A22_Amendment_0005_W912EE-17-B-0011.pdf

PDF 590 KB Posted

Attached to
FC/MR&T WEST BANK, MISSISSIPPI RIVER LEVEES GAINES LANDING, CHICOT COUNTY, ARKANSAS SEEPAGE BERMS ITEM 546-R
Solicitation number
W912EE17B0011
Issued by

About this file

Amendment 0005

View the file

Other files

File Type Posted
A22_Amendment_0007_W912EE-17-B-0011.pdf PDF
A22_W912EE17B00110006.pdf PDF
A22_Amendment_0004_W912EE-17-B-0011.pdf PDF
A22_Amendment_0003_W912EE-17-B-0011.pdf PDF
A22_Amendment_0002_W912EE-17-B-0011.pdf PDF
A22_Amendment_0001_W912EE17B00110001.pdf PDF
17b0011.pdf PDF
SPECS.pdf PDF
385-1-1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Reference Solicitation No. W912EE17B0011, for FC/MR&T West Bank Mississippi River Levees, Gaines Landing, Chicot County, Arkansas, Seepage Berms, Item 546-R, is amended as follow s:

SEE CONTINUATION PAGE FOR SUMMARY OF CHANGES.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 03-Aug-2017

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912EE17B0011

X 9B. DATED (SEE ITEM 11)

06-Jul-2017

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

03-Aug-2017

CODE

VICKSBURG CONTRACTING OFFICE

4155 CLAY ST

VICKSBURG MS 39183-3435

W912EE 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912EE17B0011

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SPECIFICATIONS: Section 31 24 00.00 09 is revised and replaced.

All current bidder inquiries as of 03 August 2017 @ 02:30 p.m. are added by this amendment.

Pages added by this amendment have the notation “Added by Amendment 0005” at the bottom of the page.

Specifications revised by this amendment have the notation "Revised by Amendment 0005" at the bottom of the page. Text added by this amendment is shown as underlined. Text deleted by this amendment is shown as overstruck.

W912EE-17-B-0011

SECTION TABLE OF CONTENTS

DIVISION 31 - EARTHWORK

SECTION 31 24 00.00 09

EMBANKMENT

PART 1 GENERAL

1.1 REFERENCES

PART 2 PRODUCTS

2.1 EMBANKMENT MATERIALS

2.1.1 General

2.1.2 Unsuitable Materials

2.1.3 Frozen Materials

PART 3 EXECUTION

3.1 EMBANKMENT FOUNDATION PREPARATION

3.1.1 General

3.1.2 Drainage

3.1.3 Frozen Ground

3.2 EMBANKMENT CONSTRUCTION

3.2.1 Uncompacted Embankment

3.3 CROSS SECTIONS

3.3.1 Berm Embankment Sections

3.3.2 Berms

3.4 HAUL ROADS

3.4.1 Haul Roads

3.4.1.1 Location

3.4.1.2 Temporary Roads

3.5 RUNWAYS

3.5.1 Temporary Runways

3.5.2 Reconstruction of Gravel Surfacing

3.6 GRADE TOLERANCES

3.6.1 Berm Embankment

3.7 SETTLEMENT OF FOUNDATION

3.7.1 Sudden Failure

3.7.2 Omitting Work

3.8 FIELD TESTING CONTROL

-- End of Section Table of Contents --

SECTION 31 24 00.00 09 Page 1 Revised By Amendment 0005

SECTION 31 24 00.00 09

EMBANKMENT

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM D1556 (2007) Density and Unit Weight of Soil in Place by the Sand-Cone Method

ASTM D2216 (2010) Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass

ASTM D2487 (2011) Soils for Engineering Purposes (Unified Soil Classification System)

ASTM D4643 (2008) Determination of Water (Moisture) Content of Soil by the Microwave Oven Method

ASTM D6938 (2015) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)

PART 2 PRODUCTS

2.1 EMBANKMENT MATERIALS

2.1.1 General

The berm embankment shall be constructed of earth obtained from the borrow area excavation as prescribed in Section 31 23 00.00 09 EXCAVATION and to the extent shown on the drawings. Contractor furnished borrow areas will not be permitted. The berm embankment shall be constructed of earth that is free from unsuitable and frozen materials as defined in paragraphs UNSUITABLE MATERIALS and FROZEN MATERIALS. Material classified in accordance with ASTM D2487 as gravels (GW, GP, GM) and sands (SW, SP, SM) shall not be used for any required embankment construction unless suitably blended with less pervious material to the extent that it no longer classifies as these materials.

2.1.2 Unsuitable Materials

Materials which are classified as unsuitable for berm embankment are defined as masses of organic matter, sticks, branches, roots, and other debris. As earth from the designated borrow area may contain excessive amounts of wood, isolated pieces of wood will not be considered objectionable in the embankment provided their length does not exceed 1

SECTION 31 24 00.00 09 Page 2 foot, their cross-sectional area is less than 4 square inches, and they are distributed throughout the fill. Not more than 1 percent (by volume) of objectionable material shall be contained in the earth material placed in each cubic yard of the berm section. Pockets and/or zones of wood shall not be placed in the embankment.

2.1.3 Frozen Materials

Under no circumstances shall frozen earth, snow, or ice be placed in any required embankment.

PART 3 EXECUTION

3.1 EMBANKMENT FOUNDATION PREPARATION

3.1.1 General

After clearing and grubbing and any required excavation of the berm embankment, test areas and other similar cavities and depressions shall be broken down to flatten out the slopes. The entire earth surface on or against which semicompacted fill is to be placed shall be thoroughly broken to a depth of 6 inches. If for any cause, this broken surface becomes compacted in such a manner that, in the opinion of the Contracting Officer, a plane of seepage or weakness might be induced, it shall again be adequately scarified before depositing material thereon. All of the foregoing work shall be completed at least 200 feet in advance of the berm embankment construction.

3.1.2 Drainage

The foundation receiving fill, and all partially completed fill shall be kept thoroughly drained. Drainage to areas outside the right-of-way limits will be allowed only after the Contractor has obtained rights-of-way for such drainage in accordance with Section 01 00 00.00 09 GENERAL CONTRACT REQUIREMENTS, paragraph RIGHTS-OF-WAY.

3.1.3 Frozen Ground

No fill shall be placed upon frozen ground.

3.2 EMBANKMENT CONSTRUCTION

3.2.1 Uncompacted Embankment

The location and extent of the uncompacted embankment shall be as shown on the drawings. Uncompacted embankment shall be placed in horizontal layers not exceeding 3 feet in thickness. The layers shall be uniformly spread, distributed, and otherwise manipulated during placement to such an extent that individual loads of material deposited on the fill will not remain intact, and large, open voids in the fill will be eliminated. Layers shall be started full out to the slope stakes, and shall be carried in lifts horizontal and parallel to the centerline with sufficient crown or slope to provide satisfactory drainage during construction. Lifts shall be placed in a manner which prevents shrinkage cracks and open voids from developing in previously placed lifts. Where material must be placed in water, it shall be dumped therein until it reaches an elevation 1 foot above the water surface, or until a stable fill surface is obtained before layer construction will be required. The material deposited under water shall be placed in such a manner to ensure that any soft material will be forced

SECTION 31 24 00.00 09 Page 3 progressively outward from the section and not be trapped within the base of the embankment.

3.3 CROSS SECTIONS

3.3.1 Berm Embankment Sections

Unless otherwise specified, the dimensions and slopes shall conform to the applicable gross grade and cross sections shown on the drawings, within allowable tolerance.

3.3.2 Berms

Berms shall be constructed at the locations and to the grade and cross section shown on the drawings.

3.4 HAUL ROADS

3.4.1 Haul Roads

3.4.1.1 Location

The Contractor's haul roads within the rights-of-way shall be constructed as necessary to perform the required work. They shall be designed to maintain the intended traffic, to be free draining and shall be constructed by placement of fill as specified in paragraph SEMICOMPACTED EMBANKMENT and shall be maintained in good condition throughout the contract period. All haul roads shall be removed after construction has been completed. No separate payment will be made for this work, and all costs therefore shall be included in the applicable bid items as listed in the Bidding Schedule.

3.4.1.2 Temporary Roads

At locations where existing roads are destroyed because of the work required under this contract, the Contractor shall provide temporary roads to give access during the construction period. The temporary roads shall be constructed by placement of fill as specified in paragraph SEMICOMPACTED EMBANKMENT. The temporary roads shall be removed after permanent access has been provided. No separate payment will be made for this work.

3.5 RUNWAYS

3.5.1 Temporary Runways

Where material is hauled over an existing levee for construction, the Contractor at his expense will be permitted to construct temporary runways over the levee by the addition of material to the levee cross section. In the construction of runways, the Contractor will not be permitted to cut or degrade the existing levee. As soon as any runway has served the purpose for which it was constructed, the levee shall be restored to the prescribed grade and section, the crown resurfaced and the disturbed areas dressed, fertilized, and turfed as specified in Section 32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT, all at no additional cost to the Government. Material used in the construction of the approach ramps of the runways shall be removed and may be used for borrow, if suitable. If not used for borrow, the material shall be disposed of by placing in abandoned portions of the borrow areas, at no additional cost to the Government. No section of the levee shall be degraded or weakened to provide runways.

SECTION 31 24 00.00 09 Page 4

3.5.2 Reconstruction of Gravel Surfacing

The Contractor shall, at his own expense, reconstruct the road surfacing where it has been damaged by runways over the existing levee, including areas damaged by detouring traffic around the runways. The surfacing shall be reconstructed as directed with the reconstruction of the surfacing conforming to the requirements of Section 32 15 00.00 09 LEVEE SURFACING.

3.6 GRADE TOLERANCES

3.6.1 Berm Embankment

All berm embankment shall be constructed to the grade and section shown on the drawings. For uncompacted berm fill, at all points, a tolerance of 3/10 of 1 foot above or below the grades and cross section shown will be permitted in the final dressing provided that there are no abrupt humps or depressions in surfaces.

3.7 SETTLEMENT OF FOUNDATION

3.7.1 Sudden Failure

In clearly established cases of sudden failure of the foundation, either where no provision has been made for the measurement of settlement or where settlement measuring devices have been installed, but the nature of settlement is such as to destroy their utility, the method of correction will be determined by the Contracting Officer. In case the sudden settlement is caused through the fault or negligence of the Contractor, the prescribed corrective operations shall be performed at no additional cost to the Government. In case the sudden settlement is not caused through the fault or negligence of the Contractor the corrective operations will be paid for in accordance with the Contract Clause CHANGES.

3.7.2 Omitting Work

Where settlement of the foundation develops to such an extent as to make it inadvisable, in the opinion of the Contracting Officer, to continue to add material, and advisable in his opinion, to postpone until a considerably later date all attempts to bring that portion of the embankment to full grade and cross section, the Contracting Officer shall have the right to omit further work on that portion of the embankment and to accept it as complete. In the event a portion of the embankment is omitted under the provisions of this paragraph, measurement and payment for the portion of the embankment accepted as complete will be based on the original ground survey, an as-constructed survey, and the settlement provisions of the contract. Payment will be made at the contract unit price for the embankment.

3.8 FIELD TESTING CONTROL

Testing shall be the responsibility of the Contractor and shall be performed by an approved Corps of Engineers validated commercial testing .

Field density and moisture content tests shall be performed on every 1,000 cubic yards of semicompacted material placed. Should conditions of lifts previously tested and accepted change and/or become suspect to meeting specifications, retests and potential reworking will be required. The Contractor shall retest after rainfall on the previously tested areas unless deemed unnecessary by the Contracting Officer's Representative.

SECTION 31 24 00.00 09 Page 5

The Contractor shall use borrow source location and Atterberg Limit results to assist in selecting the appropriate compaction control curve. Atterberg Limits shall be performed on every tenth moisture/density field test.

Field in-place density shall be determined in accordance with ASTM D6938 or ASTM D1556. If the nuclear method is used for field density testing, the sand cone method shall be used to verify the accuracy of the nuclear method. A minimum of 5 comparison tests shall be conducted at the start of construction. If the nuclear method value is within 3 percentage points of the sand cone method value, no correction of the nuclear wet density is required. (EXAMPLE: Sand Cone Results = 80, then Nuclear Method Results = 77 - 83). The nuclear method shall be verified throughout the project at a rate of at least one sand cone for every 10 nuclear tests.

Moisture content tests shall be in accordance with ASTM D2216 or ASTM D4643 or ASTM D6938. If the nuclear or microwave method is used for moisture determination, the oven dry method shall be used to verify the accuracy of these methods. A minimum of 5 comparison tests shall be performed at the start of construction. If these methods are within 3 percentage points of the oven dry method, no correction of the moisture is required. The nuclear and microwave moisture methods shall be verified by the oven moisture at a rate of at least one oven moisture for every 10 nuclear and/or microwave tests.

For nuclear methods, calibration checks of both the density and moisture gages shall be made at the beginning of a job on each different type of material encountered and at intervals as directed.

The Contractor shall prepare a QC testing report as work progresses to be submitted at completion of the project. The report shall include all Proctor control curves and field testing control data, comparison testing, calibrations, and individual field test reports with coordinates and elevations of tests. The report shall also include in spreadsheet format all test results such that any failed test can be easily cross referenced to passing retests. Lift charts shall be maintained throughout the project and included in the final report. The charts shall include a profile along the levee indicating various lifts placed daily. The location of field tests and borrow source general location shall be included on the lift charts. The Contractor shall submit three copies daily of control tests and reports as well as records of corrective action taken in accordance with Section 01 45 04.00 09 CONTRACTOR QUALITY CONTROL.

-- End of Section --

SECTION 31 24 00.00 09 Page 6

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Bid Inquiry Contractor Report All Inquiries

Project: WBMRL, Item 546-R, Gaines Landing Seepage Berms Review: Bidder Inquiry W912EE-17-B-0011 (00001) (sorted by CommentID ) Displaying 14 inquiries.

Id Discipline Sheet Detail Spec 7057220 Construction Management All All Bidding schedule Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

We request the government's breakdown of the lump sum bid items.

On: Jul 10 2017.

Government Response. . Estimated quantities provided to requestor. On: Jul 11 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7059173 Civil Page 3 section00100 00100 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

We request the government's breakdown of the lump sum bid items.

On: Jul 11 2017.

Government Response. . Estimated quantities provided to requestor. On: Jul 12 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7059258 Contracting Contracting Contracting Contracting Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Request for Estimated Quanities

On: Jul 11 2017.

Government Response. . Estimated quantities provided to requestor. On: Jul 12 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7060346 Civil 1 1 1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please send a lump sum breakdown

On: Jul 12 2017.

Government Response. . Estimated quantities provided to requestor. On: Jul 13 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7060995 Construction Phasing All All Speical Clauses and Clearingand Grubbing

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The Special clause notifies that the notice to proceed with construction will be issued after receipt and Government verification of the required performance and payment bonds. These are required just after bid opening which is schedule in August. However under the clearing grubbing specification, The landowners have reserved the right to harvest timber (timber reservation) within the rights-of-way until October 01, 2017, on which date the timber reservation is to be considered fulfilled. The Notice to Proceed will not be issued prior to the date provided for the fulfillment of the timber reservation. There appears to be conflict. Sites visit have to performed in July, timber may or may not be removed. How is this to be bid?

On: Jul 12 2017.

Page 1 of 4ProjNet: Logged In User

8/3/2017https://www.projnet.org/projnet/binKornHome/index.cfm?strKornCob=BicPublicReportAll...

"Added by Amendment 0005"

Government Response. . The Notice to Proceed will be issued in accordance with the Timber Reservation paragraph "Merchantable Timber". An amendment will be issued. On: Jul 19 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7062098 Contracting 00100 contracting construction Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

We request the government's breakdown of the lump sum bid items.

On: Jul 13 2017.

Government Response. . Estimated quantities provided to requestor. On: Jul 13 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7068850 Contracting 1 1 1 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

PLEASE SEND ESTIMATED QUANTITIES.

On: Jul 18 2017.

Government Response. . Estimated quantities provided to requestor. On: Jul 19 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7078312 Construction Management All all clering and grubbing timber reservation

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The Government has control of the process and knowledge of the situation directly or thru their customer. This information is not being provided. In this clause the government shifts their responsibility and risk to the contractor based on a board disclaiming statement. How do does the government expect the contractor to make a bid on event that may or may not happen? There could be significant impact cost and time based how the area is timber.

On: Jul 25 2017.

Government Response. . Please see amendment 0001 for Contract Clause. SITE VISIT (CONSTRUCTION)(FEB 1995) See 52.236-27 "...Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed." On: Jul 28 2017 Government Response. . This new text supercedes ALL previous replies.

Landowners have the right to harvest timber within the rights-of-way until the date given in the solicitation's technical specifications. It is likely that the merchantable timber within the areas required to be cleared and grubbed will be reduced to stumps and scattered debris after the award date and prior to the issue of the Notice to Proceed. In addition, deep ruts from logging equipment may exist. No payment will be made for any additional costs the Contractor may incur due to the timber harvesting operation. Therefore, all costs shall be included in the contract lump sum price for "Clearing and Grubbing". Please refer to Section 31 11

00.00 09 "Clearing and Grubbing", paragraph 3.2.2 for additional information. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7085225 Contracting Contracting Contracting AMEND. 0002 26-JUL-2017 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

The amend.0002 26-JUL-2017, has a "Revised by Amendment 0003" on all pages and on para. 14 Description of Work: has wrong information, this needs to be corrected.

On: Jul 28 2017.

Government Response. . An amendment will be issued to address the error. On: Jul 31 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7087090 Other Quantity

Page 2 of 4ProjNet: Logged In User

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

We request the estimated quantity for the lump sum items

On: Jul 31 2017.

Government Response. . Estimated quantities provided to requestor. On: Aug 01 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7087237 Civil All Excavation Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

1. Does the Government have the volume of dirt calculated to build the haul road from the borrow area and across the slew/swamp to the levee ROW?

2. Does the Government have a standard for the ramp to be constructed up and over the levee to gain access to the borrow area?

3. Is the access ramp and haul road to remain in place or to be removed once construction is complete?

On: Jul 31 2017.

Government Response. . 1. The Haul Road dimensions are 60' wide at El. 130.

2. The following verbiage will be added to the specs for the ramp/runway by amendment 0005:

"3.4.3 Runways

3.4.3.1 Temporary Runways

Where material is hauled over an existing levee for construction, the Contractor at his expense will be permitted to construct temporary runways over the levee by the addition of material to the levee cross section. In the construction of runways, the Contractor will not be permitted to cut or degrade the existing levee. As soon as any runway has served the purpose for which it was constructed, the levee shall be restored to the prescribed grade and section, the crown resurfaced and the disturbed areas dressed, fertilized, and turfed as specified in Section 32 92 00.00 09 EXISTING TURF MAINTENANCE AND NEW TURF ESTABLISHMENT, all at no additional cost to the Government. Material used in the construction of the approach ramps of the runways shall be removed and may be used for borrow, if suitable. If not used for borrow, the material shall be disposed of by placing in abandoned portions of the borrow areas, at no additional cost to the Government. No section of the levee shall be degraded or weakened to provide runways.

3.4.3.3 Reconstruction of Gravel Surfacing

The Contractor shall, at his own expense, reconstruct the road surfacing where it has been damaged by runways over the existing levee, including areas damaged by detouring traffic around the runways. The surfacing shall be reconstructed as directed with the reconstruction of the surfacing conforming to the requirements of Section 32 15 00.00 09 LEVEE SURFACING."

3. The ramp and haul road will be removed once construction is completed. This verbiage will be added to the specs for the ramp/runway by amendment 0005: On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7088058 Cost Engineering Page 2 01 22 00.00 09 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Please send estimated quanities.

On: Jul 31 2017.

Government Response. . Estimated quantities provided to requestor. On: Aug 01 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7089833 Contracting Amendment 3

Page 3 of 4ProjNet: Logged In User

Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

Page 10 of amendment 3 states that NTP will not be issued until the fulfillment of the timber reservation. Is someone planning to clear cut the timber? As contractors we need to know if we are digging stumps on top of a loggers mess or clearing standing timber to be able to bid the job. We also need to know if this is to happen this month, this year or next year? This is a dirt job and time is of the essence on whether we do the job right now or next summer.

On: Aug 01 2017.

Government Response. . Landowners have the right to harvest timber within the rights-of-way until the date given in the solicitation's technical specifications. It is likely that the merchantable timber within the areas required to be cleared and grubbed will be reduced to stumps and scattered debris after the award date and prior to the issue of the Notice to Proceed. In addition, deep ruts from logging equipment may exist. No payment will be made for any additional costs the Contractor may incur due to the timber harvesting operation. Therefore, all costs shall be included in the contract lump sum price for "Clearing and Grubbing". Please refer to Section 31 11 00.00 09 "Clearing and Grubbing", paragraph 3.2.2 for additional information. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

7093074 Contracting page 3 00100 Comment Classification: Unclassified\\For Official Use Only (U\\FOUO)

We request the government's breakdown of the lump sum bid items.

On: Aug 03 2017.

Government Response. . Estimated quantities provided to requestor. On: Aug 03 2017 Current Request Status: Request Closed

Information for this report is procurement sensitive.

Report Complete

UNCLASSIFIED\\FOR OFFICIAL USE ONLY

Patent 11/892,984 ProjNet property of ERDC since 2004.

Page 4 of 4ProjNet: Logged In User