This document is an Abstract of Offers for a federal construction contract issued by the US Army Corps of Engineers, Rock Island District. The solicitation (W912EK26BA010) covers the Galena 2024 PL 84-99 Flood Repair project and was issued on July 13, 2026, with bids opened on August 13, 2026. Four bidders submitted offers: Better By Design (Bidder #1) at $348,986.07, SD Resources Inc (Bidder #2) at $863,560.00, Northwind Engineering LLC (Bidder #3) at $1,384,885.00, and GWO Inc (Bidder #4) at $1,618,608.46. The government estimate was $1,843,509.05. All bidders acknowledged amendments and provided 20% bid bonds as required security.
The work consists of nine line items for flood repair and site restoration activities, including mobilization and demobilization, temporary traffic control, temporary bypass pumping, concrete work, RCP storm sewer installation (11 linear feet), manhole construction (two separate type A installations at 4 and 5 feet depths), storm sewer abandonment, and site restoration. Individual line item pricing varies significantly among bidders, with Bidder #1 submitting the lowest overall bid price. All bids came in below the government estimate, with the lowest bid representing approximately 19% of the estimated cost. The Contracting Officer Ryan R. Larrison certified that all offers were opened, read, and recorded on the abstract.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US ARMY CORPS OF ENGINEERS, ROCK ISLAND DISTRICT
Bid Opening Officer:
Abstract of Offers Project Tit Galena 2024 PL 84-99 Flood Repair Solicitatio W912Ek26BA010
Item # Description QTY UOM Unit Price
Extended Amount
Unit Price
Extended Amount
Unit Price
Extended Amount
Unit Price
Extended Amount
Unit Price
Extended Amount
Unit Price
Extended Amount
0001 Mobilization and Demobilization 1 JOB 12,505.42 12,505.42 140,000.00 140,000.00 131,190.00 131,190.00 133,495.04 133,495.04 512,761.12 512,761.12
0002 Temporary Traffic Control 1 JOB
14,907.52 14,907.52 36,000.00 36,000.00 9,970.00 9,970.00 14,310.01 14,310.01 77,390.83 77,390.83
0003 Temporary Bypass Pumping 1 JOB
151,734.59 151,734.59 212,000.00 212,000.00 5,540.00 5,540.00 667,745.47 667,745.47 165,963.60 165,963.60
0004 Concrete Work 1 JOB 69,966.87 69,966.87 65,000.00 65,000.00 182,700.00 182,700.00 127,112.55 127,112.55 305,373.02 305,373.02
0005 RCP Storm Sewer 11 LF
272.46 2,997.06 3,960.00 43,560.00 2,035.00 22,385.00 4,849.95 53,349.45 11,949.38 131,443.18
0006 Manhole Type A 4 Feet 1 EA 9,960.49 9,960.49 130,000.00 130,000.00 376,480.00 376,480.00 46,312.09 46,312.09 99,578.16 99,578.16
0007 Manhole Type A 5 Feet 1 EA
10,793.16 10,793.16 125,000.00 125,000.00 376,480.00 376,480.00 46,312.09 46,312.09 119,493.79 119,493.79
0008 Storm Sewer Abandonment 1 JOB 73,090.56 73,090.56 90,000.00 90,000.00 36,540.00 36,540.00 349,452.57 349,452.57 365,119.91 365,119.91
0009 Site Restoration 1 JOB
3,030.40 3,030.40 22,000.00 22,000.00 243,600.00 243,600.00 180,519.19 180,519.19 66,385.44 66,385.44 Total 348,986.07 863,560.00 1,384,885.00 1,618,608.46 1,843,509.05 n Bid Security Bid Bond 20% Bid Bond 20% Bid Bond 20% Bid Bonds 20% Amendments Acknowledged: Yes Yes Yes Yes Date Opened: August 13, 2026 Date Issued:July 13, 2026
Ryan R. Larrison Contracting Officer
I certify that I have opened, read, and recorded on this abstract all offers received in response to this soliciation.
Bidder #4 Better By Design SD Recources Inc Northwind Enginerring LLC GWO Inc
Government Estimate Bidder #1 Bidder #2 Bidder #3
Sheet1
| Item Row1: | |
| DescriptionRow1: | |
| QTYRow1: | |
| UOMRow1: | |
| Unit PriceRow1: | |
| Extended AmountRow1: | |
| Unit PriceRow1_2: | |
| Extended AmountRow1_2: | |
| Unit PriceRow1_3: | |
| Extended AmountRow1_3: | |
| Unit PriceRow1_4: | |
| Extended AmountRow1_4: | |
| Unit PriceRow1_5: | |
| Extended AmountRow1_5: | |
| Unit PriceRow1_6: | |
| Extended AmountRow1_6: | |
| 0001: | |
| Mobilization and Demobilization: | |
| 1: | |
| JOB: | |
| Unit Price51276112: | |
| Extended Amount51276112: | |
| 0002: | |
| Temporary Traffic Control: | |
| 1_2: | |
| JOB_2: | |
| Unit Price7739083: | |
| Extended Amount7739083: | |
| 0003: | |
| Temporary Bypass Pumping: | |
| 1_3: | |
| JOB_3: | |
| Unit Price16596360: | |
| Extended Amount16596360: | |
| 0004: | |
| Concrete Work: | |
| 1_4: | |
| JOB_4: | |
| Unit Price30537302: | |
| Extended Amount30537302: | |
| 0005: | |
| RCP Storm Sewer: | |
| 11: | |
| LF: | |
| Unit Price13144318: | |
| Extended Amount13144318: | |
| 0006: | |
| Manhole Type A 4 Feet: | |
| 1_5: | |
| EA: | |
| Unit Price9957816: | |
| Extended Amount9957816: | |
| 0007: | |
| Manhole Type A 5 Feet: | |
| 1_6: | |
| EA_2: | |
| Unit Price11949379: | |
| Extended Amount11949379: | |
| 0008: | |
| Storm Sewer Abandonment: | |
| 1_7: | |
| JOB_5: | |
| Unit Price36511991: | |
| Extended Amount36511991: | |
| Site Restoration: | |
| Unit Price6638544: | |
| Extended Amount6638544: | |
| 0009Row1: | |
| 1Total: | |
| JOBTotal: | |
| 303040Total: | |
| 220000034898607: | |
| 2436000086356000: | |
| 18051919138488500: | |
| 6638544161860846: | |
| Unit Price184350905: | |
| Extended Amount184350905: | |
| 2026-08-13T14:55:07-0500 | |
| LARRISON.RYAN.R.1285260422 |