19B0002_Mechanical_Dredging_Abstract_2019_-_2023.pdf

PDF 228 KB Posted

Attached to
Mechanical Dredging Federal contract opportunity
Solicitation number
W912ES19B0002
Issued by
Department of the Army Corps of Engineers Engineering District St Paul

About this file

This document describes a federal contract solicitation for mechanical dredging services. The U.S. Army Corps of Engineers St. Paul District intends to issue an Invitation for Bid seeking a contractor to perform dredging with backhoes, draglines or other mechanical equipment on marine plant, and transport dredged material to designated placement sites. The work includes maintenance dredging between Upper Mississippi River Miles 614.0 and 857.6 and between Minnesota River Miles 0.0 and 14.7. The procurement is set aside for total small businesses. The Government will award an Indefinite Delivery Indefinite Quantity contract consisting of a base period and four option periods, with an estimated price range of $1 million to $6 million for the base period. The appropriate NAICS code is 237990 (dredging) with a small business size standard of $36.5 million. To be considered a small business, a firm must perform at least 40 percent of dredging volume with its own equipment or that of another small dredging concern.

Bidder abstract from public bid opening held 09 May 2019.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mechanical Dredging, Mississippi and Minnesota Rivers US Army Corps of Engineers. 180 5th Street East, Suite 700, St. Paul, MN 55101-1678

Contracting Officer: Kevin P. Henricks Contract Specialist: MAJ Bryson Rossol

Government Estimate

Unit Unit Unit Unit Item Description Quantity Unit Price Amount Price Amount %+-IGE Price Amount %+-IGE Price Amount %+- IGE

0001 Mobilization and Demobilization 1 JOB $176,700.00 $176,700.00 $125,000.00 $125,000.00 70.74% $180,000.00 $180,000.00 101.87% $1,250,000.00 $1,250,000.00 707.41% 0002 Dredging 220,000 CY $9.25 $2,035,000.00 $9.10 $2,002,000.00 98.38% $12.60 $2,772,000.00 136.22% $9.50 $2,090,000.00 102.70% 0003 Transportation of Dredged Material 4-8 River Miles 70,000 CY $0.99 $69,300.00 $1.15 $80,500.00 116.16% $1.00 $70,000.00 101.01% $1.00 $70,000.00 101.01% 0004 Transportation of Dredged Material Over 8 River Miles 40,000 CY $0.99 $39,600.00 $0.40 $16,000.00 40.40% $1.50 $60,000.00 151.52% $0.80 $32,000.00 80.81% 0005 Transportation of Plant Between Dredging Sites 350 MI $261.00 $91,350.00 $190.00 $66,500.00 72.80% $250.00 $87,500.00 95.79% $200.00 $70,000.00 76.63% 0006 Standby 10 DAY $7,100.00 $71,000.00 $1,500.00 $15,000.00 21.13% $2,000.00 $20,000.00 28.17% $1,850.00 $18,500.00 26.06% 0007 Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 25,000 CY $1.98 $49,500.00 $2.40 $60,000.00 121.21% $2.00 $50,000.00 101.01% $1.75 $43,750.00 88.38%

0008 Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 30,000 CY $2.96 $88,800.00 $3.00 $90,000.00 101.35% $3.00 $90,000.00 101.35% $2.00 $60,000.00 67.57%

Highway Transportation of Material up to 10 Miles to Placement Sites 200,000 CY $8.75 $1,750,000.00 $1.75 $350,000.00 20.00% $1.00 $200,000.00 11.43% $1.25 $250,000.00 14.29%

0010 Dredging/Excavation at Temporary Placement Sites 20,000 CY $7.83 $156,600.00 $7.25 $145,000.00 92.59% $8.00 $160,000.00 102.17% $7.00 $140,000.00 89.40% 0011 Small Boat Harbor Dredging 2,000 CY $13.23 $26,460.00 $9.40 $18,800.00 71.05% $11.00 $22,000.00 83.14% $8.00 $16,000.00 60.47% 0012 Thalweg Placement 10,000 CY $1.19 $11,900.00 $0.50 $5,000.00 42.02% $0.50 $5,000.00 42.02% $0.50 $5,000.00 42.02% 0013 In-Water Placement 20,000 CY $0.66 $13,200.00 $0.30 $6,000.00 45.45% $2.00 $40,000.00 303.03% $0.50 $10,000.00 75.76%

TOTAL - BASE PERIOD - PRIMARY PLANT $4,579,410.00 $2,979,800.00 65.07% $3,756,500.00 82.03% $4,055,250.00 88.55%

0014 Mobilization and Demobilization 1 JOB $176,700.00 $176,700.00 $35,000.00 $35,000.00 19.81% $120,000.00 $120,000.00 67.91% $50,000.00 $50,000.00 28.30% 0015 Dredging 130,000 CY $9.25 $1,202,500.00 $8.65 $1,124,500.00 93.51% $12.60 $1,638,000.00 136.22% $9.50 $1,235,000.00 102.70% 0016 Transportation of Dredged Material 4-8 River Miles 20,000 CY $0.99 $19,800.00 $1.15 $23,000.00 116.16% $1.00 $20,000.00 101.01% $1.00 $20,000.00 101.01% 0017 Transportation of Dredged Material Over 8 River Miles 10,000 CY $0.99 $9,900.00 $0.40 $4,000.00 40.40% $1.50 $15,000.00 151.52% $0.80 $8,000.00 80.81% 0018 Transportation of Plant Between Dredging Sites 150 MI $261.00 $39,150.00 $190.00 $28,500.00 72.80% $300.00 $45,000.00 114.94% $200.00 $30,000.00 76.63% 0019 Standby 10 DAY $7,100.00 $71,000.00 $1,250.00 $12,500.00 17.61% $2,000.00 $20,000.00 28.17% $1,850.00 $18,500.00 26.06%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 40,000 CY $1.98 $79,200.00 $2.40 $96,000.00 121.21% $2.00 $80,000.00 101.01% $1.75 $70,000.00 88.38%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 20,000 CY $2.96 $59,200.00 $3.00 $60,000.00 101.35% $3.00 $60,000.00 101.35% $2.00 $40,000.00 67.57%

Highway Transportation of Material up to 10 Miles to Placement Sites 150,000 CY $8.75 $1,312,500.00 $1.75 $262,500.00 20.00% $1.00 $150,000.00 11.43% $1.25 $187,500.00 14.29%

0023 Dredging/Excavation at Temporary Placement Sites 20,000 CY $7.83 $156,600.00 $7.15 $143,000.00 91.32% $8.00 $160,000.00 102.17% $7.00 $140,000.00 89.40% 0024 Small Boat Harbor Dredging 2,000 CY $13.23 $26,460.00 $9.05 $18,100.00 68.41% $12.25 $24,500.00 92.59% $8.00 $16,000.00 60.47% 0025 Thalweg Placement 10,000 CY $1.19 $11,900.00 $0.45 $4,500.00 37.82% $0.50 $5,000.00 42.02% $0.50 $5,000.00 42.02% 0026 In-Water Placement 20,000 CY $0.66 $13,200.00 $0.30 $6,000.00 45.45% $2.00 $40,000.00 303.03% $0.50 $10,000.00 75.76%

TOTAL - BASE PERIOD - SECOND PLANT $3,178,110.00 $1,817,600.00 57.19% $2,377,500.00 74.81% $1,830,000.00 57.58%

TOTAL BASE PERIOD $7,757,520.00 $4,797,400.00 61.84% $6,134,000.00 79.07% $5,885,250.00 75.87%

BASE PERIOD - SECOND PLANT

BASE PERIOD - PRIMARY PLANT

LS Marine, Inc.

3000 Centerville Road, Suite D St. Paul, MN 55117

Dubuque Barge & Fleeting Service Co D/B/A Newt Marine Service 5 Jones Street Dubuque, IA 52001

Solicitation W912ES-19-B-0002

Legacy Corporation 16322 Barstow Road East Moline, IL 61244

Bid Opening: 09 May 2019 2:00 p.m. (CST)

1001 Mobilization and Demobilization 1 JOB $180,300.00 $180,300.00 $129,000.00 $129,000.00 71.55% $230,000.00 $230,000.00 127.57% $330,000.00 $330,000.00 183.03% 1002 Dredging 220,000 CY $9.44 $2,076,800.00 $9.25 $2,035,000.00 97.99% $13.00 $2,860,000.00 137.71% $9.75 $2,145,000.00 103.28% 1003 Transportation of Dredged Material 4-8 River Miles 70,000 CY $1.01 $70,700.00 $1.15 $80,500.00 113.86% $1.00 $70,000.00 99.01% $1.00 $70,000.00 99.01% 1004 Transportation of Dredged Material Over 8 River Miles 40,000 CY $1.01 $40,400.00 $0.40 $16,000.00 39.60% $1.50 $60,000.00 148.51% $0.80 $32,000.00 79.21% 1005 Transportation of Plant Between Dredging Sites 350 MI $266.00 $93,100.00 $190.00 $66,500.00 71.43% $300.00 $105,000.00 112.78% $200.00 $70,000.00 75.19% 1006 Standby 10 DAY $7,200.00 $72,000.00 $1,500.00 $15,000.00 20.83% $2,000.00 $20,000.00 27.78% $1,850.00 $18,500.00 25.69%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 25,000 CY $2.02 $50,500.00 $2.40 $60,000.00 118.81% $2.00 $50,000.00 99.01% $1.75 $43,750.00 86.63%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 30,000 CY $3.02 $90,600.00 $3.00 $90,000.00 99.34% $3.00 $90,000.00 99.34% $2.00 $60,000.00 66.23%

Highway Transportation of Material up to 10 Miles to Placement Sites 200,000 CY $8.93 $1,786,000.00 $1.75 $350,000.00 19.60% $1.00 $200,000.00 11.20% $1.25 $250,000.00 14.00%

1010 Dredging/Excavation at Temporary Placement Sites 20,000 CY $7.99 $159,800.00 $7.40 $148,000.00 92.62% $8.00 $160,000.00 100.13% $7.00 $140,000.00 87.61% 1011 Small Boat Harbor Dredging 2,000 CY $13.50 $27,000.00 $9.55 $19,100.00 70.74% $12.50 $25,000.00 92.59% $8.00 $16,000.00 59.26% 1012 Thalweg Placement 10,000 CY $1.21 $12,100.00 $0.50 $5,000.00 41.32% $0.50 $5,000.00 41.32% $0.50 $5,000.00 41.32% 1013 In-Water Placement 20,000 CY $0.67 $13,400.00 $0.30 $6,000.00 44.78% $2.00 $40,000.00 298.51% $0.50 $10,000.00 74.63%

TOTAL - FIRST OPTION YEAR - PRIMARY PLANT $4,672,700.00 $3,020,100.00 64.63% $3,915,000.00 83.78% $3,190,250.00 68.27%

1014 Mobilization and Demobilization 1 JOB $180,300.00 $180,300.00 $40,000.00 $40,000.00 22.19% $60,000.00 $60,000.00 33.28% $40,000.00 $40,000.00 22.19% 1015 Dredging 130,000 CY $9.44 $1,227,200.00 $8.80 $1,144,000.00 93.22% $13.00 $1,690,000.00 137.71% $9.75 $1,267,500.00 103.28% 1016 Transportation of Dredged Material 4-8 River Miles 20,000 CY $1.01 $20,200.00 $1.15 $23,000.00 113.86% $1.00 $20,000.00 99.01% $1.00 $20,000.00 99.01% 1017 Transportation of Dredged Material Over 8 River Miles 10,000 CY $1.01 $10,100.00 $0.40 $4,000.00 39.60% $1.50 $15,000.00 148.51% $0.80 $8,000.00 79.21% 1018 Transportation of Plant Between Dredging Sites 150 MI $266.00 $39,900.00 $190.00 $28,500.00 71.43% $300.00 $45,000.00 112.78% $200.00 $30,000.00 75.19% 1019 Standby 10 DAY $7,200.00 $72,000.00 $1,250.00 $12,500.00 17.36% $2,000.00 $20,000.00 27.78% $1,850.00 $18,500.00 25.69%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 40,000 CY $2.02 $80,800.00 $2.40 $96,000.00 118.81% $2.00 $80,000.00 99.01% $1.75 $70,000.00 86.63%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 20,000 CY $3.02 $60,400.00 $3.00 $60,000.00 99.34% $3.00 $60,000.00 99.34% $2.00 $40,000.00 66.23%

Highway Transportation of Material up to 10 Miles to Placement Sites 150,000 CY $8.93 $1,339,500.00 $1.75 $262,500.00 19.60% $1.00 $150,000.00 11.20% $1.25 $187,500.00 14.00%

1023 Dredging/Excavation at Temporary Placement Sites 20,000 CY $7.99 $159,800.00 $7.30 $146,000.00 91.36% $8.00 $160,000.00 100.13% $7.00 $140,000.00 87.61% 1024 Small Boat Harbor Dredging 2,000 CY $13.50 $27,000.00 $9.20 $18,400.00 68.15% $12.25 $24,500.00 90.74% $8.00 $16,000.00 59.26% 1025 Thalweg Placement 10,000 CY $1.21 $12,100.00 $0.50 $5,000.00 41.32% $0.50 $5,000.00 41.32% $0.50 $5,000.00 41.32% 1026 In-Water Placement 20,000 CY $0.67 $13,400.00 $0.30 $6,000.00 44.78% $2.00 $40,000.00 298.51% $0.50 $10,000.00 74.63%

TOTAL - FIRST OPTION YEAR - SECOND PLANT $3,242,700.00 $1,845,900.00 56.92% $2,369,500.00 73.07% $1,852,500.00 57.13%

TOTAL FIRST OPTION YEAR $7,915,400.00 $4,866,000.00 61.48% $6,284,500.00 79.40% $5,042,750.00 63.71%

FIRST OPTION PERIOD - SECOND PLANT

FIRST OPTION YEAR - PRIMARY PLANT

2001 Mobilization and Demobilization 1 JOB $183,800.00 $183,800.00 $133,000.00 $133,000.00 72.36% $280,000.00 $280,000.00 152.34% $335,000.00 $335,000.00 182.26% 2002 Dredging 220,000 CY $9.62 $2,116,400.00 $9.40 $2,068,000.00 97.71% $13.00 $2,860,000.00 135.14% $9.95 $2,189,000.00 103.43% 2003 Transportation of Dredged Material 4-8 River Miles 70,000 CY $1.03 $72,100.00 $1.20 $84,000.00 116.50% $1.00 $70,000.00 97.09% $1.00 $70,000.00 97.09% 2004 Transportation of Dredged Material Over 8 River Miles 40,000 CY $1.03 $41,200.00 $0.40 $16,000.00 38.83% $1.50 $60,000.00 145.63% $0.80 $32,000.00 77.67% 2005 Transportation of Plant Between Dredging Sites 350 MI $271.00 $94,850.00 $190.00 $66,500.00 70.11% $300.00 $105,000.00 110.70% $200.00 $70,000.00 73.80% 2006 Standby 10 DAY $7,400.00 $74,000.00 $1,500.00 $15,000.00 20.27% $2,000.00 $20,000.00 27.03% $1,850.00 $18,500.00 25.00%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 25,000 CY $2.05 $51,250.00 $2.40 $60,000.00 117.07% $2.00 $50,000.00 97.56% $1.75 $43,750.00 85.37%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 30,000 CY $3.08 $92,400.00 $3.00 $90,000.00 97.40% $3.00 $90,000.00 97.40% $2.00 $60,000.00 64.94%

Highway Transportation of Material up to 10 Miles to Placement Sites 200,000 CY $9.10 $1,820,000.00 $1.75 $350,000.00 19.23% $1.00 $200,000.00 10.99% $1.25 $250,000.00 13.74%

2010 Dredging/Excavation at Temporary Placement Sites 20,000 CY $8.14 $162,800.00 $7.55 $151,000.00 92.75% $10.00 $200,000.00 122.85% $7.00 $140,000.00 86.00% 2011 Small Boat Harbor Dredging 2,000 CY $13.76 $27,520.00 $9.70 $19,400.00 70.49% $12.50 $25,000.00 90.84% $8.00 $16,000.00 58.14% 2012 Thalweg Placement 10,000 CY $1.24 $12,400.00 $0.50 $5,000.00 40.32% $0.50 $5,000.00 40.32% $0.50 $5,000.00 40.32% 2013 In-Water Placement 20,000 CY $0.68 $13,600.00 $0.30 $6,000.00 44.12% $2.00 $40,000.00 294.12% $0.50 $10,000.00 73.53%

TOTAL - SECOND OPTION YEAR - PRIMARY PLANT $4,762,320.00 $3,063,900.00 64.34% $4,005,000.00 84.10% $3,239,250.00 68.02%

2014 Mobilization and Demobilization 1 JOB $183,800.00 $183,800.00 $42,000.00 $42,000.00 22.85% $70,000.00 $70,000.00 38.08% $40,000.00 $40,000.00 21.76% 2015 Dredging 130,000 CY $9.62 $1,250,600.00 $8.95 $1,163,500.00 93.04% $13.00 $1,690,000.00 135.14% $9.95 $1,293,500.00 103.43% 2016 Transportation of Dredged Material 4-8 River Miles 20,000 CY $1.03 $20,600.00 $1.20 $24,000.00 116.50% $1.00 $20,000.00 97.09% $1.00 $20,000.00 97.09% 2017 Transportation of Dredged Material Over 8 River Miles 10,000 CY $1.03 $10,300.00 $0.40 $4,000.00 38.83% $1.50 $15,000.00 145.63% $0.80 $8,000.00 77.67% 2018 Transportation of Plant Between Dredging Sites 150 MI $271.00 $40,650.00 $190.00 $28,500.00 70.11% $300.00 $45,000.00 110.70% $200.00 $30,000.00 73.80% 2019 Standby 10 DAY $7,400.00 $74,000.00 $1,250.00 $12,500.00 16.89% $2,000.00 $20,000.00 27.03% $1,850.00 $18,500.00 25.00%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 40,000 CY $2.05 $82,000.00 $2.40 $96,000.00 117.07% $2.00 $80,000.00 97.56% $1.75 $70,000.00 85.37%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 20,000 CY $3.08 $61,600.00 $3.00 $60,000.00 97.40% $3.00 $60,000.00 97.40% $2.00 $40,000.00 64.94%

Highway Transportation of Material up to 10 Miles to Placement Sites 150,000 CY $9.10 $1,365,000.00 $1.75 $262,500.00 19.23% $1.00 $150,000.00 10.99% $1.25 $187,500.00 13.74% Dredging/Excavation at Temporary Placement Sites 20,000 CY $8.14 $162,800.00 $7.45 $149,000.00 91.52% $10.00 $200,000.00 122.85% $7.00 $140,000.00 86.00%

2024 Small Boat Harbor Dredging 2,000 CY $13.76 $27,520.00 $9.35 $18,700.00 67.95% $12.25 $24,500.00 89.03% $8.00 $16,000.00 58.14% 2025 Thalweg Placement 10,000 CY $1.24 $12,400.00 $0.50 $5,000.00 40.32% $0.50 $5,000.00 40.32% $0.50 $5,000.00 40.32% 2026 In-Water Placement 20,000 CY $0.68 $13,600.00 $0.30 $6,000.00 44.12% $2.00 $40,000.00 294.12% $0.50 $10,000.00 73.53%

TOTAL - SECOND OPTION YEAR - SECOND PLANT $3,304,870.00 $1,871,700.00 56.63% $2,419,500.00 73.21% $1,878,500.00 56.84%

TOTAL SECOND OPTION YEAR $8,067,190.00 $4,935,600.00 61.18% $6,424,500.00 79.64% $5,117,750.00 63.44%

SECOND OPTION YEAR - PRIMARY PLANT

SECOND OPTION PERIOD - SECOND PLANT

3001 Mobilization and Demobilization 1 JOB $187,300.00 $187,300.00 $137,000.00 $137,000.00 73.14% $350,000.00 $350,000.00 186.87% $335,000.00 $335,000.00 178.86% 3002 Dredging 220,000 CY $9.81 $2,158,200.00 $9.55 $2,101,000.00 97.35% $13.20 $2,904,000.00 134.56% $10.15 $2,233,000.00 103.47% 3003 Transportation of Dredged Material 4-8 River Miles 70,000 CY $1.05 $73,500.00 $1.20 $84,000.00 114.29% $1.00 $70,000.00 95.24% $1.00 $70,000.00 95.24% 3004 Transportation of Dredged Material Over 8 River Miles 40,000 CY $1.05 $42,000.00 $0.40 $16,000.00 38.10% $1.50 $60,000.00 142.86% $0.80 $32,000.00 76.19% 3005 Transportation of Plant Between Dredging Sites 350 MI $277.00 $96,950.00 $190.00 $66,500.00 68.59% $300.00 $105,000.00 108.30% $200.00 $70,000.00 72.20% 3006 Standby 10 DAY $7,500.00 $75,000.00 $1,500.00 $15,000.00 20.00% $2,000.00 $20,000.00 26.67% $1,850.00 $18,500.00 24.67%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 25,000 CY $2.09 $52,250.00 $2.40 $60,000.00 114.83% $2.00 $50,000.00 95.69% $1.75 $43,750.00 83.73%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 30,000 CY $3.14 $94,200.00 $3.00 $90,000.00 95.54% $3.00 $90,000.00 95.54% $2.00 $60,000.00 63.69%

Highway Transportation of Material up to 10 Miles to Placement Sites 200,000 CY $9.28 $1,856,000.00 $1.75 $350,000.00 18.86% $1.00 $200,000.00 10.78% $1.25 $250,000.00 13.47%

3010 Dredging/Excavation at Temporary Placement Sites 20,000 CY $8.30 $166,000.00 $7.70 $154,000.00 92.77% $10.00 $200,000.00 120.48% $7.00 $140,000.00 84.34% 3011 Small Boat Harbor Dredging 2,000 CY $14.03 $28,060.00 $9.85 $19,700.00 70.21% $12.50 $25,000.00 89.09% $8.00 $16,000.00 57.02% 3012 Thalweg Placement 10,000 CY $1.26 $12,600.00 $0.50 $5,000.00 39.68% $0.50 $5,000.00 39.68% $0.50 $5,000.00 39.68% 3013 In-Water Placement 20,000 CY $0.70 $14,000.00 $0.30 $6,000.00 42.86% $2.00 $40,000.00 285.71% $0.50 $10,000.00 71.43%

TOTAL - THIRD OPTION YEAR - PRIMARY PLANT $4,856,060.00 $3,104,200.00 63.92% $4,119,000.00 84.82% $3,283,250.00 67.61%

3014 Mobilization and Demobilization 1 JOB $187,300.00 $187,300.00 $44,000.00 $44,000.00 23.49% $80,000.00 $80,000.00 42.71% $35,000.00 $35,000.00 18.69% 3015 Dredging 130,000 CY $9.81 $1,275,300.00 $9.10 $1,183,000.00 92.76% $13.20 $1,716,000.00 134.56% $10.15 $1,319,500.00 103.47% 3016 Transportation of Dredged Material 4-8 River Miles 20,000 CY $1.05 $21,000.00 $1.20 $24,000.00 114.29% $1.00 $20,000.00 95.24% $1.00 $20,000.00 95.24% 3017 Transportation of Dredged Material Over 8 River Miles 10,000 CY $1.05 $10,500.00 $0.40 $4,000.00 38.10% $1.50 $15,000.00 142.86% $0.80 $8,000.00 76.19% 3018 Transportation of Plant Between Dredging Sites 150 MI $277.00 $41,550.00 $190.00 $28,500.00 68.59% $300.00 $45,000.00 108.30% $200.00 $30,000.00 72.20% 3019 Standby 10 DAY $7,500.00 $75,000.00 $1,250.00 $12,500.00 16.67% $2,000.00 $20,000.00 26.67% $1,850.00 $18,500.00 24.67%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 40,000 CY $2.09 $83,600.00 $2.40 $96,000.00 114.83% $2.00 $80,000.00 95.69% $1.75 $70,000.00 83.73%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 20,000 CY $3.14 $62,800.00 $3.00 $60,000.00 95.54% $3.00 $60,000.00 95.54% $2.00 $40,000.00 63.69%

Highway Transportation of Material up to 10 Miles to Placement Sites 150,000 CY $9.28 $1,392,000.00 $1.75 $262,500.00 18.86% $1.00 $150,000.00 10.78% $1.25 $187,500.00 13.47%

3023 Dredging/Excavation at Temporary Placement Sites 20,000 CY $8.30 $166,000.00 $7.60 $152,000.00 91.57% $10.00 $200,000.00 120.48% $7.00 $140,000.00 84.34% 3024 Small Boat Harbor Dredging 2,000 CY $14.03 $28,060.00 $9.50 $19,000.00 67.71% $12.25 $24,500.00 87.31% $8.00 $16,000.00 57.02% 3025 Thalweg Placement 10,000 CY $1.26 $12,600.00 $0.50 $5,000.00 39.68% $0.50 $5,000.00 39.68% $0.50 $5,000.00 39.68% 3026 In-Water Placement 20,000 CY $0.70 $14,000.00 $0.30 $6,000.00 42.86% $2.00 $40,000.00 285.71% $0.50 $10,000.00 71.43%

TOTAL - THIRD OPTION YEAR - SECOND PLANT $3,369,710.00 $1,896,500.00 56.28% $2,455,500.00 72.87% $1,899,500.00 56.37%

TOTAL THIRD OPTION YEAR $8,225,770.00 $5,000,700.00 60.79% $6,574,500.00 79.93% $5,182,750.00 63.01%

THIRD OPTION YEAR - PRIMARY PLANT

THIRD OPTION PERIOD - SECOND PLANT

4001 Mobilization and Demobilization 1 JOB $190,900.00 $190,900.00 $141,000.00 $141,000.00 73.86% $380,000.00 $380,000.00 199.06% $335,000.00 $335,000.00 175.48% 4002 Dredging 220,000 CY $9.99 $2,197,800.00 $9.70 $2,134,000.00 97.10% $13.40 $2,948,000.00 134.13% $10.40 $2,288,000.00 104.10% 4003 Transportation of Dredged Material 4-8 River Miles 70,000 CY $1.07 $74,900.00 $1.25 $87,500.00 116.82% $1.00 $70,000.00 93.46% $1.00 $70,000.00 93.46% 4004 Transportation of Dredged Material Over 8 River Miles 40,000 CY $1.07 $42,800.00 $0.40 $16,000.00 37.38% $1.50 $60,000.00 140.19% $0.80 $32,000.00 74.77% 4005 Transportation of Plant Between Dredging Sites 350 MI $282.00 $98,700.00 $190.00 $66,500.00 67.38% $300.00 $105,000.00 106.38% $200.00 $70,000.00 70.92% 4006 Standby 10 DAY $7,700.00 $77,000.00 $1,500.00 $15,000.00 19.48% $2,000.00 $20,000.00 25.97% $1,850.00 $18,500.00 24.03%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 25,000 CY $2.13 $53,250.00 $2.40 $60,000.00 112.68% $2.00 $50,000.00 93.90% $1.75 $43,750.00 82.16%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 30,000 CY $3.20 $96,000.00 $3.00 $90,000.00 93.75% $3.00 $90,000.00 93.75% $2.00 $60,000.00 62.50%

Highway Transportation of Material up to 10 Miles to Placement Sites 200,000 CY $9.45 $1,890,000.00 $1.75 $350,000.00 18.52% $1.00 $200,000.00 10.58% $1.25 $250,000.00 13.23%

4010 Dredging/Excavation at Temporary Placement Sites 20,000 CY $8.46 $169,200.00 $7.85 $157,000.00 92.79% $10.00 $200,000.00 118.20% $7.00 $140,000.00 82.74% 4011 Small Boat Harbor Dredging 2,000 CY $14.29 $28,580.00 $10.00 $20,000.00 69.98% $12.00 $24,000.00 83.97% $8.00 $16,000.00 55.98% 4012 Thalweg Placement 10,000 CY $1.29 $12,900.00 $0.50 $5,000.00 38.76% $0.50 $5,000.00 38.76% $0.50 $5,000.00 38.76% 4013 In-Water Placement 20,000 CY $0.71 $14,200.00 $0.30 $6,000.00 42.25% $2.00 $40,000.00 281.69% $0.50 $10,000.00 70.42%

TOTAL - FOURTH OPTION YEAR - PRIMARY PLANT $4,946,230.00 $3,148,000.00 63.64% $4,192,000.00 84.75% $3,338,250.00 67.49%

4014 Mobilization and Demobilization 1 JOB $190,900.00 $190,900.00 $46,000.00 $46,000.00 24.10% $90,000.00 $90,000.00 47.15% $35,000.00 $35,000.00 18.33% 4015 Dredging 130,000 CY $9.99 $1,298,700.00 $9.25 $1,202,500.00 92.59% $13.40 $1,742,000.00 134.13% $10.40 $1,352,000.00 104.10% 4016 Transportation of Dredged Material 4-8 River Miles 20,000 CY $1.07 $21,400.00 $1.25 $25,000.00 116.82% $1.00 $20,000.00 93.46% $1.00 $20,000.00 93.46% 4017 Transportation of Dredged Material Over 8 River Miles 10,000 CY $1.07 $10,700.00 $0.40 $4,000.00 37.38% $1.50 $15,000.00 140.19% $0.80 $8,000.00 74.77% 4018 Transportation of Plant Between Dredging Sites 150 MI $282.00 $42,300.00 $190.00 $28,500.00 67.38% $300.00 $45,000.00 106.38% $200.00 $30,000.00 70.92% 4019 Standby 10 DAY $7,700.00 $77,000.00 $1,250.00 $12,500.00 16.23% $2,000.00 $20,000.00 25.97% $1,850.00 $18,500.00 24.03%

Overland Transportation of Dredge Material up to and including 0.5 Miles at Placement Sites With Special Consideration 40,000 CY $2.13 $85,200.00 $2.40 $96,000.00 112.68% $2.00 $80,000.00 93.90% $1.75 $70,000.00 82.16%

Overland Transportation of Dredge Material Over 0.5 Miles and up to and Including 1.5 Miles at Placement Sites With Special Consideration 20,000 CY $3.20 $64,000.00 $3.00 $60,000.00 93.75% $3.00 $60,000.00 93.75% $2.00 $40,000.00 62.50%

Highway Transportation of Material up to 10 Miles to Placement Sites 150,000 CY $9.45 $1,417,500.00 $1.75 $262,500.00 18.52% $1.00 $150,000.00 10.58% $1.25 $187,500.00 13.23%

4023 Dredging/Excavation at Temporary Placement Sites 20,000 CY $8.46 $169,200.00 $7.75 $155,000.00 91.61% $10.00 $200,000.00 118.20% $7.00 $140,000.00 82.74% 4024 Small Boat Harbor Dredging 2,000 CY $14.29 $28,580.00 $9.65 $19,300.00 67.53% $12.25 $24,500.00 85.72% $8.00 $16,000.00 55.98% 4025 Thalweg Placement 10,000 CY $1.29 $12,900.00 $0.50 $5,000.00 38.76% $0.50 $5,000.00 38.76% $0.50 $5,000.00 38.76% 4026 In-Water Placement 20,000 CY $0.71 $14,200.00 $0.30 $6,000.00 42.25% $2.00 $40,000.00 281.69% $0.50 $10,000.00 70.42%

TOTAL - FOURTH OPTION YEAR - SECOND PLANT $3,432,580.00 $1,922,300.00 56.00% $2,491,500.00 72.58% $1,932,000.00 56.28%

TOTAL FOURTH OPTION YEAR $8,378,810.00 $5,070,300.00 60.51% $6,683,500.00 79.77% $5,270,250.00 62.90%

TOTAL BID AMOUNT - BASE AND OPTIONS $40,344,690.00 $24,670,000.00 61.15% $32,101,000.00 79.57% $26,498,750.00 65.68%

NOTES:

1) The bid opening Government estimate contained clerical errors for CLINS 0009, 0022, 1009, 1022, 2009, 2022, 3009, 3022, 4009, 4022; the corrected Government estimate is $26,012,190.00

2) Clerical error made by Dubuque Barge & Fleeting Service Co in the third option year; bid discrepency of $20,000.00

I certify that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

Kevin P. Henricks Contracting Officer

FOURTH OPTION PERIOD - SECOND PLANT

FOURTH OPTION YEAR - PRIMARY PLANT

Sheet1

2019-05-16T12:59:57-0500
HENRICKS.KEVIN.PHILIP.1249726873

File details come from the government source that posted it. Updated .