Amendment 0001- Responses to questions asked during the question answer period.

View the file

Other files for this federal contract opportunity

Other files attached to Fabrication Quality Assurance Service IDIQ, newest first.
File Type Posted
Annex_B_-_Access_Requirements_and_Procedures_for_non-DoD__Identification_Card_Holders.pdf PDF
Annex_A_-_Access_Requirements_and_Procedures_for_DoD_and_Federal_Approved_Identification_Card_Holders.pdf PDF
W912EK-16-R-0004.pdf PDF
PPQ.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The reason for this amendment is as follow s:

The question and answ er period closed 15 December 2015. See summary of changes for the proposed questions and answ ers.

The solicitation close date has been extended from 22 December 2015 to 04 January 2016 at 10:00am CT.

All other information is to remain the same.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 18-Dec-2015

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EK-16-R-0004

X 9B. DATED (SEE ITEM 11)

23-Nov-2015

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

18-Dec-2015

CODE

CONTRACTING DIVISION

US ARMY CORPS OF ENGINEERS

1500 ROCK ISLAND DRIVE

ROCK ISLAND IL 61201

W912EK 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EK-16-R-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES

Question 1: Typically a Bridge Coatings Inspector (BCI) has been the requirement for this type of project, however a Protective Coatings Inspector (PCI) Level I is listed in the RFP.

Will the BCI Certification be sufficient for this project?

Answer 1: BCI certification will be sufficient for this project.

Question 2: The RFP asks for only one person per Labor Category be listed, however, we have multiple people that meet the requirements. Can multiple people be identified in the Organization Chart and referenced in the SF330 Forms as long as we only provide resumes and certifications for one for each Labor Category?

Answer 2: Offerors may submit any number of resumes to meet the requirements. A single qualified person for each labor category will render the contractor "technically acceptable," but those persons will be the only pre-approved persons to do work on task orders. Any personnel resumes not submitted in response to the solicitation would need to be submitted and approved later, if substitutions are proposed at a later date.

Question 3: Should the Unit Prices for each Labor Category be based on the individual that we’re proposing or should a blended rate be used based on our qualified personnel?

Answer 3: Individual labor rates will be evaluated for reasonableness only. Offerors may structure their rate schedules in the way the makes the most sense for their situation. Note that the overall price proposal will determine the lowest bid for award, but the proposed labor rates will also become contractual rates for the successful offeror.

Question 4: The PPQ Forms that were provided as part of the RFP Package are different from others that we have on file from previous projects. Is it OK if the forms are slightly different as long as all of the required information is listed?

Answer 3: Previous version of PPQ forms are acceptable as long as all required information is listed.

Question 5: On this contract, does the prime consultant need to provide at least 50% of the services/labor?

Answer 5: In accordance with Clause 52.219-14(c)(1), Limitations on Subcontracting, the answer would be yes. Services (except construction), at least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the concern.

Question 6: On the schedule of prices, do we submit only unit prices (sheet 3 of 122) for each of the labor categories and each option year and not any total prices for each year?

W912EK-16-R-0004

Answer 6: The Contractor only needs to supply per unit cost for each labor category for each period.

The required response date/time has changed from 22-Dec-2015 10:00 AM to 04-Jan-2016 10:00

AM.

(End of Summary of Changes)