Bid Abstract McGregot Lake HREP.pdf

PDF 172 KB Posted

Attached to
McGregor Lake Habitat Rehab & Enchancement Project
Solicitation number
W912ES20B0019
Issued by

About this file

This document contains an abstract of bids received in response to a federal contract solicitation for the McGregor Lake Habitat Rehabilitation and Enhancement Project.

The solicitation was issued by the US Army Corps of Engineers and involves construction of floodplain forests, berms, habitat dredge channels, and erosion protection structures within McGregor Lake and the Mississippi River between Marquette, Iowa and Prairie du Chien, Wisconsin. The anticipated value of the project is between $10-25 million.

Four contractors submitted bids, with total amounts ranging from $17.6-32.6 million. The base work and three options include items such as bonds, construction of berms using various fill materials, riprap installation, willow and turf establishment. Unit pricing and totals are provided for each bidder. The abstract records all offers received and will be used to evaluate bids and select a contractor in accordance with federal procurement regulations.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

McGregor Lake Habitat Rehabilitation & Enhancement Project Solicitation Number: W912ES20B0019 US Army Corps of Engineers. 180 East 5th Street, Suite 700. Saint Paul, Minnesota 55101 BID OPENING: August 11 2020 at 1400

Contracting Officer: Kevin Henricks Contract Specialist: Jesse Onkka

Unit Unit Unit Unit Item Description Quantity Unit Price Amount Price Amount Price Amount Price Amount

Base 0001 Bonds (Performance And Payment) 1 JOB $36,292.00 $36,292.00 $35,000.00 $35,000.00 $70,000.00 $70,000.00 $26,852.00 $26,852.00 0002 Berm and Floodplain Forest Construction – Granular Fill - Area F14 (tail)

0002AA FIRST 45,000 CY 45,000 CY $16.15 $726,750.00 $31.30 $1,408,500.00 $57.52 $2,588,400.00 $60.00 $2,700,000.00 0002AB OVER 45,000 CY 6,000 CY $16.15 $96,900.00 $21.65 $129,900.00 $27.28 $163,680.00 $30.31 $181,860.00

0003 Berm and floodplain forest construction – berm mixture – area f14 (tail) 0003AA First 7,500 CY 7,500 CY $20.83 $156,225.00 $45.30 $339,750.00 $89.54 $671,550.00 $35.32 $264,900.00 0003AB Over 7,500 CY 1,000 CY $20.83 $20,830.00 $35.65 $35,650.00 $55.74 $55,740.00 $35.32 $35,320.00

0004 Berm and floodplain forest construction – fine fill – area f14 (tail) 0004AA FIRST 5,500 CY 5,500 CY $62.69 $344,795.00 $40.00 $220,000.00 $72.35 $397,925.00 $45.26 $248,930.00 0004AB OVER 5,500 CY 500 CY $62.69 $31,345.00 $30.35 $15,175.00 $42.40 $21,200.00 $45.26 $22,630.00 area b 0005AA FIRST 14,000 CY 14,000 CY $24.14 $337,960.00 $45.80 $641,200.00 $89.54 $1,253,560.00 $33.94 $475,160.00 0005AB OVER 14,000 CY 800 CY $24.14 $19,312.00 $36.15 $28,920.00 $55.74 $44,592.00 $31.00 $24,800.00

0006 berm and floodplain forest construction – granular fill – area f14 (non-tail) 0006AA FIRST 6,000 CY 6,000 CY $10.58 $63,480.00 $31.30 $187,800.00 $56.93 $341,580.00 $24.00 $144,000.00 0006AB OVER 6,000 CY 5,000 CY $10.58 $52,900.00 $21.65 $108,250.00 $27.28 $136,400.00 $26.08 $130,400.00

0007 riprap – area r4 0007AA First 12,500 TON 12,500 TON $60.59 $757,375.00 $46.00 $575,000.00 $83.32 $1,041,500.00 $45.18 $564,750.00 0007AB Over 12,500 TON 1,500 TON $60.59 $90,885.00 $46.00 $69,000.00 $51.89 $77,835.00 $45.18 $67,770.00

0008 Riprap – area w1 0008AA First 4,000 TON 4,000 TON $62.07 $248,280.00 $60.00 $240,000.00 $83.32 $333,280.00 $61.00 $244,000.00 0008AB Over 4,000 TON 500 TON $62.07 $31,035.00 $60.00 $30,000.00 $51.89 $25,945.00 $61.00 $30,500.00

0009 turf establishment - Area F14 (tail) 0009AA First 4.5 ACRE 5 ACRE $7,632.00 $34,344.00 $2,500.00 $11,250.00 $5,022.89 $22,603.01 $7,106.60 $31,979.70 0009AB Over 4.5 ACRE 1 ACRE $7,566.00 $3,783.00 $2,500.00 $1,250.00 $5,022.89 $2,511.45 $7,106.60 $3,553.30

0010 turf establishment - Area F14 (non-tail) Test Area B 0010AA First 1.5 ACRE 2 ACRE $8,303.00 $12,454.50 $2,500.00 $3,750.00 $5,022.89 $7,534.34 $7,106.60 $10,659.90 0010AB Over 1.5 ACRE 0.5 ACRE $8,233.00 $4,116.50 $2,500.00 $1,250.00 $5,022.89 $2,511.45 $7,106.60 $3,553.30

0011 willows - Area F14 (tail) 0011AA Supplied - First 6,000 EACH 6,000 EA $5.10 $30,600.00 $1.00 $6,000.00 $1.23 $7,380.00 $6.40 $38,400.00 0011AB Supplied - Over 6,000 EACH 500 EA $5.10 $2,550.00 $1.00 $500.00 $1.23 $615.00 $6.40 $3,200.00 0011BB installed – first 6,000 each 6,000 EA $1.35 $8,100.00 $3.00 $18,000.00 $2.77 $16,620.00 $2.26 $13,560.00 0011BC installed – over 6,000 each 500 EA $1.35 $675.00 $3.00 $1,500.00 $2.77 $1,385.00 $2.26 $1,130.00

$3,110,987.00 $4,107,645.00 $7,284,347.23 $5,267,908.20

Option 1 1001 Bonds (Performance And Payment) 1 JOB $49,332.00 $49,332.00 $47,000.00 $47,000.00 $78,000.00 $78,000.00 $25,400.00 $25,400.00 1002 berm and floodplain forest construction – granular fill – area f15

1002AA FIRST 29,500 CY 29,500 CY $17.25 $508,875.00 $28.90 $852,550.00 $49.14 $1,449,630.00 $44.00 $1,298,000.00 1002AB OVER 29,500 CY 6,700 CY $17.25 $115,575.00 $25.85 $173,195.00 $26.91 $180,297.00 $28.00 $187,600.00

1003 berm and floodplain forest construction – berm mixture – area f15 1003AA First 7,600 CY 7,600 CY $21.41 $162,716.00 $42.85 $325,660.00 $81.32 $618,032.00 $35.36 $268,736.00 1003AB Over 7,600 CY 1,000 CY $21.41 $21,410.00 $39.80 $39,800.00 $54.99 $54,990.00 $35.36 $35,360.00

1004 berm and floodplain forest construction – fine fill – area f15 1004AA FIRST 5,800 CY 5,800 CY $29.71 $172,318.00 $39.30 $227,940.00 $64.35 $373,230.00 $45.75 $265,350.00 1004AB OVER 5,800 CY 500 CY $29.71 $14,855.00 $36.25 $18,125.00 $41.83 $20,915.00 $45.75 $22,875.00

1005 berm and floodplain forest construction – granular fill – area f16

Kaiyuh Services LLC Shinn Kellogg LLC

Base Total

Government Estimate Dubuque Barge & Fleeting Co. DBA Newt Marine

1005AA FIRST 55,000 CY 55,000 CY $17.15 $943,250.00 $28.90 $1,589,500.00 $49.14 $2,702,700.00 $27.00 $1,485,000.00 1005AB OVER 55,000 CY 16,000 CY $17.15 $274,400.00 $25.85 $413,600.00 $26.91 $430,560.00 $24.00 $384,000.00

1006 berm and floodplain forest construction – berm mixture – area f16 1006AA First 11,700 CY 11,700 CY $21.41 $250,497.00 $42.35 $495,495.00 $81.32 $951,444.00 $33.00 $386,100.00 1006AB Over 11,700 CY 1,000 CY $21.41 $21,410.00 $39.30 $39,300.00 $54.99 $54,990.00 $33.00 $33,000.00

1007 berm and floodplain forest construction – fine fill – area f16 1007AA FIRST 8,900 CY 8,900 CY $60.26 $536,314.00 $38.30 $340,870.00 $64.35 $572,715.00 $45.63 $406,107.00 1007AB OVER 8,900 CY 500 CY $60.26 $30,130.00 $35.25 $17,625.00 $41.83 $20,915.00 $45.63 $22,815.00

1008 riprap – area r2 1008AA First 2,000 TON 2,000 TON $62.86 $125,720.00 $47.00 $94,000.00 $75.17 $150,340.00 $58.00 $116,000.00 1008AB Over 2,000 TON 200 TON $62.86 $12,572.00 $47.00 $9,400.00 $51.19 $10,238.00 $58.00 $11,600.00

1009 turf establishment - Area F15 1009AA First 4.0 ACRE 4 ACRE $7,521.00 $30,084.00 $2,500.00 $10,000.00 $4,970.03 $19,880.12 $7,087.55 $28,350.20 1009AB Over 4.0 ACRE 0.5 ACRE $7,461.00 $3,730.50 $2,500.00 $1,250.00 $4,970.03 $2,485.02 $7,087.56 $3,543.78

1010 turf establishment - Area F16 1010AA First 7.0 ACRE 7 ACRE $7,529.00 $52,703.00 $2,500.00 $17,500.00 $4,970.03 $34,790.21 $7,087.55 $49,612.85 1010AB Over 7.0 ACRE 0.5 ACRE $7,461.00 $3,730.50 $2,500.00 $1,250.00 $4,970.03 $2,485.02 $7,087.56 $3,543.78

1011 willows - Area F15 1011AA SUPPLIED - First 5,600 EACH 5,600 EA $5.03 $28,168.00 $1.00 $5,600.00 $1.21 $6,776.00 $6.38 $35,728.00 1011AB SUPPLIED - Over 5,600 EACH 600 EA $5.03 $3,018.00 $1.00 $600.00 $1.21 $726.00 $6.38 $3,828.00 1011BB INSTALLED – FIRST 5,600 EACH 5,600 EA $1.33 $7,448.00 $3.00 $16,800.00 $2.73 $15,288.00 $2.25 $12,600.00 1011BC INSTALLED – OVER 5,600 EACH 600 EA $1.33 $798.00 $3.00 $1,800.00 $2.73 $1,638.00 $2.25 $1,350.00

1012 willows - Area F16 1012AA SUPPLIED - First 10,600 EACH 10,600 EA $5.03 $53,318.00 $1.00 $10,600.00 $1.21 $12,826.00 $6.38 $67,628.00 1012AB SUPPLIED - Over 10,600 EACH 1,200 EA $5.03 $6,036.00 $1.00 $1,200.00 $1.21 $1,452.00 $6.38 $7,656.00 1012BB INSTALLED – FIRST 10,600 EACH 10,600 EA $1.33 $14,098.00 $3.00 $31,800.00 $2.73 $28,938.00 $2.25 $23,850.00 1012BC INSTALLED – OVER 10,600 EACH 1,200 EA $1.33 $1,596.00 $3.00 $3,600.00 $2.73 $3,276.00 $2.25 $2,700.00

$3,444,102.00 $4,786,060.00 $7,799,556.36 $5,188,333.61

Option 2 2001 Bonds (Performance And Payment) 1 JOB $131,291.00 $131,291.00 $60,000.00 $60,000.00 $136,600.00 $136,600.00 $37,900.00 $37,900.00 2002 berm and floodplain forest construction – granular fill – area f4b

2002AA FIRST 52,000 CY 52,000 CY $35.75 $1,859,000.00 $21.70 $1,128,400.00 $44.12 $2,294,240.00 $45.69 $2,375,880.00 2002AB OVER 52,000 CY 14,000 CY $35.75 $500,500.00 $16.70 $233,800.00 $25.21 $352,940.00 $23.11 $323,540.00

2003 berm and floodplain forest construction – berm mixture – area f4b 2003AA First 104,000 CY 104,000 CY $38.43 $3,996,720.00 $35.10 $3,650,400.00 $75.33 $7,834,320.00 $29.00 $3,016,000.00 2003AB Over 104,000 CY 10,000 CY $38.43 $384,300.00 $30.10 $301,000.00 $52.65 $526,500.00 $29.00 $290,000.00

2004 berm and floodplain forest construction – fine fill – area f4b 2004AA FIRST 32,000 CY 32,000 CY $63.13 $2,020,160.00 $39.10 $1,251,200.00 $57.82 $1,850,240.00 $41.19 $1,318,080.00 2004AB OVER 32,000 CY 3,000 CY $63.13 $189,390.00 $34.10 $102,300.00 $39.19 $117,570.00 $41.19 $123,570.00

2005 berm and floodplain forest construction – FINE FILL – area f8 2005AA FIRST 7,000 CY 7,000 CY $67.52 $472,640.00 $39.10 $273,700.00 $57.82 $404,740.00 $52.39 $366,730.00 2005AB OVER 7,000 CY 500 CY $67.52 $33,760.00 $34.10 $17,050.00 $39.19 $19,595.00 $51.23 $25,615.00

2006 riprap – area c1 2006AA First 225 TON 225 TON $63.57 $14,303.25 $75.00 $16,875.00 $67.96 $15,291.00 $76.00 $17,100.00 2006AB Over 225 TON 25 TON $63.57 $1,589.25 $75.00 $1,875.00 $47.95 $1,198.75 $73.00 $1,825.00

2007 turf establishment - Area F4B 2007AA First 17.0 ACRE 17 ACRE $7,572.00 $128,724.00 $2,500.00 $42,500.00 $4,831.56 $82,136.52 $7,087.55 $120,488.35 2007AB Over 17.0 ACRE 0.5 ACRE $7,506.00 $3,753.00 $2,500.00 $1,250.00 $4,831.56 $2,415.78 $7,087.56 $3,543.78

2008 willows - Area F4B 2008AA SUPPLIED - First 1,800 EACH 1,800 EA $5.02 $9,036.00 $1.00 $1,800.00 $1.07 $1,926.00 $6.38 $11,484.00 2008AB SUPPLIED - Over 1,800 EACH 200 EA $5.02 $1,004.00 $1.00 $200.00 $1.07 $214.00 $6.38 $1,276.00 2008BB INSTALLED – FIRST 1,800 EACH 1,800 EA $1.34 $2,412.00 $3.00 $5,400.00 $2.41 $4,338.00 $2.25 $4,050.00 2008BC INSTALLED – OVER 1,800 EACH 200 EA $1.34 $268.00 $3.00 $600.00 $2.41 $482.00 $2.25 $450.00

$9,748,850.50 $7,088,350.00 $13,644,747.05 $8,037,532.13

Option 1 Total

Option 2 Total

Option 3 3001 Bonds (Performance And Payment) 1 JOB $26,944.00 $26,944.00 $12,000.00 $12,000.00 $39,000.00 $39,000.00 $8,500.00 $8,500.00

BERM AND FLOODPLAIN FOREST CONSTRUCTION – BERM MIXTURE –

AREA F14 (NON-TAIL)

3002AA First 17,000 CY 17,000 CY $25.63 $435,710.00 $45.30 $770,100.00 $122.96 $2,090,320.00 $52.00 $884,000.00 3002AB Over 17,000 CY 2,000 CY $25.63 $51,260.00 $34.55 $69,100.00 $61.98 $123,960.00 $29.00 $58,000.00

BERM AND FLOODPLAIN FOREST CONSTRUCTION – FINE FILL – AREA

F14 (NON-TAIL)

3003AA FIRST 12,600 CY 12,600 CY $45.91 $578,466.00 $41.30 $520,380.00 $103.84 $1,308,384.00 $40.56 $511,056.00 3003AB OVER 12,600 CY 1,400 CY $45.91 $64,274.00 $30.55 $42,770.00 $47.14 $65,996.00 $40.56 $56,784.00

3004 RIPRAP WITH CHINKING STONE – AREA R1

3004AA First 1,650 TON 1,650 TON $85.89 $141,718.50 $75.00 $123,750.00 $116.04 $191,466.00 $61.00 $100,650.00 3004AB Over 1,650 TON 150 TON $85.89 $12,883.50 $75.00 $11,250.00 $57.69 $8,653.50 $62.95 $9,442.50

3005 Willows – area f14 (non-tail) 3005AA supplied - first 1,800 ea 1,800 EA $6.18 $11,124.00 $1.00 $1,800.00 $1.40 $2,520.00 $6.38 $11,484.00 3005AB supplied - over 1,800 ea 225 EA $6.18 $1,390.50 $1.00 $225.00 $1.40 $315.00 $6.38 $1,435.50 3005BB INSTALLED – FIRST 1,800 EA 1,800 EA $1.64 $2,952.00 $3.00 $5,400.00 $3.15 $5,670.00 $2.25 $4,050.00 3005BC INSTALLED – OVER 1,800 EA 225 EA $1.64 $369.00 $3.00 $675.00 $3.15 $708.75 $2.25 $506.25

3006 TURF ESTABLISHMENT – AREA f14 (NON-TAIL) 3006AA FIRST 6.0 ACRE 6 AC $9,244.00 $55,464.00 $2,500.00 $15,000.00 $5,461.40 $32,768.40 $7,087.55 $42,525.30 3006AB OVER 6.0 ACRE 0.5 AC $9,171.00 $4,585.50 $2,500.00 $1,250.00 $5,461.40 $2,730.70 $7,087.56 $3,543.78

Option 3 Total $1,387,141.00 $1,573,700.00 $3,872,492.35 $1,691,977.33

Total Bid Amount for Base & All Options $17,691,080.50 $17,555,755.00 $32,601,142.99 $20,185,751.27

I certify that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.