W912EF19B0001_Amendment_0002.pdf
PDF 74 KB Posted
- Attached to
- Lower Monumental Head Cover Oil/Water Separators Federal contract opportunity
- Solicitation number
- W912EF19B0001
About this file
W912EF19B0001 Amend 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| W912EF19B0001_Bids_Worksheet.pdf | ||
| 19B0001_Plans_Amend-0002.pdf | ||
| 19B0001_Amend-0002_TechSpec_.pdf | ||
| W912EF19B0001_Amend-0001_Section_26_05_00.00_28.pdf | ||
| W912EF19B0001_Amend-0001_Plans.pdf | ||
| W912EF19B0001_Amendment_0001.pdf | ||
| Site_Visit_List_Attendee_List_19B0001_LMA_Headcover_Oil-Water_Sep.pdf | ||
| W912EF19B0001_Site_Visit_Info.pdf | ||
| W912EF19B0001_LMA_Headcover_Oil-Water_Separator.pdf | ||
| W912EF19B0001_Plans.pdf | ||
| W912EF19B0001_TechSpec.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to revise the FAR Clause 52.211-10, specif ications and plans. See Summary of Changes and attachments.
1. CONTRACT ID CODE PAGE OF PAGES
1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 12-Feb-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF19B0001
X 9B. DATED (SEE ITEM 11)
16-Jan-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
12-Feb-2019
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
CYNTHIA H JACOBSEN
201 N. THIRD AVE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF19B0001
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0002
Summary of Changes for Amend -0002 Lower Monumental Head Cover Oil Water Separator
1. Revised the following Specifications:
a. SECTION 00 01 15.00 28, LIST OF DRAWINGS
i) Updated the LIST OF DRAWINGS Section
b. SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL
i) Revised the following paragraph:
(1) 3.4.2 CQC System Manager
c. SECTION 22 00 00.00 28 PIPING, GENERAL PURPOSE
(1) 2.5.5 Totalizer
d. SECTION 45 25 14.00 28 COALESCING OIL-WATER SEPARATORS
(1) ACCESSORIES AND ACCESSORY EQUIPMENT
See revised specification for details.
2. Revised the following Drawings (See clouded areas).
a. SHEET M-001
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been modified:
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to
(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and
(c) complete the entire work ready for use not later than the dates listed below.
(1) The Contractor shall complete all on-site installation (ready for Government pre-operational test phase) of the headcover pumps for Main Units 1 - 6 between June 2019 and December 2019. No two units may be out of service at the same time (not including Unit 2) unless allowed by the Contracting Officer. Each unit must be completely operational, commissioned, and ready to be back on line prior to taking another unit out of service. Training Government personnel will be provided by the supply contractor. The Government will have the units available and prepared for the Contractor to start on-site installation work within the work windows listed below:
MAIN UNIT 4
08 Jul 2019 – 26 Jul 2019 (Installation work window and final commissioning)
MAIN UNIT 6
05 Aug 2019 – 23 Aug 2019 (Installation work window and final commissioning)
MAIN UNIT 2 (Out-of-Service)
1 Sep 2019 – 30 Nov (Installation work window and final commissioning)
MAIN UNIT 5
30 Sep 2019 – 18 Oct 2019 (Installation work window and final commissioning)
MAIN UNIT 3
04 Nov 2019 – 22 Nov 2019 (Installation work window and final commissioning)
MAIN UNIT 1
02 Dec 2019 – 20 Dec 2019 (Installation work window and final commissioning)
(2) At the end of each work window, the pumps must be operational, discharging into the existing dewatering system or other method approved by the Government.
(3) The Contractor shall complete system commissioning within 30 days of final installation.
(4) The Contractor shall complete final cleanup for each unit by not later than 7 calendar days after completion of work in (1) above. Demobilization will be not later than 15 calendar days after completion of the final unit.
(5) The Contractor shall complete final submission of O&M manuals and final approved versions of Contractor prepared drawings by not later than 30 calendar days after completion each unit in (1) above. Working “as-built” contract drawings will be completed for each unit before starting work on the next unit.
(End of clause)
(End of Summary of Changes)