Amendment_0004,_W912EF-17-R-0004.pdf

PDF 374 KB Posted

Attached to
McNary Turbine Replacement, Units 1-14 Federal contract opportunity
Solicitation number
W912EF-17-R-0004
Issued by
Department of the Army Corps of Engineers Engineering District Walla Walla

About this file

Amendment 0004, W912EF-17-R-0004

View the file

Other files for this federal contract opportunity

Other files attached to McNary Turbine Replacement, Units 1-14, newest first.
File Type Posted
Amendment_0005,_W912EF-17-R-0004.pdf PDF
Amendment_0003,_W912EF-17-R-0004.pdf PDF
Amend-0003_Plans.pdf PDF
Amend_0002,_W912EF-17-R-0004,_McN_Turbine_Replacement_Units_1-14.pdf PDF
Site_Visit_Participants,_W912EF-17-R-0004,_McN_Turbine_Replacement_1-14.pdf PDF
Amend_0001_W912EF-17-R-0004_McN_Turbine_Replacement_Units_1-14.pdf PDF
Site_Visit_Date_13_June_2017.pdf PDF
2_FIO_Plans_21.pdf PDF
2_FIO_Plans_4.pdf PDF
TechSpecs,_W912EF-17-R-0004.pdf PDF
2_FIO_Plans_2.pdf PDF
Site_visit_information,_W912EF-17-R-0004.pdf PDF
2_FIO_Plans_5.pdf PDF
2_FIO_Plans_14.pdf PDF
2_FIO_Plans_17.pdf PDF
2_FIO_Plans_13.pdf PDF
2_FIO_Plans_10.pdf PDF
2_FIO_Plans_9.pdf PDF
2_FIO_Plans_7.pdf PDF
2_FIO_Plans_18.pdf PDF
2_FIO_Plans_1.pdf PDF
1_Plans.pdf PDF
2_FIO_Plans_22.pdf PDF
2_FIO_Plans_20.pdf PDF
2_FIO_Plans_11.pdf PDF
Solicitation_W912EF-17-R-0004.pdf PDF
2_FIO_Plans_15.pdf PDF
2_FIO_Plans_3.pdf PDF
2_FIO_Plans_12.pdf PDF
2_FIO_Plans_8.pdf PDF
2_FIO_Plans_16.pdf PDF
2_FIO_Plans_19.pdf PDF
2_FIO_Plans_6.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W68SBV62093454

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0004 revises the solicitation as stated in the attached Summary of Changes.

Proposal due date is not changed. Proposals are due no later than 4:30pm, Pacific, on 04 August 2017.

MCNARY TURBINE REPLACEMENTS, UNITS 1-14

1. CONTRACT ID CODE PAGE OF PAGES

J 1 35

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Jul-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-17-R-0004

X 9B. DATED (SEE ITEM 11)

14-Apr-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Jul-2017

CODE

USAED, WALLA WALLA - CONTRACTING DIV.

PHYLLIS L. BUERSTATTE

201 N. THIRD AVENUE

WALLA WALLA WA 99362-1876

W912EF 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EF-17-R-0004

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

The following have been added by full text:

AMENDMENT 0004

Summary of changes for Amendment 0004 McNary Turbine Upgrades, Units 1-14

1. Revised the following Specifications:

SECTION: SECTION 01 78 00.00 28

Revised the following paragraph:

3.2 FINAL APPROVED VERSIONS OF CONTRACTOR PREPARED DRAWINGS

AND ELECTRONIC COPY

Added the following paragraph:

3.4 ELECTRONIC DRAWING SUBMITTAL REQUIREMENTS

2. Added the following Clause:

SECTION 00700:

FAR Clause 52.222‐62, Paid Sick Leave Under Executive Order 13706 (JAN 2017), is added to the set of clauses for Supply and to the set of clauses for Construction.

3. Revised FAR Clause 52.217-7, OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED

LINE ITEM (MAR 1989)

See YELLOW HIGHLIGHTS

SECTION 00700 - CONTRACT CLAUSES -- SUPPLY

The following have been added by reference:

52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017)

The following have been modified:

CONSTRUCTION CLAUSES

Section 00700 - Contract Clauses -- CONSTRUCTION

CLAUSES INCORPORATED BY REFERENCE

52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or

Improper Activity

MAY 2014

52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal

Transactions

OCT 2010

52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-17 Contractor Employee Whistleblower Rights and Requirement

To Inform Employees of Whistleblower Rights

APR 2014

52.204-2 Alt II Security Requirements (Aug 1996) - Alternate II APR 1984 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber

Content Paper

MAY 2011

52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards

OCT 2016

52.204-13 System for Award Management Maintenance OCT 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.209-6 Protecting the Government's Interest When Subcontracting

With Contractors Debarred, Suspended, or Proposed for Debarment

OCT 2015

52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters

JUL 2013

52.209-10 Prohibition on Contracting With Inverted Domestic Corporations

NOV 2015

52.210-1 Market Research APR 2011 52.211-13 Time Extensions SEP 2000 52.211-18 Variation in Estimated Quantity APR 1984 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--

Modifications

AUG 2011

52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.215-15 Pension Adjustments and Asset Reversions OCT 2010 52.215-17 Waiver of Facilities Capital Cost of Money OCT 1997 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits

(PRB) Other than Pensions

JUL 2005

52.215-19 Notification of Ownership Changes OCT 1997 52.215-21 Alt IV Requirements for Certified Cost or Pricing Data and Data

Other Than Certified Cost or Pricing Data -- Modifications (Oct 2010) - Alternate IV

OCT 2010

52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns

OCT 2014

52.219-8 Utilization of Small Business Concerns NOV 2016

52.219-9 ALT II

(Dev)

Small Business Subcontracting Plan (Deviation 2016-O0009)

- Alternate II

NOV 2016

52.219-16 Liquidated Damages-Subcontracting Plan JAN 1999 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime

Compensation

MAY 2014

52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and

Related Regulations

MAY 2014

52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-19 Child Labor -- Cooperation with Authorities and Remedies OCT 2016 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for

Construction

APR 2015

52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-38 Compliance With Veterans' Employment Reporting

Requirements

FEB 2016

52.222-40 Notification of Employee Rights Under the National Labor Relations Act

DEC 2010

52.222-50 Combating Trafficking in Persons MAR 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-59 Compliance with Labor Laws (Executive Order 13673) DEC 2016 52.222-60 Paycheck Transparency (Executive Order 13673) OCT 2016 52.222-61

52.222-62

Arbitration of Contractor Employee Claims (Executive Order 13673) Paid Sick Leave Under Executive Order 13706

DEC 2016

JAN 2017

52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-10 Waste Reduction Program MAY 2011 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration

Equipment and Air Conditioners.

JUN 2016

52.223-13 Acquisition of EPEAT - Registered Imaging Equipment (Jun 2014)

JUN 2014

52.223-16 Acquisition of EPEAT (R) - Registered Personal Computer Products

OCT 2015

52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts

MAY 2008

52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving

AUG 2011

52.224-1 Privacy Act Notification APR 1984 52.224-2 Privacy Act APR 1984

52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-14 Inconsistency Between English Version And Translation Of

Contract

FEB 2000

52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright

Infringement

DEC 2007

52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-23 Alt I Assignment of Claims (May 2014) - Alternate I APR 1984 52.232-27 Prompt Payment for Construction Contracts MAY 2014 52.232-33 Payment by Electronic Funds Transfer--System for Award

Management

JUL 2013

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business

Subcontractors

DEC 2013

52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

APR 1984

52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -

Alternate I

APR 1984

52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-3 Changes--Time-And-Material Or Labor-Hours SEP 2000 52.243-4 Changes JUN 2007 52.243-6 Change Order Accounting APR 1984 52.244-2 Subcontracts OCT 2010 52.244-6 Subcontracts for Commercial Items JAN 2017 52.245-1 Government Property JAN 2017 52.245-9 Use And Charges APR 2012 52.246-6 Inspection--Time-And-Material And Labor-Hour MAY 2001 52.246-12 Inspection of Construction AUG 1996

52.246-21 Warranty of Construction MAR 1994 52.247-34 F.O.B. Destination NOV 1991 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-

Price) (Apr 2012) - Alternate I

SEP 1996

52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD

Officials

SEP 2011

252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies

DEC 2008

252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General DEC 2012 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7005 Oral Attestation of Security Responsibilities NOV 2001 252.204-7008 Compliance With Safeguarding Covered Defense Information

Controls

OCT 2016

252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

OCT 2016

252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By

The Government of a Country that is a State Sponsor of Terrorism

OCT 2015

252.211-7007 Reporting of Government-Furnished Property AUG 2012 252.215-7000 Pricing Adjustments DEC 2012 252.219-7003 Small Business Subcontracting Plan (DOD Contracts)--Basic MAR 2016 252.223-7001 Hazard Warning Labels DEC 1991 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or

Hazardous Materials

SEP 2014

252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2016 252.225-7016 Restriction On Acquisition Of Ball and Roller Bearings JUN 2011 252.225-7021 Trade Agreements--Basic DEC 2016 252.225-7048 Export-Controlled Items JUN 2013 252.226-7001 Utilization of Indian Organizations and Indian-Owned

Economic Enterprises, and Native Hawaiian Small Business Concerns

SEP 2004

252.227-7033 Rights in Shop Drawings APR 1966 252.229-7000 Invoices Exclusive of Taxes or Duties JUN 1997 252.231-7000 Supplemental Cost Principles DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving

Reports

JUN 2012

252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.239-7001 Information Assurance Contractor Training and Certification JAN 2008 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.244-7001 Contractor Purchasing System Administration MAY 2014 252.245-7001 Tagging, Labeling, and Marking of Government-Furnished

Property

APR 2012

252.245-7002 Reporting Loss of Government Property APR 2012

252.245-7003 Contractor Property Management System Administration APR 2012 252.245-7004 Reporting, Reutilization, and Disposal SEP 2016 252.247-7023 Transportation of Supplies by Sea APR 2014 252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to;

(a) Commence work under this contract within 10 calendar days after the date the Contractor receives Notice To Proceed (NTP) on the hydraulic design phase.

(b) Prosecute the work diligently, and

(c) Complete the entire work ready for use not later than the timeframes listed below.

(1) The work shall be completed in (3) Phases which include (1) Hydraulic Design, (2) Prototype

Design, Manufacture and Supply/Delivery and (3) Component Installation as defined below.

These phases will involve two types of runners and at times the tasks within and between the phases will overlap depending on the scope and progress of the tasks. The Contractor shall anticipate and plan for the submittal process and timeframes required for Government review and approvals. Submittal review and approvals will occur during all phases of the project.

a. Phase (1) generally includes the hydraulic design, development, and evaluation of turbine wetted passage components and prototype design for selected components. The turbine runner designs will include two types of runners (fixed and adjustable blade) and include the integrated development and evaluation of the turbine runner and hydraulic components throughout the water passageway.

b. Phase (2) generally includes detailed component engineering of both types of runners, ancillary components, generator components, and other hydraulic components in the water passageway as required by these specifications. Phase (2) also includes manufacture and supply of the required components, delivery to site or other agreed location, and safely store the components until installation commences.

c. Phase (3) generally includes the installation of the turbine runners, generator windings (where applicable), required ancillary and water passageway components, along with the refurbishment of some existing turbine components. Phase (3) also involves the cooperative process to fully commission and test the completed unit, and generator components where applicable.

(2) Schedule Information and Constraints for Phase (1) Hydraulic Design:

a. Phase (1) work includes an iterative and collaborative effort between the Contractor and the Government as described in these specification. The time period to complete each iteration is dependent on the Contractor’s plan, facilities and resources but will generally follow the following order and duration for both the Adjustable and Fixed Designs;

b.

Task Duration

(Working Days) Ownersh ip Pre-Iteration Coordination, Design, Analysis and Model Construction Initial Submittals 20-30 days CT

Hydraulic Design Pre-Work Meeting 5-10 days

CT /

USACE

Develop CFD Model 30-35 days CT Baseline CFD - Existing Runner 20-25 days CT CFD Analysis Demonstration Meeting 4-7 days CT First Iteration 5 Blade Hydraulic Design and CFD Analyses 60-70 days CT 1st Iteration Design In-Progress Review (IPR) 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 105 days USACE In-Progress Meeting 4-7 days CT Second Iteration 6 Blade Hydraulic Design and CFD Analyses 60-70 days CT 2nd Iteration Design IPR 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 105 days USACE In-Progress Meeting 4-7 days CT Decision: 5 or 6 blade for 3rd Iteration 5 days USACE Third Iteration (5 or 6 blade) Hydraulic Design and CFD Analyses 45-50 days CT 3rd Iteration Design IPR 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 120 days USACE In-Progress Meeting 4-7 days CT Decision: for 4th Iteration 5 days USACE Fourth Iteration (5 or 6 blade) Hydraulic Design and CFD Analyses 30-35 days CT 4th Iteration Design IPR 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT

Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 120 days USACE In-Progress Meeting 4-7 days CT Decision: Issue NTP for Manufacture or 5th Iteration

5 days

USACE

c. Prior to the start of each iteration performance model testing the contractor shall ship the appropriate wicket gates to the Government’s research facility at ERDC for Observational testing.

d. Following completion of each iteration performance model testing, the Contractor shall ship the model runner to the Government’s research facility at ERDC for Observational testing.

e. Most activities in the table above have a finish-start relationship and cannot be conducted concurrent with another activity with the following exceptions: Baseline CFD – Existing Runner (Initial CFD) can be conducted in parallel with the Hydraulic Design and CFD Analysis (First Iteration); Hydraulic Design and CFD Analysis (Second Iteration) may begin following the 1st Iteration Design IPR and acceptance of the First Iteration hydraulic design for model.

f. USACE ERDC Observation Model has one test stand and can accommodate testing for one runner at a time.

g. Transition from the Adjustable Runner Hydraulic Design to the Fixed Runner Hydraulic Design - CFD Design (First Iteration) for the fixed runner can begin following CFD Design (Fourth Iteration) for the adjustable runner. Should an optional adjustable runner hydraulic design iteration be awarded, it will have priority in the Performance and Observational model test stands and a revised schedule shall be created as such.

h. Prototype Design shall begin following the Hydraulic Design and CFD Analysis (Third Iteration) for each runner type In Accordance With (IAW) with the specifications.

(3) Schedule Information and Constraints for Phase (2) Prototype Design, Manufacture and

Supply:

a. Prototype Design effort will overlap between Phase 1 and Phase 2 for each runner type as specified

b. The Government will inspect the supplies during the casting, fabrication and machining and upon delivery as required by the specifications. The Contractor shall plan for Government involvement and the required timeframes for these activities.

c. Following the approval of the Prototype Design for the Adjustable Runner and water passageway components a NTP will be issued for the manufacture and supply of the Base six (6) Adjustable Runners and all other associated equipment related to those units IAW the Adjustable Runner Supply Bid Schedule CLINs.

d. Following the acceptance of the Prototype Design for the Fixed Runner and water passageway components a NTP will be issued for the manufacture and supply of the remaining eight (8) Runners and all other associated equipment related to those units consistent with the base CLINs or associated options clause guidance. As described in 01 11 00.00 26 paragraph 1.2, the configuration (fixed or adjustable) of the remaining eight (8) units may vary based upon design outcome. Should some of the remaining eight runners be determined to be adjustable runners, award of alternate bid items and modification to the base contract will take place according to the Bid Schedule.

e. Delivery and storage of components; the government anticipates that two units may be stored in the government furnished storage building beyond unit components staged for installation in the powerhouse. Any additional space and storage that might be available should be coordinated with the Contracting Officer or the Contracting Officers Representative before delivery. All other finished items shall be stored by the contractor until space is made available.

(4) Schedule Information and Constraints for Phase (3) Component Installation: For Contractor schedule development purposes the work shall commence at the determined unit location as follows:

a. NTP for each unit will be granted only after confirmation that all parts are on-site and accepted for installation.

b. Following the Adjustable Runner and associated component design, manufacture and delivery, a NTP and outage for the First unit will be issued.

c. The first unit outage shall be conducted without any other unit installation NTPs issued until commissioning is complete and the unit is accept by the government.

d. The Contractor shall include 10 working days in the schedule for the Government to dewater and prepare each unit for disassembly.

e. Following completion of the first unit installation, no more than two units may be out of service at the same time unless allowed by the Contracting Officer.

f. Notification by government to contractor of next unit number for dewatering and replacement will be given at least 90 days in advance of dewatering

g. Following the commissioning of the first unit, NTP will be issued for each successive unit installation. A schedule pattern of starting a unit outage at approximately mid-point of the preceding unit completion is anticipated for the remaining 12 units, the exact schedule will be as coordinated between the contractor and the USACE in the execution schedule.

(5) Asbestos Containing Materials (ACM). Asbestos abatement (cleaning and wiping) in the generator rotor and stator area is planned for all fourteen units. Asbestos abatement (cleaning and wiping) of the generator rotor and stator areas will be performed under a separate contract (by others). Units 1-4, and 7-12 generator stator and rotor areas were abated during a recently completed generator rewind contract, but may contain some residual asbestos. During prosecution of the work, other ACMs may be encountered, such as wire insulation, pipe insulation, gaskets, etc. If ACMs are encountered, the Contractor shall immediately notify the Contracting Officer to coordinate further abatement (by others).

a. The Contractor shall include 28 calendar days in their schedule for asbestos abatement

(cleaning and wiping) of the stator and rotor (by others) for each unit. This time includes initial asbestos abatement pre-cleaning of the generator area. After acceptance of the pre-cleaning the Contractor shall begin disassembly of the generator and shall place the rotor on the existing rotor pedestal and provide a dust containment structure over and around the rotor. The structure shall be adequate for the abatement of asbestos and containment of any dust as a result of the abatement effort.

b. The Contractor shall provide a safe working platform for all work conducted on the stator for asbestos abatement (by others). During this time frame the Contractor shall allow for unimpeded access to the rotor and stator for asbestos abatement. The Contractor can proceed with other work in the powerhouse but will not be allowed to work in the generator/turbine pit areas that are subjected to the asbestos abatement operations.

Actual time may vary depending on the extent of the abatements as required.

(6) Upon completion of work on the First unit (and all subsequent units) and prior to unit water-up, Pre-Operational Test Phase inspections and tests will commence. Upon completion of Pre-Operational Test Phase, Operational Test Phase will commence. The Contractor shall include 15 consecutive calendar days in the project schedule for Pre-Operational Test Phase and Operational Test Phase inspections and tests. Upon completion of the Operational Test Phase, the Government will perform Post-Operational Test Phase prior to unit acceptance.

(7) After the completion of each unit, the Contractor shall complete final cleanup for the unit not later than 15 calendar days after returning the unit to service.

(8) Upon completion of the Last unit, the Contractor shall complete submission of, working “as-built” contract drawings and final approved versions of Contractor prepared drawings in accordance with Section 01 78 00.00 28.

(9) Upon returning the Last unit to service, powerhouse demobilization shall be completed within 30 calendar days and full site demobilization and clean-up shall be completed within 60 calendar days.

(10) The timeframes to complete the work will be based on the accepted proposed schedule as awarded. See specification for details in preparing a proposed project activity based schedule.

(End of Clause)

CLAUSES INCORPORATED BY FULL TEXT

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $42,161.00 for each calendar day of delay until the work specified in FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, subparagraph (c)(4), Phase 3 Component Installation, is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within the time periods stated below.

CLIN DESCRIPTION

TIMEFRAME WHEN

OPTIONAL ITEM MAY BE

EXERCISED

IF EXERCISED,

TIME

EXTENSION TO

COMPLETE

WORK FOR

ITEM

Adjustable Blade Iteration 5

Coordination, Design, Analysis, Model Testing (Optional)

NLT ten (10) days of the completion of the Adjustable Blade Iteration 4 In-Progress

Meeting

6 months from date of exercising the option

Fixed Blade Iteration 5

Coordination, Design, Analysis, Model Testing (Optional)

NLT ten (10) days of the completion of the Fixed Blade Iteration 4 In-Progress Meeting

6 months from date of exercising the option

Provide Additional Model Adjustable Blade Runner

(Optional) NLT 4 years after Contract Award No additional time

Provide Additional Model

Fixed Blade Runner (Optional) NLT 4 years after NTP to start the fixed blade design No additional time

Provide Additional Model Discharge Ring for

Performance Model Testing.

(Optional)

NLT 8 years after Contract Award No additional time

Provide Additional Model Stay Vane Assembly for

Performance Model Testing (Optional)

NLT 8 years after Contract Award No additional time

Provide Additional Set of Model Wicket gates for

Performance Model Testing (Optional)

NLT 8 years after Contract Award No additional time

Provide Additional Set of Model Wicket gates for Observational Testing

(Optional)

NLT 8 years after Contract Award No additional time

Provide Modified Model Draft Tube for Performance Model

Testing (Optional) NLT 8 years after Contract Award No additional time

Additional Performance Model

Testing (Optional) NLT 8 years after Contract Award

60 days from date of exercising the option

Thrust Bearing Structural

Analysis (Optional) NLT 4 years after Contract Award No additional time

Replacement Outer Headcover Prototype Design (Optional)

NLT 4 years after Contract Award No additional time

Replacement Intermediate

Headcover Prototype Design (Optional)

NLT 4 years after Contract Award No additional time

Replacement Lower Headcover

Prototype Design (Optional) NLT 4 years after Contract Award No additional time

Supply Draft Tube Liner Transition for 280 Inch

Adjustable Blade Runner (Optional)

NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Supply Draft Tube Liner Transition for 292 Inch

Adjustable Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Supply Outer Headcover

(Optional

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Supply Intermediate Headcover

(Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Supply Lower Headcover

(Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Furnish Blade Servomotor Shaft, Coupling Fasteners, Shaft Guard For Adjustable

Blade Units (Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Furnish Intermediate Shaft and Coupling Fasteners For Adjustable Blade Units

(Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Draft Tube Modification

Upstream of Bulkhead Gate Slot (Optional)

NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Draft Tube Modification

Downstream of Bulkhead Gate Slot (Optional)

NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Hone Wicket Gate Servomotors

(Optional)

NLT 45 days after Govt. approval after each unit’s wicket gate servomotor inspection report

No additional time

Machine Stay Ring Flange

(Optional)

NLT 45 days after Government Approval of each unit’s Stay Ring

As-Found Inspection Report 5 Additional days

Refurbish Thrust Bearing Shoes

(Optional)

NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report

Replace Discharge Ring For 280 Inch Adjustable Blade

Runner (Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances 60 additional days

Replace Discharge Ring and Draft Tube Liner Transition For

280 Inch Adjustable Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances 70 additional days

Replace Discharge Ring and Draft Tube Liner Transition For

292 Inch Adjustable Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances 120 additional days

Additional Painting to Improve

Stay Vane/Ring Surface Roughness (Optional)

NLT 24 hrs after final contractual coat of paint for each unit’s stay vane/ring assembly No additional time

Refurbish Thrust Bearing

Runner and Collar (Optional)

NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report

No additional time

Refurbish Upper Guide Bearing

Pads (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Refurbish Lower Guide Bearing

Pads (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Refurbish Turbine Guide

Bearings (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Provide Thrust Bearing Oil

Coolers (Optional)

NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time

Provide Unit 13 – 14 Thrust

Bearing Oil Coolers (Optional)

NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances

Thrust Bearing Structural

Analysis (Optional) NLT 8 years after Contract Award No additional time

Stay Vane Extensions Prototype

Design (Optional) NLT 8 years after Contract Award No additional time

Wicket Gate Prototype Design

(Optional) NLT 8 years after Contract Award No additional time

Replacement Outer Headcover Prototype Design (Optional)

NLT 8 years after Contract Award No additional time

Replacement Lower Headcover

Prototype Design (Optional) NLT 8 years after Contract Award No additional time

Replacement Intermediate

Headcover Prototype Design (Optional)

NLT 8 years after Contract Award No additional time

4107AA

Supply Embedded Discharge

Ring Section For 280 Inch Fixed Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances

4107AB

Supply Embedded Discharge

Ring Section For 292 Inch Fixed Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Draft Tube Liner

Transition For 280 Inch Fixed Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Draft Tube Liner

Transition For 292 Inch Fixed Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Outer Headcover

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Intermediate Headcover

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Lower Headcover

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners

Discharge Ring Replacement

For 280 Inch Fixed Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances 60 additional days

Discharge Ring and Draft Tube Liner Transition Replacement

For 280 Inch Fixed Blade Runner(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances 70 additional days

Discharge Ring and Draft Tube Liner Transition Replacement for 292 Inch Fixed Blade Runner (Optional)

NLT 6 monthsafter NTP for the manufacture of fixed blade runners and appurtenances 120 additional days

Additional Painting to Improve

Stay Vane/Ring Surface Roughness (Optional)

NLT 24hrs after final contractual coat of paint for each unit’s stay vane/ring assembly No additional time

Hone Wicket Gate Servomotors

(Optional)

NLT 45 days after Govt. approval of each unit’s wicket gate servomotor inspection report No additional time

Draft Tube Modification

Upstream of Bulkhead Gate Slot (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Draft Tube Modification

Downstream of Bulkhead Gate Slot (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Machine Stay Ring Flange

(Optional)

NLT 45 days after Government Approval of each unit’s Stay Ring

As-Found Inspection Report 5 additional days

Refurbish Thrust Bearing Shoes

(Optional)

NLT 45 days after Government Approval of each unit’s Thrust

Refurbish Thrust Bearing

Runner and Collar (Optional)

NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report

No additional time

Refurbish Upper Guide Bearing

Pads (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Refurbish Lower Guide Bearing

Pads (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Refurbish Turbine Guide

Bearing (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Provide Thrust Bearing Oil

Coolers (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners

Furnish Stator Core Materials and

Accessories for Unit 13 Including Factory Tests

(Optional)

NLT 45 days after Government Approval of the Unit 13 Stator

Inspection Report No additional time

Furnish Stator Core Materials And

Accessories for Unit 14 Including Factory Tests

(Optional)

NLT 45 days after Government Approval of the Unit 14 Stator

Inspection Report

Perform Additional Inter-laminar Insulation Test Units 5, 13 and 14 (Optional)

NLT 60 days after Government receipt of the unit’s Inter-laminar

Insulation Test report No additional days

Remove Existing Stator Core, Install and Test New Stator Core for Unit 13 (Optional)

NLT 45 days after Government Approval of the Unit 13 Inter-laminar Insulation Test 120 additional days

Remove Existing Stator Core, Install and Test New Stator Core for Unit 14 (Optional)

NLT 45 days after Government Approval of the Unit 14 Inter-laminar Insulation Test 120 additional days

Remove Existing Stator Core, Install and Test Government- Furnished Stator Core Unit 5

(Optional)

NLT 45 days after Government Approval of the Unit 5 Inter-laminar Insulation Test 45 additional days

8101AA

Supply 280 Inch Adjustable 5-

Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners

8101AB

Supply 280 Inch Adjustable 6-

Blade Runner and Appurtenances (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

8101AC

Supply 292 Inch Adjustable 5-

Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

8101AD

Supply 292 Inch Adjustable 6-

Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

8102AA

Supply Discharge Ring Insert For 280 Inch Adjustable Blade

Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

8102AB

Supply Embedded Discharge Ring Section and Insert For 280 Inch Adjustable Blade Runner

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

8102AC

Supply Embedded Discharge Ring Section and Insert For 292 Inch Adjustable Blade

Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Draft Tube Liner Transition For 280 Inch

Adjustable Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Draft Tube Liner Transition For 292 Inch

Adjustable Blade Runner (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Outer Headcover

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Intermediate Headcover

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Lower Headcover

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Furnish Blade Servomotor Shaft, Coupling Fasteners, Shaft Guard for Adjustable

Blade Units (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Furnish Intermediate Shaft and Coupling Fasteners for Adjustable Blade Units

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Set of Leading Edge

Stay Vane Extensions (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners

Supply Set of Trailing Edge

Stay Vane Extensions (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Set of Wicket Gates

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Turbine Shaft Seal

(Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Furnish Gate Operating

Mechanism Bushings and Bearing Plate (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Supply Headcover and Bottom Ring Facing Plate (Optional)

NLT 6 months after NTP for the manufacture of fixed blade runners

Pre-Disassembly Watered

Operational Testing (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Generating Unit Disassembly

(Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Replace Discharge Ring For 280 Inch Adjustable Blade

Runner (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances 60 additional days

Replace Discharge Ring and Draft Tube Liner Transition For

280 Inch Adjustable Blade Runner (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances 70 additional days

Modify Discharge Ring Without Demolition For 280

Inch Adjustable Blade Runner (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Replace Discharge Ring and Draft Tube Liner Transition For

292 Inch Adjustable Blade Runner (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances 120 additional days

Machine Stay Ring Flange

(Optional)

NLT 45 days after Government Approval of each unit’s Stay Ring

As-Found Inspection Report 5 additional days

Provide Draft Tube and Scroll Case Drain Valves (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Provide Thrust Bearing Oil

Coolers (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners

Provide Static Hub Pressurization System and

Refurbish/Modify Oil Head (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Provide Inner Oil Pipe and

Refurbish/Modify or Replace Existing Oil Pipes (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Lead Based Paint Removal and

Disposal (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

9113 Painting (Optional) NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances

No additional time

Refurbish Outer Headcover

(Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Lower Headcover

(Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Intermediate Headcover (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Stay Vane/Ring Refurbishment Including Stay Vane Extension

Installation

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Additional Painting to Improve

Stay Vane/Ring Surface Roughness (Optional)

NLT 24 hrs after final contractual coat of paint for each unit’s stay vane/ring assembly.

No additional time

Refurbish Bottom Ring

(Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Misc. Wicket Gate

Operating Mechanism Components (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Line Boring and Installation of

Wicket Gate Stem Bushings (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish/Replace Turbine Air Admission Valves (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Gate Operating Ring

(Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Intermediate and Generator Shafts (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Servo Shaft for

Adjustable Blade Operation (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners

Refurbish Turbine Shafts for Adjustable Blade Operation

(Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Unit 5 & 6 Turbine Shafts for Adjustable Blade

Operation (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Wicket Gate Servomotors (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Hone Wicket Gate Servomotors

(Optional)

NLT 45 days after Govt. approval of each unit’s wicket gate servomotor inspection report No additional time

Refurbish Units 5 & 6 Wicket Gate Servomotors (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Provide Water and Oil Piping

Systems and Components (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Provide Electrical Devices, Temperature Indicating Devices, Wiring/Cable

Removal (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Provide Generator Housing

Lighting Wires for Units 5 and 6 (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Provide Unit 5 and 6 Generator

Stator Heater Automatic Controls (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Install Government Furnished

Generator Air Coolers in Unit 6

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Thrust Bearing Component

Inspection, Unit 5 & 6 (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Unit 5 & 6 Thrust Bearing

Component Inspection

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Guide Bearing Component

Inspection (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Refurbish Thrust Bearing Shoes

(Optional)

NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report

No additional time

Refurbish Thrust Bearing

Runner and Collar (Optional)

NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report

No additional time

Refurbish Upper Guide Bearing

Pads (Optional)

NLT 45 days after Government Approval of each unit’s Guide

Refurbish Lower Guide Bearing

Pads (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Refurbish Turbine Guide

Bearing (Optional)

NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report

No additional time

Draft Tube Modification

Upstream of Bulkhead Slot (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Draft Tube Modification

Downstream of Bulkhead Gate Slot (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Reassembly of Adjustable

Blade Units (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time

Commissioning of Adjustable

Blade Units (Optional)

NLT 1 year after NTP for the manufacture of fixed blade runners

30…

This is the start of the file's text. The full file is on GovTribe.