B.08 W912EP25BA006TampaHarborMDFY25Volume2Specs_RTA.pdf
PDF 5 MB Posted
- Attached to
- Tampa Harbor, Maintenance Dredging, Upper Channels and Cut-G (PT), Hillsborough County, Florida
- Solicitation number
- W912EP25BA006
About this file
This is a Volume 2 solicitation specification document for the Tampa Harbor Maintenance Dredging project in Hillsborough County, Florida (Contract No. W912EP25BA006). The project involves maintenance dredging of upper channels and Cut-G, with all dredged material to be disposed of in Dredged Material Placement Facility (DMPF-2D). The work includes dredging areas with 1 foot of allowable overdepth and additional environmental monitoring services such as turbidity monitoring, sea turtle trawling and relocation, bird monitoring, and environmental species monitoring.
Key technical specifications cover dredging operations, environmental protection requirements, and detailed monitoring protocols. The project requires Coast Guard Certified dredging equipment, and contractors must comply with extensive environmental protection measures, including monitoring for marine species like sea turtles, managing turbidity levels, and protecting migratory birds. The dredging will use various techniques to minimize environmental impact, with specific requirements for equipment, reporting, and operational procedures. The contract includes multiple line items for different aspects of the work, such as mobilization, environmental monitoring, and actual dredging quantities, with payment structured to accommodate the complex environmental and operational requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP25BA006
Jacksonville District
Tampa Harbor, Maintenance Dredging Upper Channels and Cut-G (PT)
Hillsborough County, Florida
Construction Solicitation and Specifications Volume 2 of 2
See Volume 1 of 2 for issue date
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 31 21 CONTROL MONUMENT DESCRIPTIONS
00 33 50 WEATHER, WATER STAGE AND TIDE DATA
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE PROCEDURES
01 32 01 PROJECT SCHEDULE (Alternate)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 05 DREDGING/BEACH FILL PLACEMENT - QUALITY CONTROL
01 50 02 TEMPORARY CONSTRUCTION FACILITIES
01 57 20 ENVIRONMENTAL PROTECTION
01 57 25 TURBIDITY AND DISPOSAL MONITORING
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING
35 20 26 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - SCOW ULLAGE
PROFILE
35 20 27 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - PIPELINE
HYDRAULIC DREDGE
35 20 28 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - HOPPER
DREDGE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
SECTION 00 31 21 CONTROL MONUMENT DESCRIPTIONS
SECTION 00 31 21 Page 1
Designation: THFO ARP (TAMPA HYDRO FIELD OFFICE ARP)
PID: BBGK81
Stamping: N/A Stability: Monuments of questionable or unknown reliability
Setting: Unspecified setting Description: Station is in St. Petersburg, Florida at US Coast Guard Station St. Petersburg. Station is more specifically located at the US Army Corps of Engineers, Jacksonville District, Tampa Hydrographic Field Office. Station is operated by the USACE Hydrographic Survey Section. The Antenna is mounted to the NW corner of the boat storage building above the roof.
SECTION 00 31 21 Page 2
DESIGNATION - EDD 60
PID - AG5298
TIDAL BM - This is a Tidal Benchmark.
STATE/COUNTY- FL/PINELLAS
MARKER: SURVEY DISK
SETTING: SET IN A RETAINING WALL OR CONCRETE LEDGE
SP_SET: SEAWALL
STAMPING: EDD 60 1935 8.242 M.S.L.
MARK LOGO: USE
MAGNETIC: NO MAGNETIC MATERIAL
STABILITY: MAY HOLD, BUT OF TYPE COMMONLY SUBJECT TO SURFACE MOTION
SATELLITE: THE SITE LOCATION WAS REPORTED AS NOT SUITABLE FOR SATELLITE
OBSERVATIONS - August 22, 2009
STATION DESCRIPTION
AT ST. PETERSBURG, NEAR THE SOUTHWEST CORNER OF THE ALBERT WHITTED
MUNICIPAL AIRPORT, NEAR THE NORTHEAST CORNER OF THE HOUSING AREA OF THE
UNIVERSITY OF SOUTH FLORIDA BAY CAMPUS, IN THE TOP NEAR THE NORTHEAST
CORNER OF CONCRETE SEA WALL, 3.6 FEET EAST OF THE WEST END OF THE SEA
WALL, 1.1 FEET NORTH OF THE NORTH END OF THE NORTH-SOUTH SEA WALL AND
ABOUT 1 FOOT ABOVE THE PARKING AREA.
STATION RECOVERY (2009)
RECOVERED AS DESCRIBED.
SECTION 00 31 21 Page 3
DESIGNATION - 872 6668 4 RESET
PID - AG6071
TIDAL BM - This is a Tidal Benchmark
STATE/COUNTY- FL/HILLSBOROUGH
MARKER: BENCHMARK DISK SET IN ABUTMENT/PIER.
STAMPING: BM NO 4 RESET 1963
MARK LOGO: CGS
MAGNETIC: NO MAGNETIC MATERIAL
STABILITY: PROBABLY HOLD POSITION/ELEVATION WELL
SATELLITE: THE SITE LOCATION WAS REPORTED AS NOT SUITABLE FOR SATELLITE
OBSERVATIONS - November 01, 2008
STATION DESCRIPTION
DESCRIBED BY COAST AND GEODETIC SURVEY 1966
AT TAMPA, ON HOOKER POINT AT THE NORTHEAST END OF THE RICHARD E. KNIGHT
PIER, IN THE TOP OF THE CONCRETE FLOOR OF THE PIER, 4.0 FEET SOUTHWEST OF
THE NORTHEAST END, 0.5 FOOT NORTHWEST OF THE SOUTHEAST EDGE AND ABOUT
LEVEL WITH THE FLOOR.
STATION RECOVERY (2008)
RECOVERY NOTE BY FL DEPT OF ENV PRO 2008 (BPJ)
RECOVERED AS DESCRIBED.
SECTION 00 31 21 Page 4
Designation: TPA BERTH 227 BASE ARP
PID: BBHH77
Stamping: N/A Stability: Monuments of questionable or unknown reliability
Setting: Mark is an operational GNSS/GPS station Description: Station is in Tampa, Florida inside the Tampa Port
Authority Facility. The antenna is mounted on top of a 12-foot-high 4"x4" steel post at the Southwest end of Tampa Port Authority berth 227. The post is 8.0' North of the Northwest corner of a metal guard shack, 16.0' North West of the end of an 8' high chain link fence, and 2.5' South of the south end of a rack of electrical boxes mounted on 3 concrete posts. Station is operated by Tampa Port Authority Survey Division.
SECTION 00 33 50 WEATHER, WATER STAGE AND TIDE DATA
SECTION 00 33 50 Page 1
1. The following water stage, wind, wave, and weather data are provided for inclusion in the subject project’s P&S. The following water level datums are provided for information only and are not for use in conjunction with any contract-related hydrographic surveying.
a) Water Stages. Water levels in the project area are mainly affected by wind and mixed tidal fluctuations in the Gulf of America (diurnal and semi-diurnal). The project area is subject to storm surge from tropical systems from June through November. Surge from extratropical storms may minimally affect the area any time of the year.
Elevations of tidal datums in the vicinity of the project area were gathered using the National Oceanic and Atmospheric Administration’s (NOAA) National Ocean Service (NOS) tide stations shown in Figure 1 and Tables 1 – 2. These data are referred to Mean Lower-Low Water (MLLW) from the tidal epoch period of 1983 – 2001. Additional tidal data on stations in the vicinity of the subject project area can be found at the following website: https://tidesandcurrents.noaa.gov/stations.html?type=Datums#Florida.
The elevations in Table 1 were taken from NOAA’s Tide Station 8726607 (Old Port Tampa, FL) and are based on a controlling tide station near St. Petersburg, Florida (NOAA Tide Station 8726520). These datums are based on periodic analyses from January 1999 – December 2000, January 2003 – December 2003, December 2005 – November 2008, April 2010 – March 2011, and January 2012 – December 2016 from a Tampa Bay tide gauge roughly 5.0 miles north of Cut G. These values are applicable to dredging operations in the vicinity of Cut G within Tampa Harbor. Table 2 presents datums taken from NOAA’s Tide Station 8726674 (East Bay, FL) and are based on a controlling tide station near St. Petersburg, Florida (NOAA Tide Station 8726520). These elevations are based on a three-month analysis from October 2019
– December 2019 from a tide gauge roughly 1.6 miles east of the Upper Channels. These values are applicable to dredging operations in the vicinity of the Upper Channels within Tampa Harbor.
Figure 1. NOAA Tide Stations in the Vicinity of Tampa Harbor, FL https://tidesandcurrents.noaa.gov/stations.html?type=Datums#Florida
SECTION 00 33 50 Page 2
Table 1. Datums from NOAA Station 8726607 (Old Port Tampa, FL)
Location: 27° 51.5' N, 82° 33.2' W Analysis Period: Jan. 1999 – Dec. 2000, Jan. 2003 – Dec. 2003, Dec. 2005 – Nov. 2008, Apr. 2010 –
Mar. 2011, Jan 2012 – Dec. 2016 Datum Elevation (ft-MLLW)
Highest Observed (9/27/2024) 9.31 Mean Higher-High Water (MHHW) 2.48 Mean High Water (MHW) 2.16 North American Vertical Datum of 1988 (NAVD88) 1.69 Mean Sea Level (MSL) 1.30 Mean Tide Level (MTL) 1.30 Mean Low Water (MLW) 0.44 Mean Lower-Low Water (MLLW) 0.00 Lowest Observed (9/29/2022) -4.31
Table 2. Datums from NOAA Station 8726674 (East Bay, FL)
Location: 27° 55.4' N, 82° 25.3' W Analysis Period: Oct. 2019 – Dec. 2019
Datum Elevation (ft-MLLW)
Highest Observed (9/27/2024) 9.88 Mean Higher-High Water (MHHW) 2.68 Mean High Water (MHW) 2.34 North American Vertical Datum of 1988 (NAVD88) 1.82 Mean Sea Level (MSL) 1.46 Mean Tide Level (MTL) 1.43 Mean Low Water (MLW) 0.53 Mean Lower-Low Water (MLLW) 0.00 Lowest Observed (9/29/2022) -5.62
Daily tidal predictions at locations along the coastline of North and South America, including locations in the vicinity of the project area, are included in the publication East Coast of North and South America Tide Tables, United States (U.S.) Department of Commerce, National Oceanic and Atmospheric Administration, National Ocean Service. In addition to daily tidal predictions, this publication provides mean tide levels, diurnal tide ranges, and some astronomical data (sunrise, sunset, moonrise, and moonset). Of note, tidal data provided in this publication is also listed at the following website:
https://tidesandcurrents.noaa.gov/tide_predictions.html.
b) Wind and Wave Data. The publications in this section include wind and wave information in the vicinity of the project area. They are available for review at the websites or agencies indicated.
https://tidesandcurrents.noaa.gov/tide_predictions.html
SECTION 00 33 50 Page 3
i. U.S. Coast Pilot Volume 5, Gulf of America, Puerto Rico, and Virgin Islands, U.S. Department of Commerce, National Oceanic and Atmospheric Administration, National Ocean Service is a publication that supplements the navigational information shown on NOAA’s NOS nautical charts and provides miscellaneous meteorological data. This publication is available through NOAA or at the following website: https://nauticalcharts.noaa.gov/publications/coast-pilot/index.html.
ii. U.S. Army Corps of Engineers’ Coastal & Hydraulics Laboratory, Wave Information Study (WIS) Database is a wave hindcast database for various stations located along the U.S. Atlantic and Gulf of America coastlines. WIS Station 73272 is in 5.0 meters-MSL (16.4 ft-MSL) of water at 27.50° N, 82.80° W. This station is located approximately 26 miles southwest of the Cut G and Gadsden Point Cut within Tampa Harbor. Available data includes a hindcast time series of wave height, wave spread, wave period, wave and wind direction, and wind speed at 1-hour intervals for the 44-year period of January 1980 – January 2024. The following website provides links to WIS summary tables and plots, as well as other sources of wave data: https://wisportal.erdc.dren.mil/.
iii. National Data Buoy Center (NDBC) Website provides a wide range of real-time and archived meteorological and oceanographic data collected at offshore and nearshore stations worldwide. Data provided on this website include wind speed, wind gusts, atmospheric pressure, air temperature, sea temperature, wave height, and wave period. Gauge readings are updated hourly, and archived data is available for most stations. The website address for data relevant to Florida projects is as follows:
https://www.ndbc.noaa.gov/.
c) Weather Conditions. The project area is subject to tropical systems June through November and to windy and rainy weather any time of the year. The climate of the area is essentially tropical, as temperatures below freezing are seldom. During the wet season (May through October), rainfall events are usually short and sporadic and closely associated with convective activity. Winter months generally constitute the dry season, where rainfall is typically associated with mid-latitude, or extratropical, systems and distributed in a more spatially uniform pattern. Daily rainfall events in the dry season are occasionally heavy when mid-latitude systems impact southwest Florida. Notably, hazardous thunderstorms can occur in this area at any time of the year.
It is the contractor's responsibility to obtain information concerning weather conditions in the project area.
The Climate Data Online website (https://www.ncdc.noaa.gov/cdo-web/) published by NOAA’s National Centers for Environmental Information (formerly the National Climatic Data Center) in Asheville, North Carolina contains climatological and meteorological data relevant to this region. Available data includes quality-controlled daily, monthly, seasonal, and yearly measurements of temperature, precipitation, wind, and degree days as well as radar data and 15- to 30-year climate normals.
NOAA’s Climate Data Online website includes Monthly Normals (average values) for temperature, precipitation, and other climatological information over three periods: 1981-2010, 1991-2020, and 2006- 2020. NOAA’s Tampa International Airport, FL gauge (ID USW00012842) is closest to the project area and lies roughly 12.0 miles north of Cut G and 6.5 miles northwest of the Upper Channels at 27° 57.7' N, 82° 32.4' W. The most applicable period for data at this site is likely 1991-2020 and is found at the following website: https://www.ncei.noaa.gov/maps/normals/.
https://nauticalcharts.noaa.gov/publications/coast-pilot/index.html https://wisportal.erdc.dren.mil/ https://www.ndbc.noaa.gov/ http://www.ncdc.noaa.gov/cdo-web/ https://www.ncei.noaa.gov/maps/normals/
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
1.2.2 Location
1.2.3 Safety Requirements
1.2.4 Work Performed by Others
1.2.5 Dredging Commencement
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
1.5 PHYSICAL DATA
1.5.1 Physical Conditions
1.5.2 Weather, Water Stage and Tide Data
1.5.3 Contractor Investigation
1.5.4 Maritime Traffic
1.5.5 Obstruction of Channel
1.5.6 Hydrographic Surveys
1.6 LAYOUT OF WORK
1.6.1 Established Project Control
1.6.2 Layout
1.6.3 Survey
1.7 DAMAGE TO WORK
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
GDR SECTION 00 31 32, Geotechnical Data Report for Tampa Harbor Maintenance Dredging, Upper Channels and Cut-G (PT), Hillsborough County, Florida
EM 385-1-1 (2024) Safety and Occupational Health (SOH) Requirements
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
Project work consists of maintenance dredging Tampa Harbor at identified dredging areas indicated on the drawings. Dredge areas will incorporate 1 foot of allowable overdepth. All dredged material is to be disposed of in DMPF-2D. Additional work includes turbidity monitoring, sea turtle trawling and relocation, bird monitoring, and environmental species monitoring.
1.2.2 Location
The project is located in Tampa Harbor, Hillsborough County, Florida.
1.2.3 Safety Requirements
See Section 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS and EM 385-1-1 .
1.2.4 Work Performed by Others
See paragraph PROJECT COORDINATION of Section 01 30 00 ADMINISTRATIVE
PROCEDURES.
1.2.5 Dredging Commencement
Schedule commencement of dredging to start on a weekday, Monday through Friday, between the hours of 07:00 to 12:00 Eastern Timezone, excluding Federal Holidays, in order to allow for Government personnel to perform the necessary inspections on-board the dredge prior to excavation of the initial dredge loading cycle. Alternative dredging start times will be approved by the Contracting Officer prior to commencement of dredging.
SECTION 01 11 00 Page 2
1.3 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK
Read this paragraph in conjunction with the Clause COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (FAR 52.211-10).
1.4 LIQUIDATED DAMAGES - CONSTRUCTION
Refer to the Clause LIQUIDATED DAMAGES - CONSTRUCTION (FAR 52.211-12).
1.5 PHYSICAL DATA
Read this paragraph in conjunction with the Clause PHYSICAL DATA (FAR 52.236-4).
1.5.1 Physical Conditions
The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys and/or by core borings. When the indicated physical conditions are the result of site investigations by core borings, the core boring logs and laboratory data are in Section 00 31 32 GEOTECHNICAL DATA REPORT ( GDR) and the core boring locations are shown on the drawings. Also, see the GDR for instructions concerning availability of core borings for inspection.
1.5.2 Weather, Water Stage and Tide Data
See Section 00 33 50 WEATHER, WATER STAGE AND TIDE DATA.
1.5.3 Contractor Investigation
Refer to the Clause SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK
(FAR 52.236-3).
1.5.4 Maritime Traffic
Marine Traffic in the project area consists of Naval, cruise ships, commercial, pleasure, and small recreational vessels of all types and sizes which can be accommodated by existing depths.
1.5.5 Obstruction of Channel
The Government will not undertake to keep the channel free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. Conduct the work in such manner as to obstruct navigation as little as possible, and in case the Contractor's plant so obstructs the channel as to make difficult or endanger the passage of any vessels, promptly move said plant on the approach of any vessel to such an extent as may be necessary to afford a practicable passage. Upon completion of the work, promptly remove the plant, including ranges, buoys, piles, and other marks placed under the Contract in navigable waters or on shore.
1.5.6 Hydrographic Surveys
Hydrographic surveys are provided on the ehydro web site:
https://www.arcgis.com/apps/opsdashboard/index.html#/4b8f2ba307684cf597617bf1b6d2f85d Survey numbers are indicated on the drawings.
SECTION 01 11 00 Page 3
1.6 LAYOUT OF WORK
Read this paragraph in conjunction with the Clause LAYOUT OF WORK (FAR 52.236-17).
1.6.1 Established Project Control
The Government has established monuments along the work site(s). Each monument is represented in the contract drawings by a Designation and in most cases, an alphanumeric Permanent Identifier (PID). Information concerning the location and elevations can be found within the Survey Notes on the plan sheets. The Survey Notes for each included field survey will cite a particular survey number, and specify the control used to conduct that survey. Additional information is included in the Survey Notes that must be duplicated if an attempt to recreate the subject survey is desired.
For navigation channels, the Government has established tidal calibration sites for projects constructed and maintained to a tidal datum. Each tidal calibration site is represented in the plan sheet drawings by Station ID, and is cited in the Survey Notes. Calibrate all projects constructed and maintained to a tidal datum to the Station ID specified in the plan sheet drawings. Information regarding the location and associated benchmarks of the referenced Station ID is included in the Monument Description section of these specifications.
See Section 00 31 21 CONTROL MONUMENT DESCRIPTIONS.
1.6.2 Layout
From the monuments, control data and elevations established by the Government, complete the layout of the work and obtain all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work.
1.6.3 Survey
Provide equipment, tools, material, labor for laying out any part of the work from the monuments, control data, and elevations established by the Government. Maintain and preserve all monuments, stakes and other marks established by the Contracting Officer until authorized to remove them, and if such marks or monuments are destroyed by the Contractor or through negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at their discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor.
The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.
1.7 DAMAGE TO WORK
The responsibility for damage to any part of the permanent work will be as set forth in Clause PERMITS AND RESPONSIBILITIES. However, if any part of the permanent work performed by the Contractor is damaged by flood, earthquake, hurricane, or tornado, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound
SECTION 01 11 00 Page 4 engineering and construction practices in the conduct of the work, make the repairs as ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable Contract unit or job prices as fixed and established in the Contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such work, an equitable adjustment pursuant to Clause CHANGES will be made as full compensation for the repairs of that part of the permanent work for which there are no applicable contract unit or job prices. Except as herein provided, repair damage to all work (including temporary construction), utilities, materials, equipment and plant at the Contractor's expense, regardless of the cause of such damage.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
-- End of Section --
SECTION 01 11 00 Page 5
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Reference
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
1.2.2 Instructions
1.3 SUBMITTALS
1.4 JOB PAYMENT ITEMS
1.4.1 Mobilization and Demobilization (Line Item 0001)
1.4.1.1 Payment
1.4.1.2 Unit of Measure
1.4.2 Turbidity Monitoring (Line Item 0004)
1.4.2.1 Payment
1.4.2.2 Unit of Measure
1.4.3 Environmental Species Monitoring (Line Item 0005)
1.4.3.1 Payment
1.4.3.2 Unit of Measure
1.4.4 Bird Monitoring (Line Item 0006)
1.4.4.1 Payment
1.4.4.2 Unit of Measure
1.4.5 Mobilization and Demobilization for Sea Turtle Trawling
(Hopper Dredge Only, Line Item 0007)
1.4.5.1 Payment
1.4.5.2 Unit of Measure
1.5 UNIT PRICE PAYMENT ITEMS
1.5.1 Excavation, Unclassified (Line Items 0002 and 0003)
1.5.1.1 Payment
1.5.1.2 Measurement
1.5.1.3 Unit of Measure
1.5.2 Sea Turtle Trawling and Relocation (Hopper Dredge Only, Line
Item 0008)
1.5.2.1 Payment
1.5.2.2 Measurement
1.5.2.3 Unit of Measure
1.5.3 Standby Time (Line Item 0009)
1.5.3.1 Payment
1.5.3.2 Measurement
1.5.3.3 Unit of Measure
1.5.4 Partnering Regroup (Line Item 0010)
1.5.4.1 Payment
1.5.4.2 Measurement
1.5.4.3 Unit of Measure
PART 2 PRODUCTS (NOT USED)
SECTION 01 20 00 Page 1
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
3.1.1 Requesting Progress Payment
3.1.2 Options and Modification CLINS
-- End of Section Table of Contents --
SECTION 01 20 00 Page 2
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.
Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items.
1.1.1 Reference
The publication listed below forms a part of this specification to the extent referenced. This publication is referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-1003 (2013) Hydrographic Surveying
1.2 RESIDENT MANAGEMENT SYSTEM (RMS)
1.2.1 Definition
The terms Contract Line Item Number (CLIN) and Line Item are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term CLIN is a contracting term used in the Resident Management System (RMS) payment data base.
1.2.2 Instructions
See Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for more information on CLINs, schedule of values of pay activities and construction schedule, and payment procedures. The Contractor mode user manual with in-depth instructions can be downloaded from the RMS web site indicated in Section 01 45 00 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM).
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Submit the following preconstruction submittal items no later than 30 calendar
SECTION 01 20 00 Page 3 days after Notice to Proceed:
SD-01 Preconstruction Submittals
Schedule of Values ; G, RO
SD-07 Certificates
Request for Progress Payment ; G, RO
1.4 JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the CLIN SCHEDULE with the unit JOB and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, will be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
Progress payments for job CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause. Submit Schedule of Values for Government approval with the baseline schedule submittal (see Section 01 32 01 PROJECT SCHEDULE). Include a list of pay activities to breakdown bid for each job CLIN as part of the RMS Schedule. Schedule of Values will become basis for CLIN and Pay Activity data in the RMS payment data base. An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, take into account the amount reserved for contract payments when preparing the construction schedule.
1.4.1 Mobilization and Demobilization (Line Item 0001)
1.4.1.1 Payment
Payment will be made for costs associated with and incidental to mobilization and demobilization of the Contractor's plant and associated equipment, and establishment of initial project management and coordination. See Clause PAYMENT FOR MOBILIZATION AND DEMOBILIZATION.
1.4.1.2 Unit of Measure
Unit of measure: Job.
1.4.2 Turbidity Monitoring (Line Item 0004)
1.4.2.1 Payment
Payment will be made for costs associated with and incidental to obtaining, analyzing, and reporting the results of monitoring for turbidity. See Section 01 57 25 TURBIDITY AND DISPOSAL MONITORING.
SECTION 01 20 00 Page 4
1.4.2.2 Unit of Measure
Unit of measure: Job.
1.4.3 Environmental Species Monitoring (Line Item 0005)
1.4.3.1 Payment
Payment will be made for costs associated with and incidental to environmental species observers. See Section 01 57 20 ENVIRONMENTAL
PROTECTION.
1.4.3.2 Unit of Measure
Unit of measure: Job.
1.4.4 Bird Monitoring (Line Item 0006)
1.4.4.1 Payment
Payment will be made for costs associated with or incidental to furnishing a Bird Monitor and providing deterrence at Dredged Material Placement Facility 2D (DMPF-2D) during the designated monitoring period. See Section 01 57 20 ENVIRONMENTAL PROTECTION.
1.4.4.2 Unit of Measure
Unit of measure: Job.
1.4.5 Mobilization and Demobilization for Sea Turtle Trawling (Hopper Dredge Only, Line Item 0007)
1.4.5.1 Payment
Payment will be made for costs associated with and incidental to mobilization and demobilization for sea turtle trawling (Hopper Dredge Only). See Section 01 57 20 ENVIRONMENTAL PROTECTION. If performance of this line item is not required or implemented per the NOTES in the CLIN SCHEDULE, no payment will be made to the Contractor for this line item.
1.4.5.2 Unit of Measure
Unit of measure: Job.
1.5 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the CLIN SCHEDULE and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.
Each Unit Price CLIN may be a single pay activity item or may be broken down into pay activities with smaller quantities equal to CLIN total.
Contract unit price multiplied by agreed quantity is full compensation.
SECTION 01 20 00 Page 5
1.5.1 Excavation, Unclassified (Line Items 0002 and 0003)
1.5.1.1 Payment
a. Payment will be made for costs associated with and incidental to excavation, transportation, and placement of materials; providing and maintaining access to the work site(s) and disposal area(s); noise control; and debris removal. See Sections 35 20 23 DREDGING and
01 57 20 ENVIRONMENTAL PROTECTION.
b. Insofar as consistent with the paragraph CONTINUITY OF WORK of Section 35 20 23 DREDGING, monthly partial payments will be based on approximate quantities determined by soundings or sweepings performed by the Contractor behind the dredge. The term "area designated by the Contracting Officer" is also defined as "acceptance section" in paragraph CONTINUITY OF WORK of Section 35 20 23 DREDGING.
c. Hydrographic surveys for final measurement and payment and for acceptance will be made by the Government. All surveys will be performed in accordance with USACE EM 1110-2-1003 .
1.5.1.2 Measurement
a. The maps and/or drawings already prepared (clause CONTRACT DRAWINGS AND SPECIFICATIONS) are believed to represent accurately average existing conditions, but the depths shown thereon may be verified and corrected by soundings taken before dredging. Once quantities within a specified reach or section have been determined through the use of in-place measurement, they will not be reopened except on evidence of collusion, fraud, or obvious error.
b. The total amount of material removed, and to be paid for under the contract, will be measured by the cubic yard in place. The volume computed will be between the bottom surface shown by soundings taken within 3 weeks before dredging and the bottom surface shown by the soundings taken within 2 weeks after the work specified in each acceptance section has been completed. Give 10 days advance notice, in writing, to the Contracting Officer of the need for a pre-dredging survey or after-dredging survey for final acceptance for each acceptance section. The quantity will include the volume within the limits of the side slopes described in subparagraph SIDE SLOPES of paragraph REQUIRED DEPTH, ALLOWABLE OVERDEPTH, AND SIDE SLOPES of Section 35 20 23 DREDGING, less any deductions that may be required for misplaced material described in subparagraph MISPLACED MATERIALS of paragraph DISPOSAL OF EXCAVATED MATERIAL of Section 35 20 23
DREDGING.
1.5.1.3 Unit of Measure
Unit of measure: Cubic yard.
1.5.2 Sea Turtle Trawling and Relocation (Hopper Dredge Only, Line Item 0008)
1.5.2.1 Payment
Payment will be made for costs associated with and incidental to the sea turtle trawling and relocation. This price includes all costs for furnishing labor, equipment, fuel, oil, materials, and supplies required
SECTION 01 20 00 Page 6 for trawling to clear and/or relocate sea turtles from in the vicinity of the dredge, and the cost of reporting as specified. See Section 01 57 20 ENVIRONMENTAL PROTECTION. If performance of this line item is not required or implemented per the NOTES in the CLIN SCHEDULE, no payment will be made to the Contractor for this line item.
1.5.2.2 Measurement
Sea turtle trawling will be measured for payment based upon the duration of performance on a daily basis. A day of trawling is defined as 24 hours of continuous trawling. Conduct trawling as described in Section 01 57 20
ENVIRONMENTAL PROTECTION.
1.5.2.3 Unit of Measure
Unit of measure: Day.
1.5.3 Standby Time (Line Item 0009)
1.5.3.1 Payment
Payment will be made for costs associated with or incidental to standby of dredge plant only upon implementation of this line item. Standby time is defined as when, at the direction of the Contracting Officer, the dredge is put out of operation for reasons outside the requirements in the contract.
1.5.3.2 Measurement
Standby time, when exercised by the Contracting Officer, will be measured for payment by each hour, or part thereof, that the plant is not in operation.
1.5.3.3 Unit of Measure
Unit of measure: Hour.
1.5.4 Partnering Regroup (Line Item 0010)
1.5.4.1 Payment
Payment will be made for costs associated with and incidental to conducting a partnering regroup. The Contractor will only be paid for the actual number of partnering regroups conducted. See Section 01 30 00 ADMINISTRATIVE PROCEDURES. The initial partnering meeting will not be paid for under this line item as it is a distributed cost mandatory administrative action.
1.5.4.2 Measurement
The basis for payment will be for the completion of each partnering regroup meeting and Government receipt of all completed work products.
1.5.4.3 Unit of Measure
Unit of measure: Each.
SECTION 01 20 00 Page 7
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 PAYMENT PROCEDURES
Upon receiving initial Resident Management System import file, go to PAY ACTIVITIES and establish a link between bid breakdown schedule of values of PAY ACTIVITIES to contract CLINs using SCHEDULE ACTIVITIES data entry page.
3.1.1 Requesting Progress Payment
For progress payments, ensure ACTIVITY SCHEDULE, FEATURE SCHEDULE, submittal register, and punchlists are all up to date. Use PROGRESS PAYMENTS to REQUEST ACTIVITY for both ACTIVITY EARNINGS data entry page and OTHER EARNING. Provide hard copies of supporting invoices and quantity measurements to support all requested earnings. Ensure that sums of payment activities do not exceed contract award CLIN funding amounts, or unbalanced CLINs error will prevent processing the payment. Submit a request for progress payment monthly in accordance with Clause 52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS. In addition to the items listed in Clause 52.232-5(b)(1), submit the following in the request for progress payment:
a. Approved construction schedule.
b. Up-to-date payroll records.
c. Current submittal register.
d. Professional Surveyor and Mapper (PSM) or Registered Land Surveyor
(RLS) report and supporting data.
e. Approved submittals on installed property.
f. QA/QC deficiency tracking list.
g. Environmental reports.
h. Progress photographs.
i. Working/current as-built drawings.
Once the complete pay application package is received to include the Contractor's signed ENG 93, the 14 calendar days will commence.
3.1.2 Options and Modification CLINS
When additional work is added by modification, existing CLINs funding amounts must be updated, or new CLINs for modification will be created.
If contract has option CLINs not yet awarded, option CLINs will appear as zero dollar CLINs until option is awarded by modification. No payment may be requested for Options or Modification CLINs until contract modification has been funded and signed.
-- End of Section --
SECTION 01 20 00 Page 8
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.2 REFERENCES
1.3 SUBMITTALS
1.4 PROJECT COORDINATION
1.4.1 Resident Management System (RMS)
1.4.2 Coordination with Other Contracts
1.4.3 Access by Others
1.4.4 Inspections by Others
1.5 VIEW LOCATION MAP
1.6 PROGRESS AND COMPLETION PICTURES
1.7 SMALL UNMANNED AIRCRAFT SYSTEMS (SUAS)
1.8 SUPERVISION
1.8.1 Superintendent Qualifications
1.8.2 Minimum Communication Requirements
1.8.3 Duties
1.8.4 Non-Compliance Actions
1.9 PROJECT MEETINGS
1.10 PROJECT MEETINGS FORMAT
1.11 PRECONSTRUCTION CONFERENCE
1.11.1 Preconstruction Conference Minutes and Phone
1.11.2 Preconstruction Conference Submittals
1.11.2.1 Other Division 01 Submittals
1.11.2.2 Divisions 02 through 48 Submittals
1.11.3 Joint Risk Register
1.11.4 List of Subcontractors
1.12 PARTNERING
1.12.1 Initial Partnering Meeting
1.12.1.1 Contractor Responsibility
1.12.1.2 Tasks and Deliverables
1.12.2 Partnering Regroups
1.12.2.1 Contractor Responsibility (Regroups)
1.12.2.2 Tasks and Deliverables
1.12.3 Cancellation of Partnering Meeting or Regroup
1.13 NOTICE TO PROCEED
1.14 COORDINATION MEETING
1.15 PROGRESS MEETINGS
1.15.1 Progress Meeting Participants
1.16 CONTRACTOR PERFORMANCE EVALUATIONS
1.16.1 Training
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
SECTION 01 30 00 Page 1
3.1 GENERAL MEETING REQUIREMENTS
3.2 PROGRESS MEETING AGENDA
3.3 SIGNATURE AUTHORITY
3.4 DRUG-FREE WORK PLACE RECORD
3.5 MINIMUM INSURANCE REQUIREMENTS
-- End of Section Table of Contents --
SECTION 01 30 00 Page 2
SECTION 01 30 00
ADMINISTRATIVE PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
Manage project and coordinate activities of own employees, subcontractors, suppliers and offsite fabricators. Use computers, E-mail, and Internet resources for administrative work. Notify Contracting Officer of important meetings, schedule events and activities. Furnish labor and materials and equipment required to plan and execute project management functions and coordination. Coordinate activities and manage resources to construct project conforming to contract, on time and within budget.
Related Sections are 01 32 01 PROJECT SCHEDULE, and 01 45 05
DREDGING/BEACH FILL PLACEMENT - QUALITY CONTROL.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
APL 95-1-1 (2022) Aviation Policy Letter 95-1-1;
USACE Aviation Policies and Standards (Separate Document)
EM 385-1-1 (2024) Safety and Occupational Health (SOH) Requirements
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
SD-01 Preconstruction Submittals
View Location Map ; G, RO
Progress And Completion Pictures
SD-03 Product Data
Small Unmanned Aircraft Systems (SUAS)
SD-07 Certificates
Partnering Meeting(s) Written Synopsis ; G, RO
SECTION 01 30 00 Page 3
Signature Authority
Drug-Free Work Place Record
Insurance Requirements
1.4 PROJECT COORDINATION
1.4.1 Resident Management System (RMS)
Use Corps of Engineers' Resident Management System for construction information management. See Section 01 45 00 RESIDENT MANAGEMENT SYSTEM
CONTRACTOR MODE (RMS CM).
1.4.2 Coordination with Other Contracts
An active construction project may impact Contractor work at DMPF-2D.
Coordinate activities to avoid impact to adjacent Contractors and prevent problems from adjacent contracts. Assume responsibility for operating the weirs at DMPF-2D upon arrival.
1.4.3 Access by Others
Maintain access to power poles and other items owned or operated by utility companies. Coordinate with utility companies as required for line marking, hookups, and relocations as needed to perform work. Incoming electrical utilities become the responsibility of Contractor at transformers. Coordinate emergency incident response with local law enforcement and fire rescue authorities. Notify Contracting Officer in writing of coordination problems encountered affecting work.
1.4.4 Inspections by Others
During construction period, inspection or maintenance work will be performed by others within the construction limits. The Contractor is responsible for neatly mowing all grass and vegetation (not to include established trees or other protected vegetation designated as wetland areas) within the construction limits for the duration of the Contract.
Areas not accessible to mowers must be edged or trimmed neatly. Mowing or trimming must be performed every three weeks or when vegetation exceeds twelve inches in height.
1.5 VIEW LOCATION MAP
Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.
1.6 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs to include 10 aerial photographs monthly throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), SECTION 01 30 00 Page 4 cumulative of all photos to date. Indicate photographs demonstrating environmental procedures. Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file. Include a date and time stamp on each photograph as well as a date designator in the file name. Photographs provided are for unrestricted use by the Government.
1.7 SMALL UNMANNED AIRCRAFT SYSTEMS (SUAS)
Comply with all applicable aspects of USACE Aviation Policy Letter 95-1-1 ( APL 95-1-1 , https://www.saj.usace.army.mil/About/Divisions-Offices /Engineering/Design-Branch/Specifications-Section/) for the collection of aerial data by Small Unmanned Aircraft Systems (SUAS). Further, comply with location specific requirements for SUAS operations within the confines of critical infrastructure or DoD facility. Coordinate any activity associated with APL 95-1-1 through the ATPM and Contracting Office to ensure proper procedures and reporting to the USACE Aviation Office. Submit Mission Plan documentation. Submit product data on SUAS used. SUAS provided will be listed as either USACE ETP Approved in the exact configuration authorized or as a DIU Blue Cleared Aircraft in the exact authorized configuration (https://www.diu.mil/blue-uas-cleared-list).
1.8 SUPERVISION
1.8.1 Superintendent Qualifications
Provide project superintendent with a minimum of 5 years experience in construction with at least 3 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.8.2 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
1.8.3 Duties
The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
SECTION 01 30 00 Page 5
1.8.4 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.
Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.9 PROJECT MEETINGS
Contracting Officer requires following types of project meetings:
--Preconstruction Conference --Partnering Meeting --Partnering Regroup Meetings --Coordination Meeting --Preparatory and Initial Phase meeting for each feature of work --Project Progress Meetings
Project meetings are described in detail in subparts below.
1.10 PROJECT MEETINGS FORMAT
All project meetings will occur face-to-face or virtually, the default format will be face-to-face. The Contracting Officer will approve or request virtual meeting when a face-to-face meeting format can not be used. Meetings at Contractor's facility will have systems capabilities for both audio and video. The audio and video system must provide for full coverage of the conference room.
1.11 PRECONSTRUCTION CONFERENCE
Contracting Officer will conduct a Preconstruction Conference for this project in accordance with Clause PRECONSTRUCTION CONFERENCE.
Preconstruction Conference will be held within 30 to 60 calendar days after Notice to Proceed (NTP). (Refer to subparagraph PRECONSTRUCTION CONFERENCE SUBMITTALS below.) Contracting Officer will notify Contractor of time, place, and agenda. At a minimum, Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and key subcontractors and suppliers. Contracting Officer will discuss contract ground rules and general issues including:
-- Lines of Contracting Officer authority -- Lines of Contractor authority -- Contract Clauses -- Special Contract Requirements -- Contract Administration -- Progress Payment -- Correspondence Procedures -- Project Schedule -- Submittal Register -- Labor requirements -- General Site Safety -- Permit Requirements -- Joint Risk Management Processes
SECTION 01 30 00 Page 6
1.11.1 Preconstruction Conference Minutes and Phone
The Contracting Officer will take detailed minutes of Preconstruction Conference discussions and may record the meeting. Copies of typed minutes will be provided to the Contractor to review for accuracy, sign and return. Signed minutes become part of the contract file. Recordings, if used, will be made available for Contractor to review or copy.
1.11.2 Preconstruction Conference Submittals
The timing of submission of submittals and completion of the Preconstruction Conference is intended to allow the Contractor and the Government adequate time to prepare for commencement of work. However, if the Contractor fails to submit required items and receive acceptance and/or approval within the times stated, the Contractor will not be permitted to commence work until these requirements have been satisfied.
Any delays attributable to the Contractor's failure to comply with these pre-work requirements must be at the Contractor's expense and may be cause for remedial action by the Contracting Officer. Submittals required by this Section are described in paragraph SUBMITTALS above.
1.11.2.1 Other Division 01 Submittals
The Contracting Officer reviews submitted draft plans to prepare Coordination Meeting agenda and understand Contractor procedures. Submit the following preconstruction submittal items no later than 30 calendar days after Notice to Proceed unless specifically identified otherwise in the following specifications:
-- Project Schedule - See Section 01 32 01 PROJECT SCHEDULE -- Accident Prevention Plan - See Section 01 35 26 GOVERNMENTAL
SAFETY REQUIREMENTS
-- Quality Control Plan - See Section 01 45 05 DREDGING/BEACH FILL
PLACEMENT - QUALITY CONTROL
-- Temporary Facilities Plan - See Section 01 50 02 TEMPORARY
CONSTRUCTION FACILITIES
-- Environmental Protection Plan - See Section 01 57 20 ENVIRONMENTAL
PROTECTION
1.11.2.2 Divisions 02 through 48 Submittals
In addition to the above, bring submittal items for materials, workmanship, plans or events required early in project schedule which are ready for transmittal to Contracting Officer. Prepare transmittal of submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.
1.11.3 Joint Risk Register
Request a sample template from Contracting Officer or receive Government approval for a Contractor's template form prior to submission. The draft template must be project oriented with potential joint risks that will become topics of discussions for the initial partnering meeting.
1.11.4 List of Subcontractors
Documentation of compliance with Clauses SUBCONTRACTS (LABOR STANDARDS) and LIMITATIONS ON SUBCONTRACTING, and, if included, paragraph LIMITATIONS ON SUBSTITUTIONS FOR CERTAIN POSITIONS AND/OR SUBCONTRACTORS. As part of
SECTION 01 30 00 Page 7 the RMS Schedule, provide a list of subcontractors with company name, person to contact, street address, mail address, phone number, type of specialty and estimated subcontract quote no later than 30 calendar days after Notice to Proceed.
1.12 PARTNERING
Contracting Officer wants to have a bilateral project partnership with Contractor that draws on strengths of both organizations to identify and achieve common goals. Typical partnering goals include:
-- Effective and efficient contract performance -- Project completion on time and within budget -- Construction completed according to plans and specifications -- Development of cooperative management teams -- Project success with customer (stakeholders) satisfaction -- Improved Project communication -- Joint Risk Management Plan and Register
Provide a facilitator from an approved list of vendors located on the website…