This solicitation requests bids for a habitat rehabilitation and enhancement project on McGregor Lake in Wisconsin. The project includes construction of floodplain forests, berms, habitat dredge channels, and erosion protection structures to improve aquatic and terrestrial habitat without impacting navigation. The estimated value is between $10 million and $25 million. The U.S. Army Corps of Engineers is seeking bids due by July 31, 2020. The solicitation is set aside for small businesses and provides pricing tables to bid line items for base work and three options, which if exercised would extend the project scope to additional areas.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION NO. W912ES20B0019
HABITAT REHABILITATION AND ENHANCEMENT PROJECT
MISSISSIPPI RIVER
PRAIRIE DU CHIEN, WI
CONSTRUCTION
DOCUMENTS
FOR
MCGREGOR LAKE HREP
POOL 10
June 2020
US Army Corps of Engineers St. Paul District
McGregor Lake Habitat Rehabilitation and Enhancement Project (HREP) Construction.
This HREP project includes the construction of f loodplain forests and berms of various sizes and shapes w ithin the Mississippi River, Prairie du Chien, Wisconsin.
The North American Industry Classif ication System (NAICS) code for this project is 237990 - Other Heavy and Civil Engineering Construction, w ith a size standard of $39.5M.
The estimated magnitude of construction is betw een $10,000,000 and $25,000,000.
This procurement is set-aside 100% for small business.
Payment and Performance Protection is required in accordance w ith FAR Part 28.
X
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
01-Jul-2020
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
651-290-5444
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
JESSE ONKKA
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________ calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________31 Jul 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
CONTRACTING DIVISION
USACE - ST. PAUL
180 5TH STREET E SUITE 700
ST. PAUL MN 55101-1678
W912ES
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour) Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912ES20B0019 262
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W912ES20B0019
Contents Section 00 10 00 - Solicitation
BID SCHEDULE
INFORMATION TO BIDDERS
1. BIDDER INQUIRIES
2. RESPONSIBILITY DETERMINATION
3. FACSIMILE OF BIDS
7. UNBALANCED BIDS
8. REQUIREMENT FOR BID GUARANTEE
9. BIDDER QUALIFICATIONS
10. ALL OR NONE QUALIFICATIONS
Section 00 21 13 - Instructions to Bidders
52.204-16 Commercial and Government Entity Code Reporting (JUL 2016)
52.204-22 Alternative Line Item Proposal (JAN 2017)
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
52.214-5 SUBMISSION OF BIDS (DEC 2016)
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)
52.216-1 TYPE OF CONTRACT (APR 1984)
52.217-5 EVALUATION OF OPTIONS (JUL 1990)
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
52.225-12 NOTICE OF BUY AMERICAN REQUIREMENT-- CONSTRUCTION MATERIALS UNDER
TRADE AGREEMENTS (MAY 2014)
52.228-1 BID GUARANTEE (SEP 1996)
52.233-2 SERVICE OF PROTEST (SEP 2006)
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984)
5152.211-9000 Evaluation of Subline Items (DEC 2019)
Section 00 45 00 - Representations and Certifications
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)
52.204-24 Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment (DEC 2019)
52.209-13 Violation of Arms Control Treaties or Agreements--Certification (JUN 2018)
252.203-7005 REPRESENTATION RELATING TO COMPENSATION OF FORMER DOD OFFICIALS
(NOV
2011)
252.204-7007 ALTERNATE A, ANNUAL REPRESENTATIONS AND CERTIFICATIONS (APR 2020)
252.204-7017 Prohibition on the Acquisiton of Covered Defense Telecommunications Equipment or Services-- Representation (Dec 2019)
252.225-7974 REPRESENTATION REGARDING BUSINESS OPERATIONS WITH THE MADURO
REGIME (DEVIATION 2020-O0005) (FEB 2020)
Section 00 70 00 - Conditions of the Contract
52.228-11 Pledges of Assets. (DEVIATION 2020-O0016)
52.228-15 Performance and Payment Bonds-Construction
52.210-1 MARKET RESEARCH
52.202-1 DEFINITIONS (NOV 2013)
52.203-3 GRATUITIES (APR 1984)
52.203-5 COVENANT AGAINST CONTINGENT FEES (MAY 2014)
52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT (SEP 2006)
52.203-7 ANTI-KICKBACK PROCEDURES. (MAY 2014)
52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER
ACTIVITY (MAY 2014)
52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY (MAY 2014)
52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS
(OCT 2010)
52.203-13 CONTRACTOR CODE OF BUSINESS ETHICS AND CONDUCT (OCT 2015)
52.203-17 CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM
EMPLOYEES OF WHISTLEBLOWER RIGHTS (APR 2014)
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS
OR STATEMENTS (JAN 2017)
52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper (May 2011)
52.204-10 REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS
(OCT 2018)
52.204-13 SYSTEM FOR AWARD MANAGEMENT Maintenance (OCT 2018)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (JUL 2016)
52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014)
52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (Jul 2018)
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment (AUG 2019)
52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment (OCT 2015)
52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY
MATTERS (OCT 2018)
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations. (NOV 2015)
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) -
ALTERNATE I (APR 1984)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
52.211-18 VARIATION IN ESTIMATED QUANTITY (APR 1984)
52.214-26 Audit and Records--Sealed Bidding (OCT 2010)
52.214-27 PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA -
MODIFICATIONS - SEALED BIDDING. (AUG 2011)
52.214-28 Subcontractor CERTIFIED Cost or Pricing Data - Modifications - Sealed Bidding. (OCT 2010) . 110
52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (DEVIATION 2020-O0008) (MAR 2020) .. 111
52.219-8 UTILIZATION OF SMALL BUSINESS CONCERNS (OCT 2018)
52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION 2020-O0008) (MAR 2020)
52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2020)
52.222-3 Convict Labor (JUN 2003)
52.222-4 Contract Work Hours and Safety Standards - Overtime Compensation (MAY 2018)
52.222-6 Construction Wage Rate Requirements (AUG 2018)
52.222-7 WITHHOLDING OF FUNDS (MAY 2014)
52.222-8 PAYROLLS AND BASIC RECORDS (AUG 2018)
52.222-9 APPRENTICES AND TRAINEES (JUL 2005)
52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS (FEB 1988)
52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014)
52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014)
52.222-13 Compliance With Construction Wage Rate Requirements and Related Regulations (MAY 2014)
52.222-14 DISPUTES CONCERNING LABOR STANDARDS (FEB 1988)
52.222-15 CERTIFICATION OF ELIGIBILITY (MAY 2014)
52.222-21 PROHIBITION OF SEGREGATED FACILITIES (APR 2015)
52.222-26 EQUAL OPPORTUNITY (SEPT 2016)
52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION (APR
2015)
52.222-30 CONSTRUCTION WAGE RATE REQUIREMENTS--PRICE ADJUSTMENT (NONE OR
SEPARATELY SPECIFIED METHOD) (AUG 2018)
52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015)
52.222-36 Equal Opportunity for Workers with Disabilities (JUL 2014)
52.222-37 EMPLOYMENT REPORTS ON VETERANS (FEB 2016)
52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT
(DEC 2010)
52.222-50 COMBATING TRAFFICKING IN PERSONS (JAN 2019)
52.222-54 Employment Eligibility Verification (OCT 2015)
52.222-55 Minimum Wages Under Executive Order 13658 (DEC 2015)
52.222-62 Paid Sick Leave Under Executive Order 13706 (JAN 2017)
52.223-2 AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND
CONSTRUCTION CONTRACTS (SEP 2013)
52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION (MAY 2011)
52.223-6 DRUG-FREE WORKPLACE (MAY 2001)
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-
DESIGNATED ITEMS (MAY 2008)
52.223-17 AFFIRMATIVE PROCUREMENT OF EPA-DESIGNATED ITEMS IN SERVICE AND
CONSTRUCTION CONTRACTS (AUG 2018)
52.223-18 ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING
(AUG 2011)
52.225-11 BUY AMERICAN--CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT
2019)
52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES (JUN 2008)
52.227-1 AUTHORIZATION AND CONSENT (DEC 2007)
52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT
(DEC 2007)
52.227-4 PATENT INDEMNITY--CONSTRUCTION CONTRACTS (DEC 2007)
52.228-2 ADDITIONAL BOND SECURITY (OCT 1997)
52.228-5 INSURANCE--WORK ON A GOVERNMENT INSTALLATION (JAN 1997)
52.228-12 Prospective Subcontractor Requests for Bonds. (MAY 2014)
52.228-14 IRREVOCABLE LETTER OF CREDIT (NOV 2014)
52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)
52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (MAY 2014)
52.232-16 PROGRESS PAYMENTS (MAR 2020) (DEVIATION 2020-O0010)
52.232-17 INTEREST (MAY 2014)
52.232-23 ASSIGNMENT OF CLAIMS (MAY 2-14) - ALTERNATE I (APR 1984)
52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)
52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD
MANAGEMENT (OCT 2018)
52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013)
52.232-40 PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS (DEC
2013)
52.233-1 Disputes. (MAY 2014)
52.233-3 PROTEST AFTER AWARD (AUG. 1996)
52.233-4 APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM (OCT 2004)
52.236-2 DIFFERING SITE CONDITIONS (APR 1984)
52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK (APR 1984)
52.236-4 PHYSICAL DATA (APR 1984)
52.236-5 MATERIAL AND WORKMANSHIP (APR 1984)
52.236-6 SUPERINTENDENCE BY THE CONTRACTOR (APR 1984)
52.236-7 PERMITS AND RESPONSIBILITIES (NOV 1991)
52.236-8 OTHER CONTRACTS (APR 1984)
52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS (APR 1984)
52.236-10 OPERATIONS AND STORAGE AREAS (APR 1984)
52.236-11 USE AND POSSESSION PRIOR TO COMPLETION (APR 1984)
52.236-12 CLEANING UP (APR 1984)
52.236-13 ACCIDENT PREVENTION (NOV 1991)
52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS (APR 1984)
52.236-16 QUANTITY SURVEYS (APR 1984) - ALTERNATE I (APR 1984)
52.236-17 LAYOUT OF WORK (APR 1984)
52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) - ALTERNATE I
(APR 1984
52.236-26 PRECONSTRUCTION CONFERENCE (FEB 1995)
52.242-13 BANKRUPTCY (JUL 1995)
52.242-14 SUSPENSION OF WORK (APR 1984)
52.243-4 CHANGES (JUN 2007)
52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS (AUG 2019)
52.246-12 INSPECTION OF CONSTRUCTION (AUG 1996)
52.246-21 WARRANTY OF CONSTRUCTION (MAR 1994)
52.248-3 VALUE ENGINEERING--CONSTRUCTION (OCT 2015)
52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (APR 2012) -
ALTERNATE I (SEP 1996)
52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984)
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
252.201-7000 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 1991)
252.203-7000 REQUIREMENTS RELATING TO COMPENSATION OF FORMER DOD OFFICIALS (SEP
2011)
252.203-7001 PROHIBITION ON PERSONS CONVICTED OF FRAUD OR OTHER DEFENSE-
CONTRACT-RELATED FELONIES (DEC 2008)
252.203-7002 REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS (SEP 2013)
252.203-7003 AGENCY OFFICE OF THE INSPECTOR GENERAL (AUG 2019)
252.203-7004 DISPLAY OF HOTLINE POSTERS (AUG 2019)
252.204-7003 CONTROL OF GOVERNMENT PERSONNEL WORK PRODUCT (APR 1992)
252.204-7004 Level I Antiterrorism Awareness Training for Contractors (FEB 2019)
252.204-7015 NOTICE OF AUTHORIZED DISCLOSURE OF INFORMATION FOR LITIGATION
SUPPORT (MAY 2016)
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services (Dec 2019)
252.205-7000 PROVISION OF INFORMATION TO COOPERATIVE AGREEMENT HOLDERS (DEC
1991)
252.209-7004 SUBCONTRACTING WITH FIRMS THAT ARE OWNED OR CONTROLLED BY THE ... 214
GOVERNMENT OF A COUNTRY THAT IS A STATE SPONSOR OF TERRORISM (MAY 2019)
252.223-7008 Prohibition of Hexavalent Chromium (JUN 2013)
252.225-7012 PREFERENCE FOR CERTAIN DOMESTIC COMMODITIES (DEC 2017)
252.225-7048 Export-Controlled Items (June 2013)
252.227-7033 RIGHTS IN SHOP DRAWINGS (APR 1966)
252.232-7010 LEVIES ON CONTRACT PAYMENTS (DEC 2006)
252.236-7000 MODIFICATION PROPOSALS - PRICE BREAKDOWN. (DEC 1991)
252.236-7002 OBSTRUCTION OF NAVIGABLE WATERWAYS. (DEC 1991)
252.236-7008 CONTRACT PRICES - BIDDING SCHEDULES. (DEC 1991)
252.242-7006 ACCOUNTING SYSTEM ADMINISTRATION (FEB 2012)
252.243-7001 PRICING OF CONTRACT MODIFICATIONS (DEC 1991)
252.243-7002 REQUESTS FOR EQUITABLE ADJUSTMENT (DEC 2012)
252.244-7000 SUBCONTRACTS FOR COMMERCIAL ITEMS (JUN 2013)
252.247-7023 TRANSPORTATION OF SUPPLIES BY SEA (FEB 2019)
5152.211-9001 VARIATIONS IN ESTIMATED QUANTITIES — SUBLINE ITEMS (DEC 2019)
Section 00 73 00 - Supplementary Conditions
SUPPLEMENTARY CONDITIONS
Insurance
Invoice Procedures
Floating Plant Equipment
Obstruction of Channel
Signal Lights
Equipment Ownership and Operating Expense Schedule
OPTION FOR ADDITIONAL WORK (Construction)
APPLICABLE WAGE DECISION
BASIS FOR SETTLEMENT OF PROPOSALS
APPARENT CLERICAL MISTAKES
WAGE DETERMINATION
Section 00 10 00 - Solicitation
BID SCHEDULE
ITEM
NO.
DESCRIPTION QUANTITY
UNIT
UNIT PRICE
AMOUNT
BASE
0001 BONDS (PERFORMANCE AND
PAYMENT)
1 JOB $ $
0002 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
GRANULAR FILL - AREA F14 (TAIL)
0002AA FIRST 45,000 CY 45,000 CY $ $
0002AB OVER 45,000 CY 6,000 CY $ $
0003 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
BERM MIXTURE – AREA F14 (TAIL)
0003AA FIRST 7,500 CY 7,500 CY $ $
0003AB OVER 7,500 CY 1,000 CY $ $
0004 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
FINE FILL – AREA F14 (TAIL)
0004AA FIRST 5,500 CY 5,500 CY $ $
0004AB OVER 5,500 CY 500 CY $ $
0005 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
BERM MIXTURE – AREA F14 (NON-TAIL) TEST AREA
B
0005AA FIRST 14,000 CY 14,000 CY $ $
0005AB OVER 14,000 CY 800 CY $ $
0006 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
GRANULAR FILL – AREA F14 (NON-TAIL)
0006AA FIRST 6,000 CY 6,000 CY $ $
0006AB OVER 6,000 CY 5,000 CY $ $
0007 RIPRAP – AREA R4
0007AA FIRST 12,500 TON 12,500 TON $ $
0007AB OVER 12,500 TON 1,500 TON $ $
0008 RIPRAP – AREA W1
0008AA FIRST 4,000 TON 4,000 TON $ $
0008AB OVER 4,000 TON 500 TON $ $
0009 TURF ESTABLISHMENT - AREA F14 (TAIL)
0009AA FIRST 4.5 ACRE 4.5 ACRE $ $
0009AB OVER 4.5 ACRE 0.5 ACRE $ $
0010 TURF ESTABLISHMENT - AREA F14 (NON-TAIL) TEST
AREA B
0010AA FIRST 1.5 ACRE 1.5 ACRE $ $
0010AB OVER 1.5 ACRE 0.5 ACRE $ $
0011 WILLOWS - AREA F14 (TAIL)
0011AA SUPPLIED - FIRST 6,000 EACH 6,000 EA $ $
0011AB SUPPLIED - OVER 6,000 EACH 500 EA $ $
0011BB INSTALLED – FIRST 6,000 EACH 6,000 EA $ $
0011BC INSTALLED – OVER 6,000 EACH 500 EA $ $
TOTAL BASE $________________
OPTION 1
1001 BONDS (PERFORMANCE AND
PAYMENT)
1 JOB $ $
1002 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
GRANULAR FILL – AREA F15
1002AA FIRST 29,500 CY 29,500 CY $ $
1002AB OVER 29,500 CY 6,700 CY $ $
1003 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
BERM MIXTURE – AREA F15
1003AA FIRST 7,600 CY 7,600 CY $ $
1003AB OVER 7,600 CY 1,000 CY $ $
1004 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
FINE FILL – AREA F15
1004AA FIRST 5,800 CY 5,800 CY $ $
1004AB OVER 5,800 CY 500 CY $ $
1005 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
GRANULAR FILL – AREA F16
1005AA FIRST 55,000 CY 55,000 CY $ $
1005AB OVER 55,000 CY 16,000 CY $ $
1006 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
BERM MIXTURE – AREA F16
1006AA FIRST 11,700 CY 11,700 CY $ $
1006AB OVER 11,700 CY 1,000 CY $ $
1007 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
FINE FILL – AREA F16
1007AA FIRST 8,900 CY 8,900 CY $ $
1007AB OVER 8,900 CY 500 CY $ $
1008 RIPRAP – AREA R2
1008AA FIRST 2,000 TON 2,000 TON $ $
1008AB OVER 2,000 TON 200 TON $ $
1009 TURF ESTABLISHMENT - AREA F15
1009AA FIRST 4.0 ACRE 4.0 ACRE $ $
1009AB OVER 4.0 ACRE 0.5 ACRE $ $
1010 TURF ESTABLISHMENT - AREA F16
1010AA FIRST 7.0 ACRE 7.0 ACRE $ $
1010AB OVER 7.0 ACRE 0.5 ACRE $ $
1011 WILLOWS - AREA F15
1011AA SUPPLIED - FIRST 5,600 EACH 5,600 EA $ $
1011AB SUPPLIED - OVER 5,600 EACH 600 EA $ $
1011BB INSTALLED – FIRST 5,600 EACH 5,600 EA $ $
1011BC INSTALLED – OVER 5,600 EACH 600 EA $ $
1012 WILLOWS - AREA F16
1012AA SUPPLIED - FIRST 10,600 EACH 10,600 EA $ $
1012AB SUPPLIED - OVER 10,600 EACH 1,200 EA $ $
1012BB INSTALLED – FIRST 10,600 EACH 10,600 EA $ $
1012BC INSTALLED – OVER 10,600 EACH 1,200 EA $ $
TOTAL OPTION 1 $________________
OPTION 2
2001 BONDS (PERFORMANCE AND
PAYMENT)
1 JOB $ $
2002 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
GRANULAR FILL – AREA F4B
2002AA FIRST 52,000 CY 52,000 CY $ $
2002AB OVER 52,000 CY 14,000 CY $ $
2003 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
BERM MIXTURE – AREA F4B
2003AA FIRST 104,000 CY 104,000 CY $ $
2003AB OVER 104,000 CY 10,000 CY $ $
2004 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
FINE FILL – AREA F4B
2004AA FIRST 32,000 CY 32,000 CY $ $
2004AB OVER 32,000 CY 3,000 CY $ $
2005 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
FINE FILL – AREA F8
2005AA FIRST 7,000 CY 7,000 CY $ $
2005AB OVER 7,000 CY 500 CY $ $
2006 RIPRAP – AREA C1
2006AA FIRST 225 TON 225 TON $ $
2006AB OVER 225 TON 25 TON $ $
2007 TURF ESTABLISHMENT - AREA F4B
2007AA FIRST 17.0 ACRE 17.0 ACR
E
2007AB OVER 17.0 ACRE 0.5 ACR $ $
E
2008 WILLOWS - AREA F4B
2008AA SUPPLIED - FIRST 1,800 EACH 1,800 EA $ $
2008AB SUPPLIED - OVER 1,800 EACH 200 EA $ $
2008BB INSTALLED – FIRST 1,800 EACH 1,800 EA $ $
2008BC INSTALLED – OVER 1,800 EACH 200 EA $ $
TOTAL OPTION 2 $________________________
OPTION 3
3001 BONDS (PERFORMANCE AND
PAYMENT)
1 JOB $ $
3002 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
BERM MIXTURE – AREA F14 (NON-TAIL)
3002AA FIRST 17,000 CY 17,000 CY $ $
3002AB OVER 17,000 CY 2,000 CY $ $
3003 BERM AND FLOODPLAIN FOREST CONSTRUCTION –
FINE FILL – AREA F14 (NON-TAIL)
3003AA FIRST 12,600 CY 12,600 CY $ $
3003AB OVER 12,600 CY 1,400 CY $ $
3004 RIPRAP WITH CHINKING STONE – AREA R1
3004AA FIRST 1,650 TON 1,650 TON $ $
3004AB OVER 1,650 TON 150 TON $ $
3005 WILLOWS – AREA F14 (NON-TAIL)
3005AA SUPPLIED - FIRST 1,800 EA 1,800 EA $ $
3005AB SUPPLIED - OVER 1,800 EA 225 EA $ $
3005BB INSTALLED – FIRST 1,800 EA 1,800 EA $ $
3005BC INSTALLED – OVER 1,800 EA 225 EA $ $
3006 TURF ESTABLISHMENT – AREA F14 (NON-TAIL)
3006AA FIRST 6.0 ACRE 6.0 AC $ $
3006AB OVER 6.0 ACRE 0.5 AC $ $
TOTAL OPTION 3 $__________________________
TOTAL CONTRACT (BASE PLUS ALL OPTIONS) $__________________________
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Bonds
FFP
BONDS (PERFORMANCE AND PAYMENT)
FOB: Destination
NET AMT
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
BERM AND FLOODPLAIN FOREST CONSTRUCTION - GRANULAR FILL -
AREA F14 (TAIL)
0002AA 45,000 Cubic
Yard
FIRST 45,000 CY
FFP
0002AB 6,000 Cubic
OVER 45,000 CY
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
BERM AND FLOODPLAIN FOREST CONSTRUCTION - BERM MIXTURE -
AREA F14 (TAIL)
0003AA 7,500 Cubic
FIRST 7,500 CY
FIRST 7,500 CY
0003AB 1,000 Cubic
OVER 7,500 CY
OVER 7,500 CY
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
BERM AND FLOODPLAIN FOREST CONSTRUCTION - FINE FILL - AREA
F14 (TAIL)
0004AA 5,500 Cubic
FIRST 5,500 CY
FIRST 5,500 CY
0004AB 500 Cubic
OVER 5,500 CY
OVER 5,500 CY
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F14 (NON-TAIL) TEST AREA B
0005AA 14,000 Cubic
FIRST 14,000 CY
FIRST 14,000 CY
0005AB 800 Cubic
OVER 14,000 CY
OVER 14,000 CY
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F14 (NON-TAIL)
0006AA 6,000 Cubic
FIRST 6,000 CY
FIRST 6,000 CY
0006AB 5,000 Cubic
OVER 6,000 CY
OVER 6,000 CY
RIPRAP - AREA R4
RIPRAP - AREA R4
0007AA 12,500 Net Ton
(2,000
LB).
FIRST 12,500 TON
FIRST 12,500 TON
0007AB 1,500 Net Ton
OVER 12,500 TON
OVER 12,500 TON
RIPRAP - AREA W1
RIPRAP - AREA W1
0008AA 4,000 Net Ton
FIRST 4,000 TON
FIRST 4,000 TON
0008AB 500 Net Ton
OVER 4,000 TON
OVER 4,000 TON
TURF ESTABLISHMENT - AREA F14 (TAIL)
TURF ESTABLISHMENT - AREA F14 (TAIL)
0009AA 4.50 Acre
FIRST 4.5 ACRE
FFP
FIRST 4.5 ACRE
0009AB .50 Acre
OVER 4.5 ACRE
FFP
OVER 4.5 ACRE
TURF ESTABLISHMENT - AREA F14 (NON-TAIL)
TURF ESTABLISHMENT - AREA F14 (NON-TAIL) TEST AREA B
0010AA 1.50 Acre
FIRST 1.5 ACRE
FFP
FIRST 1.5 ACRE
0010AB .50 Acre
OVER 1.5 ACRE
FFP
OVER 1.5 ACRE
WILLOWS - AREA F14 (TAIL)
WILLOWS - AREA F14 (TAIL)
0011AA 6,000 Each
SUPPLIED - FIRST 6,000 EACH
FFP
SUPPLIED - FIRST 6,000 EACH
0011AB 500 Each
SUPPLIED - OVER 6,000 EACH
FFP
SUPPLIED - OVER 6,000 EACH
0011BB 6,000 Each
INSTALLED - FIRST 6,000 EACH
FFP
INSTALLED - FIRST 6,000 EACH
0011BC 500 Each
INSTALLED - OVER 6,000 EACH
FFP
INSTALLED - OVER 6,000 EACH
1001 1 Job
OPTION BONDS (PERFORMANCE AND PAYMENT)
FFP
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F15
1002AA 29,500 Cubic
OPTION FIRST 29,500 CY
FIRST 29,500 CY
1002AB 6,700 Cubic
OPTION OVER 29,500 CY
OVER 29,500 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F15
1003AA 7,600 Cubic
OPTION FIRST 7,600 CY
FIRST 7,600 CY
1003AB 1,000 Cubic
OPTION OVER 7,600 CY
OVER 7,600 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
F15
1004AA 5,800 Cubic
OPTION FIRST 5,800 CY
FIRST 5,800 CY
1004AB 500 Cubic
OPTION OVER 5,800 CY
OVER 5,800 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F16
1005AA 55,000 Cubic
OPTION FIRST 55,000 CY
FIRST 55,000 CY
1005AB 16,000 Cubic
OPTION OVER 55,000 CY
OVER 55,000 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F16
1006AA 11,700 Cubic
OPTION FIRST 11,700 CY
FIRST 11,700 CY
1006AB 1,000 Cubic
OPTION OVER 11,700 CY
OVER 11,700 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
F16
1007AA 8,900 Cubic
OPTION FIRST 8,900 CY
FIRST 8,900 CY
1007AB 500 Cubic
OPTION OVER 8,900 CY
OVER 8,900 CY
OPTION RIPRAP - AREA R2
RIPRAP - AREA R2
1008AA 2,000 Net Ton
OPTION FIRST 2,000 TON
FIRST 2,000 TON
1008AB 200 Net Ton
OPTION OVER 2,000 TON
OVER 2,000 TON
OPTION TURF ESTABLISHMENT - AREA F15
TURF ESTABLISHMENT - AREA F15
1009AA 4 Acre
OPTION FIRST 4.0 ACRE
FFP
FIRST 4.0 ACRE
1009AB .50 Acre
OPTION OVER 4.0 ACRE
FFP
OVER 4.0 ACRE
OPTION TURF ESTABLISHMENT - AREA F16
TURF ESTABLISHMENT - AREA F16
1010AA 7 Acre
OPTION FIRST 7.0 ACRE
FFP
FIRST 7.0 ACRE
1010AB .50 Acre
OPTION OVER 7.0 ACRE
FFP
OVER 7.0 ACRE
OPTION WILLOWS - AREA F15
WILLOWS - AREA F15
1011AA 5,600 Each
OPTION SUPPLIED - FIRST 5,600 EACH
FFP
SUPPLIED - FIRST 5,600 EACH
1011AB 600 Each
OPTION SUPPLIED - OVER 5,600 EACH
FFP
SUPPLIED - OVER 5,600 EACH
1011BB 5,600 Each
OPTION INSTALLED - FIRST 5,600 EACH
FFP
INSTALLED - FIRST 5,600 EACH
1011BC 600 Each
OPTION INSTALLED - OVER 5,600 EACH
FFP
INSTALLED - OVER 5,600 EACH
OPTION WILLOWS - AREA F16
WILLOWS - AREA F16
1012AA 10,600 Each
OPTION SUPPLIED - FIRST 10,600 EACH
FFP
SUPPLIED - FIRST 10,600 EACH
1012AB 1,200 Each
OPTION SUPPLIED - OVER 10,600 EACH
FFP
SUPPLIED - OVER 10,600 EACH
1012BB 10,600 Each
OPTION INSTALLED - FIRST 10,600 EACH
FFP
INSTALLED - FIRST 10,600 EACH
1012BC 1,200 Each
OPTION INSTALLED - OVER 10,600 EACH
FFP
INSTALLED - OVER 10,600 EACH
BONDS (PERFORMANCE AND PAYMENT)
FFP
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F4B
2002AA 52,000 Cubic
OPTION FIRST 52,000 CY
FIRST 52,000 CY
2002AB 14,000 Cubic
OPTION OVER 52,000 CY
OVER 52,000 CY
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F4B
2003AA 104,000 Cubic
OPTION FIRST 104,000 CY
FIRST 104,000 CY
2003AB 10,000 Cubic
OPTION OVER 104,000 CY
OVER 104,000 CY
BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
F4B
2004AA 32,000 Cubic
OPTION FIRST 32,000 CY
FIRST 32,000 CY
2004AB 3,000 Cubic
OPTION OVER 32,000 CY
OVER 32,000 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
F8
2005AA 7,000 Cubic
OPTION FIRST 7,000 CY
FIRST 7,000 CY
2005AB 500 Cubic
OPTION OVER 7,000 CY
OVER 7,000 CY
OPTION RIPRAP - AREA C1
RIPRAP - AREA C1
2006AA 225 Net Ton
OPTION FIRST 225 TON
FIRST 225 TON
2006AB 25 Net Ton
OPTION OVER 225 TON
OVER 225 TON
OPTION TURF ESTABLISHMENT - AREA F4B
TURF ESTABLISHMENT - AREA F4B
2007AA 17 Acre
OPTION FIRST 17.0 ACRE
FFP
FIRST 17.0 ACRE
2007AB .50 Acre
OPTION OVER 17.0 ACRE
FFP
OVER 17.0 ACRE
OPTION WILLOWS - AREA F4B
WILLOWS - AREA F4B
2008AA 1,800 Each
OPTION SUPPLIED - FIRST 1,800 EACH
FFP
SUPPLIED - FIRST 1,800 EACH
2008AB 200 Each
OPTION SUPPLIED - OVER 1,800 EACH
SUPPLIED - OVER 1,800 EACH
2008BB 1,800 Each
OPTION INSTALLED - FIRST 1,800 EACH
FFP
INSTALLED - FIRST 1,800 EACH
2008BC 200 Each
OPTION INSTALLED - OVER 1,800 EACH
FFP
INSTALLED - OVER 1,800 EACH
3001 1 Job
OPTION BONDS (PERFORMANCE AND PAYMENT)
FFP
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
AREA F14 (NON-TAIL)
3002AA 17,000 Cubic
OPTION FIRST 17,000 CY
FIRST 17,000 CY
3002AB 2,000 Cubic
OPTION OVER 17,000 CY
OVER 17,000 CY
OPTION BERM AND FLOODPLAIN FOREST CONSTRUCTION
FFP
F14 (NON-TAIL)
3003AA 12,600 Cubic
OPTION FIRST 12,600 CY
FIRST 12,600 CY
3003AB 1,400 Cubic
OPTION OVER 12,600 CY
OVER 12,600 CY
OPTION RIPRAP WITH CHINKING STONE - AREA R1
RIPRAP WITH CHINKING STONE - AREA R1
3004AA 1,650 Net Ton
OPTION FIRST 1,650 TON
FIRST 1,650 TON
3004AB 150 Net Ton
OPTION OVER 1,650 TON
OVER 1,650 TON
OPTION WILLOWS - AREA F14 (NON-TAIL)
WILLOWS - AREA F14 (NON-TAIL)
3005AA 1,800 Each
OPTION SUPPLIED - FIRST 1,800 EA
FFP
SUPPLIED - FIRST 1,800 EA
3005AB 225 Each
OPTION SUPPLIED - OVER 1,800 EA
FFP
SUPPLIED - OVER 1,800 EA
3005BB 1,800 Each
OPTION INSTALLED - FIRST 1,800 EA
FFP
INSTALLED - FIRST 1,800 EA
3005BC 225 Each
OPTION INSTALLED - OVER 1,800 EA
FFP
INSTALLED - OVER 1,800 EA
OPTION TURF ESTABLISHMENT - AREA F14 (NON-TAIL)
3006AA 6 Acre
OPTION FIRST 6.0 ACRE
FFP
FIRST 6.0 ACRE
3006AB .50 Acre
OPTION OVER 6.0 ACRE
FFP
OVER 6.0 ACRE
INFORMATION TO BIDDERS
1. BIDDER INQUIRIES. Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must submit their questions using the ProjNet system at https://www.projnet.org
Clause 52.214-6 requires that all inquiries be submitted in writing. To submit a new inquiry or to view inquiries submitted by other prospective bidders, users must be registered and signed into the ProjNet system . Bidders may register online at https://www.projnet.org (click on “Register”). The following information will be needed to submit or view bidder inquiries:
Managing Agency: USACE The Solicitation Number is: W912ES20B0019 The Bidder Inquiry “Key” Number is: J8M5JG-9EFZ9W
Bidders shall submit inquiries not later than 10 days prior to bid opening in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation if necessary. Those who submit an inquiry will receive a system-generated email acknowledgement. All answers to inquiries will be posted in ProjNet after they have been reviewed by the USACE technical team. Bidders are advised to review the solicitation in its entirety and to review all previously submitted questions and responses prior to submitting a new inquiry.
2. RESPONSIBILITY DETERMINATION. In accordance with Federal Acquisition Regulation (FAR) Subpart 9.1, the apparent low bidder will be requested to provide the following information:
a. A detailed description of the work to be self-performed and resources available to demonstrate the firm is capable of complying with: 52.219-14, Limitations on Subcontracting.
https://www.projnet.org/
b. Financial Statements, including balance sheets that identify major categories of assets, liabilities, and owner’s equity; and profit and loss statements for the past three (3) years.
c. A Bank Certification of Financial Capability (line of credit).
Bidder qualification information, as referenced below, must be received by the Contracting Officer within two (2) business days after the bid opening. This information will be treated as confidential commercial or financial information to the extent permitted by law under exemption 4 to the Freedom of Information Act, 5 U.S.C. § 552(b)(4). The financial statements should be not over 60 days old. If over 60 days old, a certification should be attached stating that the financial condition of the firm is substantially the same or, if not the same, the changes that have taken place.
3. FACSIMILE OF BIDS AND MODIFICATIONS THERETO WILL NOT BE ACCEPTED.
4. This solicitation and any forthcoming amendments will only be available on www.beta.sam.gov.
It is recommended that each registered firm check this website periodically for updates.
5. All Quantities are estimated except where unit is given as "EA" (each) or "JOB" (job).
6. All extensions of the unit prices shown will be subject to verification by the Government. In case of a discrepancy between the unit price and the extension, the unit price will govern.
(a) For the purpose of initial evaluation of bids, the following will be utilized in resolving arithmetic discrepancies found on the face of bidding schedule as submitted by the bidder:
(1) Obviously misplaced decimal points will be corrected;
(2) Discrepancy between unit price and extended price, the unit price will govern;
(3) Apparent errors in extension of unit prices will be corrected;
(4) Apparent errors in addition of lump sum and extended prices will be corrected.
(b) For the purpose of bid evaluation, the Government will proceed on the assumption that the bidder intends its bid to be evaluated on the basis of the unit prices, the totals arrived at by resolution of arithmetic discrepancies as provided above and the bid will be so reflected on the abstract of bids.
7. UNBALANCED BIDS. The government may reject as non-responsive any bid that is materially unbalanced between contract line item numbers or sub-items on the bidding schedule. A bid is materially unbalanced when it is based on prices that are significantly less than cost for some work and significantly more than cost for other work. A materially unbalanced bid may be rejected if the Contracting Officer has a reasonable doubt as to whether the bid will result in the lowest overall cost to the government even though it may be the low evaluated bid. Additionally, a bid that is unbalanced so as to be tantamount to an advance payment will be rejected as non-responsive even if acceptance of the bid would result in the lowest overall cost to the government. Reference is made to paragraph (d) of clause 52.214-19, “Contract Award
– Sealed Bidding – Construction.”
8. REQUIREMENT FOR BID GUARANTEE. Each bidder shall submit with its bid a Bid Bond (current version of Standard Form 24) with good and sufficient surety or sureties acceptable to the Government or other security as provided in the clause BID GUARANTEE in the form of twenty percent (20%) of the bid price or $3,000,000 whichever is lesser. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents.
9. BIDDER QUALIFICATIONS. Before a bid is considered for award, the bidder may be requested by the Government to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial resources, and plant available to be used in performing the work.
10. ALL OR NONE QUALIFICATIONS. A vendor must provide a price on all items in this solicitation to be eligible for award. The Government will award on an “All or None” basis. Evaluation of bids will be based upon only the total price included on the pricing schedule for all items. If options are included in the pricing schedule the evaluation will be conducted in accordance with the applicable option clause in the solicitation.
Section 00 21 13 - Instructions to Bidders
52.204-16 Commercial and Government Entity Code Reporting (JUL 2016)
(a) Definition. As used in this provision--
Commercial and Government Entity (CAGE) code means—
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity;
or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
(b) The Offeror shall enter its CAGE code in its offer with its name and address or otherwise include it prominently in its proposal. The CAGE code entered must be for that name and address. Enter ``CAGE'' before the number. The CAGE code is required prior to award.
(c) CAGE codes may be obtained via--
(1) Registration in the System for Award Management (SAM) at www.sam.gov. If the Offeror is located in the United States or its outlying areas and does not already have a CAGE code assigned, the DLA Commercial and Government Entity (CAGE) Branch will assign a CAGE code as a part of the SAM registration process. SAM registrants located outside the United States and its outlying areas shall obtain a NCAGE code prior to registration in SAM (see paragraph (c)(3) of this provision).
(2) The DLA Commercial and Government Entity (CAGE) Branch. If registration in SAM is not required for the subject procurement, and the offeror does not otherwise register in SAM, an offeror located in the United States or its outlying areas may request that a CAGE code be assigned by submitting a request at https://cage.dla.mil.
(3) The appropriate country codification bureau. Entities located outside the United States and its outlying areas may obtain an NCAGE code by contacting the Codification Bureau in the foreign entity's country if that country is a member of NATO or a sponsored nation. NCAGE codes may be obtained from the NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx if the foreign entity's country is not a member of NATO or a sponsored nation. Points of contact for codification bureaus, as well as additional information on obtaining NCAGE codes, are available at http://www.nato.int/structur/AC/135/main/links/contacts.htm.
(d) Additional guidance for establishing and maintaining CAGE codes is available at https://cage.dla.mil.
(e) When a CAGE Code is required for the immediate owner and/or the highest-level owner by 52.204-17 or 52.212-3(p), the Offeror shall obtain the respective CAGE Code from that entity to supply the CAGE Code to the Government.
(f) Do not delay submission of the offer pending receipt of a CAGE code.
(End of Provision)
52.204-22 Alternative Line Item Proposal (JAN 2017) http://www.sam.gov/ https://cage.dla.mil/ https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx http://www.nato.int/structur/AC/135/main/links/contacts.htm https://cage.dla.mil/
(a) The Government recognizes that the line items established in this solicitation may not conform to the Offeror's practices. Failure to correct these issues can result in difficulties in acceptance of deliverables and processing payments. Therefore, the Offeror is invited to propose alternative line items for which bids, proposals, or quotes are requested in this solicitation to ensure that the resulting contract is economically and administratively advantageous to the Government and the Offeror.
(b) The Offeror may submit one or more additional proposals with alternative line items, provided that alternative line items are consistent with subpart 4.10 of the Federal Acquisition Regulation. However, acceptance of an alternative proposal is a unilateral decision made solely at the discretion of the Government. Offers that do not comply with the line items specified in this solicitation may be determined to be nonresponsive or unacceptable.
(End of provision)
52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)
(a) Definitions. As used in this provision--
Administrative proceeding means a non-judicial process that is adjudicatory in nature in order to make a determination of fault or liability (e.g., Securities and Exchange Commission Administrative Proceedings, Civilian Board of Contract Appeals Proceedings, and Armed Services Board of Contract Appeals Proceedings). This includes administrative proceedings at the Federal and State level but only in connection with performance of a Federal contract or grant. It does not include agency actions such as contract audits, site visits, corrective plans, or inspection of deliverables.
Federal contracts and grants with total value greater than $10,000,000 means--
(1) The total value of all current, active contracts and grants, including all priced options; and
(2) The total value of all current, active orders including all priced options under indefinite-delivery, indefinite-quantity, 8(a), or requirements contracts (including task and delivery and multiple-award Schedules).
Principal means an officer, director, owner, partner, or a person having primary management or supervisory responsibilities within a business entity (e.g., general manager; plant manager; head of a division or business segment; and similar positions).
(b) The offeror ( ) has ( ) does not have current active Federal contracts and grants with total value greater than $10,000,000.
(c) If the offeror checked “has” in paragraph (b) of this provision, the offeror represents, by submission of this offer, that the information it has entered in the Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete as of the date of submission of this offer with regard to the following information:
(1) Whether the offeror, and/or any of its principals, has or has not, within the last five years, in connection with the award to or performance by the offeror of a Federal contract or grant, been the subject of a proceeding, at the Federal or State level that resulted in any of the following dispositions:
(i) In a criminal proceeding, a conviction.
(ii) In a civil proceeding, a finding of fault and liability that results in the payment of a monetary fine, penalty, reimbursement, restitution, or damages of $5,000 or more.
(iii) In an administrative proceeding, a finding of fault and liability that results in--
(A) The payment of a monetary fine or penalty of $5,000 or more; or
(B) The payment of a reimbursement, restitution, or damages in excess of $100,000.
(iv) In a criminal, civil, or administrative proceeding, a disposition of the matter by consent or compromise with an acknowledgment of fault by the Contractor if the proceeding could have led to any of the outcomes specified in paragraphs (c)(1)(i), (c)(1)(ii), or (c)(1)(iii) of this provision.
(2) If the offeror has been involved in the last five years in any of the occurrences listed in (c)(1) of this provision, whether the offeror has provided the requested information with regard to each occurrence.
(d) The offeror shall post the information in paragraphs (c)(1)(i) through (c)(1)(iv) of this provision in FAPIIS as required through maintaining an active registration in the System for Award Management, which can be accessed via https://www.sam.gov (see 52.204-7).
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
52.214-4 FALSE STATEMENTS IN BIDS (APR 1984)
Bidders must provide full, accurate, and complete information as required by this solicitation and its attachments.
The penalty for making false statements in bids is prescribed in 18 U.S.C. 1001.
https://www.sam.gov/
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount…