About this file

Amendment 0004 Miami Dade Hot Spots

View the file

Other files

File Type Posted
Abstract.xls XLS spreadsheet
Amendment_0006_Hot_Spots_16B0001_1.pdf PDF
Amendment_0005_Hot_Spots_16B0001.pdf PDF
Amendment_0003_HotSpots_16B0001.pdf PDF
Amendment_0002.pdf PDF
Amendment_0001_16B0001.pdf PDF
Volume_2_Specs_16B0001.pdf PDF
SURVEY_CONTROL_NOTES_VH_15_145.pdf PDF
Volume_1_Specs_16B0001.pdf PDF
Plans_16B0001.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

BEACH EROSION CONTROL AND HURRICANE PROTECTION PROJECT, MIAMI-DADE COUNTY, FLORIDA, BEACH RENOURISHMENT 2016, MIAMI BEACH – HOTSPOTS

1.Please see continuation sheet for summary of changes.

2.Update w age rates revised 20 May 2016

3.Included Site Visit Roster

The Receipt of Bids date remains unchanged 07 June 2016 @ 2:00 PM.

All other conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EP-16-B-0001

X 9B. DATED (SEE ITEM 11)

25-Feb-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-May-2016

CODE

USA ENGINEER DISTRICT, JACKSONVILLE

CONTRACTING DIVISION

701 SAN MARCO BLVD

JACKSONVILLE FL 32207-8175

W912EP 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SF 30 CONTINUATION SHEET

Beach Erosion Control and Hurricane Protection Project, Miami-Dade County, Florida, Beach Renourishment 2016, Miami Beach - Hotspots

W912EP-16-B-0001 2 Am0004

CHANGES TO THE SPECIFICATIONS: The following are changes to the specifications. Specifications should be adequately marked or annotated to indicate that they have been changed

Volume 1 of 2:

SECTION 00010A – LINE ITEMS AND PRICING SCHEDULE: Delete Section 00010A and replace it with the attached Section 00010A.

Volume 2 of 2:

SECTION 01 22 00 – MEASUREMENT AND PAYMENT: Delete Section 01 22 00 and replace it with the attached Section 01 22 00.

SECTION 35 30 00 – BEACH FILL: Delete Section 35 30 00 and replace it with the attached Section 35 30 00.

DRAWINGS: W912EP-16-B-0001 Plans dated 2016 in 7 Sheets + Cover:

There are no changes to the drawings.

--END OF AMENDMENT 0004 CHANGES --

SECTION 00010A

LINE ITEMS AND PRICING SCHEDULE

BEACH EROSION CONTROL AND HURRICANE PROTECTION PROJECT

MIAMI-DADE COUNTY, FLORIDA

BEACH RENOURISHMENT 2016

MIAMI BEACH - HOTSPOTS

W912EP-16-B-0001 00010A-1 Am0004

LINE ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL

0001 BEACH FILL

(ESTIMATED QUANTITY, SEE NOTE 3 AND 7) 220,000 CUBIC YARD $___________ $_______________

0002 BEACH TILLING

(ESTIMATED QUANTITY, SEE NOTE 3) 10 ACRE $___________ $_______________

0003 CONSTRUCTION/VIBRATION CONTROL AND

MONITORING LUMP SUM $_______________

0004 ENVIRONMENTAL SPECIES * COORDINATION * LUMP SUM $_______________

0005 TURBIDITY MONITORING LUMP SUM $_______________

0006 CONTRACTING OFFICER'S FIELD OFFICE 6 MONTH $___________ $_______________

(ESTIMATED QUANTITY, SEE NOTE 3)

0007 55TH STREET HOTSPOT STAGING AREA 75 DAY $__520_______ $__39,000________

(ESTIMATED QUANTITY, SEE NOTE 6)

TOTAL BID (LINE ITEMS 0001 THROUGH 0007) $_______________

NOTES: (1) OFFER MUST PRICE ALL LINE ITEMS.

(2) FAILURE TO COMPLETE AND RETURN ALL REQUIRED SUBMISSIONS MAY RENDER YOUR BID NON-RESPONSIVE.

(3) ACTUAL QUANTITIES MAY VARY.

(4) FULL PAYMENT UNDER LINE ITEM "BEACH FILL" IS CONDITIONED ON REPAIRING ALL STAGING AND ACCESS AREAS

TO PRECONSTRUCTION CONDITION. SEE SECTION 01 22 00 MEASUREMENT AND PAYMENT.

(5) ANY VEGETATION IMPACTED BY CONSTRUCTION ACTIVITIES SHALL BE REPLACED.

(6) THE AMOUNT ENTERED FOR LINE ITEM 0007 IS FOR CONTRACTOR BIDDING PURPOSES ONLY. ACTUAL PAYMENT

WILL BE FOR THE AMOUNT SHOWN ON PAID INVOICES PROVIDED TO THE CONTRACTING OFFICER.

(7) BEACH QUANTITY SHOWN IS THE ESTIMATED QUANTITY FOR THE FILL TEMPLATE AND DOES NOT TAKE

COMPACTION INTO CONSIDERATION.

BECHPP, MIAMI-DADE COUNTY, FLORIDA, BEACH

RENOURISHMENT 2016, MIAMI BEACH - HOTSPOTS

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUMMARY

1.2 QUALITY CONTROL SYSTEM (QCS)

1.2.1 Definition

1.2.2 Instructions

1.3 DEFINITIONS

1.3.1 Compensating Slopes

1.4 SUBMITTALS

1.5 LUMP SUM PAYMENT ITEMS

1.5.1 Construction/Vibration Control and Monitoring (Line Item 0003)

1.5.2 Environmental Species Coordination (Line Item 0004)

1.5.3 Turbidity Monitoring (Line Item 0005)

1.6 UNIT PRICE PAYMENT ITEMS

1.6.1 Beach Fill (Line Item 0001)

1.6.1.1 Payment

1.6.1.2 Measurement

1.6.1.3 Unit of Measure

1.6.2 Beach Tilling (Line Item 0002)

1.6.2.1 Payment

1.6.2.2 Measurement

1.6.2.3 Unit of Measure

1.6.3 Contracting Officer's Field Office (Line Item 0006)

1.6.3.1 Payment

1.6.3.2 Measurement

1.6.3.3 Unit of Measure

1.6.4 55th Street Hotspot Staging Area (Line Item 0007)

1.6.4.1 Payment

1.6.4.2 Measurement

1.6.4.3 Unit of Measure

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 PAYMENT PROCEDURES

3.1.1 Requesting Progress Payment

3.1.2 Options and Modification CLINS

-- End of Section Table of Contents --

SECTION 01 22 00 Page 1 W912EP-16-B-000 Am0004

SECTION 01 22 00

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 SUMMARY

This section describes how Line Items will be measured and paid for when making progress payments. Work to be measured is described in specification sections listed for each Line Item. Measurement procedures for payment, required quantity survey or procurement documentation and payment restrictions are described in applicable specification sections.

Allocate costs for work not specifically mentioned to the Line Item most closely associated with work involved. Unless there is a specific Line Item for administrative costs, such as Quality Control and Safety, allocate such costs proportionally across all Line Items.

1.2 QUALITY CONTROL SYSTEM (QCS)

1.2.1 Definition

The terms "Contract Line Item Number (CLIN)" and "Line Item" are interchangeable herein (e.g.: CLIN 0001 is Line Item 0001). The term "CLIN" is a contracting term used in the Quality Control System (QCS) payment data base.

1.2.2 Instructions

See Section 01 45 04 C0NTRACTOR QUALITY CONTROL for instructions on linking a CLIN to a schedule of values of pay activities and construction schedule, and in-depth payment procedure.

1.3 DEFINITIONS

1.3.1 Compensating Slopes

The allowance for material to be placed above the specified fill tolerance to compensate for the specified foreshore slope being below grade due to sediment relocated by natural forces between the time of placement and payment surveys. This is permitted for payment purposes only.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Transmit submittal items in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Values; G, RO

SECTION 01 22 00 Page 2

Provide a breakdown of lump sum items into proposed pay activities. Schedule of Values will become basis for CLIN and Pay Activity data in the QCS payment data base.

1.5 LUMP SUM PAYMENT ITEMS

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved. The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

Progress payments for lump sum CLINs will be made in accordance with the Payments Under Fixed-Price Construction Contracts clause of Section 00700 CONTRACT CLAUSES in Volume 1. Provide a list of pay activities, (Schedule of Values) to breakdown bid for each lump sum CLIN. Within 20 calendar days after receiving Notice to Proceed, submit Schedule of Values for Government approval. An unbalanced Schedule of Values and Pay Activity Schedule will be returned for revision. If this contract contains either the Continuing Contracts clause or the Continuing Contracts (Alternate) clause, the Contractor should take into account the amount reserved for contract payments when preparing the construction schedule.

1.5.1 Construction/Vibration Control and Monitoring (Line Item 0003)

Payment will be made for costs associated with or incidental to the protection of existing structures from construction activities and monitoring. See Section 02 22 13 VIBRATION MONITORING REQUIREMENTS FOR

EXISTING STRUCTURES.

1.5.2 Environmental Species Monitoring Coordination (Line Item 0004)

Payment will be made for costs associated with or incidental to daily coordination with Miami-Dade County - Environment Resource Management (DERM) on their daily management of the monitoring of sea turtles, migratory birds, and other endangered species. Contacts to DERM will be provided at the Pre-construction conference. See Section 01 57 20

ENVIRONMENTAL PROTECTION.

1.5.3 Turbidity Monitoring (Line Item 0005)

Payment will be made for costs associated with or incidental to obtaining, analyzing, and reporting the results of monitoring for turbidity. See Section 01 57 25 TURBIDITY AND DISPOSAL MONITORING.

1.6 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the LINE ITEMS AND PRICING SCHEDULE and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, SECTION 01 22 00 Page 3 tests and reports, and for performing all work required for each of the unit price items.

Each Unit Price CLIN may be a single pay activity item or may be broken down into pay activities with smaller quantities equal to CLIN total.

Contract unit price multiplied by agreed quantity is full compensation.

1.6.1 Beach Fill (Line Item 0001)

1.6.1.1 Payment

a. Payment will be made for costs associated with or incidental to preparation of access areas, barricades and signs, debris removal, pipeline crossing, excavation and transportation of beach fill, constructing the beach profile and final dressing; noise control;

condition surveys; and restoration of all access areas to preconstruction condition or as otherwise indicated on the drawings.

See Sections 01 57 20 ENVIRONMENTAL PROTECTION and 35 30 00 BEACH FILL.

b. In addition to the above, payment will be made for in-place beach fill to the tolerance line indicated in Section 35 30 00 BEACH FILL.

Payment quantities will be determined by the Government using average end area method of calculation. When beach fill is placed up-slope above slough zone to compensate for wave action, payment of end area will be based on a cut and fill calculation. No payment will be made for material placed on the up-slope above the tolerance A(u) that exceeds A(s) (Refer to Beach Fill Tolerance figure indicated in the paragraph CONSTRUCTION FORMS AND DETAILS of Section 35 30 00 BEACH

FILL).

c. The Government will pay 95 percent (withhold 05 percent) of progress and total payment made under this line item until all access areas have been restored as indicated above. This is not considered retainage under clause PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section 00700 CONTRACT CLAUSES. This is considered payment withheld for work paid for under this line item which has not been performed. Acceptance of repairs to access routes may be subject to final approval of local permitting authorities.

1.6.1.2 Measurement

a. The maps and/or drawings already prepared (clause CONTRACT DRAWINGS, MAPS, AND SPECIFICATIONS of Section 00700 CONTRACT CLAUSES in Volume 1) are believed to represent accurately the existing conditions at the time the surveys were performed, but the depths and elevations shown thereon may be verified and corrected by elevations and soundings taken before commencing the work. Once quantities within a specified reach or section have been determined through the use of in-place measurement, they will not be reopened except on evidence of collusion, fraud, or obvious error.

b. Beach fill satisfactorily placed will be measured for payment by use of the average end area method. The quantities will be computed by the Government in accordance with clause QUANTITY SURVEYS of Section 00700 CONTRACT CLAUSES in Volume 1. Measurement of quantity placed for pay purposes will be based on original and final cross sections made on the section or reach indicated on the drawings. The Contractor shall give 3 calendar days advance notice, in writing, to the Contracting Officer's Representative of the need to perform the original and final

SECTION 01 22 00 Page 4 surveys. Quality Control Surveys shall be the responsibility of the Contractor. Monthly partial payments will be based on approximate quantities determined by measurement of the in-place beach fill and in accordance with clause QUANTITY SURVEYS of Section 00700 CONTRACT CLAUSES in Volume 1.

c. In accordance with clause QUANTITY SURVEYS of Section 00700 CONTRACT CLAUSES in Volume 1, the Government will perform pre- and post-construction topographic survey at 100-foot stations with elevations taken at 10-foot range intervals from the baseline to the toe slope elevation. In order to achieve final grade in slough zone, and account for natural fencing prior to Government survey, the Contractor shall place material to final grade within tolerance for the entire slope or may stockpile beach fill up-slope of the swash zone as long as the upslope fill volume above tolerance does not exceed volume on the foreshore slope below tolerance, known herein as the compensating slopes. After stockpiled beach fill is measure for payment, the Contractor shall produce a smooth uniform slope to within the acceptable tolerances of the final grade from the top of slope to the water line. Once post-construction survey is performed, no measurements will be revised except on suspicion of fraud or obvious error.

1.6.1.3 Unit of Measure

Cubic yard.

1.6.2 Beach Tilling (Line Item 0002)

1.6.2.1 Payment

Payment will be made for costs associated with or incidental to beach tilling. See Sections 01 57 20 ENVIRONMENTAL PROTECTION and 35 30 00 BEACH

FILL.

1.6.2.2 Measurement

Beach tilling will be measured for payment by the actual area tilled to the tenth of a acre.

1.6.2.3 Unit of Measure

Acre.

1.6.3 Contracting Officer's Field Office (Line Item 0006)

1.6.3.1 Payment

Payment will be made for costs associated with or incidental to providing, maintaining, and final disposition of the Contracting Officer's field office including all costs for rent and provision of all services indicated in Section 01 52 10 CONTRACTING OFFICER'S FIELD OFFICE. Costs for such provision and maintenance of the Contractor's own field office and other facilities will not be paid for under this line item.

1.6.3.2 Measurement

The basis for payment will be the amount of time that the Contracting Officer's field office is available to the Government within the duration

SECTION 01 22 00 Page 5 of the contract.

1.6.3.3 Unit of Measure

Month.

1.6.4 55th Street Hotspot Staging Area (Line Item 0007)

1.6.4.1 Payment

Payment will be made for costs associated with or incidental to use of the staging area at the 55th Street Hotspot. A total of 52 parking spaces are available within the limits of the staging area shown on the drawings.

This encompasses 2 full rows of parking located along the southern most parking aisle. Each spot has a cost of $10 per day per spot. See Section

01 50 02 TEMPORARY CONSTRUCTION FACILITIES.

1.6.4.2 Measurement

Payment shall be measured by the actual number of days used by the Contractor. The estimated duration in Section 00010A LINE ITEMS AND PRICING SCHEDULE is provided for bidding purposes only and will be determined on actual quantity used.

1.6.4.3 Unit of Measure

Day.

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 PAYMENT PROCEDURES

Upon receiving initial Resident Management System import file, go to "Pay Activities" and establish a link between bid breakdown schedule of values of "Pay Activities" to contract CLINs using "Schedule Activities" data entry page.

3.1.1 Requesting Progress Payment

For progress payments, ensure "Activity Schedule", "Feature Schedule", submittal register, and punchlists are all up to date. Use "Progress Payments" to "request Activity Earnings" for both "Activity Earnings" data entry page and "Other Earning". Provide hard copies of supporting invoices and quantity measurements to support all requested earnings. Ensure that sum of payment activities do not exceed contract award CLIN funding amounts, or "unbalanced" CLINs error will prevent processing the payment.

3.1.2 Options and Modification CLINS

When additional work is added by modification, existing CLINs funding amounts must be updated, or new CLINs for modification will be created. If contract has option CLINs not yet awarded, option CLINs will appear as zero dollar CLINs until option is awarded by modification. No payment may be requested for Options or Modification CLINs until contract modification has been funded and signed.

-- End of Section --

SECTION 01 22 00 Page 6

SECTION TABLE OF CONTENTS

DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION

SECTION 35 30 00

BEACH FILL

PART 1 GENERAL

1.1 SCOPE

1.2 REFERENCES

1.3 SUBMITTALS

1.4 ORDER OF WORK

1.5 HISTORICAL PERIOD SHIPWRECK SITES

1.6 FINAL CLEANUP

1.7 WORK VIOLATIONS

PART 2 PRODUCTS

2.1 CHARACTER OF MATERIALS

2.1.1 Sand Sources

2.1.1.1 Physical Requirements

2.1.1.2 HTRW Evaluation for Sand Source

PART 3 EXECUTION

3.1 PROTECTION OF EXISTING STRUCTURES FROM CONSTRUCTION ACTIVITIES

3.2 EXCAVATION

3.2.1 Mine Operations

3.2.2 Deduction for Nonconforming Work

3.3 TRANSPORT OF BEACH FILL MATERIALS

3.3.1 Mine Production and Loading

3.3.2 Transport

3.4 BEACH FILL

3.4.1 General

3.4.2 Construction

3.4.3 Dedicated Safety and Flag Person

3.4.4 Tilling

3.4.5 Escarpment Monitoring and Removal

3.4.6 Dressing for Progress Payment

3.4.7 Dressing for Final Acceptance

3.4.8 Tolerances

3.4.9 Misplaced Materials

3.5 NOISE CONTROL

3.6 QUALITY CONTROL

3.6.1 Preparatory Inspection

3.6.2 Initial Inspections

3.6.3 Follow-up Inspection

3.7 QUALITY CONTROL FOR BEACH FILL

3.7.1 Compliance Criteria for Beach Fill Material

3.7.2 Beach Fill Observation and Sampling

3.7.3 Determination of Areal Extent of Noncompliant Beach Fill

3.7.4 Remediation

SECTION 35 30 00 Page 1

3.7.5 Noncompliant Material Contingency Plan

3.8 INSPECTION

3.8.1 Quality Assurance Representative (QAR)

3.8.2 Failure to Comply

3.9 CONSTRUCTION FORMS AND DETAILS

-- End of Section Table of Contents --

SECTION 35 30 00 Page 2

SECTION 35 30 00

BEACH FILL

PART 1 GENERAL

1.1 SCOPE

The work covered by this section consists in furnishing all plant, labor, equipment, supplies and material, and in performing all operations in connection with excavating from upland source(s) provided by the Contractor, transporting, and placing fill on the beaches as indicated on the drawings and specified herein.

1.2 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D422 (1963; R 2007; E 2014; E 2014)

Particle-Size Analysis of Soils

ASTM E1527 (2005) Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process

U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)

EPA/CE-81-1 (1981) Procedures for Handling and Chemical Analysis of Sediment and Water Samples

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 Safety and Health Requirements Manual

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Work Plan; G, RO

The Contractor shall submit a Work Plan 15 calendar days after Notice to Proceed, for review and approval by the Contracting Officer. The work plan shall include but not be limited to the following:

SECTION 35 30 00 Page 3

a. Provide a detailed description of methods and equipment to be used for each operation, and the sequence of operations.

b. Submit methods and equipment plan on how fill is to be placed onto the beach fill template, such as obtaining fill, transporting fill, stockpiling fill, managing stock pile, placement of fill onto beach from stockpile, and final grading.

c. Provide an anticipated construction schedule for when each access area is to be used and rehabilitated back for public access.

d. Provide a general existing sketch and photographic documentation of each access area to be used by the Contractor and all affected structures. Sketch shall include location of any structure within access area such as access roads, ramps, walkovers, fences, showers, limits of pavers, etc as well as existing vegetation.

e. Provide an additional sketch showing alterations for each access area to be impacted by construction activities. Also include final restoration plans of the access area upon completion of work.

Pedestrian Protection Plan; G, RO

Submit means and methods for pedestrian protection during beach fill operations for review and approval by the Contracting Officer. The Contractor shall have a dedicated safety and flag person on site at all times, whose sole responsibility is preventing the public from entering the work area and answering any questions they may have. Submit product information and methods of installation for orange safety fencing for crowd control. Submit methods of staking in place and maintenance of system for duration of construction. Submit off road trucking operation safety plan. See Section 01 50 02 TEMPORARY FACILITIES.

Progress Map; G, DO

Provide and maintain a map depicting the construction progress and projected fill volumes and completion dates. The progress map shall be a plan view drawing depicting the beach fill site, acceptance sections (AS), staging/access areas, and all other relevant project features. For each AS, the information shall list the anticipated quantity of material per acceptance section and projected dates for fill to be placed and completed. The map shall provide dates when access areas are to be used and when they will be ready for public use. The map will be color coordinated with the following color scheme: Red depicting an area not ready for construction; Orange depicting an area currently being worked, and Green meaning an area accepted by the Contracting Officer and ready for public use. The map shall be updated every other day and whenever significant changes occur to the projected dates. Since the map will be used by the Government for coordination with the public and to track progress, the updated map shall be provided prior to the weekly project progress meeting, or at the request of the Contracting Officer..

SECTION 35 30 00 Page 4

Source of Fill; G, DO

Submit source(s) of beach quality fill and representative samples to the Contracting Officer prior to construction. Submit testing data and grain size distribution test reports of borrow materials in accordance with paragraph QUALITY CONTROL FOR BEACH

FILL.

SD-02 Shop Drawings

Noncompliant Material Contingency Plan

Within 14 calendar days after Notice to Proceed, submit a Noncompliant Material Contingency Plan as indicated in paragraph QUALITY CONTROL FOR BEACH FILL below.

SD-04 Samples

Sand Source Quality Control Samples

Submit source of beach quality fill and representative samples to the Government prior to construction. Within 10 days after Notice of Award, the Contractor shall furnish a 5-pound sample of the proposed beach fill material to the project geologist, CESAJ-EN-GG, of Jacksonville District USACE, telephone (904) 232-1140.

SD-06 Test Reports

Sand Source Test Report

Submit as indicated in paragraph QUALITY CONTROL FOR BEACH FILL below.

Environmental and Hazardous Toxic and Radioactive Waste (HTRW) Evaluation Report for Sand Source; G, DO

The Contractor shall submit an Environmental and Hazardous Toxic and Radioactive Waste (HTRW) Evaluation Report for Government's approval and concurrence within fifteen (15) days from the Notice to Proceed in accordance with subparagraph "HTRW Evaluation for Sand Source" below.

SD-07 Certificates

Truck Information

Submit Department of Transportation information for each truck to be utilized for hauling beach fill for inventory tracking purposes.

Equipment and Performance Data

The Contractor shall furnish proof of electronic positioning equipment calibration to the Contracting Officer.

Grade Stake Recovery; G, DO

After completion of the project, the Contractor shall provide a

SECTION 35 30 00 Page 5 letter to the Contracting Officer certifying that all grade stakes have been recovered in accordance with the Contractor's approved Construction and Grade Stake Recovery Plan.

Notification of Discovery of Historical Period Shipwreck Sites

The Contractor shall immediately notify the Contracting Officer if any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered.

Daily/Monthly Report of Operations

The Contractor shall prepare on QCS and submit two (2) hard copies and (1) soft copy of the Daily Report of Operations, using either ENG Form No. 27A or ENG Form No. 4267, for each truck and/or unloader working. This report shall be submitted to the Contracting Officer on a daily basis and not in groups (groups = multi-days reports packaged together at one time). In addition to the daily report, the Contractor shall prepare a Monthly Report of Operations for each month or partial month's work on either ENG Form No. 27A or ENG Form No. 4267. The monthly report shall be submitted on or before the 7th of each month, consolidating the previous month's work. Upon completion of the job, the Contractor shall submit a consolidated job report, combining the monthly reports. The Contractor shall distribute one copy of each report to the District Engineer, ATTN: CESAJ-EN-C; U.S. Army Engineer District, Jacksonville, P.O. Box 4970, Jacksonville, Florida 32232-0019. Reports shall be submitted on a monthly basis with daily reports accompanying the monthly report and job report.

Additionally, one copy of these forms shall be maintained by the Contractor for the Contracting Officer's inspection purpose.

Further instructions on the preparation of the reports will be furnished at the Preconstruction Conference.

Grade Stake Log

The Contractor shall prepare and maintain a log to inventory the grade stakes used on the project. The log shall include information concerning the location, installation, and recovery of all grade stakes. The Contractor shall make this log available for review by the appropriate Government personnel upon request.

Upon completion of the project, the Contractor shall furnish the log to the Contracting Officer.

Permits

Submit received permits for construction and hauling activities and access-way demolition and reconstruction. Contracting Officer may use final acceptance of local building permits as support criteria for acceptance and payment of access route repairs.

1.4 ORDER OF WORK

The Contractor may begin their filling operations at either placement location and is allowed to work at both locations simultaneously. See paragraph "Work Restrictions" in Section 01 11 00 SUMMARY OF WORK. The Contractor shall begin his filling operations within each placement

SECTION 35 30 00 Page 6 location at the south end and proceed northward. Once beach fill begins, the Contractor shall maintain a continuous filling operation without any intervening gaps.

1.5 HISTORICAL PERIOD SHIPWRECK SITES

If any shipwreck, artifact, or other objects of antiquity that have scientific or historical value, or are of interest to the public, are discovered, located, and/or recovered, the Contractor acknowledges that:

a. The site(s), articles, or other materials are the property of the State of Florida, with title vested in the Department of State, Division of Historical Resource; and that,

b. The Contracting Officer shall be immediately notified.

Refer to subparagraph "Preservation and Recovery of Historic, Archeological, and Cultural Resources" of Section 01 57 20 ENVIRONMENTAL

PROTECTION.

1.6 FINAL CLEANUP

Final cleanup, as stated in the paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK of Section 00700 CONTRACT CLAUSES in Volume 1, shall include the removal of all of the Contractor's equipment either for disposal or reuse. Equipment to be disposed of shall ONLY be disposed of in a manner and at locations approved by the Contracting Officer. Unless otherwise approved in writing by the Contracting Officer, the Contractor will not be permitted to abandon equipment at the work site or other areas adjacent to the work site. Debris removed or created as a result of the execution of this contract shall be disposed of in a manner and at locations approved by the Contracting Officer.

1.7 WORK VIOLATIONS

Work done in violation of these specifications or a verbal or written stop order of the Contracting Officer will be considered as unsatisfactory progress for purposes of progress payments in accordance with Clause PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS of Section 00700 CONTRACT CLAUSES in Volume 1.

PART 2 PRODUCTS

2.1 CHARACTER OF MATERIALS

2.1.1 Sand Sources

The Contractor shall use domestic upland sources of sand. The sand supplied shall be naturally created. The sand may be processed, but manufactured sand is not allowed. The sand must be composed of quartz and/or calcium carbonate with no more than 5 percent sand of other mineralogical compostion. No offshore sand sources shall be considered as an acceptable source. Submit source of beach quality fill and representative samples to the Government prior to construction. Submit grain size distribution and testing reports of borrow materials in accordance with paragraph QUALITY CONTROL FOR BEACH FILL below. The submitted sand samples will be used for verification laboratory testing of proposed submittals and for visual comparison by Government inspectors during construction. All sand sources shall meet NEPA and SHPO

SECTION 35 30 00 Page 7 requirements, and sand shall only be provided from the portions which are compliant.

The Contractor shall provide with the "Source of Fill" submittal all NEPA and SHPO letters and correspondence from all sources which indicate the portions that are compliant.

2.1.1.1 Physical Requirements

The Contractor shall have on-site personnel to visually monitor the sand being stockpiled at the sand mine for beach placement. The selected individual shall have training or experience in beach nourishment, construction inspection and testing, and be knowledgeable of the contract requirements and permit conditions. The Contractor shall perform daily visual observation of the fill material during construction by personnel who can identify obvious changes in beach fill quality. The Contractor shall conduct testing and sampling at the mine at an interval not to exceed 3,000 tons to confirm compliance of beach fill with the specifications.

Beach fill sampling and testing shall be in accordance with the following procedures:

a.) Each sample shall be archived with the date, time, and location of the sample. The sample shall be visually compared to the compliance criteria provided in Table 1. All samples shall be stored until project completion.

b. Should any stockpile sample not comply with the compliance criteria stated above, the Contractor shall notify the Contracting Officer at the first available normal business hour. Should stockpile samples not comply with the compliance criteria, the Contracting Officer shall be notified immediately and take necessary actions to avoid placement of noncompliant material.

c.d. If requested by the Contracting Officer, the Contractor shall take the collected stockpile sample for analysis of grain size distribution, Munsell color, carbonate content, and percent visual shell by a certified laboratory. Gradation analysis shall be performed according to ASTM D422. U.S. Standard sieve sizes shall include 3/4 inch, 3/8 inch, and numbers 4, 7, 10, 14, 18, 25, 35, 45, 60, 80, 120, 170, 200, and 230. The results shall be sent to the Contracting Officer within two (2) weeks.

2.1.1.2 HTRW Evaluation for Sand Source

Comply with Rule 62B-41.007(2)(j)(4), F.A.C. which states that fill material shall be free from any toxic materials. If the borrow site contains or is suspected of containing HTRW, environmental contaminants or otherwise toxic materials, it shall not be used as a borrow source. All material brought in as part of this contract shall be environmentally clean and free from any such materials and shall not exceed the Soil Cleanup Target Levels for both "Direct Exposure" as well as "Leachability Based on Marine Surface Water Criteria" mentioned in the Soil Cleanup Standards in Chapter 62-777, Florida Administrative Code. If contaminant levels of the borrow material exceed the mean naturally occurring contaminant levels at the beach area, the site shall not be used as a borrow source. The measurements shall also fall within 2 standard deviation or suspect high values will be determined to be the most conservative representation of the results. Elutriate values shall be compared to state water quality standards to determine whether runoff will violate state standards.

SECTION 35 30 00 Page 8

Approval of the Environmental and HTRW Report will not relieve the Contractor of their responsibility to document such conditions and to avoid contaminating any portion of the beach placement area with substandard material. The submittal requirements for this report will depend on the borrow source.

a. Requirements for Radioactivity. Testing for radioactivity is necessary if the source of material is from non-silicate sands, phosphate mine tailings or from other suspected source(s) which potentially have unacceptable radiation levels. Radiation levels shall be measured for the borrow material and for beach placement areas. The borrow area and the beach placement area shall be surveyed and background radioactivity and radiation levels of the borrow area versus the beach site shall be compared. The levels of radioactivity in the borrow material shall not exceed the mean levels existing at the beach placement area. If radiation levels of the source material exceed the mean naturally occurring radiation levels at the beach area, the material from the site shall not be used as a borrow source. The findings of this investigation shall be included in the Environmental and Hazardous Toxic and Radioactive Waste (HTRW) Evaluation Report.

b. Existing Commercial Sources. If the material will be brought in from an existing commercial quarry, the Contractor shall submit the Environmental and Hazardous Toxic and Radioactive Waste (HTRW) Evaluation Report for Government approval that includes all existing environmental information including but not limited to the environmental permits, environmental investigations conducted to obtain such permits, Phase I/II environmental reports, and any other pertinent information documenting the environmental suitability of the material.

If no such information is available, the same requirements mentioned below for new/alternate sand sources shall be evaluated and its report submitted for Government approval.

c. New/Alternate Sand Sources. If the Contractor intends to bring material from any other alternate sand source, the Environmental and Hazardous Toxic and Radioactive Waste (HTRW) Evaluation Report shall at a minimum include, but not be limited to, the following:

(1) Phase 1 HTRW Evaluation. A Phase I Hazardous Toxic and Radioactive Waste (HTRW) evaluation to meet the requirements of ASTM E1527 shall be conducted and its report included.

(2) Environmental Sampling. Contractor shall conduct sampling on the source sand and provide laboratory results based on the number of samples and parameters mentioned in the table below.

The report shall include the scope, project drawings of the borrow area with proposed sampling locations shown on the drawings, a log of field notes collected during sampling, photographs, summary of any Quality Control issues and a table that compares the concentration from the sand sources to the Soil Cleanup Target Levels for both "Direct Exposure" as well as "Leachability Based on Marine Surface Water Criteria" mentioned in the Soil Cleanup Standards in Chapter 62-777, Florida Administrative Code.

Laboratories shall be NELAP certified.

(3) Information on the certified laboratory or laboratories (names, addresses, and phone numbers) that where utilized to conduct the testing.

SECTION 35 30 00 Page 9

(4) Methodologies and procedures for sampling and laboratory analysis. Methodologies and procedures for sampling shall conform to FDEP sampling protocols. Laboratory analyses shall conform to EPA methodologies. Elutriate Preparation shall be by the method provided in EPA/CE-81-1.

(5) Testing Requirements, Schedules, Sampling Frequency and Stockpile Sampling. Testing for all below contaminants shall also be performed on elutriates. Testing requirements, schedules, sampling frequency and stockpile sampling shall be as per the following table:

Testing Requirements based on the Fill Source Area Borrow Area Vicinity Testing Requirements

Land near an existing freeway, PAHs, TPH, PCBs, heavy metals residential/acceptable commercial including lead.

land, a mining area or rock quarry

Agricultural land Pesticides, Organochlorine Pesticides, Organophosporous Pesticides, Chlorinated, Herbicides, heavy metals, PAHs, VOCs, semi-VOCs TPH, PCBs.

Non-silicate sands, phosphate mine Radioactive isotopes, PAHs, TPH tailings or from other suspected PCBs, heavy metals including lead.

source(s), which potentially have unacceptable radiation levels

Testing Schedule and Frequency Area of Individual Borrow Area Sampling Requirements

2 acres or less Minimum of 4 samples

2 to 4 acres Minimum of 1 sample every 1/2 acre

4 to 10 acres Minimum of 8 samples

Greater than 10 acres Minimum of 8 locations with 1 additional sample every acre

Stockpile Sampling Volume of Borrow Area Stockpile Samples Per Volume

Up to 1,000 cubic yards 1 sample per 500 cubic yards

1,000 to 5,000 cubic yards 2 samples for first 1000 cubic yards plus 1 sample per each additional 1,000 cubic yards

Greater than 5,000 cubic yards 5 samples for first 5,000 cubic yards plus 1 sample for each additional 1,000 cubic yards

In addition to the HTRW Evaluation Report provided to the Contracting Officer, provide one copy to the Chief, Environmental and HTRW Section, SECTION 35 30 00 Page 10

CESAJ-EN-GE, USACE Jacksonville District, 701 San Marco Blvd, Jacksonville, Florida 32207-8175.

PART 3 EXECUTION

3.1 PROTECTION OF EXISTING STRUCTURES FROM CONSTRUCTION ACTIVITIES

Refer to Sections 01 50 02 TEMPORARY CONSTRUCTION FACILITIES and 02 22 13

VIBRATION MONITORING REQUIREMENTS FOR EXISTING STRUCTURES.

3.2 EXCAVATION

3.2.1 Mine Operations

Beach fill shall be placed on a vibrating screen. Material shall be washed to remove excess silt/fines and sorted utilizing a classifying tank to meet the specified product. Beach fill shall be dewatered and placed in stockpiles. Beach fill shall be stored in a stockpile for a minimum of three (3) days, to allow for proper drying. Stockpiled beach fill shall be clearly identified in stockpiles, for periodic inspection by Contracting Officer. The Contractor shall maintain mine production rates and stockpiling to not delay project.

3.2.2 Deduction for Nonconforming Work

Beach fill that is obtained from unauthorized areas will not be paid for under this contract. Beach fill shall only be obtained from upland borrow sources that meet the Character of Material specifications and are approved by the Contracting Officer.

3.3 TRANSPORT OF BEACH FILL MATERIALS

The method of transporting the fill from the mine to the fill area shall be as indicated in the Work Plan and approved by the Contracting Officer. The Work Plan shall include the route from the Borrow area to the Beach fill placement area for the Contracting Officer's approval. Use of alternate routes is prohibited unless approved in writing by the Contracting Officer.

3.3.1 Mine Production and Loading

Beach Fill shall be hauled to the project site by truck. Each truck shall be approved by the Contracting Officer. The Contractor shall submit Department of Transportation information for each truck, and trucking subcontractors shall comply with contract requirements.

3.3.2 Transport

No overflow or spill-out of beach fill shall be permitted during transport to the fill site. All trucks shall be covered in order to prevent spillage. Failure to modify those methods of operation which are resulting in spillage during transport will result in suspension of transport operations, and shall require prompt repair or change of operations so as to prevent spillage as a prerequisite to resumption of transport operations. Trucks shall be maintained in a safe and legal condition, and operators shall obey all traffic laws. Truck shall remain within the approved project route.

SECTION 35 30 00 Page 11

3.4 BEACH FILL

3.4.1 General

All beach fill sand shall be transported to and deposited on the beach within the lines, grades, and cross section shown on the drawings except as may be modified by the provisions of subparagraph b. of subparagraph "Construction" below. Except as specified in subparagraph "Dressing for Payment" below, the Contractor shall maintain and protect the fill in a satisfactory condition at all times until acceptance of the work. Any fill sand which is lost in transit or permitted to flow into the offshore waters or onto the upland from the point the sand is discharged on the beach will not be subject to payment. The fill shall be free of clay lenses, rock or silt pockets. Any such material remaining in the fill shall be removed and disposed of by the Contractor as approved by the Contracting Officer. Any existing signs, other structures within the work lines shall be protected and/or removed and later replaced by the Contractor as directed.

3.4.2 Construction

a. Prior to placement of fill, the Contractor shall remove from the site of the work all snags, driftwood, wrack, sea vegetation and similar debris lying within the foundation limits of the beach fill section. All materials removed shall be disposed of in areas provided by and at the expense of the Contractor and approved by the Contracting Officer. Any groins within the fill area shall be adequately ramped over by the Contractor to prevent damage thereto by the Contractor's equipment. Grading and other construction equipment will not be permitted outside the easement lines shown on the drawings except for designated ingress and egress to and from the site. Mobile equipment of any type operating within 50 feet of any seawall, building, groins, or other structure as determined by the Contracting Officer shall be rubber wheeled. Tracked equipment shall not be permitted to operate within 50 feet of any seawall, building, groin, or other structure as determined by the Contracting Officer. Hand tools may be required in these areas.

b. The transported material shall be placed and brought to rest on the beach to the lines, grades, and cross section indicated on the drawings, unless otherwise provided for herein or directed by the Contracting Officer. The Contractor shall not stockpile any equipment or debris on private property which is west of the landward limit of work. The beach is subject to changes and the elevations on the beach at the time the work is done may vary from the elevations shown on the drawings. The Contracting Officer reserves the right to vary the width and grade of the berm from the lines and grades shown on the plans in order to establish a uniform beach for the entire length of the project. The beach fill cross sections shown on the drawings are for the purpose of estimating the theoretical amount of fill needed and will be used by the Contracting Officer in making any change in the lines and grades. The Contractor will not be required to dress the fill below the mean high water to the slopes shown but will be required to do the dressing specified in subparagraph "Dressing for Payment" below.

c. Grade stakes and any other stakes for any purpose shall be made of steel pipe that can and will be removed intact after filling to cross sections accepted by or as directed by the Contracting Officer.

All stakes shall have sufficient length above grade so they may not be

SECTION 35 30 00 Page 12 accidentally covered by fill. The Contractor shall consecutively number each piece of pipe used for grade stakes, shall clearly mark that number upon the pipe, and shall record the location of each numbered pipe in a grade stake log. The removal of each numbered pipe shall be recorded in the grade stake log at the time of the pipe/stake removal. At the request of the Contracting Officer, all of the grade stake pipes shall be displayed after their removal to demonstrate those pipes that have been removed. All pipes used for grade stakes placed within the limits of the beach fill work shall be numbered and shall be recorded in the log. It is the Contractor's responsibility to track, locate, and completely remove all grade stakes in their entirety to the satisfaction of the Contracting Officer. The Contractor shall possess a magnetic locator of sufficient strength to locate all stakes.

d. The Contractor shall identify outfall pipes in the construction area prior to construction and notify the Contracting Officer. Outfall pipes shall be marked, and protected from damage during construction.

Outfalls shall be covered with beach fill to the lines and grades shown on the plans, but shall not be blocked. Beach fill shall be placed and graded adjacent to the outfalls with a slope not steeper than 1 vertical on 10 horizontal from the berm to the top elevation of the outfalls' concrete structure.

3.4.3 Dedicated Safety and Flag Person

The Contractor shall have dedicated safety and flag persons on site at all time, whose sole responsibly is preventing the public from entering the work area.

3.4.4 Tilling

The Contractor shall till the completed beach fill from the landward limit of the fill to the mean high water line upon completion of each segment of beach construction. Tilling shall be completed by the use of suitable equipment by pulling a rake with the tines modified to a length of 36 inches or more and spaced approximately 12 to 18 inches apart. Tilling shall be to a minimum depth of 36 inches throughout the newly placed beach seaward to the visible high water mark. Following tilling, the beach shall again be dressed by dragging a pipe lengthwise over the beach. The pipe may be positioned immediately behind the tilling tines as a single operation.

3.4.5 Escarpment Monitoring and Removal

See Section 01 57 20 ENVIRONMENTAL PROTECTION.

3.4.6 Dressing for Progress Payment

Immediately following placement of the new beach fill the Contractor shall grade, level and dress the beach fill to meet the required elevations and dimensions indicated on the drawings.