RFP: W912ER-16-R-0009 P2# 450533

PROJECT: P-976 Mina Salman Pier Replacement

LOCATION: NAVSUPPACT BAHRAIN

ITEM NO. DESCRIPTION QTY UNIT TOTAL

Design in accordance with the contract documents

1 JA

Mobilization and Demobilization in accordance with the contract documents

1 JA

Steel Pier Construct in accordance with the contract documents

1 JA

Water Front Electrical Utilities Construct in accordance with the contract documents

1 JA

Water Front Fire Protection Utilities Construct in accordance with the contract documents

1 JA

Water Front Demolition Construct in accordance with the contract documents

1 JA

Water Front ATFP Construct in accordance with the contract documents

1 JA

Operations and Maintenance in accordance with the contract documents

1 JA

Option #1 Navigation Dredging and

Reclamation Construct in accordance with the contract documents

1 JA

*OUSD has mandated that the "dollars" or "lump sum" units of measure no longer be used on DoD contracts. "JA" will be used for "LS"

PROPOSAL SCHEDULE

Base Bid Items

Total Base Bid Price

Optional Bid Items

Total Options Price

TOTAL BASE + OPTIONS PRICE (ITEMS 0001 - 0009)