This is Amendment 0006 to Solicitation W912EK26BA007, issued by the Department of the Army, Fort Independence Rock Island Arsenal, WID Endist Rock Island NO Contracting Division, effective July 20, 2026. The amendment addresses questions received from interested bidders regarding coating and painting requirements for equipment and materials in a pump station renovation project.
The amendment clarifies painting specifications through five question-and-answer pairs: existing equipment requires painting only if damaged during construction; new equipment should arrive factory-coated with additional painting required only for unpainted areas or damage; the newly installed diesel fuel tank must be painted white with weather-resistant paint per specification section 33 56 10 (paint color need not match existing); pneumatic piping appears painted and should be replaced in kind with verification required onsite; and diesel fuel piping must be painted yellow per specification section 33 52 10. The amendment does not extend the offer receipt deadline. Offerors must acknowledge receipt of this amendment by completing items 8 and 15 and returning copies, acknowledging receipt on each offer copy, or submitting separate written communication referencing the solicitation and amendment numbers prior to the specified deadline. Failure to acknowledge receipt may result in offer rejection.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER.
If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The reason for this amendment is to Block 14 (Description of Amendment/Modification):
address the questions received and to provide both questions and answers to all interested bidders. See the below questions and answers:
Q1: Do any existing equipment or existing building materials require coatings?
A1: On MD102 and M-101, it says "CAP AND FILL UNUSED PENETRATIONS TO MATCH EXISTING WALLS" and specs say in 02 41 00, 3.1.5, "Replace metal walls and insulation in kind to match surrounding areas. Paint to match as closely as possible." Existing equipment should not need painted unless it is damaged during construction. New equipment should come factory coated or painted and will not need additional painting unless there is unpainted parts or damage.
Refer to the specs for specific instances where painting is necessary.
Q2: Is it correct that the newly installed equipment inside the pump station shall be painted to match the existing?
A2: Assume that most equipment will come prepainted from the manufacturer. If items are not painted, refer to spec section 09 90 00 or associated spec section to describe painting necessary.
If there are questions onsite about specific items, submit an RFI or discuss with the COR.
Q3: Is it correct that the newly installed diesel fuel tank shall be painted to match existing?
A3: According to spec section 33 56 10, 2.4.1.1 "Tank to be painted white with weather resistant paint." Paint color does not necessarily have to match existing diesel tank. Assume that tank would come prepainted from the manufacturer. Touchup painting may be required.
Q4: Does the newly installed pneumatic piping require paint coating?
A4: M-102, keynote 13 referring to replacing pipe sections removed for the radiator says, "REPLACE IN KIND." From pictures, piping appears to be painted, but will have to be verified onsite.
Q5: Is it correct that the newly installed diesel fuel piping requires yellow coating?
A5: Yes correct per spec section 33 52 10, 2.11, "Fuel piping to be painted yellow."
W912EK26BA0070006
| IDCode: J |
| Page: 1 |
| Pages: 2 |
| AmendNo: 0006 |
| EffDate: 20 JUL 2026 |
| ReqNo: |
| ProjNo: 13 |
| IssCode: W912EK |
| AdmCode: |
| IssuedBy: W07V ENDIST ROCK ISLAND |
KO CONTRACTING DIVISION, 1 ROCK ISLAND ARSENAL
ROCK ISLAND, IL 61299-5001
UNITED STATES
JAKE ANDERSON, EMAIL: JAKE.T.ANDERSON@USACE.ARMY.MIL TELEPHONE: (309) 794-6131
AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: W912EK26BA007 |
| SolDate: 18 JUN 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: SEE SECTION G - CONTRACT ADMINISTRATION DATA |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Schedule |
| ContNameTitle: |
| CoNameTitle: RYAN R. LARRISON |
| ContDate: |
| CODate: 13 AUG 2026 |
File details come from the government source that posted it. Updated .