AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

Reference Solicitation No. W912EE18B0007, for FC&CE, Ouachita River Basin, Ouachita River; Ouachita Parish, Louisiana; Levee Bank

Stabilization and Levee Rehabilitation; Miles 161 and 167, Ouachita River, is amended as follow s:

SEE CONTINUATION PAGE FOR SUMMARY OF CHANGES.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 07-Aug-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EE18B0007

X 9B. DATED (SEE ITEM 11)

23-Jul-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

06-Aug-2018

CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EE18B0007

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SPECIFICATIONS: Bidding Schedule and Section 01 00 00.00 09 are revised and replaced.

DRAWINGS: Drawings revised by this amendment are attached.

Specifications revised by this amendment have the notation "Revised by Amendment 0001" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.

Drawings revised by this amendment have the notation "Revised by Amendment 0001" at the bottom of the page.

FC&CE, OUACHITA RIVER BASIN, OUACHITA RIVER

OUACHITA PARISH, LOUISIANA LEVEE BANK STABILIZATION

AND LEVEE REHABILITATION

MILES 161 AND 167N

ITEM DESCRIPTION

EST

QTY U/M UNIT PRICE AMOUNT

MOBILIZATION AND

DEMOBILIZATION 1 JOB FOR $

0002 CLEARING AND GRUBBING 1 JOB FOR $

0003 GRADED STONE “A”

0003AA FIRST 305,850 TONS 305,850 TONS $ $

0003AB OVER 308,850 TONS 203,900 TONS $ $

0004 GRADED STONE “C”

0004AA FIRST 59,550 TONS 59,550 TONS $ $

0004AB OVER 59,550 TONS 39,700 TONS $ $

ENVIRONMENTAL

PROTECTION FEATURES 1 JOB FOR $

DEMOLITION: STRUCTURE

REMOVAL 1 JOB FOR $

TOTAL $

"Revised by Amendment 0001"

W912EE-18-B-0007

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PARTNERING

1.4 RIGHTS-OF-WAY

1.5 LAYOUT AND MARKING OF RIGHTS-OF-WAY

1.6 INITIAL SURVEYS AND QUANTITIES SURVEYS

1.7 MONITOR SURVEYS

1.8 COMPLIANCE SURVEYS

1.9 PRECONSTRUCTION CONFERENCE

1.10 SUBMITTAL OF SUBCONTRACTING PLAN

1.11 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

1.12 ORDER OF WORK

1.13 PROGRESS CHART

1.14 DESIGNATED BILLING OFFICE

1.15 PAYMENT INVOICES

1.16 TEMPORARY PROJECT FENCING

1.17 AS-BUILT DRAWINGS

1.18 PROJECT SIGN

1.19 MINIMUM REQUIRED INSURANCE

1.20 WORK IN QUARANTINED AREA

1.21 CERTIFICATES OF COMPLIANCE

1.22 PROCESS FOR OBTAINING CURRENT REQUIREMENTS OF THE U.S. ARMY CORPS

OF ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)

1.23 SAFETY SIGN

1.24 ACCIDENT PREVENTION PLAN

1.25 DAILY INSPECTIONS

1.26 ACCIDENT INVESTIGATIONS AND REPORTING

1.27 MACHINERY AND MECHANIZED EQUIPMENT

1.28 VEHICLE WEIGHT LIMITATIONS

1.29 PUBLIC AND PRIVATE UTILITIES

1.30 DAMAGE TO WORK

1.31 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

1.32 CONTROL OF ACCESS TO CONSTRUCTION AREAS

1.33 MAINTENANCE OF TRAFFIC

1.34 HARBOR MAINTENANCE FEE

1.35 PERMISSIBLE HOURS OF OPERATION

PART 2 PRODUCTS (Not Applicable)

PART 3 EXECUTION (Not Applicable)

-- End of Section Table of Contents --

SECTION 01 00 00.00 09 Page 1 Revised By Amendment 0001

SECTION 01 00 00.00 09

GENERAL CONTRACT REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

19 CFR 24.24 Harbor Maintenance Fee

33 CFR 156 Oil and Hazardous Material Transfer Operations

1.2 SUBMITTALS

Government approval is required for all submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Plan; G, GA

1.3 PARTNERING

The Government encourages formation of informal project partnerships on all projects. A project partnership strives to utilize a cooperative working relationship to jointly establish and effectively reach mutual project execution goals. The partnering process will in no way relax or stiffen the requirements of the contract, but will enhance the likelihood of success through improved working relationships. The possibility of an informal partnership may be discussed at the Pre-construction Conference for this project.

1.4 RIGHTS-OF-WAY

a. The rights-of-way for the work to be constructed under this contract, within the limits indicated on the drawings, will be provided by the Government without cost to the Contractor. If these rights-of-way are used by the Contractor, he shall, at his own expense, do all work necessary to make such rights-of-way suitable for traveling to and from the worksite. Upon completion of the Contractor's work, any such rights-of-way furnished by the Government shall be left in a

SECTION 01 00 00.00 09 Page 2 condition satisfactory to the Contracting Officer.

b. When so directed by the Contracting Officer, the Contractor shall, without expense to the Government and at any time during the progress of the work when it is not being actively used for contract operations, promptly vacate and clean up any part of the Government grounds or rights-of-way that have been allotted to or have been in use by the Contractor.

c. The Contractor shall not obstruct any existing roads on lands controlled by the United States except with written permission of the Contracting Officer and shall maintain such roads in as good condition as exists at the time of commencement of work under this contract.

d. The Contractor shall procure, without expense to the Government, all additional lands, access roads, or rights-of-way necessary for his use in the performance of the work or as required by his method of operation. The Contractor shall submit written evidence to the Contracting Officer that he has obtained the rights-of-way from the property owners. The written evidence shall consist of an authenticated copy of the conveyance under which the Contractor acquired such rights-of-way, prepared and executed in accordance with the laws of the State in which the land is located. The Contractor shall also obtain from the owners a release for the Government for any damages which may result from his use of such rights-of-way. The written conveyance and release shall be provided to the Government prior to use of Contractor obtained additional lands, access roads, or rights-of-way. If temporary rights-of-way are obtained by the Contractor the period of time for those rights shall coincide with Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK, plus a reasonable time for any extension granted for the completion of the work. Any agreements or permits with levee boards, counties, parishes, municipalities, or other political subdivisions for moving material and equipment will be the responsibility of the Contractor and shall be obtained at no expense to the Government. Any delays to the Contractor resulting from delays in procuring such additional lands, access roads, rights-of-way, or permits for moving material and equipment for his work under this contract will not be a basis for any claim for increase in the cost of this contract. The Contractor shall make his own investigations to determine the conditions, restrictions and difficulties which may be encountered in acquiring such rights-of-way and in the transportation of material and equipment. In addition, the Contractor shall be solely liable for any and all damages and claims of any nature whatsoever arising from or growing out of the acquisition and use of rights-of-way, etc., other than those furnished by the Government.

f. The Contractor shall repair at no expense to the Government, any and all damage to any existing roads when such damage is a result of his operations under this contract. (CEMVK-OC, 1989)

1.5 LAYOUT AND MARKING OF RIGHTS-OF-WAY

The Contractor shall layout and mark the rights-of-way limits as indicated on the drawings prior to beginning any other work, unless otherwise approved. The marking shall be placed at intervals approved by the Contracting Officer. The rights-of-way limits shall be marked by stakes, flagging or other approved means. The marking shall be highly visible from

SECTION 01 00 00.00 09 Page 3 a distance of at least 100 feet, and shall be maintained for the duration of the contract. If the rights-of-way marking should fade significantly in color, become damaged or lost as a result of the Contractor's operation or as a result of vandalism, or in any other way cease to function as a highly visible marker of the rights-of-way limits, the Contractor shall layout and restore the marking to the original condition. After all work is complete and upon approval of the Contracting Officer, the Contractor shall remove all marking. No separate payment will be made for layout, marking and maintaining the rights-of-way limits or for removing the marking.

1.6 INITIAL SURVEYS AND QUANTITIES SURVEYS

Prior to any construction of any definable feature of work, the Contractor shall locate the centerline and baseline stations as specified in the before-construction drawings, task order specifications, and/or as directed in the field by the Contracting Officer Representative. The surveys shall be under the direct supervision of a licensed surveyor with at least five years of hydrographic surveying experience, no less than 7 days before the work commences. Submit the name and address of the professional surveyor responsible for surveying to the Contracting Officer's Representitive prior to the start of survey activities. All Hydrographic surveys shall be conducted using multi-beam technology. The Contractor shall provide overbank surveys at each dig-in portion of the dike. Overbank survey shall extend 400 ft inland along the baseline and shall extend 75 ft each side of the Structural Azimuth Line. The Contractor shall layout the work and take the following surveys of placed stone for compliance with the grades, limits, and tolerances specified in the before-construction drawings, task order specifications, and/or as directed in the field by the Contracting Officer Representative.

Survey profiles, not to exceed 20 feet intervals, shall be taken and plotted to cover the area of the stone construction before stone placement begins. Survey cross-sections, not to exceed 100 feet intervals, shall be taken and plotted to cover the area of the stone construction before stone placement begins. Additional profiles and cross-sections shall be taken and plotted as necessary or as directed by the onsite Government Representative during construction operations. Complete electronic survey data files (.xyz, .txt File: (Point # Northing, Easting, Elevation), .dtm, etc.), copies of the field notes, plotted profiles and cross-sections, and quantity computations for all stone placement under this contract shall be furnished through the Contracting Officer's Representative for review and approval at least 7 calendar days ahead of the initial placement of any stone. Surveys mentioned above shall be provided as RAW data and processed in a 2 X 2 grid. Profiles and cross-sections taken more than 14 calendar days ahead of construction will not be acceptable.

1.7 MONITOR SURVEYS

Once stone placement has begun on the first dike, as shown in SECTION 01 15 00.00 09 GENERAL REQUIREMENTS, para. 3.2.1 Sequece, additional monitor surveys shall be taken of the next or subsequent dikes if stone placement of the next or subsequent dike begins more than 14 days after the initial surveys in para. INITIAL SURVEYS AND QUANTITIES SURVEYS. These monitor surveys shall also be performed before stone placement resumes after more than 14 days delay in stone placement operations. As directed by the Government Representative, if these monitor surveys indicate changed conditions from the initial surveys (para. INITIAL SURVEYS AND QUANTITIES SURVEYS), additional surveys shall be performed. Survey profiles not to exceed 20 feet intervals shall be taken and plotted to cover the area of

SECTION 01 00 00.00 09 Page 4 stone placement. Survey cross-sections not to exceed 100 feet intervals, shall be taken and plotted to cover the area before any additional stone placement begins. Additional profiles and cross-sections shall be taken and plotted as necessary or as directed by the on-site Government Representative during construction operations. Complete electronic survey data files (.xyz, .txt File: (Point # Northing, Easting, Elevation), .dtm, etc.), copies of the field notes, plotted profiles and cross-sections, and quantity computations for all stone placement under this contract shall be furnished through the Area Office to the Vicksburg District, Engineering Division, River Stabilization Section for review and approval at least 7 calendar days ahead of the initial placement of any stone.

1.8 COMPLIANCE SURVEYS

Survey profiles and cross-sections shall be taken and plotted of the completed stone placement daily or as directed by the Government Quality Assurance Representative. Copies of the field notes, plotted cross-sections, and quantity computations shall be furnished as requested by the Contracting Officer or his/her representative.

The profiles and cross-sections shall be plotted on 10 x 10 cross-section tracing paper to a scale of 1-inch = 20 feet vertical and horizontal. The profiles and cross-sections shall be plotted with the profiles and corresponding vertical and horizontal scales at the top of the sheet. The horizontal stationing for the profiles shall be plotted with increasing stationing running as if looking upstream. The cross-sections with corresponding vertical and horizontal scales shall be plotted beneath the profile directly under the corresponding stationing of the profile. The area of daily stone placement shall be identified by coloring the area of placement with alternating color pencils. The right and left sides of the cross-section shall conform with the direction of the increasing stations.

Horizontal distance shall be shown on the top margin in distances of 100 feet, and datum shown on the appropriate horizontal lines. The cross-sections shall be identified by station number under each section.

Approximately one foot shall be left void at each end of the roll. Near each end of the roll, pertinent information shall be shown, including job name, item number, inclusive stations, contract number, completion data and name of inspector. Sections plotted by the electronic plotter will be acceptable. Pencil work shall be of such firmness and line weight that a good reproduction may be obtained.

1.9 PRECONSTRUCTION CONFERENCE

a. A preconstruction conference will be arranged by the Area Engineer as soon after contract award as possible, and the conference will be conducted before work is allowed to commence. The Area Engineer will notify the Contractor of the time, date, and location for the meeting.

At this conference, the Contractor will be oriented with respect to contract administration procedures, lines of authority, and construction matters. All known subcontractors performing at least 20 percent of the contract are required to attend this conference.

Additional conferences may be established by the Area Engineer for any major subcontractors unknown at the time of the initial conference.

b. Submission by the Contractor of the items listed below will determine the date of the conference. The following items shall be submitted to the Area Engineer in hard copy and electronic (pdf) format for review at least seven (7) calendar days prior to the preconstruction conference:

SECTION 01 00 00.00 09 Page 5

(1) Accident Prevention Plan

(2) Quality Control Plan

(3) Environmental Protection Plan

(4) Six copies of the certified Small Construction Notice of Intent (SCNOI) for each site

c. The Contractor shall bring to this conference, in completed form, the following:

(1) Letter of superintendent appointment and authority

(2) List of subcontractors

d. The Contractor should bring to this conference, or at least be prepared to discuss, the following:

(1) Submittal register

(2) Progress chart or Network Analysis System (as applicable)

e. Minutes of this conference will be taken and prepared by the Area Engineer and sent to the Contractor for his concurrence and signature.

1.10 SUBMITTAL OF SUBCONTRACTING PLAN

a. This paragraph does not apply to small business concerns.

b. After bid opening, and within 7 days, the apparent low bidder, upon telephone notification by the Small and Disadvantaged Business Utilization Specialist, shall submit a Small and Disadvantaged Business Subcontracting Plan. The plan shall be submitted in accordance with the Contract Clauses SMALL BUSINESS SUBCONTRACTING PLAN - ALTERNATE I.

The person responsible for administering the plan shall be named in paragraph AGENT FOR SUBMITTING SMALL BUSINESS SUBCONTRACTING PLAN of the Representations and Certifications.

1.11 NOTIFICATION OF AREA ENGINEER BEFORE BEGINNING WORK

At least 7 days before beginning work, and at least one day before resuming work after a period of 7 days or more when no work has been performed, the Contractor shall notify U.S. Army Corps of Engineers, Mr. Robin Blake, Chief, Vidalia Area Office, 100 Advocate Row, Vidalia, Louisiana 71373-3032, telephone (318) 336-5226.

1.12 ORDER OF WORK

The work shall be carried on in accordance with the Progress Chart (schedule) required by paragraph (a) of the Contract Clause SCHEDULES FOR CONSTRUCTION CONTRACTS. In preparing the Progress Chart (schedule), the Contractor shall adhere to the following order of work:

a. All construction shall begin at the upstream end of the job and proceed to the downstream end unless otherwise directed by the Contracting Officer.

SECTION 01 00 00.00 09 Page 6

b. Debris, tree removal, and clearing.

c. Construction of the longitudinal stonefill revetment shall be from the river unless otherwise directed by the Contracting Officer.

d. Construction of the stone paving.

e. Erosion control shall follow, as closely as practicable, completion of all other work in the area to receive erosion control.

1.13 PROGRESS CHART

The progress chart required by provisions of paragraph (a) of the Contract Clause SCHEDULES FOR CONSTRUCTION CONTRACTS shall be prepared on ENG FORM 2454, copies of which will be furnished to the Contractor by the Government. Three (3) copies of the schedule will be required. The Progress Chart shall be updated by the Contractor monthly and submitted in accordance with paragraph PAYMENT INVOICES.

1.14 DESIGNATED BILLING OFFICE

The designated billing office for this contract shall be U.S. Army Corps of Engineers, Vidalia Area Office, 100 Advocate Row, Vidalia, Louisiana 71373-3032.

1.15 PAYMENT INVOICES

a. The Federal Acquisition Regulation requires that the "REMIT TO" address on the invoice match the "REMIT TO" address on the contract or a proper notice of assignment. The Payment Office will verify a match of the "REMIT TO" address in the contract and Contractor’s invoice prior to payment. If the addresses do not match, the invoice will be determined improper and returned to the Contractor for correction and resubmission. If an invoice is improperly returned, the original invoice receipt date shall be used as the basis for determining interest to be paid in accordance with the PROMPT PAYMENT ACT.

b. Among other things, the Contract Clause PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS requires that a proper invoice for payment include substantiation of the amounts requested. As required in Office of Management and Budget, Circular A-125 (Rev.), PROMPT PAYMENT, dated December 12, 1989, substantiation of the amount requested for progress payments under construction contracts includes the following:

(1) An itemization of the amounts requested related to the various elements of work required by the contract covered by the payment request;

(2) A listing of the amount included for work performed by each subcontractor under the contract;

(3) A listing of the total amount of each subcontract under the contract;

(4) A listing of the amounts previously paid to each such subcontractor under the contract; and,

(5) Additional supporting data in a form and detail required by the Contracting Officer.

SECTION 01 00 00.00 09 Page 7

(6) Updated ENG Form 2454 Progress Chart.

c. Failure to include the above information in a Contractor’s invoice will result in the invoice being considered defective under the provisions of the PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS clause of the contract, and it will be returned to the Contractor for correction and resubmission. (CEMVK-OC, 1997)

1.16 TEMPORARY PROJECT FENCING

Temporary project fencing as required by Section 4, "Temporary Facilities", paragraph 04.A.04 of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual, is not required on this project.

1.17 AS-BUILT DRAWINGS

This paragraph supplements the Contract Clause SPECIFICATIONS AND DRAWINGS

FOR CONSTRUCTION.

a. As-Built Contract Drawings. The Contractor shall maintain two (2) full-size sets of blueline prints of the contract drawings depicting in red a record of as-built conditions. These drawings shall be maintained in current condition at all times during the entire contract period. The blueline drawings shall be updated daily by the Contractor showing all changes from the contract plans which are made in the work, additional information which might be uncovered in the course of construction, and information for future construction reference (such as debris disposed by burying). This information shall be recorded on the blueline prints accurately and neatly by means of details and notes. Each month, prior to submitting a request for progress payment, the Contractor shall review the blueline as-built drawings with the Contracting Officer, and the Contractor shall certify that the as-built drawings are accurate and up-to-date before progress payment is made.

The Contractor shall deliver to the Contracting Officer the two (2) original full-size completed sets of as-built marked blueline prints at the time of the final inspection of the project. In addition, the Contractor shall provide two CD-ROM's, each containing a full-size, 400 dpi PDF (portable document format) set of as-built drawings, to the Contracting Officer at the time of final inspection. The as-built drawings shall be identified by entering the words "AS-BUILT DRAWINGS" in letters at least 3/16-inch high, placed in the lower right corner of each drawing.

b. No separate measurement or payment will be made for providing as-built drawings, electronic drawings and plates, or for any of the work required by this clause, and all costs therefor shall be included in the applicable contract prices contained in the Bidding Schedule.

1.18 PROJECT SIGN

The Contractor shall fabricate, erect and maintain one sign for project identification. The sign shall be displayed and positioned for reading by passing viewers. The exact location is subject to Contracting Officer's approval. Information for the right side of the project sign shall be as follows:

Project Title: FC&CE, Ouachita River Basin,Ouachita River Ouachita Parish, Louisiana

SECTION 01 00 00.00 09 Page 8

Levee Bank Stabilization and Levee Rehabilitation Miles 161 and 167

Contract No: W912EE-18-C-0XXX

Contractor: (Contractor's name and city)

The project identification sign shall meet the requirements specified in the U.S. Army Corps of Engineers Sign (USACES) Standards Manual, EP 310-1-6a and EP 310-1-6b. A copy of the sign standards manual is available for review at the office of the Vicksburg District Sign Program Manager and questions concerning manufacture and installation of the project identification sign may be addressed to:

Vicksburg District Sign Program Manager (Aaron Posner)

ATTN: CEMVK-OD-MN

4155 Clay Street Vicksburg, MS 39183-3435 Telephone: (601) 631-5287

1.19 MINIMUM REQUIRED INSURANCE

The following paragraph is applicable if the services involved are performed on a Government Installation. Government Installation is defined as property where the Government holds by fee simple title, by construction rights-of-way, or perpetual easement, etc., an interest in real property.

See the Contract Clause INSURANCE-WORK ON A GOVERNMENT INSTALLATION.

a. Workmen's Compensation and Employer's Liability Insurance. The Contractor shall comply with all applicable workmen's compensation Statutes of the State of Louisiana and shall furnish evidence of Employer's Liability Insurance in an amount of not less than $100,000.

b. General Liability Insurance. Bodily injury liability insurance in the minimum limits of $500,000 per occurrence on the comprehensive form of policy.

c. Automobile Liability Insurance. Minimum limits of $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. This insurance shall be on the comprehensive form of policy and shall cover the operation of all automobiles used in performance of the contract.

d. Marine Insurance. Hull policy must be endorsed for towers liability (tow and cargo) and the amount of the policy must be supplemented by excess towers' liability in the minimum amount of $1,000,000, and also by insurance in an amount not less than $5,000,000 to cover damage to the Louisiana Hwy 80 Bridge over the Ouachita River. All policies must be endorsed for navigation limits applicable to this contract. The United States Corps of Engineers, Vicksburg District, must be named as an additional insured on all policies, and the policies shall contain an endorsement waiving subrogation against the United States. In the event of material changes in coverage or of cancellation of any policy, written notice shall be given to the Contracting Officer at least 30 days prior to the effective date of such change or cancellation.

SECTION 01 00 00.00 09 Page 9

1.20 WORK IN QUARANTINED AREA

The work called for by this contract involves activities in parishes quarantined by the Department of Agriculture to prevent the spread of certain plant pests which may be present in the soil. The Contractor agrees that all construction equipment and tools to be moved from such parishes shall be thoroughly cleaned of all soil residues at the construction site with water under pressure and that hand tools shall be thoroughly cleaned by brushing or other means to remove all soil. In addition, if this contract involves the identification, shipping, storage, testing, or disposal of soils from such quarantined area, the Contractor agrees to comply with the provisions of ER 1110-1-5, "Plant Pest Quarantined Areas and Foreign Soil Samples" attachments, a copy of which will be made available by the Contracting Officer upon request. The Contractor agrees to assure compliance with this obligation by all subcontractors.

1.21 CERTIFICATES OF COMPLIANCE

Any certificates required for demonstrating proof of compliance of material with specification requirements shall be executed in accordance with Section 01 33 00 SUBMITTAL PROCEDURES. Each certificate shall be signed by an official authorized to certify on behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies.

Certification shall not be construed as relieving the Contractor from furnishing satisfactory material, if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.22 PROCESS FOR OBTAINING CURRENT REQUIREMENTS OF THE U.S. ARMY CORPS OF

ENGINEERS SAFETY AND HEALTH REQUIREMENTS MANUAL (EM 385-1-1)

Contractors are required to comply with the latest version, and all posted changes, of the U.S. Army Corps of Engineers Safety and Health Requirements Manual in effect on the issue date of this solicitation. EM 385-1-1 version 2014 and changes are available on the Internet at http://www.publications.usace.army.mil/USACEPublications/EngineerManuals.aspx, Search for EM_385-1-1, then click on EM_385-1-1 2014 english version.

Prior to making an offer, offerors should check the referenced website for the latest changes. No separate payment will be made for compliance with the requirements of this paragraph, or for compliance with other safety requirements of the contract.

1.23 SAFETY SIGN

The Contractor shall fabricate, erect and maintain a safety sign at the site, as located by the Contracting Officer. The sign shall be erected as soon as practicable, but not later than 15 calendar days after the date established for commencement of work. The data required shall be current.

The safety sign shall meet the requirements specified in the U.S. Army Corps of Engineers Sign (USACES) Standards Manual, EP 310-1-6a and EP 310-1-6b. A copy of the sign standards manual is available for review at the office of the Vicksburg District Sign Program Manager and questions concerning manufacture and installation of the safety sign may be addressed to:

SECTION 01 00 00.00 09 Page 10

Vicksburg District Sign Program Manager (Aaron Posner)

ATTN: CEMVK-OD-MN

4155 Clay Street Vicksburg, MS 39183-3435 Telephone: (601) 631-5287

1.24 ACCIDENT PREVENTION PLAN

Refer to the Contract Clause ACCIDENT PREVENTION (Alternate I). Within 15 days after receipt of award of the contract, an Accident Prevention Plan shall be submitted to the Contracting Officer for review and acceptance.

The plan shall be prepared as specified in Appendix A, "Minimum Basic Outline for Accident Prevention Plans" of EM 385-1-1. In addition to the requirements listed, the Contractor shall also submit the required information on the forms outlined below, which can be found on the Vicksburg District Construction Division home page, http://www.mvk.usace.army.mil/Missions/EngineeringandConstructionDivision.aspx, click on Construction Services Branch, then click on Forms.

a. An executed LMV Form 358-R, "Administrative Plan".

b. An executed MVK Form 385-359-R, "Hazard Analysis" for each definable feature of work.

c. When marine plant and equipment are in use under a contract, the method of fuel oil transfer shall be submitted on LMV Form 414R, "Fuel Oil Transfer-Floating Plant". (Refer to 33 CFR 156 .)

d. The Contractor shall not commence physical work at the site until the plan has been accepted by the Contracting Officer, or his authorized representative. At the Contracting Officer's discretion, the Contractor may submit his Hazard Analysis only for the first phase of construction provided that it is accompanied by an outline of the remaining phases of construction. All remaining phases shall be submitted and accepted prior to the beginning of work in each phase.

Also, refer to Section 1, "Program Management", paragraph 01.B, "Indoctrination and Training" of EM 385-1-1.

1.25 DAILY INSPECTIONS

Refer to Section 01 45 04.00 09 CONTRACTOR QUALITY CONTROL and the Contract Clause INSPECTION OF CONSTRUCTION. The Contractor shall perform daily safety inspections and record them on the forms approved by the Contracting Officer. Reports of daily inspections shall be maintained at the job site.

The reports shall be records of the daily inspections and resulting actions. As a minimum each report shall include the following:

a. Phase(s) of construction underway during the inspection.

b. Locations or areas inspections were made.

c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.

1.26 ACCIDENT INVESTIGATIONS AND REPORTING

Refer to EM 385-1-1, Section 1, "Program Management", paragraph 01.D, "Accident Reporting and Recordkeeping". Accidents shall be investigated

SECTION 01 00 00.00 09 Page 11 and reports completed by the immediate supervisor of the employee(s) involved and reported in writing to the Contracting Officer or his representative within one working day after the accident occurs.

1.27 MACHINERY AND MECHANIZED EQUIPMENT

Machinery and mechanized equipment used under this contract shall comply with the following:

a. When mechanized equipment is operated on floating plant, the Contractor shall provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front-end loaders, bulldozers, trucks (both on- and off-road), backhoes, hydraulic excavators (track hoes), and similar equipment. If the Contractor plans to use such equipment on floating plant, an activity hazard analysis must be developed for this feature of work. The plan must include a detailed explanation of the type or types of physical barriers, curbs, structures, etc., which will be incorporated to protect the operator and prevent the equipment from entering the water.

Nonstructural warning devices may be considered for situations where the use of structural barriers is determined to be impracticable. The activity hazard analysis must thoroughly address the procedure and be submitted to the Corps for review and acceptance prior to start of this feature of work.

b. The stability of crawler, truck, and wheel-mounted cranes shall be assured.

(1) The manufacturer's load-rating chart may be used to determine the maximum allowable working load for each particular crane's boom angle provided a test load, with a boom angle of 20 degrees, confirms the manufacturer's load-rating table.

(2) Stability tests are required if:

(i) there is no manufacturer's load-rating chart securely fixed to the operator's cab;

(ii) there has been a change in boom or other structural member;

or

(iii) there has been a change in the counterweight.

The test shall consist of lifting a load with the boom in the least stable undercarriage position and at an angle of 20 degrees above the horizontal. The test shall be conducted under close supervision on a firm, level surface. The load that tilts the machine shall be identified as the test load. The test load moment (in ft-lbs) shall then be calculated by multiplying the horizontal distance (in feet) from the center of rotation of the machine to the test load, times the test load (in lbs).

Three-fourths of this test-load moment shall then be used to compute the maximum allowable operating loads for the boom at 20, 40, 60, and 80 degrees above horizontal. From these maximum allowable operating loads, curve shall be plotted and posted in the cab of the machine in sight of the operator. These values shall not be exceeded except in the performance test described below. The test load shall never exceed 100 percent of the

SECTION 01 00 00.00 09 Page 12 manufacturer's maximum rated capacity.

(3) In lieu of the test and computations above, the crane may be load tested for stability at each of the four boom positions listed above.

c. Performance tests shall be performed in accordance with Section 18.G, "Machinery and Mechanized Equipment" of EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual, except as specified below. Performance tests shall be conducted after each stability test, when the crane is placed in service on a project, and at least every 12 months.

(1) When conducting a performance load test which is required of a new crane or a crane in which load sustaining parts have been altered, replaced, or repaired (excluding replacement of the rope), the test load shall be as specified in ASME/ANSI B30 Series. That is, for overhead, gantry, portal, pillar, tower, monorail, and underhung cranes, the test load shall not exceed 125 percent of the manufacturer's load rating capacity chart at the configuration of the test; and for hammerhead tower, mobile, and floating cranes and boom trucks, the test load shall not exceed 110 percent of the manufacturer's load rating capacity chart at the configuration of the test.

(2) When conducting a performance load test which is required because a crane is reconfigured, or reassembled after disassembly, or because the crane requires an annual load test, the test loads shall not exceed 100 percent of the manufacturer's load rating capacity chart at the configuration of the test.

(3) All load tests are required to be conducted in accordance with the manufacturer's recommendations.

d. Inspections shall be made which will ensure a safe and economical operation of both cranes and draglines with inspection documented.

Copies of the inspections and tests shall be available at the job site for review. All stability and performance tests on cranes and all complete dragline inspections shall be witnessed by the Contracting Officer or his authorized representative.

e. A complete dragline inspection shall be made:

(1) at least annually;

(2) prior to the dragline being placed in operation; and

(3) after the dragline has been out of service for more than 6 months.

f. All heavy equipment moved onto the worksite shall be inspected for compliance with this contract. The CEMVK-SO Inspection forms attached at the end of this section shall be completed by the Contractor. All completed forms, including abatement schedule of any violations, shall be maintained at the job site for continued review and update as needed.

1.28 VEHICLE WEIGHT LIMITATIONS

Vehicle weight limitations for operation on rural roads and bridges may

SECTION 01 00 00.00 09 Page 13 affect the prosecution of work in this contract. The Contractor will be responsible for obtaining all necessary licenses and permits in accordance with the Contract Clause PERMITS AND RESPONSIBILITIES. Current information regarding road and bridge weight limits may be obtained by contacting the Louisiana Department of Transportation and Development and the police jury for the parishes through which equipment and materials will be transported as a result of this contract.

1.29 PUBLIC AND PRIVATE UTILITIES

a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not remove or disturb any public or private utilities and structures. Such removals, alterations, and relocations, where necessary, will be made by others.

The locations, if any, shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.

b. The attention of the Contractor is directed to the possibility that he may encounter, within the right-of-way limits, utilities, some of which may be buried, and the existence of which is presently not known.

Should any such utilities be encountered, the Contractor shall immediately notify the Contracting Officer so that he may determine whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required, and an equitable adjustment will be made in accordance with the Contract Clause CHANGES. In event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latter's removal, alteration, or relocation operations in accordance with the Contract Clause OTHER CONTRACTS.

c. The Contractor shall notify the below at least 14 days (2 weeks) prior to any operations in the vicinity.

Louisiana OneCallPhone: 811 (call from a land line for proper location ID) www.laonecall.com

1.30 DAMAGE TO WORK

a. The responsibility for damage to any part of the permanent work shall be as set forth in the Contract Clause PERMITS AND RESPONSIBILITIES. However, if, in the judgment of the Contracting Officer, any part of the permanent work performed by the Contractor is damaged by flood (see Section 00 80 00.00 09 SPECIAL CONTRACT REQUIREMENTS, paragraph PHYSICAL DATA, subparagraph FLOODS) or earthquake, which damage is not due to the failure of the Contractor to take reasonable precautions or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make repairs as ordered by the Contracting Officer and full compensation for such repairs to permanent work will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, for any part of such damaged permanent work, there is no applicable contract unit or lump sum price, then an equitable adjustment pursuant to the Contract Clause CHANGES will be made as full compensation for the repairs for that part of the permanent work for which there is no

SECTION 01 00 00.00 09 Page 14 applicable contract unit or lump sum price.

b. Except as herein provided, damage to all work (including temporary construction), utilities, materials, equipment, and plant shall be repaired to the satisfaction of the Contracting Officer, at the Contractor's expense, regardless of the cause of such damage.

1.31 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER

a. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the Contract Clause DEFAULT (FIXED PRICE CONSTRUCTION). In order for the Contracting Officer to award a time extension under this paragraph, the following conditions must be satisfied:

(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.

(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.

b. The following schedule of monthly anticipated adverse weather delays is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The Contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities.

MONTHLY ANTICIPATED ADVERSE WEATHER DELAY

WORK DAYS BASED ON FIVE (5) DAY WORK WEEK

JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

(3) (3) (4) (3) (3) (3) (3) (3) (2) (2) (3) (4)

c. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph b, above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the Contract Clause DEFAULT

(FIXED PRICE CONSTRUCTION).

1.32 CONTROL OF ACCESS TO CONSTRUCTION AREAS

a. This paragraph supplements the Contract Clauses PERMITS AND RESPONSIBILITIES and OPERATIONS AND STORAGE AREAS.

SECTION 01 00 00.00 09 Page 15

b. It shall be the responsibility of the Contractor to prevent possible injury to visitors to the project site. Only personnel engaged in contract work and others authorized by the Contracting Officer shall be permitted to enter into the construction areas.

Suitable barriers, warning signs and directives shall be placed by the Contractor to direct persons not engaged in the work away from the areas of danger. The Contractor shall be responsible for effective enforcement of this paragraph during the period of this contract.

1.33 MAINTENANCE OF TRAFFIC

a. The Contractor shall conduct his operations in such manner as to offer the least possible obstruction to the safe and satisfactory movement of traffic over the existing roads during the life of the contract.

b. The Contractor shall be responsible for providing, erecting, maintaining, and removal of all traffic signs, barricades, and other traffic control devices necessary for maintenance of traffic. See also paragraph ACCIDENT PREVENTION PLAN of these specifications and the Contract Clause ACCIDENT PREVENTION.

c. All barricades, warning signs, lights, temporary signals, other devices, flagmen, and signaling devices shall meet or exceed the minimum requirements of Louisiana DOTD, Manual On Uniform Traffic Control Devices See EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Manual, Section 8, paragraph 08.C, "Traffic Control". The Contractor is responsible for the protection, maintenance, and replacement of all existing signs, route markers, traffic control signals, and other traffic control features during the life of this contract.

d. Prior to the commencement of construction operations the Contractor shall submit for the acceptance of the Contracting Officer, complete details of his proposed plans for the maintenance of traffic and access through the construction area.

e. The requirements of this paragraph shall be met by the Contractor at no additional expense to the Government.

1.34 HARBOR MAINTENANCE FEE

a. Offerors or bidders contemplating use of U.S. ports in the performance of contract are subject to paying a harbor maintenance fee on cargo. Federal law establishes an ad valorem port use fee on commercial cargo imported into or exported from various U.S. ports.

The fee is 0.125 percent (0.00125). Cargo to be used in performing work under contracts with the U.S. Government is not exempt from the fee, although certain exemptions do exist. Offerors are responsible for ensuring that the applicable fee and associated costs are taken into consideration in the preparation of their offers. Failure to pay the harbor maintenance fee may result in assessment of penalties by the Customs Service.

b. The statute is at Title 26 U.S. Code section 4461 and 4462.

Department of Treasury Customs Service regulations implementing the statute, including a list of ports subject to the fee, are found at 19 CFR 24.24 , Harbor Maintenance Fee. Additional information may be obtained from local U.S. Customs Service Offices or by writing to the

SECTION 01 00 00.00 09 Page 16

Director, Budget Division, Office of Finance, Room 6328, U.S. Customs Service, 1301 Constitution Avenue, N.W., Washington, D.C. 20229.

1.35 PERMISSIBLE HOURS OF OPERATION

No work shall be performed at the job site between the hours of 7 p.m.