Amendment 0002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Results W912EF-12-B-0004 LoMo Mono 15 Concrete Phase 3.pdf | ||
| Site Visit Attendees 12-B-0004.pdf | ||
| Amend_Plans.pdf | ||
| Amendment 0001 W912EF-12-B-0004.pdf | ||
| Site Visit Information.pdf | ||
| W912EF-12-B-0004.pdf | ||
| 12-B-0004_Plans.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W68SBV12175562
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
TITLE: Low er Monumental Monolith 15 Concrete Repair, Phase 3
The purpose of this amendment is to revise Technical Specification Section 01 55 10.00 28, Paragraph 1.5, and to remove the statement regarding funds availability. (See Summary of Changes)
Bid opening date remains unchanged, December 2, 2011 at 2:00 p.m.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 29-Nov-2011
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EF-12-B-0004
X 9B. DATED (SEE ITEM 11)
02-Nov-2011
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Nov-2011
CODE
USAED, WALLA WALLA - CONTRACTING DIV.
JANI C. LONG
201 N. THIRD AVENUE
WALLA WALLA WA 99362-1876
W912EF 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912EF-12-B-0004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
1. Bid opening date remains unchanged. Bids are due no later than 2:00 pm, Pacific Time, on December 02, 2011.
2. Bidders must acknowledge receipt of this amendment. See Block No. 11 of Standard Form 30 for methods of acknowledging solicitation amendments.
3. The following changes are made as a result of this amendment:
A. Since funds are presently available, remove the following statement from the Bid Schedule:
“Funds are not presently available for this work. No contract will be awarded unless funds become available.”
B. Revise Specification Section 01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS, Paragraph 1.5 MOORAGE AREA
W912EF-12-B-0004
SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS
The following have been modified:
Walla Walla District Corps of Engineers Lower Monumental Monolith 15 Repair Phase 3
Magnitude of the Construction Project
Between $1,000,000 and $5,000,000
ITEM
DESCRIPTION
QUANTITY
U/M
U/P
AMOUNT
0001 Fabricate Pre-Cast Concrete Blocks 1 LS XXXXX $________
0002 Pre-Cast Concrete Block Installation 1 LS XXXXX $________
0003 Cast-In-Place Concrete above Elevation
545.0 feet mean sea level (fmsl)
1 LS XXXXX $________
0004 Waterstop Installation 1 LS XXXXX $________
SCHEDULE TOTAL $__________
Due to the regional economic and environmental impacts of navigation lock closures, the completion date listed in Section 00700, FAR Clause 52.211-10, Commencement, Prosecution and Completion of Work, is a firm completion date. Navigation lock closures are coordinated and scheduled regionally based on economic and environmental factors. Any changes to scheduled lock closures could create legal liabilities for the Walla Walla District. Therefore, time is of the essence and the contractor will prosecute this work using its best efforts to meet the referenced completion date. The Government suggests that the contractor go to 24 hour/7day a week shifts if it appears from the contractor’s construction schedule that the contractor will not complete the work by the completion date. Finally, the per diem liquidated damages rate under FAR Clause 52.211-12 represents a reasonable forecast of costs estimated for 24 hour/7 day a week inspections and superintendence by the Government.
(End of Summary of Changes)
Lower Monumental Navlock Monolith 15 Wall Repair Phase 3 W912EF-12-B-0004 Amend-0002
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 55 10.00 28
CONTRACTOR WORK, ACCESS AND STORAGE AREAS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 CONTRACTOR'S STORAGE AND STAGING AREA
1.4 ACCESS TO THE WORK AREA
1.5 MOORAGE AREA
1.6 FLOATING MOORING BITTS
1.7 DECK ACCESS AND USE
1.7.1 Deck Access and Roadway Coordination
1.8 TRAFFIC CONTROL AND PUBLIC ACCESS
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
SECTION 01 55 10.00 28
G4EDDRJR
Line
This page intentionally left blank
SECTION 01 55 10.00 28
CONTRACTOR WORK, ACCESS AND STORAGE AREAS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2008) Safety and Health Requirements Manual
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI A10.22 (2007) Safety Requirements for Rope-Guided and Non-Guided Workers’ Hoists American National Standard for Construction and Demolition Operations
ANSI A10.4 (2007)Safety requirements for Personnel Hoists and Employee Elevators for Construction and Demolition Operations
ASME INTERNATIONAL (ASME)
ASME B30.7 (2006)Base Mounted Drum Hoists
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Personnel Hoist System Plan; G C
1.3 CONTRACTOR'S STORAGE AND STAGING AREA
The Contractor's storage and staging areas shall be at locations indicated or as otherwise approved. The storage and staging areas may be used for activities such as setup of an office trailer, parking of private vehicles, storage of materials and equipment and for work activities. Security at the storage and staging site will be the Contractor's responsibility.
Temporary security fencing may be installed in a manner approved by the Contracting Officer. Security fencing may not be installed in a manner
SECTION 01 55 10.00 28
that damages existing facilities, such as punching post holes in existing pavement.
1.4 ACCESS TO THE WORK AREA
The Contractor shall provide a dedicated means for personnel access from the Navigation Lock upper deck to the work area in the lock chamber. A personnel hoist system shall be provided by the Contractor that allows 12 feet of access on the North Deck Access Road. The Contractor shall submit a personnel hoist system plan that provides details of the equipment to be used, safety and lifting capacity, the equipment footprint and set-up location. All components and systems shall conform to the requirements of the following standards: EM 385-1-1, ANSI A10.22, ANSI A10.4, and ASME B30.7.
If any of these standards conflicts with another, the more restrictive requirements shall be used. The proposed personnel system shall be certified by professional engineer or the manufacturer that it conforms to the applicable standards. Hoisting equipment shall only be operated by designated qualified personnel. Proof of qualifications shall be included in the plan. The Contractor shall make this access available at any time the Contracting Officer requests access from the deck to the work area.
1.5 MOORAGE AREA
The Contractor may moor floating plant in an approved location near the Navigation Lock. The forebay max normal pool is 540.0 FMSL (Feet Mean Sea Level) Min. normal pool is 537.0 FMSL. River water levels may fluctuate during construction. There will be no access through the upstream navigation lock gate during the scheduled Full Navigation Lock Outage.
1.6 FLOATING MOORING BITTS
The floating mooring bitts located immediately upstream and downstream of the work area in the lock may be used only for securing floating plant in place; they shall not be used for winching or moving of floating plant. No construction equipment, work platforms, scaffolding, safety railings, etc.
shall be connected to or braced from the mooring bits.
1.7 DECK ACCESS AND USE
During the time periods of this contract, it is anticipated that there will be ongoing Project Work and other awarded Contracts that will require access to the deck and deck roadway in the vicinity of this work. The work area and restrictions and limitations caused by the work to be performed by others shall be considered by the Contractor in scheduling work to be performed. No allowance will be made for damage or extra compensation because of the required cooperation.
1.7.1 Deck Access and Roadway Coordination
The following shall be coordinated with Project Personnel and the Contracting Officer a minimum of 24 hours prior to impacts to deck access.
Any changes to the agreed upon schedule and coordination will be approved by the Contracting Officer prior to commencement of impacted work or operations.
1. All activities involving use of deck area and roadway.
2. Contractor shipments across deck.
SECTION 01 55 10.00 28
G4EDDRJR
Line
3. Removing equipment and materials from deck.
4. All complete blockages of deck access.
1.8 TRAFFIC CONTROL AND PUBLIC ACCESS
Existing public roads and access roads shall be kept open to vehicle traffic at all times. The Contractor shall conduct all work in such a manner as will obstruct and inconvenience traffic as little as possible.
When necessary for the Contractor to operate on or cross existing highways or roads, the Contractor shall furnish signs lights, and/or other necessary safe guards to safely control and direct the flow of traffic. The Contractor shall obtain any and all required permits for such operations from the appropriate private or public authority at no additional cost to the Government.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section --