Site_Visit_Info _Dworshak_Unit_3.pdf

PDF 180 KB Posted

Attached to
Dworshak Unit 3 Winding Replacement Federal contract opportunity
Solicitation number
W912EF-15-R-0019
Issued by
Department of the Army Corps of Engineers Engineering District Walla Walla

About this file

SITE VISIT information

View the file

Other files for this federal contract opportunity

Other files attached to Dworshak Unit 3 Winding Replacement, newest first.
File Type Posted
Amendment_0003 _W912EF-15-R-0019.pdf PDF
FIOs_Part9.pdf PDF
FIOs_Part8.pdf PDF
FIOs_Part4.pdf PDF
FIOs_Part3.pdf PDF
Amendment_0002 _W912EF-15-R-0019 _Dworshak_Unit_3.pdf PDF
FIOs_Part6.pdf PDF
FIOs_Part5.pdf PDF
FIOs_Part7.pdf PDF
FIOs_Part1.pdf PDF
FIOs_Part2.pdf PDF
Plans_Amend_0002.pdf PDF
Site_Visit_List_of_Attendees _Dworshak_Unit_3 _15-R-0019.pdf PDF
Amendment_0001_W912EF-15-R-0019_(2).pdf PDF
PLANS_15-R-0019_fio1.pdf PDF
PLANS_15-R-0019_fio2.pdf PDF
PLANS_15-R-0019_fio3.pdf PDF
PLANS_15-R-0019.pdf PDF
Solicitation_with_specs _W912EF-15-R-0019 _Dworshak_Unit_3.pdf PDF
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for-- Tuesday, 02 June 2015 at 10:00 a.m. local time

(c) Participants will meet at—the parking lot located roughly ¼ mile downstream of the

Dworshak Dam powerhouse. At 10:00am, Government personnel will bring participants into the Project, and we expect the site visit to end by 2:00pm. Participants should bring hard hats, safety shoes, and safety glasses.

There will be only one site visit offered. Offerors planning to attend must register for the site visit by sending an email to: Phyllis.L.Buerstatte@usace.army.mil and Jani.C.Long@usace.army.mil

Firms must register no later than the day before the site visit.

Site visit attendees must provide the following information: 1) Solicitation Number; 2) Project Title; 3)

Name(s) of individual(s) attending site visit; 4) Are all individuals U.S. Citizens? If not, please refer to

ACCESS FOR FOREIGN NATIONALS in Section 00800; 5) Name of Company; 6) Phone Number of

Company. Each individual must have picture identification on his/her person while at the project site. There can be no substitutions of one individual for another. If an individual arrives at the site visit without having called ahead of time and/or without picture identification, that individual may not be allowed on the project.

Participants of scheduled site visit must abide by the U.S. Army Corps of Engineers Safety and Health Requirements

Manual (EM 385-1-1, latest version) in accordance with Section 5, “Personal Protective and Safety Equipment.” It is the responsibility of the participants to wear personal protective and safety equipment as required by this regulation.

Failure to comply could result in denial of access to site visit location.

The latest version of EM 385-1-1 is available online at:

http://www.usace.army.mil/SafetyandOccupationalHealth.aspx.

(End of provision)

Participants will be led into the powerhouse to look at spare parts, tooling, lifting beams, Unit 3. On Unit 3, the expectation is to remove a top hatch cover and a top air shroud to allow access to the top of the end winding for inspection and measurements. Will also remove some of the inspection hatches on the barrel on the perimeter of the stator to allow visual view of the back of the core.

Vendors will not be allowed to crawl around the whole top of the rotor, but only in the small restricted area designated by the Government. Only 2-3 people will be allowed to enter the unit at one time; 10 minutes maximum until all visitors have had access, then the unit will remain open for others who wish to reenter.