16-B-0001-0004.pdf
PDF 74 KB Posted
- Attached to
- Marsh Lake Ecosystem Restoration Phases 1 and 2 Federal contract opportunity
- Solicitation number
- W912ES-16-B-0001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_W912ES-16-B-0001.pdf | ||
| W912ES-16-B-0001_Amendment_0007.pdf | ||
| MLER_SJ101-P1_HALF.pdf | ||
| MLER_SJ101-P1_FULL.pdf | ||
| 16-B-0001-0006.pdf | ||
| CS401-A6.pdf | ||
| 01_00_00.00_13_GENERAL_ATTACHMENTS_-_PERMITS.pdf | ||
| CS205-A6.pdf | ||
| Plan_Sheet_CS401.pdf | ||
| 16-B-0001-0005.pdf | ||
| Plan_Sheet_CH101.pdf | ||
| 16-B-0001-0003.pdf | ||
| 16-B-0001-0002.pdf | ||
| 16-B-0001-0001.pdf | ||
| W912ES-16-B-0001_FullSize.pdf | ||
| W912ES-16-B-0001_HalfSize.pdf | ||
| W912ES-16-B-0001_Specs.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W81G6761129348
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The reason for this amendment is to update the bid schedule and specifications. .
1. CONTRACT ID CODE PAGE OF PAGES
J 1 7
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Aug-2016
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912ES-16-B-0001
X 9B. DATED (SEE ITEM 11)
25-Jul-2016
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Aug-2016
CODE
CONTRACTING DIVISION
USACE - ST PAUL
180 5TH STREET EAST
SUITE 700
ST. PAUL MN 55101-1678
W912ES 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912ES-16-B-0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT #4
The following changes have been made to the solicitation:
Bid Schedule:
The Clearing and Grubbing CLIN (0016) has been removed from the “Outlet Channel Downstream Of Drawdown Structure” section of the bid schedule and added to the” Access Ramp, Road, And Parking Area West Of Drawdown Structure” section (CLIN 0022). The CLIN’s in these sections have been renumbered accordingly.
Clauses:
The CLIN numbers in clauses 52.211‐5000 & 52.211‐5001 have been updated to reflect the changes to the bid schedule.
Specifications:
Section 31 00 00.00 03:
Change paragraph 3.4 STRIPPING OF TOPSOIL to allow for excess stripped topsoil to be spread on site.
The current paragraph is as follows:
3.4 STRIPPING OF TOPSOIL
Topsoil shall be stripped to the depth indicated on the contract drawings or to the extent that all organic material has been removed. Topsoil shall be kept separate from other excavated materials, brush, litter, objectionable weeds, roots, stones larger than 1‐inch in diameter, and other materials that would interfere with planting and maintenance operations. Topsoil shall be spread on areas already graded and prepared for topsoil, or transported and deposited in stockpiles convenient to areas that are to receive application of the topsoil later, or placed at locations indicated or specified. Any surplus topsoil from excavations and grading shall be removed from the site.
The revision is as follows to allow material to be spread on site:
3.4 STRIPPING OF TOPSOIL
Topsoil shall be stripped to the depth indicated on the contract drawings or to the extent that all organic material has been removed. Topsoil shall be kept separate from other excavated materials, brush, litter, objectionable weeds, roots, stones larger than 1‐inch in diameter, and other materials that would interfere with planting and maintenance operations. Topsoil shall be spread on areas already graded and prepared for topsoil, or transported and deposited in stockpiles convenient to areas that are to receive application of the topsoil later, or placed at locations indicated or specified. Any surplus topsoil shall be spread on site within the work limits.
Change paragraph 3.5.5 Disposal of Excavated Material to remove the reference to material obtained from stripping operations.
The current paragraph is as follows:
3.5.5 Disposal of Excavated Material
Excavated material, including material obtained from stripping operations, that is in excess of what is required for use in the project or that is unsuitable for reuse in the project shall be disposed of at the designated borrow site at locations identified by the Contracting Officer, provided it does not contain woody or man made debris. Material shall be spread in lifts not to exceed 12 inches with tracked construction equipment and shall be shaped to provide positive drainage. Woody or man made debris shall be disposed of at an approved off site facility as identified in the Demolition Plan.
The revised paragraph is as follows:
3.5.5 Disposal of Excavated Material
Excavated material that is in excess of what is required for use in the project or that is unsuitable for reuse in the project shall be disposed of at the designated borrow site at locations identified by the Contracting Officer, provided it does not contain woody or man made debris. Material shall be spread in lifts not to exceed 12 inches with tracked construction equipment and shall be shaped to provide positive drainage. Woody or man made debris shall be disposed of at an approved off site facility as identified in the Demolition Plan.
Section 01 22 00.00 13:
Change paragraph 1.9.1.1 Payment to remove disposal of excess stripped material in accordance with the changes to Section 31 00 00.00 03 paragraph 3.4.
The current paragraph is as follows:
1.9.1.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary to complete stripping operations as shown and specified. Stripping shall be completed to the depths shown on the contract drawings or as directed by the Contracting Officer to remove all organic material and topsoil. Work shall include, but not be limited to, stripping vegetation, topsoil, and organic material within the limits shown, stockpiling of topsoil for reuse, and disposing of excess stripped materials. No payment will be made for stripping outside the limits of construction unless authorized.
The revision is as follows:
1.9.1.1 Payment
Payment will be made for furnishing all materials, equipment and labor and performing all operations necessary to complete stripping operations as shown and specified. Stripping shall be completed to the depths shown on the contract drawings or as directed by the Contracting Officer to remove all organic material and topsoil. Work shall include, but not be limited to, stripping vegetation, topsoil, and organic material within the limits shown, stockpiling of topsoil for reuse, and spreading of excess stripped materials on site. No payment will be made for stripping outside the limits of construction unless authorized.
SECTION 02 24 00.00 13
The following paragraph is added to 1.7
1.7.2 Disposal of Cofferdam Material
Soils used for cofferdam construction that are not reused elsewhere in the project shall be disposed of at the borrow site.
SECTION 00010 - SOLICITATION CONTRACT FORM
The required response date/time has changed from 24-Aug-2016 02:00 PM to 02-Sep-2016 02:00 PM.
CLIN 0016
This CLIN has been renumbered to CLIN 0022.
The CLIN extended description has changed from OUTLET CHANNEL DOWNSTREAM OF DRAWDOWN STRUCTURE to ACCESS RAMP, ROAD, AND PARKING AREA WEST OF DRAWDOWN
STRUCTURE.
CLIN 0017
This CLIN has been renumbered to CLIN 0016.
SUBCLIN 0017AA
This SUBCLIN has been renumbered to SUBCLIN 0016AA.
SUBCLIN 0017AB
This SUBCLIN has been renumbered to SUBCLIN 0016AB.
CLIN 0018
This CLIN has been renumbered to CLIN 0017.
CLIN 0019
This CLIN has been renumbered to CLIN 0018.
CLIN 0020
This CLIN has been renumbered to CLIN 0019.
CLIN 0021
This CLIN has been renumbered to CLIN 0020.
CLIN 0022
This CLIN has been renumbered to CLIN 0021.
DELIVERIES AND PERFORMANCE
The following Delivery Schedule Item has been deleted from CLIN 0016:
DELIVERY DATE QUANTITY SHIP TO ADDRESS UIC
28-NOV-2018 1 N/A
FOB: Destination
The following Delivery Schedule Item has been deleted from CLIN 0018:
28-NOV-2018 1,520 N/A
The following Delivery Schedule Item has been deleted from CLIN 0019:
28-NOV-2018 460 N/A
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been modified:
52.211-5000 EVALUATION OF SUBDIVIDED ITEMS
Item Nos: 0003, 0006, 0007, 0008, 0016, 0023, 0024, 0025, 0039, 0040, 0041, 0042, 0043, 0045, 0046, 0047, 0048, 1005, 1008, 1009, 1011, 1012, 1014, 1015, 1020, 1026, 1034, 1035, and 1039 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub-items.
(End of provision)
SECTION 00700 - CONTRACT CLAUSES
The following have been modified:
52.211-5001 VARIATIONS IN ESTIMATED QUANTITIES, SUBDIVIDED ITEMS
This variation in estimated quantities clause is applicable only to Items Nos. 0003, 0006, 0007, 0008, 0016, 0023, 0024, 0025, 0039, 0040, 0041, 0042, 0043, 0045, 0046, 0047, 0048, 1005, 1008, 1009, 1011, 1012, 1014, 1015, 1020, 1026, 1034, 1035, and 1039.
(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.
(b) Where the actual quantity of work performed for Items Nos 0003, 0006, 0007, 0008, 0016, 0023, 0024, 0025, 0039, 0040, 0041, 0042, 0043, 0045, 0046, 0047, 0048, 1005, 1008, 1009, 1011, 1012, 1014, 1015, 1020, 1026, 1034, 1035, and 1039is less than 85% of the quantity of the first sub-item listed under such item, the contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.
(c) If the actual quantity of work performed under Items Nos. 0003, 0006, 0007, 0008, 0016, 0023, 0024, 0025, 0039, 0040, 0041, 0042, 0043, 0045, 0046, 0047, 0048, 1005, 1008, 1009, 1011, 1012, 1014, 1015, 1020, 1026, 1034, 1035, and 1039exceeds 115% or is less than 85% of the total estimated quantity of the sub‐ item under that item and/or if the quantity of the work performed under the second sub‐item or any subsequent sub‐item under Items Nos. 0003, 0006, 0007, 0008, 0016, 0023, 0024, 0025, 0039, 0040, 0041, 0042, 0043, 0045, 0046, 0047, 0048, 1005, 1008, 1009, 1011, 1012, 1014, 1015, 1020, 1026, 1034, 1035, and 1039 exceeds 115% or is less than 85% of the estimated quantity of any such sub‐item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211‐18, Variation in Estimated Quantities.
(End of clause)