Questions_and_Responses_6.7.18.docx
DOCX document 13 KB Posted
- Solicitation number
- W912EP-18-R-0039
About this file
This document includes a questions and responses file and a solicitation for an indefinite delivery indefinite quantity contract for multi-discipline miscellaneous civil works and other architect and engineering services within the Florida boundaries of the Jacksonville District, Puerto Rico and the U.S. Virgin Islands. The solicitation seeks proposals from qualified firms to provide engineering and design services for civil works and military projects, including preparation of design reports, engineering studies, cost estimates, construction plans and specifications. Responses are due by May 30, 2018. The contract will have a one year base period and four one-year options, not to exceed five years total. The contract has a total capacity of $49 million to be allocated across unrestricted, small business, and woman-owned small business awards. Firms must demonstrate experience with civil works and military design, have qualified professional staff, and the capacity to complete work in a timely manner. Past performance and knowledge of the locality will also be evaluated.
Contractor's questions and Government responses dated 7 June 2018
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Vendor_Questions_&_Government_Responses_2018-05-22.pdf | ||
| PreProposal_Slides.pptx | PPTX presentation |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912EP-18-R-0039
Questions and Government Responses 07 June 2018
1. Question: Are electronic signatures accepted at the end of Form DS 330 Part 2?
Government Response: Yes
2. Question: The solicitation states that “The contractor will have the right to refuse orders for services to be performed outside the geographic Florida boundaries.” Can a contractor refuse an order within the Florida boundaries that they do not believe they are well suited?
Government Response: Yes, a Contractor under contract has the right to decline a task order request for proposal. However, it should be said - the Government is charged with selecting firms which are highly qualified and well suited to complete orders within the Florida boundaries.
3. Question: Does the Corps of Engineers have a current list of orders for services/projects?
Government Response: No