- McNary Turbine Replacement, Units 1-14 Federal contract opportunity
- Solicitation number
- W912EF-17-R-0004
About this file
Amendment 0004, W912EF-17-R-0004
View the file
Other files for this federal contract opportunity
Show all 33
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W68SBV62093454
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0004 revises the solicitation as stated in the attached Summary of Changes.
Proposal due date is not changed. Proposals are due no later than 4:30pm, Pacific, on 04 August 2017.
MCNARY TURBINE REPLACEMENTS, UNITS 1-14
1. CONTRACT ID CODE PAGE OF PAGES
J 1 35
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Jul-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-17-R-0004
X 9B. DATED (SEE ITEM 11)
14-Apr-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Jul-2017
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
PHYLLIS L. BUERSTATTE
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-17-R-0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00010 - SOLICITATION CONTRACT FORM
The following have been added by full text:
AMENDMENT 0004
Summary of changes for Amendment 0004 McNary Turbine Upgrades, Units 1-14
1. Revised the following Specifications:
SECTION: SECTION 01 78 00.00 28
Revised the following paragraph:
3.2 FINAL APPROVED VERSIONS OF CONTRACTOR PREPARED DRAWINGS
AND ELECTRONIC COPY
Added the following paragraph:
3.4 ELECTRONIC DRAWING SUBMITTAL REQUIREMENTS
2. Added the following Clause:
SECTION 00700:
FAR Clause 52.222‐62, Paid Sick Leave Under Executive Order 13706 (JAN 2017), is added to the set of clauses for Supply and to the set of clauses for Construction.
3. Revised FAR Clause 52.217-7, OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED
LINE ITEM (MAR 1989)
See YELLOW HIGHLIGHTS
SECTION 00700 - CONTRACT CLAUSES -- SUPPLY
The following have been added by reference:
52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2017)
The following have been modified:
CONSTRUCTION CLAUSES
Section 00700 - Contract Clauses -- CONSTRUCTION
CLAUSES INCORPORATED BY REFERENCE
52.202-1 Definitions NOV 2013 52.203-3 Gratuities APR 1984 52.203-5 Covenant Against Contingent Fees MAY 2014 52.203-6 Restrictions On Subcontractor Sales To The Government SEP 2006 52.203-7 Anti-Kickback Procedures MAY 2014 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or
Improper Activity
MAY 2014
52.203-10 Price Or Fee Adjustment For Illegal Or Improper Activity MAY 2014 52.203-12 Limitation On Payments To Influence Certain Federal
Transactions
OCT 2010
52.203-13 Contractor Code of Business Ethics and Conduct OCT 2015 52.203-17 Contractor Employee Whistleblower Rights and Requirement
To Inform Employees of Whistleblower Rights
APR 2014
52.204-2 Alt II Security Requirements (Aug 1996) - Alternate II APR 1984 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber
Content Paper
MAY 2011
52.204-9 Personal Identity Verification of Contractor Personnel JAN 2011 52.204-10 Reporting Executive Compensation and First-Tier
Subcontract Awards
OCT 2016
52.204-13 System for Award Management Maintenance OCT 2016 52.204-18 Commercial and Government Entity Code Maintenance JUL 2016 52.209-6 Protecting the Government's Interest When Subcontracting
With Contractors Debarred, Suspended, or Proposed for Debarment
OCT 2015
52.209-9 Updates of Publicly Available Information Regarding Responsibility Matters
JUL 2013
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.210-1 Market Research APR 2011 52.211-13 Time Extensions SEP 2000 52.211-18 Variation in Estimated Quantity APR 1984 52.215-2 Audit and Records--Negotiation OCT 2010 52.215-11 Price Reduction for Defective Certified Cost or Pricing Data--
Modifications
AUG 2011
52.215-13 Subcontractor Certified Cost or Pricing Data--Modifications OCT 2010 52.215-15 Pension Adjustments and Asset Reversions OCT 2010 52.215-17 Waiver of Facilities Capital Cost of Money OCT 1997 52.215-18 Reversion or Adjustment of Plans for Postretirement Benefits
(PRB) Other than Pensions
JUL 2005
52.215-19 Notification of Ownership Changes OCT 1997 52.215-21 Alt IV Requirements for Certified Cost or Pricing Data and Data
Other Than Certified Cost or Pricing Data -- Modifications (Oct 2010) - Alternate IV
OCT 2010
52.219-4 Notice of Price Evaluation Preference for HUBZone Small Business Concerns
OCT 2014
52.219-8 Utilization of Small Business Concerns NOV 2016
52.219-9 ALT II
(Dev)
Small Business Subcontracting Plan (Deviation 2016-O0009)
- Alternate II
NOV 2016
52.219-16 Liquidated Damages-Subcontracting Plan JAN 1999 52.219-28 Post-Award Small Business Program Rerepresentation JUL 2013 52.222-3 Convict Labor JUN 2003 52.222-4 Contract Work Hours and Safety Standards- Overtime
Compensation
MAY 2014
52.222-6 Construction Wage Rate Requirements MAY 2014 52.222-7 Withholding of Funds MAY 2014 52.222-8 Payrolls and Basic Records MAY 2014 52.222-9 Apprentices and Trainees JUL 2005 52.222-10 Compliance with Copeland Act Requirements FEB 1988 52.222-11 Subcontracts (Labor Standards) MAY 2014 52.222-12 Contract Termination-Debarment MAY 2014 52.222-13 Compliance With Construction Wage Rate Requirements and
Related Regulations
MAY 2014
52.222-14 Disputes Concerning Labor Standards FEB 1988 52.222-15 Certification of Eligibility MAY 2014 52.222-19 Child Labor -- Cooperation with Authorities and Remedies OCT 2016 52.222-21 Prohibition Of Segregated Facilities APR 2015 52.222-26 Equal Opportunity SEP 2016 52.222-27 Affirmative Action Compliance Requirements for
Construction
APR 2015
52.222-35 Equal Opportunity for Veterans OCT 2015 52.222-36 Equal Opportunity for Workers with Disabilities JUL 2014 52.222-37 Employment Reports on Veterans FEB 2016 52.222-38 Compliance With Veterans' Employment Reporting
Requirements
FEB 2016
52.222-40 Notification of Employee Rights Under the National Labor Relations Act
DEC 2010
52.222-50 Combating Trafficking in Persons MAR 2015 52.222-54 Employment Eligibility Verification OCT 2015 52.222-55 Minimum Wages Under Executive Order 13658 DEC 2015 52.222-59 Compliance with Labor Laws (Executive Order 13673) DEC 2016 52.222-60 Paycheck Transparency (Executive Order 13673) OCT 2016 52.222-61
52.222-62
Arbitration of Contractor Employee Claims (Executive Order 13673) Paid Sick Leave Under Executive Order 13706
DEC 2016
JAN 2017
52.223-3 Hazardous Material Identification And Material Safety Data JAN 1997 52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011 52.223-6 Drug-Free Workplace MAY 2001 52.223-10 Waste Reduction Program MAY 2011 52.223-12 Maintenance, Service, Repair, or Disposal of Refrigeration
Equipment and Air Conditioners.
JUN 2016
52.223-13 Acquisition of EPEAT - Registered Imaging Equipment (Jun 2014)
JUN 2014
52.223-16 Acquisition of EPEAT (R) - Registered Personal Computer Products
OCT 2015
52.223-17 Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
MAY 2008
52.223-18 Encouraging Contractor Policies To Ban Text Messaging While Driving
AUG 2011
52.224-1 Privacy Act Notification APR 1984 52.224-2 Privacy Act APR 1984
52.225-13 Restrictions on Certain Foreign Purchases JUN 2008 52.225-14 Inconsistency Between English Version And Translation Of
Contract
FEB 2000
52.227-1 Authorization and Consent DEC 2007 52.227-2 Notice And Assistance Regarding Patent And Copyright
Infringement
DEC 2007
52.227-4 Patent Indemnity-Construction Contracts DEC 2007 52.228-2 Additional Bond Security OCT 1997 52.228-5 Insurance - Work On A Government Installation JAN 1997 52.228-11 Pledges Of Assets JAN 2012 52.228-12 Prospective Subcontractor Requests for Bonds MAY 2014 52.228-14 Irrevocable Letter of Credit NOV 2014 52.228-15 Performance and Payment Bonds--Construction OCT 2010 52.229-3 Federal, State And Local Taxes FEB 2013 52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014 52.232-17 Interest MAY 2014 52.232-23 Alt I Assignment of Claims (May 2014) - Alternate I APR 1984 52.232-27 Prompt Payment for Construction Contracts MAY 2014 52.232-33 Payment by Electronic Funds Transfer--System for Award
Management
JUL 2013
52.232-39 Unenforceability of Unauthorized Obligations JUN 2013 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2013
52.233-1 Disputes MAY 2014 52.233-3 Protest After Award AUG 1996 52.233-4 Applicable Law for Breach of Contract Claim OCT 2004 52.236-2 Differing Site Conditions APR 1984 52.236-3 Site Investigation and Conditions Affecting the Work APR 1984 52.236-5 Material and Workmanship APR 1984 52.236-6 Superintendence by the Contractor APR 1984 52.236-7 Permits and Responsibilities NOV 1991 52.236-8 Other Contracts APR 1984 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements
APR 1984
52.236-10 Operations and Storage Areas APR 1984 52.236-11 Use and Possession Prior to Completion APR 1984 52.236-12 Cleaning Up APR 1984 52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I NOV 1991 52.236-14 Availability and Use of Utility Services APR 1984 52.236-15 Schedules for Construction Contracts APR 1984 52.236-17 Layout of Work APR 1984 52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) -
Alternate I
APR 1984
52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-3 Changes--Time-And-Material Or Labor-Hours SEP 2000 52.243-4 Changes JUN 2007 52.243-6 Change Order Accounting APR 1984 52.244-2 Subcontracts OCT 2010 52.244-6 Subcontracts for Commercial Items JAN 2017 52.245-1 Government Property JAN 2017 52.245-9 Use And Charges APR 2012 52.246-6 Inspection--Time-And-Material And Labor-Hour MAY 2001 52.246-12 Inspection of Construction AUG 1996
52.246-21 Warranty of Construction MAR 1994 52.247-34 F.O.B. Destination NOV 1991 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed-
Price) (Apr 2012) - Alternate I
SEP 1996
52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.203-7001 Prohibition On Persons Convicted of Fraud or Other Defense- Contract-Related Felonies
DEC 2008
252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General DEC 2012 252.204-7000 Disclosure Of Information OCT 2016 252.204-7003 Control Of Government Personnel Work Product APR 1992 252.204-7005 Oral Attestation of Security Responsibilities NOV 2001 252.204-7008 Compliance With Safeguarding Covered Defense Information
Controls
OCT 2016
252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting
OCT 2016
252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By
The Government of a Country that is a State Sponsor of Terrorism
OCT 2015
252.211-7007 Reporting of Government-Furnished Property AUG 2012 252.215-7000 Pricing Adjustments DEC 2012 252.219-7003 Small Business Subcontracting Plan (DOD Contracts)--Basic MAR 2016 252.223-7001 Hazard Warning Labels DEC 1991 252.223-7004 Drug Free Work Force SEP 1988 252.223-7006 Prohibition On Storage, Treatment, and Disposal of Toxic or
Hazardous Materials
SEP 2014
252.223-7008 Prohibition of Hexavalent Chromium JUN 2013 252.225-7012 Preference For Certain Domestic Commodities DEC 2016 252.225-7016 Restriction On Acquisition Of Ball and Roller Bearings JUN 2011 252.225-7021 Trade Agreements--Basic DEC 2016 252.225-7048 Export-Controlled Items JUN 2013 252.226-7001 Utilization of Indian Organizations and Indian-Owned
Economic Enterprises, and Native Hawaiian Small Business Concerns
SEP 2004
252.227-7033 Rights in Shop Drawings APR 1966 252.229-7000 Invoices Exclusive of Taxes or Duties JUN 1997 252.231-7000 Supplemental Cost Principles DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
JUN 2012
252.232-7010 Levies on Contract Payments DEC 2006 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.239-7001 Information Assurance Contractor Training and Certification JAN 2008 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.244-7001 Contractor Purchasing System Administration MAY 2014 252.245-7001 Tagging, Labeling, and Marking of Government-Furnished
Property
APR 2012
252.245-7002 Reporting Loss of Government Property APR 2012
252.245-7003 Contractor Property Management System Administration APR 2012 252.245-7004 Reporting, Reutilization, and Disposal SEP 2016 252.247-7023 Transportation of Supplies by Sea APR 2014 252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to;
(a) Commence work under this contract within 10 calendar days after the date the Contractor receives Notice To Proceed (NTP) on the hydraulic design phase.
(b) Prosecute the work diligently, and
(c) Complete the entire work ready for use not later than the timeframes listed below.
(1) The work shall be completed in (3) Phases which include (1) Hydraulic Design, (2) Prototype
Design, Manufacture and Supply/Delivery and (3) Component Installation as defined below.
These phases will involve two types of runners and at times the tasks within and between the phases will overlap depending on the scope and progress of the tasks. The Contractor shall anticipate and plan for the submittal process and timeframes required for Government review and approvals. Submittal review and approvals will occur during all phases of the project.
a. Phase (1) generally includes the hydraulic design, development, and evaluation of turbine wetted passage components and prototype design for selected components. The turbine runner designs will include two types of runners (fixed and adjustable blade) and include the integrated development and evaluation of the turbine runner and hydraulic components throughout the water passageway.
b. Phase (2) generally includes detailed component engineering of both types of runners, ancillary components, generator components, and other hydraulic components in the water passageway as required by these specifications. Phase (2) also includes manufacture and supply of the required components, delivery to site or other agreed location, and safely store the components until installation commences.
c. Phase (3) generally includes the installation of the turbine runners, generator windings (where applicable), required ancillary and water passageway components, along with the refurbishment of some existing turbine components. Phase (3) also involves the cooperative process to fully commission and test the completed unit, and generator components where applicable.
(2) Schedule Information and Constraints for Phase (1) Hydraulic Design:
a. Phase (1) work includes an iterative and collaborative effort between the Contractor and the Government as described in these specification. The time period to complete each iteration is dependent on the Contractor’s plan, facilities and resources but will generally follow the following order and duration for both the Adjustable and Fixed Designs;
b.
Task Duration
(Working Days) Ownersh ip Pre-Iteration Coordination, Design, Analysis and Model Construction Initial Submittals 20-30 days CT
Hydraulic Design Pre-Work Meeting 5-10 days
CT /
USACE
Develop CFD Model 30-35 days CT Baseline CFD - Existing Runner 20-25 days CT CFD Analysis Demonstration Meeting 4-7 days CT First Iteration 5 Blade Hydraulic Design and CFD Analyses 60-70 days CT 1st Iteration Design In-Progress Review (IPR) 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 105 days USACE In-Progress Meeting 4-7 days CT Second Iteration 6 Blade Hydraulic Design and CFD Analyses 60-70 days CT 2nd Iteration Design IPR 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 105 days USACE In-Progress Meeting 4-7 days CT Decision: 5 or 6 blade for 3rd Iteration 5 days USACE Third Iteration (5 or 6 blade) Hydraulic Design and CFD Analyses 45-50 days CT 3rd Iteration Design IPR 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 120 days USACE In-Progress Meeting 4-7 days CT Decision: for 4th Iteration 5 days USACE Fourth Iteration (5 or 6 blade) Hydraulic Design and CFD Analyses 30-35 days CT 4th Iteration Design IPR 4-7 days CT Manufacture Model Runner/other Modifications Contractor determined CT Performance Model Testing Contractor determined CT
Government Witness Testing 4-7 days CT Ship Components to ERDC 4-7 days CT ERDC Model Testing 120 days USACE In-Progress Meeting 4-7 days CT Decision: Issue NTP for Manufacture or 5th Iteration
5 days
USACE
c. Prior to the start of each iteration performance model testing the contractor shall ship the appropriate wicket gates to the Government’s research facility at ERDC for Observational testing.
d. Following completion of each iteration performance model testing, the Contractor shall ship the model runner to the Government’s research facility at ERDC for Observational testing.
e. Most activities in the table above have a finish-start relationship and cannot be conducted concurrent with another activity with the following exceptions: Baseline CFD – Existing Runner (Initial CFD) can be conducted in parallel with the Hydraulic Design and CFD Analysis (First Iteration); Hydraulic Design and CFD Analysis (Second Iteration) may begin following the 1st Iteration Design IPR and acceptance of the First Iteration hydraulic design for model.
f. USACE ERDC Observation Model has one test stand and can accommodate testing for one runner at a time.
g. Transition from the Adjustable Runner Hydraulic Design to the Fixed Runner Hydraulic Design - CFD Design (First Iteration) for the fixed runner can begin following CFD Design (Fourth Iteration) for the adjustable runner. Should an optional adjustable runner hydraulic design iteration be awarded, it will have priority in the Performance and Observational model test stands and a revised schedule shall be created as such.
h. Prototype Design shall begin following the Hydraulic Design and CFD Analysis (Third Iteration) for each runner type In Accordance With (IAW) with the specifications.
(3) Schedule Information and Constraints for Phase (2) Prototype Design, Manufacture and
Supply:
a. Prototype Design effort will overlap between Phase 1 and Phase 2 for each runner type as specified
b. The Government will inspect the supplies during the casting, fabrication and machining and upon delivery as required by the specifications. The Contractor shall plan for Government involvement and the required timeframes for these activities.
c. Following the approval of the Prototype Design for the Adjustable Runner and water passageway components a NTP will be issued for the manufacture and supply of the Base six (6) Adjustable Runners and all other associated equipment related to those units IAW the Adjustable Runner Supply Bid Schedule CLINs.
d. Following the acceptance of the Prototype Design for the Fixed Runner and water passageway components a NTP will be issued for the manufacture and supply of the remaining eight (8) Runners and all other associated equipment related to those units consistent with the base CLINs or associated options clause guidance. As described in 01 11 00.00 26 paragraph 1.2, the configuration (fixed or adjustable) of the remaining eight (8) units may vary based upon design outcome. Should some of the remaining eight runners be determined to be adjustable runners, award of alternate bid items and modification to the base contract will take place according to the Bid Schedule.
e. Delivery and storage of components; the government anticipates that two units may be stored in the government furnished storage building beyond unit components staged for installation in the powerhouse. Any additional space and storage that might be available should be coordinated with the Contracting Officer or the Contracting Officers Representative before delivery. All other finished items shall be stored by the contractor until space is made available.
(4) Schedule Information and Constraints for Phase (3) Component Installation: For Contractor schedule development purposes the work shall commence at the determined unit location as follows:
a. NTP for each unit will be granted only after confirmation that all parts are on-site and accepted for installation.
b. Following the Adjustable Runner and associated component design, manufacture and delivery, a NTP and outage for the First unit will be issued.
c. The first unit outage shall be conducted without any other unit installation NTPs issued until commissioning is complete and the unit is accept by the government.
d. The Contractor shall include 10 working days in the schedule for the Government to dewater and prepare each unit for disassembly.
e. Following completion of the first unit installation, no more than two units may be out of service at the same time unless allowed by the Contracting Officer.
f. Notification by government to contractor of next unit number for dewatering and replacement will be given at least 90 days in advance of dewatering
g. Following the commissioning of the first unit, NTP will be issued for each successive unit installation. A schedule pattern of starting a unit outage at approximately mid-point of the preceding unit completion is anticipated for the remaining 12 units, the exact schedule will be as coordinated between the contractor and the USACE in the execution schedule.
(5) Asbestos Containing Materials (ACM). Asbestos abatement (cleaning and wiping) in the generator rotor and stator area is planned for all fourteen units. Asbestos abatement (cleaning and wiping) of the generator rotor and stator areas will be performed under a separate contract (by others). Units 1-4, and 7-12 generator stator and rotor areas were abated during a recently completed generator rewind contract, but may contain some residual asbestos. During prosecution of the work, other ACMs may be encountered, such as wire insulation, pipe insulation, gaskets, etc. If ACMs are encountered, the Contractor shall immediately notify the Contracting Officer to coordinate further abatement (by others).
a. The Contractor shall include 28 calendar days in their schedule for asbestos abatement
(cleaning and wiping) of the stator and rotor (by others) for each unit. This time includes initial asbestos abatement pre-cleaning of the generator area. After acceptance of the pre-cleaning the Contractor shall begin disassembly of the generator and shall place the rotor on the existing rotor pedestal and provide a dust containment structure over and around the rotor. The structure shall be adequate for the abatement of asbestos and containment of any dust as a result of the abatement effort.
b. The Contractor shall provide a safe working platform for all work conducted on the stator for asbestos abatement (by others). During this time frame the Contractor shall allow for unimpeded access to the rotor and stator for asbestos abatement. The Contractor can proceed with other work in the powerhouse but will not be allowed to work in the generator/turbine pit areas that are subjected to the asbestos abatement operations.
Actual time may vary depending on the extent of the abatements as required.
(6) Upon completion of work on the First unit (and all subsequent units) and prior to unit water-up, Pre-Operational Test Phase inspections and tests will commence. Upon completion of Pre-Operational Test Phase, Operational Test Phase will commence. The Contractor shall include 15 consecutive calendar days in the project schedule for Pre-Operational Test Phase and Operational Test Phase inspections and tests. Upon completion of the Operational Test Phase, the Government will perform Post-Operational Test Phase prior to unit acceptance.
(7) After the completion of each unit, the Contractor shall complete final cleanup for the unit not later than 15 calendar days after returning the unit to service.
(8) Upon completion of the Last unit, the Contractor shall complete submission of, working “as-built” contract drawings and final approved versions of Contractor prepared drawings in accordance with Section 01 78 00.00 28.
(9) Upon returning the Last unit to service, powerhouse demobilization shall be completed within 30 calendar days and full site demobilization and clean-up shall be completed within 60 calendar days.
(10) The timeframes to complete the work will be based on the accepted proposed schedule as awarded. See specification for details in preparing a proposed project activity based schedule.
(End of Clause)
CLAUSES INCORPORATED BY FULL TEXT
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $42,161.00 for each calendar day of delay until the work specified in FAR Clause 52.211-10, Commencement, Prosecution, and Completion of Work, subparagraph (c)(4), Phase 3 Component Installation, is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
52.217-7 OPTION FOR INCREASED QUANTITY--SEPARATELY PRICED LINE ITEM (MAR 1989)
The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within the time periods stated below.
CLIN DESCRIPTION
TIMEFRAME WHEN
OPTIONAL ITEM MAY BE
EXERCISED
IF EXERCISED,
TIME
EXTENSION TO
COMPLETE
WORK FOR
ITEM
Adjustable Blade Iteration 5
Coordination, Design, Analysis, Model Testing (Optional)
NLT ten (10) days of the completion of the Adjustable Blade Iteration 4 In-Progress
Meeting
6 months from date of exercising the option
Fixed Blade Iteration 5
Coordination, Design, Analysis, Model Testing (Optional)
NLT ten (10) days of the completion of the Fixed Blade Iteration 4 In-Progress Meeting
6 months from date of exercising the option
Provide Additional Model Adjustable Blade Runner
(Optional) NLT 4 years after Contract Award No additional time
Provide Additional Model
Fixed Blade Runner (Optional) NLT 4 years after NTP to start the fixed blade design No additional time
Provide Additional Model Discharge Ring for
Performance Model Testing.
(Optional)
NLT 8 years after Contract Award No additional time
Provide Additional Model Stay Vane Assembly for
Performance Model Testing (Optional)
NLT 8 years after Contract Award No additional time
Provide Additional Set of Model Wicket gates for
Performance Model Testing (Optional)
NLT 8 years after Contract Award No additional time
Provide Additional Set of Model Wicket gates for Observational Testing
(Optional)
NLT 8 years after Contract Award No additional time
Provide Modified Model Draft Tube for Performance Model
Testing (Optional) NLT 8 years after Contract Award No additional time
Additional Performance Model
Testing (Optional) NLT 8 years after Contract Award
60 days from date of exercising the option
Thrust Bearing Structural
Analysis (Optional) NLT 4 years after Contract Award No additional time
Replacement Outer Headcover Prototype Design (Optional)
NLT 4 years after Contract Award No additional time
Replacement Intermediate
Headcover Prototype Design (Optional)
NLT 4 years after Contract Award No additional time
Replacement Lower Headcover
Prototype Design (Optional) NLT 4 years after Contract Award No additional time
Supply Draft Tube Liner Transition for 280 Inch
Adjustable Blade Runner (Optional)
NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Supply Draft Tube Liner Transition for 292 Inch
Adjustable Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Supply Outer Headcover
(Optional
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Supply Intermediate Headcover
(Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Supply Lower Headcover
(Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Furnish Blade Servomotor Shaft, Coupling Fasteners, Shaft Guard For Adjustable
Blade Units (Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Furnish Intermediate Shaft and Coupling Fasteners For Adjustable Blade Units
(Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Draft Tube Modification
Upstream of Bulkhead Gate Slot (Optional)
NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Draft Tube Modification
Downstream of Bulkhead Gate Slot (Optional)
NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Hone Wicket Gate Servomotors
(Optional)
NLT 45 days after Govt. approval after each unit’s wicket gate servomotor inspection report
No additional time
Machine Stay Ring Flange
(Optional)
NLT 45 days after Government Approval of each unit’s Stay Ring
As-Found Inspection Report 5 Additional days
Refurbish Thrust Bearing Shoes
(Optional)
NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report
Replace Discharge Ring For 280 Inch Adjustable Blade
Runner (Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances 60 additional days
Replace Discharge Ring and Draft Tube Liner Transition For
280 Inch Adjustable Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances 70 additional days
Replace Discharge Ring and Draft Tube Liner Transition For
292 Inch Adjustable Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of adjustable blade runners and appurtenances 120 additional days
Additional Painting to Improve
Stay Vane/Ring Surface Roughness (Optional)
NLT 24 hrs after final contractual coat of paint for each unit’s stay vane/ring assembly No additional time
Refurbish Thrust Bearing
Runner and Collar (Optional)
NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report
No additional time
Refurbish Upper Guide Bearing
Pads (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Refurbish Lower Guide Bearing
Pads (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Refurbish Turbine Guide
Bearings (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Provide Thrust Bearing Oil
Coolers (Optional)
NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances No additional time
Provide Unit 13 – 14 Thrust
Bearing Oil Coolers (Optional)
NLT 1 year after NTP for the manufacture of adjustable blade runners and appurtenances
Thrust Bearing Structural
Analysis (Optional) NLT 8 years after Contract Award No additional time
Stay Vane Extensions Prototype
Design (Optional) NLT 8 years after Contract Award No additional time
Wicket Gate Prototype Design
(Optional) NLT 8 years after Contract Award No additional time
Replacement Outer Headcover Prototype Design (Optional)
NLT 8 years after Contract Award No additional time
Replacement Lower Headcover
Prototype Design (Optional) NLT 8 years after Contract Award No additional time
Replacement Intermediate
Headcover Prototype Design (Optional)
NLT 8 years after Contract Award No additional time
4107AA
Supply Embedded Discharge
Ring Section For 280 Inch Fixed Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances
4107AB
Supply Embedded Discharge
Ring Section For 292 Inch Fixed Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Draft Tube Liner
Transition For 280 Inch Fixed Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Draft Tube Liner
Transition For 292 Inch Fixed Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Outer Headcover
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Intermediate Headcover
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Lower Headcover
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners
Discharge Ring Replacement
For 280 Inch Fixed Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances 60 additional days
Discharge Ring and Draft Tube Liner Transition Replacement
For 280 Inch Fixed Blade Runner(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances 70 additional days
Discharge Ring and Draft Tube Liner Transition Replacement for 292 Inch Fixed Blade Runner (Optional)
NLT 6 monthsafter NTP for the manufacture of fixed blade runners and appurtenances 120 additional days
Additional Painting to Improve
Stay Vane/Ring Surface Roughness (Optional)
NLT 24hrs after final contractual coat of paint for each unit’s stay vane/ring assembly No additional time
Hone Wicket Gate Servomotors
(Optional)
NLT 45 days after Govt. approval of each unit’s wicket gate servomotor inspection report No additional time
Draft Tube Modification
Upstream of Bulkhead Gate Slot (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Draft Tube Modification
Downstream of Bulkhead Gate Slot (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Machine Stay Ring Flange
(Optional)
NLT 45 days after Government Approval of each unit’s Stay Ring
As-Found Inspection Report 5 additional days
Refurbish Thrust Bearing Shoes
(Optional)
NLT 45 days after Government Approval of each unit’s Thrust
Refurbish Thrust Bearing
Runner and Collar (Optional)
NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report
No additional time
Refurbish Upper Guide Bearing
Pads (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Refurbish Lower Guide Bearing
Pads (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Refurbish Turbine Guide
Bearing (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Provide Thrust Bearing Oil
Coolers (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners
Furnish Stator Core Materials and
Accessories for Unit 13 Including Factory Tests
(Optional)
NLT 45 days after Government Approval of the Unit 13 Stator
Inspection Report No additional time
Furnish Stator Core Materials And
Accessories for Unit 14 Including Factory Tests
(Optional)
NLT 45 days after Government Approval of the Unit 14 Stator
Inspection Report
Perform Additional Inter-laminar Insulation Test Units 5, 13 and 14 (Optional)
NLT 60 days after Government receipt of the unit’s Inter-laminar
Insulation Test report No additional days
Remove Existing Stator Core, Install and Test New Stator Core for Unit 13 (Optional)
NLT 45 days after Government Approval of the Unit 13 Inter-laminar Insulation Test 120 additional days
Remove Existing Stator Core, Install and Test New Stator Core for Unit 14 (Optional)
NLT 45 days after Government Approval of the Unit 14 Inter-laminar Insulation Test 120 additional days
Remove Existing Stator Core, Install and Test Government- Furnished Stator Core Unit 5
(Optional)
NLT 45 days after Government Approval of the Unit 5 Inter-laminar Insulation Test 45 additional days
8101AA
Supply 280 Inch Adjustable 5-
Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners
8101AB
Supply 280 Inch Adjustable 6-
Blade Runner and Appurtenances (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
8101AC
Supply 292 Inch Adjustable 5-
Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
8101AD
Supply 292 Inch Adjustable 6-
Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
8102AA
Supply Discharge Ring Insert For 280 Inch Adjustable Blade
Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
8102AB
Supply Embedded Discharge Ring Section and Insert For 280 Inch Adjustable Blade Runner
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
8102AC
Supply Embedded Discharge Ring Section and Insert For 292 Inch Adjustable Blade
Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Draft Tube Liner Transition For 280 Inch
Adjustable Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Draft Tube Liner Transition For 292 Inch
Adjustable Blade Runner (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Outer Headcover
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Intermediate Headcover
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Lower Headcover
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Furnish Blade Servomotor Shaft, Coupling Fasteners, Shaft Guard for Adjustable
Blade Units (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Furnish Intermediate Shaft and Coupling Fasteners for Adjustable Blade Units
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Set of Leading Edge
Stay Vane Extensions (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners
Supply Set of Trailing Edge
Stay Vane Extensions (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Set of Wicket Gates
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Turbine Shaft Seal
(Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Furnish Gate Operating
Mechanism Bushings and Bearing Plate (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Supply Headcover and Bottom Ring Facing Plate (Optional)
NLT 6 months after NTP for the manufacture of fixed blade runners
Pre-Disassembly Watered
Operational Testing (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Generating Unit Disassembly
(Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Replace Discharge Ring For 280 Inch Adjustable Blade
Runner (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances 60 additional days
Replace Discharge Ring and Draft Tube Liner Transition For
280 Inch Adjustable Blade Runner (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances 70 additional days
Modify Discharge Ring Without Demolition For 280
Inch Adjustable Blade Runner (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Replace Discharge Ring and Draft Tube Liner Transition For
292 Inch Adjustable Blade Runner (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances 120 additional days
Machine Stay Ring Flange
(Optional)
NLT 45 days after Government Approval of each unit’s Stay Ring
As-Found Inspection Report 5 additional days
Provide Draft Tube and Scroll Case Drain Valves (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Provide Thrust Bearing Oil
Coolers (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners
Provide Static Hub Pressurization System and
Refurbish/Modify Oil Head (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Provide Inner Oil Pipe and
Refurbish/Modify or Replace Existing Oil Pipes (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Lead Based Paint Removal and
Disposal (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
9113 Painting (Optional) NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances
No additional time
Refurbish Outer Headcover
(Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Lower Headcover
(Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Intermediate Headcover (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Stay Vane/Ring Refurbishment Including Stay Vane Extension
Installation
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Additional Painting to Improve
Stay Vane/Ring Surface Roughness (Optional)
NLT 24 hrs after final contractual coat of paint for each unit’s stay vane/ring assembly.
No additional time
Refurbish Bottom Ring
(Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Misc. Wicket Gate
Operating Mechanism Components (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Line Boring and Installation of
Wicket Gate Stem Bushings (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish/Replace Turbine Air Admission Valves (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Gate Operating Ring
(Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Intermediate and Generator Shafts (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Servo Shaft for
Adjustable Blade Operation (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners
Refurbish Turbine Shafts for Adjustable Blade Operation
(Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Unit 5 & 6 Turbine Shafts for Adjustable Blade
Operation (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Wicket Gate Servomotors (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Hone Wicket Gate Servomotors
(Optional)
NLT 45 days after Govt. approval of each unit’s wicket gate servomotor inspection report No additional time
Refurbish Units 5 & 6 Wicket Gate Servomotors (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Provide Water and Oil Piping
Systems and Components (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Provide Electrical Devices, Temperature Indicating Devices, Wiring/Cable
Removal (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Provide Generator Housing
Lighting Wires for Units 5 and 6 (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Provide Unit 5 and 6 Generator
Stator Heater Automatic Controls (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Install Government Furnished
Generator Air Coolers in Unit 6
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Thrust Bearing Component
Inspection, Unit 5 & 6 (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Unit 5 & 6 Thrust Bearing
Component Inspection
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Guide Bearing Component
Inspection (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Refurbish Thrust Bearing Shoes
(Optional)
NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report
No additional time
Refurbish Thrust Bearing
Runner and Collar (Optional)
NLT 45 days after Government Approval of each unit’s Thrust Bearing Site Inspection Report
No additional time
Refurbish Upper Guide Bearing
Pads (Optional)
NLT 45 days after Government Approval of each unit’s Guide
Refurbish Lower Guide Bearing
Pads (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Refurbish Turbine Guide
Bearing (Optional)
NLT 45 days after Government Approval of each unit’s Guide Bearing Site Inspection Report
No additional time
Draft Tube Modification
Upstream of Bulkhead Slot (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Draft Tube Modification
Downstream of Bulkhead Gate Slot (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Reassembly of Adjustable
Blade Units (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners and appurtenances No additional time
Commissioning of Adjustable
Blade Units (Optional)
NLT 1 year after NTP for the manufacture of fixed blade runners
30…