| Name: | Scheduler Services Support |
| RFP# | W912DY21R0044 |
No. Area/Spec Section/Number Question Response
| 1 | General | Is the contractor overseeing all 130-200 programs via input from those individual programs? | No, the contractor is not overseeing all 130-200 programs. The contractor will support project manager(s) who collectively may have 130-200 projects. | ||
| 2 | General | How is EVM applied within the ISPM Directorate? Does each project produce individual IPMDAR content? | Each project is tracked independently, and progress is monitored based on work breakdown structure/task advancement versus contractor advancement and billing. Yes, each project produces Integrated Program Management Data and Analysis Report (IPMDAR) content. | ||
| 3 | Section L | Please confirm if Volume 3 should be submitted. It is listed as a solicitation document, however the description states that this Volume is not needed for this solicitation "Volume 3, Past Performance the Offeror shall not submit any information for the past performance factor ". Please clarify of Volume 3 is required for this solicitation. | Volume 3 will be submitted. An amendment will be disseminated for clarification. The Government will evaluate this factor based on recent past performance of relevant size and complexity to the Government’s requirement. To be recent, previous contracts must be ongoing, or must have been performed during the last five (5) years from the date of issuance of this solicitation. To be relevant, the previous contracts must be similar in size, scope and complexity. You must submit a minimum of (3) projects with your proposal. | ||
| 4 | The solicitation states for the Price Volume: "Labor rates contained in proposals shall not exceed the approved Department of Labor rates for this category of work." Can you please indicate where we can find the approved DOL rates for this category of work? | Labor rates contained in the proposal shall meet or exceed the approved Department of Labor rates for this category of work. Reference INSTRUCTION TO OFFERORS, Number 6., Wage Determination, for labor rate direction. | |||
| 5 | General | Of the 130-200 projects to be sustain / supported, does each project represent at least one (1) of the 30 programs within the ISPM Directorate? | Yes. Each project may represent at least one (1) of the 30 programs within the ISPM Directorate. | ||
| 6 | PWS | 6.7 Deliverable | “Conduct PM training with the COR and PDT…”, can the Government provide an estimated number of personnel within the PDT to be trained? | Anticipate up to 75 people within the PDT(s) to be trained over the course of 3 training sessions. | |
| 7 | General | How many training sessions are required during the period of performance? | There is one (1) training session within the base six (6) month period and two (2) training sessions within the 6-month option period | ||
| 8 | General | Will HNC be willing to extend the proposal due date? | Yes. All proposals shall be due no later than 27 August 2021, 3:00 PM, Central Time | ||
| 9 | General | Does this mean a firm wishing to submit a proposal must be certified by the SBA as a HubZone or can the firm just be located within a HubZone area? | The firm must be certified as a HUBZone by the SBA. | ||
| 10 | General | Will the Government issue NTP before or after the 10 -15 business days it typically takes the Government to issues access cards? | The Government will not issue a NTP. Your period of performance starts from the award “Effective Date.” The potential firm should factor this into their proposed work schedule. | ||
| 11 | General | Does the Government request one lump sum FFP amount for the base six (6) month-period and separate lump sum FFP amount for the one (1) optional six (6) month-period? If so, how will price be evaluated for fairness and reasonableness for providing the best value to the Government, based on a single lump sum amount? | The Government provided clarification in Amendment 01 disseminated on 12 August 2021. The file format in Amendment 01 is to be used for the base period and six-month period. The Price Sheet format will aid in proposal evaluation. | ||
| 12 | PWS | 3.1.5 | What constitutes “all training required’? Does this include training related to specific job roles, or training specifically for scheduling and project management roles? | “All training required” for the contract denotes any training required needed to access this specific contract. For example, if employee training is required for a Common Access Card (CAC) to support this requirement, it can be assessed to this Government. If there is training that the firm normally provides as part of its routine and reoccurring basis such as “Ethics” it cannot be assessed to the Government. | |
| 13 | General | Amendment 01 | Page 2. The Amended Solicitation states “Deadline for contractor questions is 10:00am, Tuesday, 17 August 2021”, but the letter uploaded to SAM states the deadline as Monday, 16 August 2021. | The deadline was the latter of the two, 10:00am Tuesday, 17 August 2021. | |
| 14 | PWS | 3.3.1.1 | Section 3.3.1.1 indicates there is one key person, a Scheduler. Does the government expect that the work will be performed by one person, or is the Scheduler the only resume that is considered key personnel? | This solicitation is a request for proposed contractor services. The proposal should indicate technical qualifications and labor category mix in order to accomplish this requirement, as well as methodology to provide proposed services. However, the Scheduler is the only resume that is considered key personnel. | |
| 15 | PWS | 3.3.1.1 | Section 3.3.1.1 specifies that the Scheduler shall have 5 years experience with USACE. Our company currently has highly qualified schedulers with Army experience, but not specifically with the Army Corp of Engineers. Would the government consider removing the requirement that the Scheduler shall have experience with USACE? | The USACE uses specialized enterprise systems that are particular to the agency. Due to the short duration of the period of performance, it is imperative to include USACE experience. | |
| 16 | PWS | 3.4 | Page 8. Section 3.4 lists “Contractor team” qualifications that include certifications not typically held by Schedulers. Would the government consider removing these certification requirements? | The RFP did not state certifications were for a Scheduler solely. The Government will not consider removing the requirement. | |
| 17 | PWS | Section 6.0 | Page 10. Section 6.0 Scope of Work does not include enough information for a bidder to determine the Level of Effort required to perform this work under a FFP contract, unless they are an incumbent. RFP states there are 130-200 projects, but does not describe the size or complexity of these projects. Would the government provide a more detailed description of the Scope of Work sufficient to support a FFP offer? | The RFP Performance Work Statement 2.0 Objective states “The objective of this requirement is to provide scheduling services and project management support for ISPM.” The size of projects range from ~$200,000 per year to in excess $20,000,000 per year. Projects include firm-fixed price, cost, or hybrid type contracts and range between Single Award Stand-Alone Contracts, Multiple Award Task Order Contract (MATOC) or Single Award Task Order Contracts (SATOC). In additon, projects range from six months to a five-year duration. Complexity of projects is deemed medium based on project management support, planning, and customer interaction. | |
| 18 | PWS | Section 2.0 | Is there an incumbent? If so, who is the incumbent? | No, there is not an incumbent. | |
| 19 | Section M | Eval Factors | Element 3, Tab C Experience section states a page limit of two pages for the experience narrative. Is that page limit for the entire project, or just for the narrative portion? | Page restrictions for Element 3 have been removed. | |
| 20 | Section M | Eval Factors | Element 3, Tab C Experience section. Would a follow-on contract be considered a separate project or can these two contracts be combined? | Each individual contract represents a separate project | |
| 21 | Section M | Eval Factors | Element 3, Tab C Experience section asks for Government POC. For a project where we are a subcontractor, does the government want us to give our prime contractor contracts person as the POC instead of a government POC? | For a project where you were the subcontractor, please identify the name of the prime contract, contractor, and what duties performed in support of the contract. | |
| 22 | Section M | Eval Factors | Element 3, Tab C Experience section states “The Government will assign the following adjectival ratings when evaluating Factor 1: Technical”. It appears that part of the paragraph is missing. Would the government provide the adjectival ratings that will be used for Factor 1? | Response 10: You are correct in your assumption that part of the paragraph is missing. An adjectival rating of “Outstanding,” “Good,” “ Acceptable,” “Marginal,” or “Unacceptable” will be assigned to Factor 1: Technical. The Outstanding description is “Proposal meeting requirements and indicates an exceptional approach and understanding of the requirements. Strengths far outweigh any weaknesses. Risk of unsuccessful performance is very low.” The Good description is “Proposal meets requirements and indicates a thorough approach and understanding of the requirements. Proposal contains strengths which outweigh any weaknesses. Risk of unsuccessful performance is low..” The Acceptable description is “Proposal meets requirements and indicates an adequate approach and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. Risk of unsuccessful performance is no worse than moderate.” The Marginal description is “Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high.” The Unacceptable description is “ Proposal does not clearly meet requirements and has not demonstrated an adequate approach and understanding of the requirements. The proposal has one or more weaknesses which are not offset by strengths. Risk of unsuccessful performance is high. Proposal does not meet requirements and contains one or more deficiencies. Proposal is un-awardable.” | |
| 23 | PWS | 6.0 | “Scheduling support services will sustain 130-200 projects within the ISPM Directorate.” | ||
| a. | What is the average amount of line items in these projects? | ||||
| b. | What is the average amount of line items that may be active each fiscal year? | a. The number of line items is unique to the acquisition methodology and can vary from project to project b. The number of line items active each fiscal year is unique to the acquisition methodology and can vary from project to project. | |||
| 24 | PWS | 6.6 | Are there existing templates for any or all of the program divisions? | No, existing templates do not exist. The acquisition templates produced will be used to standardize templates for supported program(s). | |
| 25 | PWS | 6.6 | Is HNC currently using a Dashboard application? If yes, what are they using? If not, is there an existing software that may be utilized to create a dashboard? | No, there is not an existing dashboard application. It is the responsibility of the contractor to produce a dashboard as a deliverable. | |
| 26 | PWS | 8.0 | The period of performance is 6-month base w/ a 6 months option; this timeline does not seem sufficient to successfully complete the deliverable list. Is HNC willing to extend the period of performance to a more realistic timeline? | No, HNC is not willing to extend the period of performance. |