AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The reason for this amendment is to revise SECTION 22 10 00, provide revised draw ings and extend the closing date to 2:00 pm CT, Thursday, March 1, 2018.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 09-Feb-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK18R0003

X 9B. DATED (SEE ITEM 11)

12-Jan-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

09-Feb-2018

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

1500 ROCK ISLAND DRIVE

ROCK ISLAND IL 61201

W912EK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EK18R0003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The required response date/time has changed from 15-Feb-2018 02:00 PM to 01-Mar-2018 02:00 PM.

AMENDMENT 0002

The following modifications are made to SECTION 22 10 00; and the DRAWINGS.

SECTION 22 10 00

a. PAGE 22 10 00-17. Delete page 22 10 00-17, in its entirety, and substitute therefor revised and new page 22 10 00-17, Amendment No. 0002, dated 7 February 2018, attached hereto.

DRAWING (SUPERSEDED)

b. Revised drawing bearing the revision number and date listed below is being issued with this amendment.

SHEET ID – G-002, MARK 1, Dated 02/05/2018;

SHEET ID – GC001, MARK 1, Dated 02/05/2018;

SHEET ID – GC402, MARK 1, Dated 02/05/2018;

SHEET ID – GC403, MARK 1, Dated 02/05/2018;

SHEET ID – E-002, MARK 1, Dated 02/05/2018;

SHEET ID – E-100, MARK 1, Dated 02/02/2018;

SHEET ID – E-504, MARK 1, Dated 02/05/2018;

SHEET ID – E-505, MARK 1, Dated 02/05/2018;

SHEET ID – E-604, MARK 1, Dated 02/05/2018;

SHEET ID – EI100, MARK 1, Dated 02/05/2018;

SHEET ID – EI101, MARK 1, Dated 02/05/2018;

SHEET ID – EI102, MARK 1, Dated 02/05/2018; and SHEET ID – EI103, MARK 1, Dated 02/05/2018;

ATTACHMENTS: 22 10 00-17; G-002, GC001, GC402, GC403, E-002, E-100, E-504,

E-505, E-604, EI100, EI101, EI102, and EI103.

W912EK18R0003

for use. Support leads and protect from water and mechanical damage.

Terminate leads outside of pump casing in a waterproof connection head, Design Basis: Minco CH 339, and cap until final connections are made in the field. The connection head to be rated watertight to 25 psi. Lead protection consists of pipes fastened to pump with brackets using bolts and nuts to permit their removal, and constructed with enough unions to be completely disassembled. Leads passing through pump water passage in pump to either be contained in a guide vane or be protected by Schedule 120 pipe. Protection pipe to be removable if connected to shaft-enclosing tube. Install bearing heat sensors as shown in Attachment A, Figure 2 at end of the section. Run leads and wiring to a junction box located on baseplate. Provide terminal strip in junction box for connection of wiring to temperature readouts.

2.3.13 Thrust Bearings

Provide thrust and steady bearings in the motor to carry total thrust and radial loads in accordance with Section 26 29 01 ELECTRIC MOTORS, 3-PHASE

VERTICAL INDUCTION TYPE.

2.3.14 Deleted

2.4 LUBRICATION SYSTEM

Provide either oil or grease. Product lubrication is prohibited.

Support grease lines to each bearing and protect from water and mechanical damage. Grease line protection consists of channels fastened to pump with brackets, using bolts and nuts to permit removal. Grease lines passing through pump water passage to either be contained in a guide vane or be protected by Schedule 120 pipe. This protection pipe to be removable if connected to shaft-enclosing tube. Prefill grease lines before connection to bearings. Terminate grease lines above baseplate for connection to lubricating grease pump.

Oil lubrication of shaft bearings consists of introducing oil at the top line shaft bearing and allowing oil to run down the shaft for the lubrication of the lower bearings. Oil lubrication consists of an oil reservoir mounted on the pump baseplate or pump driver at such height to permit gravity flow of oil to the highest lubrication point of the pump shaft. Construct the reservoir of the transparent material to permit observation of the quantity of oil in the reservoir. The oil reservoir to have a minimum capacity of 1 gallon. The reservoir to have a solenoid valve to permit oil flow whenever the pump driver is in operation. The flow rate from the oil reservoir to be adjustable from five drips per minute to constant flow. The reservoir valve to permit manual flow of oil when the pump driver is not operating for prelubrication of the shaft bearing. Construct the oil line from the oil reservoir to the pump line shaft of stainless steel tubing and support at sufficient locations to preclude vibration of tubing when the pump is operating. Maintain pump bearings in an oil bath, with sealing system to prevent oil passage to the water being pumped. If the pump has a bearing located below the impeller, this bearing must be grease-lubricated. Provide a grease line with a grease fitting from this bearing to a location on top of the baseplate.

22 10 00-17

AMEND 0002

7 FEB 2018

0002
B5BCBD1801-SPEC-2018-02-07-AMEND 0002