 3 EA 0030 R30 Riprap 150 CY 0031 R140 Riprap 350 CY 0032 B1 Bedding 60 CY 0033 B2 Bedding 90 CY 0034 Geotextile - Type 1 750 SY 0035 Filter Material 175 CY Total Bid
(End of Summary of Changes)