This solicitation is for the Little Goose DC System and LV Switchgear Upgrades project. The solicitation number is W912EF22R0001 and is issued by the Department of the Army Corps of Engineers Engineering District Walla Walla. The project involves removing existing transformers, switchgear, motor control centers, panelboards, batteries, battery chargers, conductors and conduit. It also includes furnishing and installing new equipment including 480V AC switchgear and transformers, unit motor control centers, station service motor control centers, panelboards, 480V governor oil pump motors, 125V battery chargers, batteries, battery monitoring equipment, battery switchboards, and distribution panelboards. The bid response date is October 12, 2022. The solicitation includes requirements for an Accident Prevention Plan, Activity Hazard Analyses, confined space entry plans, critical lift plans, and fall protection plans.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate the changes outlined below .

1. CONTRACT ID CODE PAGE OF PAGES

1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 14-Sep-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF22R0001

X 9B. DATED (SEE ITEM 11)

22-Aug-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Sep-2022

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

HILLARY A. MORGAN

201 N. THIRD AVENUE

WALLA WALLA WA 99362

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF22R0001

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Summary of changes for Amendment-0001 LGA DC System and LV Switchgear Upgrades

Solicitation Number: W912EF22R0001

1. Revised solicitation:

a. SECTION 00 10 00 - SOLICITATION

• The required response date/time has changed from 21-Sep-2022 03:00 PM to 12-Oct-

2022 03:00 PM.

b. SECTION 00 21 00 - INSTRUCTIONS

• The bid schedule was revised as follows:

• Revised CLIN 0032 – Changed 0031 to 0032

• Added CLIN 0033 – New CLIN

2. Revised the following Specifications:

c. SECTION 01 22 00.00 28 “MEASUREMENT AND PAYMENT”

• Revised paragraph 1.35 “GOVERNOR AIR SUPPLY CROSSOVER MODIFICATION”

• Added paragraph 1.36 “CLIN 0033 - FURNISH AND INSTALL NEW CABLE TRAYS”

d. SECTION 01 35 29.10 28 “GOVERNMENTAL SAFETY REQUIREMENTS”

• Revised paragraph 1.6.1.1 “Site Safety and Health Officer (SSHO)”

e. SECTION 26 05 36.00 28 “CABLE TRAYS FOR ELECTRICAL SYSTEMS”

• Revised paragraph 3.5 “CABLE CLEATS”

• Revised paragraph 3.6 “CABLE TRAY FILL”

f. SECTION 26 32 36.00 26 “BATTERY CHARGERS AND INVERTERS”

• Revised paragraph 1.3 “SUBMITTALS”

• Deleted paragraph 2.5 “INVERTER ISOLATION TRANSFORMERS”

See revised specifications for details.

SECTION 00 10 00 - SOLICITATION

The required response date/time has changed from 21-Sep-2022 03:00 PM to 12-Oct-2022 03:00 PM.

The Issued By organization has changed from

USAED, WALLA WALLA - CONTRACTING DIV.

DAVID C BOONE 201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

to

USAED, WALLA WALLA - CONTRACTING DIV.

HILLARY A. MORGAN

201 N. THIRD AVENUE

WALLA WALLA WA 99362

SECTION 00 21 00 - INSTRUCTIONS

Walla Walla District Corps of Engineers Little Goose DC System and Low Voltage Switch Gear Upgrades

The magnitude of construction is estimated to be between $10,000,000 and $25,000,000

ITEM DESCRIPTION QTY U/M U/P AMOUNT

Base Items

0001 MOBILIZATION AND DEMOBILIZATION 1 JOB XXXXX $_______

0002 REMOVE AND DISPOSE OF EXISTING TRANSFORMERS AND 480V

AC SWITCHGEAR SQO, SQ1, and SQ2 1 JOB XXXXX $_______

0003 REMOVE AND DISPOSE OF EXISTING UNIT MOTOR CONTROL

CENTERS SU1-SU6 AND CP1-CP6 1 JOB XXXXX $_______

0004 REMOVE AND DISPOSE OF EXISTING MOTOR CONTROL CENTERS

CQO1, CQO2, CQO4, CQO5, SH AND THE SH TRANSFORMER 1 JOB XXXXX $_______

0005 REMOVE AND DISPOSE OF EXISTING PANELBOARDS CQO3,

FCQ1, and FCQ2 1 JOB XXXXX $_______

0006AA REMOVE AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR OIL

PUMP MOTORS FROM UNITS 1 - 3 1 JOB XXXXX $_______

0006AB REMOVE AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR OIL

PUMP MOTORS FROM UNITS 4 - 6 1 JOB XXXXX $_______

0007 REMOVE AND DISPOSE OF EXISTING 125V AND 48V BATTERIES 1 JOB XXXXX $_______

0008 REMOVE AND DISPOSE OF EXISTING BATTERY CHARGERS BC1,

BC2, AND BC3 1 JOB XXXXX $_______

0009 REMOVE AND DISPOSE OF EXISTING DC SWITCHBOARDS AND

PANELBOARDS AND PREFERRED AC PANELS 1 JOB XXXXX $_______

0010 REMOVE AND DISPOSE OF EXISTING CONDUCTORS, CONDUIT

RISERS, AND EXPOSED CONDUIT 1 JOB XXXXX $_______

0011 REMOVE AND DISPOSE OF EXISTING TURBINE SUPPORT

EQUIPMENT STARTERS AND CONTROLS 1 JOB XXXXX $_______

FURNISH AND INSTALL NEW 480V AC SWITCHGEAR AND

TRANSFORMER LINEUPS SQO, SQ1 AND SQ2, INCLUDING NEW

FEEDER CABLES

1 JOB XXXXX $_______

FURNISH AND INSTALL NEW UNIT MOTOR CONTROL CENTERS

SU1 - SU6, INCLUDING ASSOCIATED CONTROLS AND NEW

FEEDER CABLES

FURNISH AND INSTALL NEW STATION SERVICE MOTOR

CONTROL CENTERS CQ01, CQO2, CQO4, CQO5 AND SH,

INCLUDING ASSOCIATED CONTROLS, NEW SH TRANSFORMER,

AND FEEDER CABLES

0015 FURNISH AND INSTALL NEW PANELBOARDS CQO3, FCQ1, AND

FCQ2, INCLUDING NEW FEEDER CABLES 1 JOB XXXXX $_______

0016AA FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP

MOTORS IN UNITS 1 - 3 1 JOB XXXXX $_______

0016AB FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP

MOTORS IN UNITS 4 - 6 1 JOB XXXXX $_______

0017 FURNISH AND INSTALL NEW 125V BATTERY CHARGERS IN BC1

AND BC2 1 JOB XXXXX $_______

FURNISH AND INSTALL NEW BATTERIES, BATTERY

MONITORING COMPUTER, CART, DIAGNOSTIC EQUIPMENT,

WIRING, BATTERY MONITORING HARDWARE & SOFTWARE

PACKAGE

FURNISH AND INSTALL NEW BATTERY SWITCHBOARDS, DC

DISTRIBUTION PANELBOARDS, 120V AC DISTRIBUTION

PANELBOARDS, AND MANUAL BREAKER TRANSFER PANELS

INCLUDING NEW FEEDER CABLES

0020 FURNISH AND INSTALL BATTERY ROOM UPGRADES 1 JOB XXXXX $_______

0021 PROVIDE NEW LOAD BANK 1 JOB XXXXX $_______

0022 FURNISH AND INSTALL SQ REMOTE CONTROL PANELS 1 JOB XXXXX $_______

0023 FURNISH THEN INSTALL SBC AND SG PANELS 1 JOB XXXXX $_______

0024 RELOCATE EXISTING INVERTERS 1 JOB XXXXX $_______

0025 FURNISH SPARE PARTS AND ACCESSORIES 1 JOB XXXXX $_______

0026 CORE DRILLING AND CONCRETE WORK 1 JOB XXXXX $_______

0027 FURNISH O&M MANUALS 1 JOB XXXXX $_______

0028 FURNISH FINAL RECORD DRAWINGS 1 JOB XXXXX $_______

0029 PROVIDE COMMISSIONING SERVICES AND TRAINING 1 JOB XXXXX $_______

0030 FIRESTOPPING 1 JOB XXXXX $_______

IMPORTANT: See Section 01 22 00.00 28; MEASUREMENT AND PAYMENT; Paragraph; Retainage of Payment, for withholding of payment for final deliverables.

U/M* = Unit of Measure U/P* = Unit Price NTE* = Not to Exceed EST* = Estimated

Quantities identified as Estimated (“Est”) in the bid schedule are subject to FAR Clause 52.211-18, VARIATION IN ESTIMATED QUANTITY, located in Section 00 70 00.

SECTION 00 70 00 - CONDITIONS OF THE CONTRACT

The following have been added by reference:

52.211-18 Variation in Estimated Quantity APR 1984

(End of Summary of Changes)

0031 FURNISH AND INSTALL NEW PLC GOVERNOR OIL PUMP

CONTROLS 1 JOB XXXXX $_______

Optional Items

0032 GOVERNOR AIR SUPPLY CROSSOVER MODIFICATION 1 JOB XXXXX $_______

0033 FURNISH AND INSTALL NEW CABLE TRAYS 800

EST LF $______ $_______

SCHEDULE TOTAL $_________

Little Goose DC System & LV Switchgear Upgrade W912EF22R0001 Amend - 0001

LGA455595DCLVSU

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15.00 28 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00.00 28 GENERAL REQUIREMENTS

01 11 00.00 28 SUMMARY OF WORK

01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS

01 12 16.00 28 WORK SEQUENCE

01 14 00.10 28 PROJECT SITE RESTRICTIONS

01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY

(OPSEC)

01 22 00.00 28 MEASUREMENT AND PAYMENT

01 32 01.00 28 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 45 04.00 28 CONTRACTOR QUALITY CONTROL

01 51 00.00 28 TEMPORARY UTILITIES

01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS

01 57 20.00 28 ENVIRONMENTAL PROTECTION

01 78 00.00 28 CLOSEOUT SUBMITTALS

01 78 23.00 28 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00.00 28 DEMOLITION

02 83 33.12 28 LEAD BASED PAINT (LBP) REMOVAL AND DISPOSAL

DIVISION 03 - CONCRETE

03 60 00.01 28 CONCRETE DEMOLITION, REPAIR OF CONCRETE SURFACES, AND

MINOR EQUIPMENT FOUNDATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 41 16.00 28 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 84 00.00 28 FIRESTOPPING

DIVISION 08 - OPENINGS

08 11 13.00 28 STEEL DOORS AND FRAMES

08 71 00.00 28 DOOR HARDWARE

DIVISION 09 - FINISHES

09 67 23.13 28 EPOXY FLOORING

09 90 00.00 28 PAINTS AND COATINGS

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 00.00 26 SEISMIC RESTRAINT FOR MECHANICAL AND ELECTRICAL EQUIPMENT

Amendment - 0001 PROJECT TABLE OF CONTENTS Page 1 g4ecctgh Line Amendment-0001 Section 01 22 00.00 28 g4ecctgh Line Amendment-0001 - Section 01 35 29.10 28

DIVISION 22 - PLUMBING

22 00 00.00 28 PLUMBING, GENERAL PURPOSE

22 15 13.16 26 COMPRESSED-AIR PIPING, PIPING COMPONENTS, AND VALVES

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 00 00.00 28 MECHANICAL GENERAL REQUIREMENTS

23 05 24.00 28 METAL SUPPORTS FOR MECHANICAL SYSTEMS

23 05 93.00 28 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 30 00.00 28 HVAC AIR DISTRIBUTION

23 34 00.00 28 FANS

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.00 28 CYBERSECURITY

DIVISION 26 - ELECTRICAL

26 05 00.00 28 BASIC ELECTRICAL MATERIALS AND METHODS

26 05 13.00 28 MEDIUM-VOLTAGE CABLE

26 05 19.00 28 INSULATED WIRE AND CABLE

26 05 26.00 28 GROUNDING

26 05 36.00 28 CABLE TRAYS FOR ELECTRICAL SYSTEMS

26 08 00.00 28 APPARATUS INSPECTION AND TESTING

26 08 01.00 28 SYSTEMS TESTING AND COMMISSIONING

26 23 10.10 28 480 VOLT SWITCHGEAR AND TRANSFORMERS

26 24 19.00 28 MOTOR CONTROL CENTERS

26 28 00.00 28 SWITCHBOARDS AND PANELBOARDS

26 32 34.00 26 BATTERIES

26 32 36.00 26 BATTERY CHARGERS AND INVERTERS

DIVISION 27 - COMMUNICATIONS

27 21 10.00 26 FIBER OPTIC DATA TRANSMISSION SYSTEM

DIVISION 40 - PROCESS INTERCONNECTIONS

40 95 00.00 26 PROGRAMMABLE LOGIC CONTROLLER HARDWARE AND PANELS

DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT

41 22 13.19 26 BATTERY LIFTING DEVICE

-- End of Project Table of Contents --

Amendment - 0001 PROJECT TABLE OF CONTENTS Page 2 g4ecctgh Line Amendment-0001 - Section 26 05 36.00 28 g4ecctgh

Amendment-0001 - Section 26 32 36.00 26

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 28

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 RETAINAGE OF PAYMENT

1.2 CLIN 0001 - MOBILIZATION AND DEMOBILIZATION

1.3 CLIN 0002 - REMOVE AND DISPOSE OF EXISTING TRANSFORMERS AND 480V

AC SWITCHGEAR SQO, SQ1, and SQ2

1.4 CLIN 0003 - REMOVE AND DISPOSE OF EXISTING MAIN UNIT AUXILIARY

BOARDS SU1-SU6 AND CP1-CP6

1.5 CLIN 0004 - REMOVE AND DISPOSE OF EXISTING MOTOR CONTROL CENTERS

CQO1, CQO2, CQO4, CQO5, SH AND THE SH TRANSFORMER

1.6 CLIN 0005 - REMOVE AND DISPOSE OF EXISTING PANELBOARDS CQO3, CQO7,

FCQ1, and FCQ2

1.7 CLIN 0006AA - REMOVE AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR

OIL PUMP MOTORS FROM UNITS 1 - 3

1.8 CLIN 0006AB - REMOVE AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR

OIL PUMP MOTORS FROM UNITS 4 - 6

1.9 CLIN 0007 - REMOVE AND DISPOSE OF EXISTING 125V AND 48V BATTERIES

1.10 CLIN 0008 - REMOVE AND DISPOSE OF EXISTING BATTERY CHARGERS BC1,

BC2, AND BC3

1.11 CLIN 0009 - REMOVE AND DISPOSE OF EXISTING DC SWITCHBOARDS AND

PANELBOARDS AND PREFERRED AC PANELS

1.12 CLIN 0010 - REMOVE AND DISPOSE OF EXISTING CONDUCTORS, CONDUIT

RISERS, AND EXPOSED CONDUIT

1.13 CLIN 0011 - REMOVE AND DISPOSE OF EXISTING HEADCOVER, TURBINE

BEARING OIL PUMP STARTERS AND CONTROLS

1.14 CLIN 0012 - FURNISH AND INSTALL NEW 480V AC SWITCHGEAR AND

TRANSFORMER LINEUPS SQO, SQ1 AND SQ2, INCLUDING NEW FEEDER CABLES

1.15 CLIN 0013 - FURNISH AND INSTALL NEW UNIT MOTOR CONTROL CENTERS

SU1 - SU6, INCLUDING NEW FEEDER CABLES

1.16 CLIN 0014 - FURNISH AND INSTALL NEW STATION SERVICE MOTOR CONTROL

CENTERS CQ01, CQO2, CQO4, CQO5 AND SH, INCLUDING NEW SH

TRANSFORMER AND FEEDER CABLES

1.17 CLIN 0015 - FURNISH AND INSTALL NEW PANELBOARDS CQO3, FCQ1, AND

FCQ2, INCLUDING NEW FEEDER CABLES

1.18 CLIN 0016AA - FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP

MOTORS IN UNITS 1 - 3

1.19 CLIN 0016AB - FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP

MOTORS IN UNITS 4 - 6

1.20 CLIN 0017 - FURNISH AND INSTALL NEW 125V BATTERY CHARGERS IN BC1

AND BC2

1.21 CLIN 0018 - FURNISH AND INSTALL NEW BATTERY, BATTERY MONITORING

COMPUTER, CART, DIAGNOSTIC EQUIPMENT, WIRING, BATTERY MONITORING

HARDWARE AND SOFTWARE PACKAGE

1.22 CLIN 0019 - FURNISH AND INSTALL NEW BATTERY SWITCHBOARDS, DC

DISTRIBUTION PANELBOARDS, 120V AC DISTRIBUTION PANELBOARDS, AND

MANUAL BREAKER TRANSFER PANELS INCLUDING NEW FEEDER CABLES

SECTION 01 22 00.00 28 Page 1 Amendment - 0001

1.23 CLIN 0020 - FURNISH AND INSTALL BATTERY ROOM UPGRADES

1.24 CLIN 0021 - PROVIDE NEW LOAD BANK

1.25 CLIN 0022 - FURNISH AND INSTALL SQ REMOTE CONTROL PANELS

1.26 CLIN 0023 - FURNISH THEN INSTALL SBC AND SG PANELS

1.27 CLIN 0024 - RELOCATE EXISTING INVERTERS THEN FURNISH AND INSTALL

125V/48V DC/DC CONVERTERS

1.28 CLIN 0025 - FURNISH SPARE PARTS AND ACCESSORIES

1.29 CLIN 0026 - CORE DRILLING AND CONCRETE WORK

1.30 CLIN 0027 - FURNISH O&M MANUALS

1.31 CLIN 0028 - FURNISH FINAL RECORD DRAWINGS

1.32 CLIN 0029 - PROVIDE COMMISSIONING SERVICES AND TRAINING

1.33 CLIN 0030 - FIRESTOPPING

1.34 CLIN 0031 - LEAD BASED PAINT REMEDIATION AND DISPOSAL

1.35 OPTIONAL ITEMS

1.35.1 CLIN 0032 - GOVERNOR AIR SUPPLY CROSSOVER MODIFICATION

1.35.2 CLIN 0033 - FURNISH AND INSTALL NEW CABLE TRAYS

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section Table of Contents --

SECTION 01 22 00.00 28 Page 2 Amendment - 0001 g4ecctgh

Amendment-0001 - Sections 01 22 00.00 28 - Paragraphs 1.35.1 & 1.35.2

SECTION 01 22 00.00 28

MEASUREMENT AND PAYMENT

PART 1 GENERAL

In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.

1.1 RETAINAGE OF PAYMENT

Retainage in the amount of 10 percent of original contract award amount will be withheld until the final submittals listed below have been approved by the Government. The 10 percent final submittals retainage will be held until the Contractor has earned 90 percent of the original contract value. See SECTION 01 78 00.00 28 "CLOSEOUT SUBMITTALS" and SECTION 01 78 23.00 28 "OPERATION AND MAINTENANCE DATA" for additional information.

a. Final Shop Drawings.

b. Final As-built Drawings.

c. Final Record Drawings.

d. Return of Government Issued Items.

e. Final Operation and Maintenance Manuals and Parts Catalogs.

f. Final Spare Parts submission.

g. Complete all required training.

1.2 CLIN 0001 - MOBILIZATION AND DEMOBILIZATION

Measurement and payment for mobilization and demobilization will be in accordance with Contract CLAUSE: PAYMENT FOR MOBILIZATION AND DEMOBILIZATION. This item will be measured for payment as a complete pay item (JOB) under Item No. 0001, "Mobilization and Demobilization", which price and payment shall be full compensation for mobilizing and demobilizing all plant and equipment required for performance of the work, as specified and approved.

1.3 CLIN 0002 - REMOVE AND DISPOSE OF EXISTING TRANSFORMERS AND 480V AC

SWITCHGEAR SQO, SQ1, and SQ2

Removal and disposal of existing transformers and 480V AC switchgear SQO, SQ1, and SQ2 will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0002, "REMOVE AND DISPOSE OF EXISTING TRANSFORMERS AND 480V AC SWITCHGEAR SQO, SQ1, and SQ2", which price and payment shall be full compensation for all work required to remove and dispose of existing transformers and 480V AC switchgear SQO, SQ1, and SQ2, complete, as specified and approved.

1.4 CLIN 0003 - REMOVE AND DISPOSE OF EXISTING MAIN UNIT AUXILIARY BOARDS

SU1-SU6 AND CP1-CP6

Remove and dispose of existing main unit auxiliary boards SU1 - SU6 and CP1-CP6 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0003, "REMOVE AND DISPOSE

SECTION 01 22 00.00 28 Page 3

OF EXISTING MAIN UNIT AUXILIARY BOARDS SU1 - SU6 AND CP1-CP6", which price and payment shall be full compensation for all work required to remove and dispose of existing main unit auxiliary boards SU1 - SU6 and CP1-CP6, complete, as specified and approved.

1.5 CLIN 0004 - REMOVE AND DISPOSE OF EXISTING MOTOR CONTROL CENTERS CQO1,

CQO2, CQO4, CQO5, SH AND THE SH TRANSFORMER

Remove and dispose of existing motor control centers CQO1, CQO2, CQO4, CQO5, SH and the SH transformer will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No.

0004, "REMOVE AND DISPOSE OF EXISTING MOTOR CONTROL CENTERS CQO1, CQO2,

CQO4, CQO5, SH AND THE SH TRANSFORMER", which price and payment shall be full compensation for all work required to remove and dispose of existing motor control centers CQO1, CQO2, CQO4, CQO5, SH and the SH transformer, complete, as specified and approved.

1.6 CLIN 0005 - REMOVE AND DISPOSE OF EXISTING PANELBOARDS CQO3, CQO7,

FCQ1, and FCQ2

Remove and dispose of existing panelboards CQO3, CQO7, FCQ1, and FCQ2 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0005, "REMOVE AND DISPOSE OF EXISTING PANELBOARDS CQO3, CQO7, FCQ1, and FCQ2", which price and payment shall be full compensation for all work required to remove and dispose of existing panelboards CQO3, CQO7, FCQ1, and FCQ2 as specified and approved.

1.7 CLIN 0006AA - REMOVE AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR OIL

PUMP MOTORS FROM UNITS 1 - 3

Remove and dispose of existing 4160 volt governor oil pump motors from units 1 - 3 will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0006AA, "REMOVE

AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR OIL PUMP MOTORS FROM UNITS 1 -

3", which price and payment shall be full compensation for all work required to remove and dispose of existing 4160 volt governor oil pump motors from units 1 - 3 complete, as specified and approved.

1.8 CLIN 0006AB - REMOVE AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR OIL

PUMP MOTORS FROM UNITS 4 - 6

Remove and dispose of existing 4160 volt governor oil pump motors from units 4 - 6 will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0006AB, "REMOVE

AND DISPOSE OF EXISTING 4160 VOLT GOVERNOR OIL PUMP MOTORS FROM UNITS 4 -

6", which price and payment shall be full compensation for all work required to remove and dispose of existing 4160 volt governor oil pump motors from units 4 - 6 complete, as specified and approved.

1.9 CLIN 0007 - REMOVE AND DISPOSE OF EXISTING 125V AND 48V BATTERIES

Removal and disposal of existing 125V and 48V batteries will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0007, "REMOVE AND DISPOSE OF EXISTING 125V AND 48V BATTERIES" which price and payment shall be full compensation for all work required to remove and dispose of existing 125V and 48V batteries complete, as specified and approved.

SECTION 01 22 00.00 28 Page 4

1.10 CLIN 0008 - REMOVE AND DISPOSE OF EXISTING BATTERY CHARGERS BC1, BC2,

AND BC3

Remove and dispose of existing battery chargers BC1, BC2, AND BC3 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0008, "REMOVE AND DISPOSE OF EXISTING BATTERY CHARGERS BC1, BC2, AND BC3", which price and payment shall be full compensation for all work required to remove and dispose of existing battery chargers BC1, BC2, AND BC3, complete, as specified and approved.

1.11 CLIN 0009 - REMOVE AND DISPOSE OF EXISTING DC SWITCHBOARDS AND

PANELBOARDS AND PREFERRED AC PANELS

Remove and dispose of existing DC switchboards and panelboards and preferred AC panels will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0009, "REMOVE AND DISPOSE OF EXISTING DC SWITCHBOARDS AND PANELBOARDS AND

PREFERRED AC PANELS", which price and payment shall be full compensation for all work required to remove and dispose of existing DC switchboards and panelboards and preferred AC panels complete, as specified and approved.

1.12 CLIN 0010 - REMOVE AND DISPOSE OF EXISTING CONDUCTORS, CONDUIT

RISERS, AND EXPOSED CONDUIT

Remove and dispose of existing conductors, conduit risers, and exposed conduit will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0010, "REMOVE AND DISPOSE OF EXISTING CONDUCTORS, CONDUIT RISERS, AND EXPOSED CONDUIT", which price and payment shall be full compensation for all work required to remove and dispose of existing conductors, conduit risers, and exposed conduit complete, as specified and approved.

1.13 CLIN 0011 - REMOVE AND DISPOSE OF EXISTING HEADCOVER, TURBINE BEARING

OIL PUMP STARTERS AND CONTROLS

Remove and dispose of existing headcover, turbine bearing oil pump starters and controls will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0011, "REMOVE AND DISPOSE OF EXISTING HEADCOVER, TURBINE BEARING OIL PUMP

STARTERS AND CONTROLS", which price and payment shall be full compensation for all work required to Remove and dispose of existing headcover and turbine bearing oil pump starters and controls, complete, as specified and approved.

1.14 CLIN 0012 - FURNISH AND INSTALL NEW 480V AC SWITCHGEAR AND

TRANSFORMER LINEUPS SQO, SQ1 AND SQ2, INCLUDING NEW FEEDER CABLES

Furnish and install new 480V AC switchgear and transformer lineups SQO, SQ1 and SQ2, including new feeder cables will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0012, "FURNISH AND INSTALL NEW 480V AC SWITCHGEAR AND TRANSFORMER LINEUPS SQO, SQ1 AND SQ2, INCLUDING NEW FEEDER CABLES," which price and payment shall be full compensation for all work required to furnish and install new 480V AC switchgear and transformer lineups SQO, SQ1 and SQ2, including new feeder cables, complete, as specified and approved.

SECTION 01 22 00.00 28 Page 5

1.15 CLIN 0013 - FURNISH AND INSTALL NEW UNIT MOTOR CONTROL CENTERS SU1 -

SU6, INCLUDING NEW FEEDER CABLES

Furnish and install new unit motor control centers SU1 - SU6, including new feeder cables will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0013, "FURNISH AND

INSTALL NEW UNIT MOTOR CONTROL CENTERS SU1 - SU6, INCLUDING NEW FEEDER

CABLES", which price and payment shall be full compensation for all work required to furnish and install new unit motor control centers SU1 - SU6, including new feeder cables complete, as specified and approved.

1.16 CLIN 0014 - FURNISH AND INSTALL NEW STATION SERVICE MOTOR CONTROL

CENTERS CQ01, CQO2, CQO4, CQO5 AND SH, INCLUDING NEW SH TRANSFORMER AND

FEEDER CABLES

Furnish and install new station service motor control centers CQ01, CQO2, CQO4, CQO5 AND SH, including new SH transformer and feeder cables will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0014, "PROVIDE NEW STATION SERVICE MOTOR

CONTROL CENTERS CQ01, CQO2, CQO4, CQO5 AND SH, INCLUDING NEW SH

TRANSFORMER AND FEEDER CABLES", which price and payment shall be full compensation for all work required to furnish and install new station service motor control centers CQ01, CQO2, CQO4, CQO5 AND SH, including new SH transformer and feeder cables complete as specified and approved.

1.17 CLIN 0015 - FURNISH AND INSTALL NEW PANELBOARDS CQO3, FCQ1, AND FCQ2,

INCLUDING NEW FEEDER CABLES

Furnish and install new panelboards CQO3, FCQ1, and FCQ2, including new feeder cables will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0015, "FURNISH AND INSTALL NEW PANELBOARDS CQO3, FCQ1, and FCQ2", INCLUDING NEW FEEDER CABLES which price and payment shall be full compensation for all work required to furnish and install new panelboards CQO3, FCQ1, and FCQ2, including new feeder cables complete, as specified and approved.

1.18 CLIN 0016AA - FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP

MOTORS IN UNITS 1 - 3

Furnish and install new 480 volt governor oil pump motors in units 1 - 3 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0016AA, "PROVIDE NEW 480 VOLT GOVERNOR OIL PUMP MOTORS. UNITS 1 - 3", which price and payment shall be full compensation for all work required to provide new 480 volt governor oil pump motors for units 1 - 3 complete, as specified and approved.

1.19 CLIN 0016AB - FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP

MOTORS IN UNITS 4 - 6

Furnish and install new 480 volt governor oil pump motors in units 4 - 6 will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0016AB, "FURNISH AND INSTALL NEW 480 VOLT GOVERNOR OIL PUMP MOTORS IN UNITS 4 - 6", which price and payment shall be full compensation for all work required to Furnish and install new 480 volt governor oil pump motors in units 4 - 6 complete, as specified and approved.

SECTION 01 22 00.00 28 Page 6

1.20 CLIN 0017 - FURNISH AND INSTALL NEW 125V BATTERY CHARGERS IN BC1 AND

BC2

Furnish and install new 125v battery chargers in BC1 and BC2, which will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0017, "FURNISH AND INSTALL NEW 125V BATTERY CHARGERS IN BC1 AND BC2", which price and payment shall be full compensation for all work required to Furnish and install new 125v battery chargers in BC1 and BC2, complete, as specified and approved.

1.21 CLIN 0018 - FURNISH AND INSTALL NEW BATTERY, BATTERY MONITORING

COMPUTER, CART, DIAGNOSTIC EQUIPMENT, WIRING, BATTERY MONITORING HARDWARE

AND SOFTWARE PACKAGE

Furnish and install new battery, battery monitoring computer, cart, diagnostic equipment, wiring, battery monitoring hardware and software package will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0018, "FURNISH AND INSTALL

NEW BATTERY, BATTERY MONITORING COMPUTER, CART, DIAGNOSTIC EQUIPMENT,

WIRING, BATTERY MONITORING HARDWARE AND SOFTWARE PACKAGE", which price and payment shall be full compensation for all work required to furnish and install new battery, battery monitoring computer, cart, diagnostic equipment, wiring, battery monitoring hardware and software package, as specified and approved.

1.22 CLIN 0019 - FURNISH AND INSTALL NEW BATTERY SWITCHBOARDS, DC

DISTRIBUTION PANELBOARDS, 120V AC DISTRIBUTION PANELBOARDS, AND MANUAL

BREAKER TRANSFER PANELS INCLUDING NEW FEEDER CABLES

Furnish and install new battery switchboards, DC distribution panelboards, 120V AC distribution panelboards, and manual breaker transfer panels including new feeder cables will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0019, "FURNISH AND INSTALL NEW BATTERY SWITCHBOARDS, DC DISTRIBUTION

PANELBOARDS, 120V AC DISTRIBUTION PANELBOARDS, AND MANUAL BREAKER TRANSFER

PANELS INCLUDING NEW FEEDER CABLES", which price and payment shall be full compensation for all work required to Furnish and install new battery switchboards, DC distribution panelboards, 120V AC distribution panelboards, and manual breaker transfer panels including new feeder cables complete, as specified and approved.

1.23 CLIN 0020 - FURNISH AND INSTALL BATTERY ROOM UPGRADES

Furnish and install battery room upgrades will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0020, "FURNISH AND INSTALL BATTERY ROOM UPGRADES", which price and payment shall be full compensation for all upgrades made to the battery room according to contract plans and specifications, as specified and approved.

Battery Room Upgrades consist, but not limited to the following work items:

a. Remove existing belt driven exhaust fan EF-6 and provide direct drive exhaust fan (retain mark EF-6) and associated fire damper and duct work items.

b. Piping serving existing emergency shower and eyewash station.

c. Hydrogen Detector, Smoke Detector, Room Differential Pressure Switch, and Emergency Shower and Eyewash Station Water flow detector; with the output from each of these devices annunciated in the Control Room.

d. Combination fire smoke damper in the supply air duct serving the

SECTION 01 22 00.00 28 Page 7 battery room with power to the damper and activation annunciated in the Control Room.

e. Fire damper at the exhaust air opening in the Battery Room.

f. Battery Monitoring System

g. Fire rated battery room door and fire barrier signs

h. Epoxy flooring and containment curb

i. Battery racks

1.24 CLIN 0021 - PROVIDE NEW LOAD BANK

The new load bank will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0021, "PROVIDE NEW LOAD BANK", which price and payment shall be full compensation for all work required to provide provide new load bank complete, as specified and approved.

1.25 CLIN 0022 - FURNISH AND INSTALL SQ REMOTE CONTROL PANELS

Furnish and install SQ remote control panels will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0022, "FURNISH AND INSTALL SQ REMOTE CONTROL PANELS", which price and payment shall be full compensation for all work required to furnish and install SQ remote control panels complete, as specified and approved.

1.26 CLIN 0023 - FURNISH THEN INSTALL SBC AND SG PANELS

Furnishing, then installing the SBC and SG panels will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0023, "FURNISH THEN INSTALL SBC AND SG PANELS", which price and payment shall be full compensation for all work required to furnish, then install the SBC and SG panels complete, as specified and approved.

1.27 CLIN 0024 - RELOCATE EXISTING INVERTERS THEN FURNISH AND INSTALL

125V/48V DC/DC CONVERTERS

Relocate existing inverters will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0024, "RELOCATE EXISTING INVERTERS", which price and payment shall be full compensation for all work required to relocate existing inverters complete, as specified and approved.

1.28 CLIN 0025 - FURNISH SPARE PARTS AND ACCESSORIES

Furnish spare parts and accessories will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0025, "FURNISH SPARE PARTS AND ACCESSORIES", which price and payment shall be full compensation for all work required to furnish spare parts and accessories complete, as specified and approved.

1.29 CLIN 0026 - CORE DRILLING AND CONCRETE WORK

Core drilling and concrete work will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No.

0026, "CORE DRILLING AND CONCRETE WORK", which price and payment shall be full compensation for all work required for core drilling and concrete work complete, as specified and approved.

SECTION 01 22 00.00 28 Page 8

1.30 CLIN 0027 - FURNISH O&M MANUALS

Furnish O&M manuals will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0027, "FURNISH O&M MANUALS", which price and payment shall be full compensation for all work required to furnish O&M manuals complete, as specified and approved.

1.31 CLIN 0028 - FURNISH FINAL RECORD DRAWINGS

Furnish final record drawings will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No.

0028, "FURNISH FINAL RECORD DRAWINGS", which price and payment shall be full compensation for all work required to furnish final record drawings complete, as specified and approved.

1.32 CLIN 0029 - PROVIDE COMMISSIONING SERVICES AND TRAINING

Provide commissioning services and training will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0029, "PROVIDE COMMISSIONING SERVICES AND TRAINING", which price and payment shall be full compensation for all work required to Provide commissioning services complete, as specified and approved.

1.33 CLIN 0030 - FIRESTOPPING

Firestopping will be measured for payment as a complete pay item (JOB).

Payment will be made at the lump sum price for CLIN No. 0030, "FIRESTOPPING", which price and payment shall be full compensation for all work required to Provide commissioning services complete, as specified and approved.

1.34 CLIN 0031 - LEAD BASED PAINT REMEDIATION AND DISPOSAL

CLIN 0003 - "LEAD BASED PAINT REMEDIATION AND DISPOSAL" will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0031, "Lead Based Paint Remediation And Disposal", which price and payment shall be full compensation for all work required for the Lead Based Paint Remediation And Disposal on existing Battery Room Floor LBP, complete, as specified and approved.

1.35 OPTIONAL ITEMS

1.35.1 CLIN 0031 0032 - GOVERNOR AIR SUPPLY CROSSOVER MODIFICATION

Governor air supply crossover modification will be measured for payment as a complete pay item (JOB). Payment will be made at the lump sum price for CLIN No. 0031, "GOVERNOR AIR SUPPLY CROSSOVER MODIFICATION" which price and payment shall be full compensation for all parts and labor required to modify the governor air supply crossover, as specified and approved.

1.35.2 CLIN 0033 - FURNISH AND INSTALL NEW CABLE TRAYS

Furnish and install up to an estimated 800 lineal feet (LF) of 24 inch new cable trays for existing trays not meeting NEC fill requirements. Payment is measured and made at the price per lineal foot for CLIN No. 0032, "FURNISH AND INSTALL NEW CABLE TRAYS", which price and payment is full compensation for all work required to furnish and install new cable trays, complete, as specified and approved.

SECTION 01 22 00.00 28 Page 9 Amendment - 0001 g4ecctgh Line Amendment-0001 - Paragraph 1.35.1 g4ecctgh

Amendment-0001 - Paragraph 1.35.2

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION (NOT APPLICABLE)

-- End of Section --

SECTION 01 22 00.00 28 Page 10

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 35 29.10 28

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

1.2.2 Competent Person, Confined Space

1.2.3 Competent Person, Cranes and Rigging

1.2.4 Competent Person, Fall Protection

1.2.5 Competent Person, Scaffolding

1.2.6 Competent Person (CP) Trainer

1.2.7 High Risk Activities

1.2.8 High Visibility Accident

1.2.9 Load Handling Equipment (LHE)

1.2.10 Medical Treatment

1.2.11 Near Miss

1.2.12 Operating Envelope

1.2.13 Qualified Person (QP)

1.2.14 Qualified Person, Fall Protection (QP for FP)

1.2.15 Recordable Injuries or Illnesses

1.2.16 USACE Property and Equipment

1.2.17 Load Handling Equipment (LHE) Accident or Load Handling

Equipment Mishap

1.3 SUBMITTALS

1.4 MONTHLY EXPOSURE REPORTS

1.5 REGULATORY REQUIREMENTS

1.6 SITE QUALIFICATIONS, DUTIES, AND MEETINGS

1.6.1 Personnel Qualifications

1.6.1.1 Site Safety and Health Officer (SSHO)

1.6.1.2 Competent Person Qualifications

1.6.1.2.1 Competent Person for Confined Space Entry

1.6.1.2.2 Competent Person for Scaffolding

1.6.1.2.3 Competent Person for Fall Protection

1.6.1.3 Qualified Trainer Requirements

1.6.1.4 Crane Operators/Riggers

1.6.2 Personnel Duties

1.6.2.1 Duties of the Site Safety and Health Officer (SSHO)

1.6.3 Meetings

1.6.3.1 Preconstruction Meeting

1.6.3.2 Safety Meetings

1.7 ACCIDENT PREVENTION PLAN (APP)

1.7.1 Names and Qualifications

1.7.2 Plans

1.7.2.1 Confined Space Entry Plan

1.7.2.2 Standard Lift Plan (SLP)

1.7.2.3 Critical Lift Plan- Crane or Load Handling Equipment

1.7.2.4 Fall Protection and Prevention (FP&P) Plan

SECTION 01 35 29.10 28 Page 1 Amendment - 0001 g4ecctgh

Amendment-0001 - Paragraph 1.6.1.1

1.7.2.5 Rescue and Evacuation Plan

1.7.2.6 Hazardous Energy Control Program (HECP)

1.7.2.7 Lead Compliance Plan

1.7.2.7.1 RCRA Metal Based Paint Removal And Disposal

1.7.2.7.2 Electrical Safety Precautions

1.7.2.8 Asbestos Hazard Abatement Plan

1.7.2.9 Site Safety and Health Plan

1.8 ACTIVITY HAZARD ANALYSIS (AHA)

1.8.1 AHA Management

1.8.2 AHA Signature Log

1.9 LOCKOUT/TAGOUT (LOTO)-SAFE CLEARANCE OR HAZARDOUS ENERGY CONTROL

PROGRAM (HECP) PROCEDURES

1.9.1 Safe Clearance Training

1.10 DISPLAY OF SAFETY INFORMATION

1.10.1 Safety Bulletin Board

1.10.2 Safety and Occupational Health (SOH) Deficiency Tracking

System

1.11 SITE SAFETY REFERENCE MATERIALS

1.12 EMERGENCY MEDICAL TREATMENT

1.13 NOTIFICATIONS and REPORTS

1.13.1 Mishap Notification

1.13.2 Accident Reports

1.13.3 LHE Inspection Reports

1.13.4 Certificate of Compliance and Pre-lift Plan/Checklist for LHE and Rigging

1.13.5 Contractor's Cranes

1.14 USE OF POWERHOUSE BRIDGE AND INTAKE CRANES

1.14.1 General

1.14.2 Crane Operators

1.14.3 Use of the Cranes

1.14.4 Riggers

1.14.5 Lifting Devices

1.15 HOT WORK

1.16 CONFINED SPACE ENTRY REQUIREMENTS.

1.16.1 Entry Procedures

1.16.2 Forced Air Ventilation

1.16.3 Sewer Wet Wells

1.16.4 Rescue Procedures and Coordination with Local Emergency

Responders

PART 2 PRODUCTS (NOT APPLICABLE)

PART 3 EXECUTION

3.1 CONSTRUCTION AND OTHER WORK

3.1.1 Worksite Communication

3.1.2 Hazardous Material Exclusions

3.1.3 Unforeseen Hazardous Material

3.2 FALL PROTECTION PROGRAM

3.2.1 Training

3.2.2 Fall Protection Equipment and Systems

3.2.2.1 Additional Personal Fall Protection

3.2.2.2 Personal Fall Protection Harnesses

3.2.3 Horizontal Lifelines (HLL)

3.2.4 Guardrails and Safety Nets

3.2.5 Rescue and Evacuation Plan and Procedures

3.3 WORK PLATFORMS

3.3.1 Scaffolding

SECTION 01 35 29.10 28 Page 2

3.3.2 Elevated Aerial Work Platforms (AWPs)

3.4 EQUIPMENT

3.4.1 Material Handling Equipment (MHE)

3.4.2 Load Handling Equipment (LHE)

3.4.3 Machinery and Mechanized Equipment

3.5 ELECTRICAL

3.5.1 Conduct of Electrical Work

3.5.2 Qualifications

3.5.3 Grounding

3.5.4 Testing

ATTACHMENTS:

Crane/Rigging Mishap Investigation Form

Accident Prevention Plan

Activity Hazard Analysis Template

-- End of Section Table of Contents --

SECTION 01 35 29.10 28 Page 3

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 35 29.10 28 Page 4

SECTION 01 35 29.10 28

GOVERNMENTAL SAFETY REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF SAFETY ENGINEERS (ASSE/SAFE)

ASSE/SAFE A10.34 (2001; R 2012) Protection of the Public on or Adjacent to Construction Sites

ASSE/SAFE A10.44 (2016) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations

ASSE/SAFE Z244.1 (2003; R 2014) Control of Hazardous Energy Lockout/Tagout and Alternative Methods

ASSE/SAFE Z359.0 (2012) Definitions and Nomenclature Used for Fall Protection and Fall Arrest

ASSE/SAFE Z359.1 (2007) Safety Requirements for Personal Fall Arrest Systems, Subsystems and Components

ASSE/SAFE Z359.11 (2014) Safety Requirements for Full Body Harnesses

ASSE/SAFE Z359.12 (2009) Connecting Components for Personal Fall Arrest Systems

ASSE/SAFE Z359.13 (2013) Personal Energy Absorbers and Energy Absorbing Lanyards

ASSE/SAFE Z359.14 (2014) Safety Requirements for Self-Retracting Devices for Personal Fall Arrest and Rescue Systems

ASSE/SAFE Z359.15 (2014) Safety Requirements for Single Anchor Lifelines and Fall Arresters for Personal Fall Arrest Systems

ASSE/SAFE Z359.2 (2017) Minimum Requirements for a Comprehensive Managed Fall Protection Program

ASSE/SAFE Z359.3 (2019) Safety Requirements for Positioning and Travel Restraint Systems

ASSE/SAFE Z359.4 (2013) Safety Requirements for

SECTION 01 35 29.10 28 Page 5

Assisted-Rescue and Self-Rescue Systems, Subsystems and Components

ASSE/SAFE Z359.6 (2009) Specifications and Design Requirements for Active Fall Protection Systems

ASSE/SAFE Z359.7 (2011) Qualification and Verification Testing of Fall Protection Products

ASME INTERNATIONAL (ASME)

ASME B30.20 (2013; INT Oct 2010 - May 2012) Below-the-Hook Lifting Devices

ASME B30.22 (2016) Articulating Boom Cranes

ASME B30.26 (2015; INT Jun 2010 - Jun 2014) Rigging Hardware

ASME B30.3 (2016) Tower Cranes

ASME B30.5 (2014) Mobile and Locomotive Cranes

ASME B30.8 (2015) Floating Cranes and Floating Derricks

ASME B30.9 (2014; INT Feb 2011 - Nov 2013) Slings

ASTM INTERNATIONAL (ASTM)

ASTM F855 (2015) Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 1048 (2003) Guide for Protective Grounding of Power Lines

IEEE C2 (2017) National Electrical Safety Code

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2018; TIA 18-1) Standard for Portable Fire Extinguishers

NFPA 241 (2013; Errata 2015) Standard for Safeguarding Construction,Alteration, and Demolition Operations

NFPA 51B (2014) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70 (2017) National Electrical Code

NFPA 70E (2018; TIA 18-1; TIA 81-2) Standard for Electrical Safety in the Workplace

SECTION 01 35 29.10 28 Page 6

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 Safety and Health Requirements Manual

The Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1910.147 Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1910.333 Selection and Use of Work Practices

29 CFR 1910.1025 Lead

29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment

29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.1400 Cranes and Derricks in Construction

29 CFR 1926.16 Rules of Construction

29 CFR 1926.450 Scaffolds

29 CFR 1926.62 Lead

29 CFR 1926.500 Fall Protection

CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.

1.2.2 Competent Person, Confined Space

The CP, Confined Space, is a person meeting the competent person

SECTION 01 35 29.10 28 Page 7 requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of OSHA’s Confined Space Standard, 29 CFR 1910 .146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.3 Competent Person, Cranes and Rigging

The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.4 Competent Person, Fall Protection

The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with ASSE/SAFE Z359.0 , who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems/equipment, is capable of identifying, evaluating, and addressing existing or potential fall hazards, and has the authority to take prompt corrective measures with regard to such hazards.

1.2.5 Competent Person, Scaffolding

The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualifications must be documented and include experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding must have a documented, minimum of 8-hours of scaffold training to include training on the specific type of scaffold being used (e.g. mast-climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.

1.2.6 Competent Person (CP) Trainer

A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry. The competent person trainer must evaluate the knowledge and skills of the competent persons as part of the training process.

SECTION 01 35 29.10 28 Page 8

1.2.7 High Risk Activities

High Risk Activities are activities that involve work at heights, crane and rigging, excavations and trenching, scaffolding, electrical work, and confined space entry.

1.2.8 High Visibility Accident

A High Visibility Accident is any mishap which may generate publicity or high visibility.

1.2.9 Load Handling Equipment (LHE)

LHE is a term used to describe cranes, hoists and all other hoisting equipment (hoisting equipment means equipment, including crane, derricks, hoists and power operated equipment used with rigging to raise, lower or horizontally move a load).

1.2.10 Medical Treatment

Medical Treatment is treatment administered by a physician or by registered professional personnel under the standing orders of a physician. Medical treatment does not include first aid treatment even through provided by a physician or registered personnel.

1.2.11 Near Miss

A Near Miss is a mishap resulting in no personal injury and zero property damage, but given a shift in time or position, damage or injury may have occurred (e.g., a worker falls off a scaffold and is not injured; a crane swings around to move the load and narrowly misses a parked vehicle).

1.2.12 Operating Envelope

The Operating Envelope is the area surrounding any crane or load handling equipment. Inside this "envelope" is the crane, the operator, riggers and crane walkers, other personnel involved in the operation, rigging gear between the hook, the load, the crane's supporting structure (i.e. ground or rail), the load's rigging path, the lift and rigging procedure.

1.2.13 Qualified Person (QP)

The QP is a person designated in writing, who, by possession of a recognized degree, certificate, or professional standing, or extensive knowledge, training, and experience, has successfully demonstrated their ability to solve or resolve problems related to the subject matter, the work, or the project.

1.2.14 Qualified Person, Fall Protection (QP for FP)

A QP for FP is a person meeting the requirements of EM 385-1-1 Appendix Q, and ASSE/SAFE Z359.0 , with a recognized…