DRAFT_PERFORMANCE_WORK_STATEMENT_8-22-18.pdf
PDF 116 KB Posted
- Attached to
- Facilities Reduction Program (FRP)
- Solicitation number
- W912DY-18-R-0063
About this file
This sources sought notice is seeking information from commercial demolition services firms to support the Facilities Reduction Program Multiple Award Task Order Contract. The U.S. Army Corps of Engineers intends to solicit offers and award an indefinite delivery/indefinite quantity multiple award task order contract to reduce the federal government's excess facilities inventory. The contract would have a two-year base period and three one-year options. Interested firms should respond to the capabilities questionnaire by September 26th with no more than ten pages describing their relevant experience in areas such as facility demolition, hazardous material abatement, and waste management. The submission should address questions in the attached draft performance work statement and capabilities questionnaire. The notice is for market research only and not a request for proposal.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRAFT PERFORMANCE WORK STATEMENT
FACILITIES REDUCTION PROGRAM
MULTIPLE AWARD TASK ORDER CONTRACT
17 August 2018 U. S. Army Engineering and Support Center Huntsville, Alabama
1.0 GENERAL INFORMATION
1.1 Background
1.2 Objective
1.3 Scope
1.4 Dismantling and Demolition of Property
1.5 Contractor Management and Personnel Requirements
1.6 Access and Security Requirements
1.7 Pre-Proposal Conference and Site Investigation
1.8 Conditions Affecting the Work
1.9 Contractor Quality Control
1.10 Government Quality Assurance
1.11 Safety and Health
1.12 Construction and Demolition Waste Management and Diversion
1.13 Licensing, Bonding, and Insurance
1.14 Required Submittals
1.15 Acceptance of Plans
1.16 Unforeseen Developments
1.17 Environmental Protection
1.18 Cleanup
1.19 Performance Schedule
1.20 Performance Objectives and Criteria
1.21 Liquidated Damages
1.22 Weather Delays
1.23 Technical Proposals
1.24 Technical Proposal Evaluation Matrix
2.0 DEFINITIONS
2.1 General Definitions
2.2 Technical Definitions
3.0 GOVERNMENT- FURNISHED PROPERTY/ITEMS AND SERVICES
3.1 Government-Furnished Facilities
3.2 Government-Furnished Records and Documents
3.3 Government-Furnished Landfill / Borrow Pit
3.4 Government-Furnished Utilities
4.0 CONTRACTOR-FURNISHED ITEMS AND SERVICES
5.0 SPECIFIC TASKS
5.1 Task Order Proposals
5.2 Summary of Work
5.3Emergency Response – This contract does not involve emergency response.
54 Site-Specific Demolition Work Plan
5.5 Waste Management and Diversion Plan
5.6 Safety and Occupational Health
5.7 Contractor’s Quality Control Plan
5.8 Storm Water Pollution Prevention Plan
5.9 Environmental Protection Plan
6.0 APPLICABLE DOCUMENTS
6.1 References
1.0 GENERAL INFORMATION
1.1 Background
In 2004, the Installation Management Command (IMCOM) assigned management of the OMA (Operations and Management, Army) and AFH (Army Family Housing) facility demolition programs to the U.S. Army Corps of Engineers, Huntsville Center (CEHNC). The Huntsville Center centrally manages these programs with execution accomplished through installations, Corps Districts, and Huntsville Center integrated product delivery teams.
The Army installations maintain master plans for mission transformation at Army installations include the demolition and deconstruction of buildings and structures. The Army’s Facilities Reduction Program (FRP) consists of removal, demolition and/or deconstruction of small to very large buildings and structures to include the removal of trees and vegetation, parking lots, drives, sidewalks, roadways, utility and electrical disconnections, removal and rerouting of utility connections, removal of outbuildings, site-assessments, environmental assessments, abatement of facilities contaminants (i.e. lead, asbestos, chemicals, PCBs, petroleum byproducts), removal of above or underground storage tanks, recycling of building materials, redirection of debris waste streams, value engineering, site restoration, data collection, data analysis and reporting, both hazardous and non-hazardous debris transportation, environmental sampling, and other activities pertaining to demolition, destruction, reduction and restoration. Projects may also include emergency response to disasters causing either man-made or natural destruction, such as hurricanes, floods, tornadoes, terrorist activities, etc.
This performance work statement (PWS) supports the Facilities Reduction Program (FRP) Multiple Award Task Order Contract (MATOC) which is performance-based. The MATOC and this PWS is applicable to facilities reduction work for all other Department of Defense armed services, as well as other Federal Departments and Agencies when required by those organizations. Variations to the PWS may be required by any Federal Department or Agency to meet the specific needs of the organization.
1.2 Objective
The purpose of this acquisition is to reduce the Federal Government’s inventory of excess (no longer needed) facilities, thereby saving energy and maintenance cost; eliminate safety hazards, nuisances and unsightly structures and free up valuable Army real estate for future development.
In addition, Contractors must be capable of mobilizing equipment and personnel with very short notice within specified time constraints in response to man-made or natural disasters.
1.3 Scope
This contract is for commercial demolition related services. General work activities performed under this contract shall be for the planning, coordination, and execution of building and facility removal/demolition. Major aspects of the fieldwork include, but are not limited to, facility abatement and hazardous material removal, demolition, debris management and disposition, and site restoration and cleanup. The Contractor shall provide a full range of professional services in a proficient, productive, and knowledgeable manner to efficiently and effectively accomplish all contract work. Each task order awarded under this contract is for firm fixed price (FFP) unless site conditions warrant an award based on Labor Hour reimbursement. In this case the task order shall be converted to FFP after the full extent of the project has been confirmed. Work shall be conducted pursuant to Federal, state, county, and local laws and regulations. Required facility demolition/removal services include, but are not limited to:
• Securing the site and buildings/structures;
• Development and submission of site-specific Demolition Work Plan (DWP) to include an:
1) Environmental Protection Plan
2) Asbestos Containing Material (ACM) Abatement and Hazardous Materials Removal Plan
3) Access/Egress and Security Plan,
4) Waste Management and Diversion Plan
5) Development and submission of an Accident Prevention Plan (APP)
5) Contractor Quality Control Plan;
6) Storm Water Pollution Prevention Plan
7) Erosion and Sediment Control Plan
• Obtaining all permits and making all required notifications;
• Disconnecting, capping and/or rerouting all utilities;
• Hazardous material abatement/removal including, but not limited to ACM, mercury switches, light ballast, as well as transportation, and disposal of same;
• Removal and disposal of underground/above ground (UST/AST) storage tanks;
• Demolition of facilities
• Transportation and disposal of construction and demolition (C&D) building debris materials;
• Diversion of demolition waste materials for reuse, recycling or salvage per U.S Army
Policy;
• Site-restoration (backfilling, grading, reseeding, etc.); and
• Tracking and submission of required submittals and reports.
Under this PWS, the contractor shall not perform Munitions and Explosives of Concern (MEC) remediation activities. However, the Contractor may be required to assess the presence of explosives within a building or structure using an Expray/Dropex method of explosive constituent sampling.
1.4 Dismantling and Demolition of Property
Except where specified or reserved by the Government in other sections, all materials and equipment dismantled, demolished, or removed, and not reused, shall become the property of the Contractor and shall be removed from Government property.
1.5 Contractor Management and Personnel Requirements
1.5.1 Contractor Management
The contractor shall provide all personnel necessary to manage and perform the services specified. The contractor shall furnish the general management, safety management, quality management, training, administration, travel, supervision, quality control (QC), supplies, materials and equipment (not otherwise furnished as Government Furnished Materials) necessary to deliver services in compliance with required schedule and in accordance with contract terms and conditions, reference documents, contract and task order requirements, and contract clauses.
At all times during performance of this contract, and until the work is completed and accepted, the Contractor shall directly superintend the work and have a Program/Project Manager (designated in writing), as well as an on-worksite qualified Job-Site Superintendent (designated in writing.). The Project/Program Manager must have full authority to act on behalf of the Contractor. The Job-Site Superintendent must be on the worksite during all work activities, and when absent from the job site, a fully qualified alternate shall be appointed and shall be present at the job site. The Project/Program Manager and Job-Site Superintendent (and/or designated alternate) must be satisfactory to the Contracting Officer and have authority to act for the Contractor.
1.5.2 Personnel Duties, Qualifications, and Training
The Contractor is responsible for and shall ensure that all Contractor and subcontractor personnel working under this contract are fully qualified and have current and valid certifications and training for their assigned duties per all applicable Federal, state, and local regulations. Key personnel identified in the original proposal may not be substituted without written approval by the Contracting Officer. The duties, qualifications, and training requirements for the Key Personnel positions include, but are not limited to, the following:
1.5.2.1. Program Manager (Key Personnel). This is the individual who has the direct responsibility for the Contractor’s entire facility reduction program contract. This individual shall serve as the single point of contact and liaison between the Contracting Officer and the Contractor. The Program Manager shall have a Bachelor’s degree from an accredited college or university in the relevant field, 6-8 years of relevant experience and/or training, or an equivalent combination of education and experience, in addition to a minimum of four years in a supervisory position. If a Program Manager has no college degree, they shall have a minimum of 12 years relevant experience. The Program Manager should be familiar and conversant with the various environmental and safety laws and regulations applicable to facility reduction project tasks covered in the Performance Work Statement.
1.5.2.2. Job-Site Superintendent (Key Personnel). The Superintendent is the on-site person who plans, assigns, directs safe work activities for all Contractor and subcontractor personnel, and is qualified to perform as “Competent Person.” The Superintendent is responsible and accountable for all work-site activities and outcomes and acts as primary Contractor liaison with the COR.
The Superintendent also conducts daily safety meetings and safety/health inspections, mishap investigations, maintain OSHA logs, and implements the APP and AHAs per USACE EM 385- 1-1. The Superintendent shall have sufficient relevant education and/or demolition and supervisory experience to effectively and properly oversee the project. Sufficient education and experience is, a Bachelor’s degree; 4-10 years experience and/or training; or an equivalent combination of education and experience. The Superintendent may fulfill the SSHO duties and responsibilities provided he/she is properly trained and meets minimum requirements to include, but not limited to, completion of 30-hour OSHA construction safety class and demolition safety training, as well as CPR and First Aid certification.
1.5.2.3. Site Safety and Health Officer (SSHO). When required by the nature and complexity of the project and/or specified by a task order, a dedicated Site Safety and Health Officer (SSHO) shall be provided at the work site to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, per EM 385-1-1 and Federal, state, and local laws and regulations. The SSHO shall have sufficient documented education, training, and experience in safety work with at least 4 years of experience on similar projects. Training shall include a 30-hour OSHA construction safety class, demolition safety training, CPR and First Aid certification. This individual reports to the Job-Site Superintendent.
The Task order will identify when the SSHO may not have any other assigned duties.
1.5.2.4. Certified Industrial Hygienist (CIH). When required by the nature of complexity of the project and/or specified by task order instructions, a dedicated Certified Industrial Hygienist (CIH) shall be provided at the work site to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor, per EM 385- 1-1. The CIH shall have sufficient documented education, training, and experience, and shall be currently certified by a State authority, and shall have a minimum of 3 years of field experience. The CIH shall be the safety and occupational health "Competent Person" as defined by USACE EM 385- 1-1.
1.5.2.5 Professional Engineer (PE) (Key Personnel) The PE is the person who represents the Contractor in the case of requirement for seals, stamps and certification required in structural integrity, safety, and work procedures. This Key Person may be a direct employee of the Contractor, or provided through a Consultant Agreement with the Contractor. Either case this PE represents the Contractor for the required Seals and Stamps for Work Plan, Engineering Surveys, and any minimal design or construction documents. The PE may be registered in any State or Trust Territory of the United States. The requirements for each State differs in recognition of reciprocity, and that is the responsibility of the PE/Contractor to ensure registration requirements within each State are met, as required by that State.
1.5.2.6 Crane Operators (Non-Key Personnel). Crane operators shall meet the requirements in USACE EM 385-1-1, Section 16 and Appendix G. In addition, for mobile cranes with Original Equipment Manufacturer (OEM) rated capacities of 50,000 pounds or greater, crane operators shall be designated as qualified by a source that qualifies crane operators (i.e., union, a government agency, or an organization that tests and qualifies crane operators). Proof of current qualification shall be provided. Crane operators shall report to the Job-Site Superintendent.
1.5.3 Competent Person(s)
29 CFR 1926.32(f) defines “Competent Person” as one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them. Per EM 385-1-1, the Contractor shall, as a minimum, designate and submit qualifications for competent person(s) for each of the following major areas: excavation;
scaffolding; fall protection; hazardous energy; confined space; health hazard recognition, evaluation and control of chemical, physical and biological agents; personal protective equipment and clothing to include selection, use and maintenance.
1.5.4 Contractor Personnel
The contractor must comply with installation security requirements for installation access.
1.6 Access and Security Requirements
The Contractor shall submit to and comply with each individual installation’s access control and security procedure requirements. Contractor instructions for gaining site access shall be provide in each task order. The Contractor is responsible for conducting a law enforcement background check of all contractor and subcontractor employees for criminal warrants prior to NTP. All documentation will be provided to the Contracting Officer for review and acceptance by the Security Office. The contractor shall provide all such documentation to each installation if required by their security procedures. All Contractor and Subcontractor personnel may be subject to intense in processing and vehicle searches prior to being granted access to an installation and this process may be time consuming and access may be delayed, or denied. At a minimum, the Contractor should expect 100% ID check and commercial vehicle search when entering any installation. The need for and level of installation access control measures may change during contract performance. Any changes shall be communicated to the Contractor at the time of change. Requirements for installation passes and site-specific security requirements shall be included with task order instructions.
1.7 Pre-Proposal Conference and Site Investigation
Contractors are advised to attend a pre-proposal conference/site visit and preview the project site prior to the submission of any task order proposals. During the pre-proposal conference, the Contractor shall be provided information such as local transportation routes, availability of onsite landfills and stockpile areas, hours of operation, special conditions, limitation/restrictions, and additional specifications, as required. In addition the Contractor shall have an opportunity to personally view and assess the project area(s). Future task orders may require attendance at a pre-proposal/site visit in order to respond to the RFP.
1.8 Conditions Affecting the Work
The Contractor shall be aware of, conform to, and verify all general and specific technical project terms, conditions, and circumstances before proposing on this contract or any subsequent task order resulting from this contract. During the site visit the Contractor shall take reasonable steps to ascertain the nature and location of the work, and ensure it has investigated and satisfied itself as to the general and local conditions which can affect the work or its cost, including but not limited to (l) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) the conformation and conditions of the ground; and (4) the type of equipment and facilities needed prior to and during work performance. The Contractor must satisfy itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract.
Any failure of the Contractor to take the actions described and acknowledged in this paragraph shall not relieve the Contractor from responsibility for properly estimating the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government. See FAR Clause 52.236-2
1.9 Contractor Quality Control
At a minimum, quality control, as discussed in this PWS shall apply to all task orders awarded under this contract. The Contractor shall submit a Contractor Quality Control (CQC) Plan for review and acceptance for all task order awards. The Job-Site Superintendent shall be held responsible for the quality of work on the job. The Superintendent in this context shall be the highest-level manager responsible for the overall construction activities at the site, including quality and production. The Superintendent shall maintain a physical presence at the site at all times, except as otherwise acceptable to the COR, and shall be responsible for all demolition/removal and related activities at the site. The contractor is solely responsible for the quality of all contract deliverables and should develop its products by referring to their CQC to assure service quality.
1.10 Government Quality Assurance
In accordance with FAR 52.246-4 (a) the Government shall evaluate the contractor’s performance under this contract. For the desired outcomes listed on the Performance Requirement Summary/Quality Assurance Surveillance Plan (PRS/QASP) (Technical Exhibit 1), the contracting officer’s representative (COR) or evaluators shall perform quality checks to assure conformance with contractual requirements during all phases of the work as outlined in Section 5 – Specific Tasks. The government may also provide the contractor with information for reasonable in-scope quality improvement that the contractor shall then implement. The specific task order awarded may provide more specific details of this process. The responsibility for effective Quality Control rests with the contractor.
1.11 Safety and Health
While performing contract services, the Contractor shall comply with safety and occupational health requirements in USACE EM 385-1-1, 29 CFR 1910, 29 CFR 1915, and 29 CFR 1926, as well as all other applicable Federal, state, local, and host installation laws, ordinances, regulations, and policies. In addition, all work shall conform to the current issue of the National Electrical Code (NEC), National Fire Codes (NFC), and the National Fire Protection Agency (NFPA), NFPA 101, Code for Safety to Life for Structures and Buildings, Occupational Safety and Health Administration (OSHA), Army Installation Fire Prevention Standards, and other applicable Federal, state and local regulations.
In addition to complying with the above stated references, the Contractor shall prepare and submit a site-specific Accident Prevention Plan (APP) and detailed Activity Hazard Analysis (AHA) in accordance with USACE EM 385-1-1, Safety and Health Requirements. (See Appendix A, USACE EM 385-1-1 for minimum basic outline for APP.) If a Contractor is only visiting an Army installation (pre-proposal conference accepted), where they are not already performing demolition activities under an APP, they shall complete and submit a “fill-in-the-blank Abbreviated Accident Prevention Plan (AAPP) a minimum of 5 work days prior to the visit using the template in Technical Exhibit 4 – MFRP002 Safety and Health Program, Enclosure 1. The AAAP must be reviewed and accepted by the Government before the visit can take place.
Display of Safety Information, site safety reference materials, emergency response, contingency procedures, medical treatment, accident reports, hot work requirements, hazardous materials exposure, fall hazard protection and prevention, material handling, rescue procedures, utility hazards and location verification, scaffolding, heavy equipment, and conduct of electrical work, among other safety requirements are addressed in USACE EM 385-1-1 and apply to this contract. Accidents involving personal injury/illness or property damage shall be reported to the Contracting Officer, or authorized representative, immediately.
1.12 Construction and Demolition Waste Management and Diversion
Government policy is to apply sound environmental principles in the design, construction, use and removal of facilities. As part of the implementation of that policy, the Contractor shall: (1) practice efficient waste management when removing, collecting, sizing, cutting, separating demolition/ deconstruction debris and (2) use all reasonable means to divert construction and demolition waste from landfills and incinerators and to facilitate their recycling or reuse. Waste diversion projects performed under this contract shall comply with U.S. Army Policy, Requirements for Sustainable Management of Waste in Military Construction, Renovation, and Demolition Activities, dated 5 July 2006 (Technical Exhibit 9). The diversion goal for FY-14 projects is 58%. The diversion goal for FY-15 and beyond is 60%. The necessary containers, bins and storage areas to facilitate effective waste management shall be provided by the Contractor, unless otherwise specified by task order.
Unless otherwise specified in this contract, the contractor shall be responsible for the transportation and disposal of all hazardous materials resulting from the performance of this work. The contractor shall not dispose of any hazardous materials / waste in any dumpster, sanitary sewer, storm sewer or dispose of hazardous materials / waste by any other means on government property without authorization from the Government. The contractor shall provide copies of all manifests or bills of lading for the transportation and disposal of all asbestos or asbestos containing materials to the Contracting Officer. The contractor shall immediately contain, cleanup all spills or release of hazardous materials, including all motor vehicle fuels, motor oil, anti-freeze, and hydraulic fluid and report all spills to the host installation Fire Department and the Department of Public Work - Environmental Branch Office.
1.12.1 Management
The Contractor shall be responsible for the management of construction and demolition waste and require all subcontractors, vendors, and suppliers to participate in the effort. Construction and demolition waste includes all products of demolition or removal, excess or unusable construction materials and other associated items identified for removal as part of the project. In the management of waste, consideration shall be given to the availability of viable markets, the condition of the material, the ability to provide the material in suitable condition and in a quantity acceptable to available markets, and time constraints imposed by internal project completion mandates. The Contractor shall be responsible for implementation of any special programs involving rebates or similar incentives related to recycling of waste. Revenues or other savings obtained for salvage, or recycling shall accrue to the Contractor and are expected to be listed and accounted for in the final bid price. Firms and facilities used for recycling, reuse, and disposal shall be appropriately permitted for the intended use to the extent required by Federal, state, and local regulations.
1.12.2 Waste Disposition Records
Records shall be maintained to document the type and quantity of waste generated for each structure to be demolished as part of this contract. These records shall be made available to the COR during demolition, and a copy of the records shall be delivered to the COR upon completion of the project. The Project C&D Materials and Quantity Report shall contain segregated data for metals/steel salvage, concrete materials, wood timbers, all other recyclable and/or reusable materials, and all other debris. Other debris material that is diverted from landfills shall be so identified. See paragraph 1.12 for applicable requirements in the Waste Management and Diversion Plan.
1.13 Licensing, Bonding, and Insurance
The Contractor, or their designated subcontractor, shall be licensed to perform ACM abatement and all other hazardous material removal activities in the State/Locality where the work is performed. Similarly, the Contractor shall be licensed to perform demolition work in the State/Locality where the work is performed. Work shall not proceed until all permits and licenses are approved by the COR. All insurance and bonding requirements are as stated in the MATOC contract and/or respective task order. Unless otherwise stated, the contractor is required to obtain and provide a Bid Bond.
1.14 Required Submittals
Contractor shall provide a minimum list of submittals and/or samples to the Contracting Officer in strict accordance with the contract/task order specifications. A list of required submittals shall be included in each Task Order award issued under this MATOC. This list does not relieve the Contractor of the responsibility of insuring the accuracy or completeness of the list, or from the responsibility of providing all submittals required by contract documents.
1.15 Acceptance of Plans
Contractor must ensure Government acceptance of all work plan documents required and submitted under this contract prior to the mobilization and start of any on-site work activities under this contract, or any subsequent task order award. Acceptance is conditional and shall be predicated on satisfactory performance during the work activity. The Government reserves the right to require the Contractor to make changes in his Work Plan and operations including removal of personnel, as necessary, to obtain the quality specified.
1.16 Unforeseen Developments
The Contractor shall promptly advise the Contracting Officer, or the Contracting Officer’s Representative (COR), of significant or unforeseen developments affecting the contract within 1 day of the event. The Contractor shall take appropriate measures to obtain clarification of any direction or contract requirement which is not fully understood and incorporate such information into the work being performed.
1.17 Environmental Protection
In order to prevent, and to provide for abatement and control of any environmental pollution arising from the demolition activities in the performance of this contract, the Contractor and all subcontractors shall comply with all applicable Federal, state, and local laws and regulations and shall obtain all necessary permits required by the same. Prior to commencement of the work, the Contractor shall submit for approval, an Environmental Protection Plan that addresses regulatory requirements. Environmental protection shall include a sub plan for Spill Prevention and Pollution Control. The COR shall notify the Contractor in writing of any non-compliance with the aforementioned Federal, state, or local laws or regulations. Such notice, when delivered to the authorized representative of the Contractor at the site of the work, shall be deemed sufficient for this purpose. The Contractor shall, after receipt of such notice, immediately inform the COR in writing, of the proposed corrective action and take such action, once approval has been obtained in writing from the COR. If the Contractor fails or refuses to comply promptly, the COR may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time lost, due to any such stop orders, shall be made subject of a claim for extension of time or for excess costs of damages by the Contractor. See FAR Clause 52.223-5
1.17.1 Protection of Land Resources
The land resources within the project boundaries and outside the limits of permanent work performed under this contract shall be preserved as set forth in these Specifications and on the drawings. Except in areas indicated on the plans that are specified to be cleared, the Contractor shall not deface, injure, or destroy trees or shrubs, nor remove or cut them without the approval of the Contracting Officer. Ropes, cables, or guys shall not be fastened to or attached to any existing nearby trees for anchorages unless specifically authorized. Where such special emergency use is permitted, it shall be performed in such a manner as to avoid damage to the trees. The Contractor shall in any event be responsible for any damage resulting from such use and shall be required to repair or place the damage trees at no additional cost to the Government.
Where the possibility exists that trees may be defaced, bruised, injured, or otherwise damaged by the Contractor's equipment or operations, the Contractor shall adequately protect such trees.
Stone, earth or other material that is displaced into undisturbed areas shall be removed.
Monuments and markers shall be protected before construction operations commence. Any landscape features damaged during the performance of this contract shall be restored to original condition or, to a condition approved be the COR.
1.17.2 Protection of Water Resources
The Contractor shall not pollute any streams, rivers or waterways with fuels, oils, bitumen, calcium chloride, acids, insecticides, herbicides or other harmful materials. The Contractor shall investigate and comply with all applicable Federal, state, county, and municipal laws concerning pollution of rivers and streams. The Contractor shall submit for approval, a Storm Water Pollution Prevention Plan (SWPPP) in accordance with Federal, state, and local requirements.
The Contractor shall conduct operations in conformance with the SWPPP. The Contractor shall also be responsible for submitting Notices of Intent (NOI) and Notices of Termination (NOT) and procuring any necessary permits required by Federal, state, county or municipal laws. A copy of the NOI, NOT and any such permits shall be furnished to the COR. Surface drainage from cuts and fills within the limits of the work shall be held in suitable sedimentation ponds or shall be graded to control erosion within acceptable limits. Temporary erosion and sediment control measures, in conformance with the SWPPP, shall be provided and maintained until the permanent work and permanent erosion and sediment control measures are completed and operative and the SWPPP is successfully closed out by the issuing authority.
1.17.3 Recording and Preserving Historical and Archaeological Finds
Any and all items having any apparent historical or archaeological interest that are discovered in the course of any construction activities shall be carefully preserved. The Contractor shall leave the archaeological find undisturbed and shall immediately report the find to the COR so that proper authorities may be notified. If an archaeological find is discovered and a job stop is required, the delay shall not be reason for the Contractor to submit a claim against the Government. In accordance with 16 U.S.C. Section 470hh, Contractor shall not publically disclose information concerning the nature and location of any archeological resource for which excavation or removal requires a permit.
1.18 Cleanup
The Contractor shall at all times keep the work area, including storage areas, free from accumulations of waste materials except as required to maintain the proper pace and flow of the demolition process. Before completing the work, the Contractor shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the Contractor shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer. All material and debris shall be hauled to an appropriate disposal site.
1.19 Performance Schedule
The performance schedule and required delivery date for each project under this contract is reflected in the respective task order. Optional services may also be exercised in accordance with the schedule established for each project under the respective task order.
1.20 Performance Objectives and Criteria
The Contractor shall furnish all required services in a manner that best meets the following Performance Objectives and standards:
• Timeliness, accuracy, and completeness of project deliverables;
• Waste stream management (diversion);
• Quality and effectiveness of practices, means, and methods;
• Safety program;
• Budget, cost, and productivity;
• Conformance and ability to relate and respond to project requirements;
• Schedule and resource management.
1.20.1 Performance Standards and Criteria
The Contractor’s performance shall be evaluated by assessing the key project deliverables described in the Performance Requirements Summary (Technical Exhibit 1).
1.21 Liquidated Damages
Liquidated damages will be applied in each Task order under the Northeast MATOC.
1.22 Weather Delays
Weather delays shall be determined for each Task Order with respect to the project location.
Time Extensions for Unusually Severe Weather (ER 415-1-15) (OCT 1989). This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(a) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(b) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the contractor.
(c) Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the contractor's scheduled work day.
Monthly anticipated adverse weather delays are based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations. The contractor's progress schedule must reflect these anticipated adverse weather delays in all weather dependent activities. The NOAA data will be provided with each task order PWS. The provided information shall be regarded as the normal and anticipatable number of calendar days for each month during which demolition activity shall be expected to be prevented and suspended by cause of adverse weather. Suspension of demolition activity for the number of days each month is included in the project PWS. These days shall be included in the submitted work plans and schedules and is not eligible for extension of Contract Time.
Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the contractor will record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work.
1.23 Technical Proposals
A Technical proposal shall be submitted with the Contractor’s price proposal for each Task Order. Contractor’s shall use due diligence in evaluating and investigating specific technical needs for accomplishing the work in a timely and professional manner under each Task Order.
The following guidelines will be used in evaluating the Technical Proposal for technical acceptability:
Technical proposals submitted in response to a Request For Proposal under the Facilities Reduction Program will be evaluated as being technically acceptable using the following guidelines.
• The proposal shall provide a clear, concise, and logical description of the work methods, means, and sequence to be used in meeting the specific requirements of the statement of work and associated Appendices and Attachments.
• The proposal shall be site-specific and not generic, and shall not repeat the PWS.
• A proposed project schedule in a Microsoft Project compatible format (2013) shall be provided. The proposed schedule shall provide an estimated NTP date, mobilization, and then detail the sequence of work for each major activity (abatement, demolition, restoration) by building or groups of buildings that meets the overall schedule. Separate schedules shall be provided for any /all PWS options.
• The proposal shall clearly describe the Contractor’s on-site management and project planning processes through which it will adapt work schedules and processes when encountering changing conditions based on owner needs, site condition problems, and/or weather delays.
• The proposal shall describe the types and expected amount of equipment, number of personnel, identity of subcontractors, etc. required to perform the work within the allotted timeframe, as provided in the proposed project schedule.
• The proposal shall indicate the Contractor’s expected diversion rate and whether it will meet Army goals for the fiscal year of the task order.
• The proposal shall describe the anticipated quantities and types of materials for diversion/recycle and the locations and company names which are to receive those materials. A table(s) is acceptable for this and the next element below.
• The locations and company names to receive ACM and ORM items will be provided.
• The proposal shall not contain details of corporate or personal experience since all MATOC contractors are already pre-qualified for experience. The names and position held by the expected key personnel shall be furnished in the proposal.
2.0 DEFINITIONS
2.1 General Definitions
2.1.1 Defective Service. A service output that does not meet the standard of performance requirement specified in the contract for that service.
2.1.2 Performance Requirement. The point that divides acceptable and unacceptable performance of the task according to the Performance Requirement Summary/Quality Assurance Surveillance Plan (PRS/QASP) and the inspection of services clause. It is the number of defects or maximum percentage of defects that is acceptable.
2.1.3 Performance Requirements Summary. A listing of the services under the contract that are to be evaluated by the COR on a regular basis, the surveillance methods to be used for these outputs, and the performance requirements of the listed outputs.
2.1.4 Quality Assurance. A planned and systematic pattern of all Government actions necessary to provide confidence that adequate technical requirements are established; services conform to established technical requirements; and satisfactory performance is achieved. Quality assurance refers to actions by the Government assurance functions for a contracted service.
2.1.5 Quality Control. Those actions taken by the Contractor to control the production of outputs to ensure that they conform to the contract requirements.
2.1.6 Specialized Demolition. Demolition of a structure that is contaminated by explosives, and/ or any other extraordinary substance, or is of such design/size that it is unique and requires specialized expertise for demolition. Asbestos, mercury switches, and other such ordinary hazardous wastes are not considered extraordinary substances.
2.1.7 Building Demolition Complete. The structure, foundation, and ancillary elements are removed.
2.2 Technical Definitions
• ACM - asbestos-containing materials
• AHA - Activity Hazard Analysis
• APP - Accident Prevention Plan
• AST - above-ground storage tank
• C&D - construction and demolition
• Calendar Day - The time from midnight to midnight.
• CIH - Certified Industrial Hygienist
• Competent Person - One who meets the requirements in 29 CFR 1926.32 (f), and is capable of identifying existing asbestos hazards in the workplace, able to select the appropriate control strategy, and has the authority to take prompt corrective measures to mitigate them.
• COR - Contracting Officer’s Representative is the individual appointed in writing by the contracting officer and delegated specific authority to monitor contractor performance.
• CQC - Contractor Quality Control
• DoD – Department of Defense
• DSPOYR - Disposition year of removal/demolition
• DWP - Demolition Work Plan
• EPA - Environmental Protection Agency
• Facility - A separate building, structure, or other real property improvements including, but not limited to, fences and utility systems.
• FACNO - Facility number. Real property is identified by a distinct facility number
• FFP - firm fixed price
• FRP - Facilities Reduction Program
• ID/IQ - Indefinite Delivery / Indefinite Quantity
• LBP – Lead Based Paint
• MATOC - Multiple award task order contract
• MEC - Munitions and explosives of concern
• OEM - Original Equipment Manufacturer
• ORM – Other Regulated Material(s)
• OSHA - Occupational Safety and Health Administration
• NEC - National Electrical Code
• NFPA - National Fire Protection Association
• NOI - Notice of Intent – An application for coverage under a general NPDES permit required by EPA notifying them of any construction project of .5 acres or more and the effect of such construction project on the nation’s waterways.
• NOT - Notice of Termination- A notice informing EPA of the closeout of a project covered under an NOI.
• NPDES - National Pollutant Discharge Elimination System- A program intended to eliminate discharges of sediments and other pollution into the nation’s waterways.
• Performance Measures - Performance measures provide a series of indicators, expressed in qualitative, quantitative or other tangible terms that indicate whether current performance is reasonable and cost effective. Performance measures can include workload and output-to-cost ratios, transaction ratios, error rates, consumption rates, inventory fill rates, timeliness measures, completion and back order rates, etc. Quality service measures may include responsiveness rates, user satisfaction rates, etc.
• PRS/QASP - PERFORMANCE REQUIREMENTS SUMMARY/QUALITY
ASSURANCE SURVEILANCE PLAN - The PRS/QASP lists those tasks that are key performance indicators of the function. The result is a list of key required services, standards of performance, method of surveillance, and the incentives/disincentives with respect to outcomes.
• Performance Standard- A performance standard reflects the minimum, sector-specific, Federal Standard requirement for the performance of a commercial service or activity. It incorporates both quality measures and cost measures.
• PWS PERFORMANCE WORK STATEMENT - A performance work statement is a statement of the technical, functional and performance characteristics of the work to be performed, identifies essential functions to be performed, determines performance factors, including the location of the work, the units of work, the quantity of work units, and the quality and timeliness of the work units.
• QA QUALITY ASSURANCE - This is a structured program used by the Army to monitor the actions of the contractor to ensure the Army gets the work done that is required by the PWS.
• Quality Assurance - Quality Assurance Surveillance is the method by which Federal Surveillance employees shall monitor contract performance to ensure that the standards of the PWS are met within the costs agreed to.
• RFP - Request for Proposal
• SSHO - Site Safety and Health Officer
• SWPPP - Storm Water Pollution Prevention Plan - A plan conforming to federal, state, local and municipal codes which addresses measures to reduce and/or eliminate discharge of sediments and pollutants to the watershed from construction sites.
• TCLP - Toxic Characteristic Leaching Procedure is one of the tests for the determinations of whether a solid waste is classified as a hazardous substance via EPA Method 1311.
• T.O. - Task Order
• UM - Unit(s) of measure (square feet, cubic yards, etc.)
• USACE - United States Army Corps of Engineers
• UST - underground storage tank
• Wage - The wage determination sets the minimum wages and fringe benefits that
Determination contractors and/or their subcontractors must pay their employees subject to the Service Contract Act.
• Work Day (WD) - Normal schedule day of work not including weekends and holidays.
3.0 GOVERNMENT- FURNISHED PROPERTY/ITEMS and SERVICES
The Government shall furnish the following items and services as described below. In addition, the Government shall provide a list of host installation contacts
3.1 Government-Furnished Facilities
The Government shall furnish a list of all facilities, buildings, structures, and appurtenances to be completely removed, or partially removed/altered as part of the demolition process. The Contractor shall be entitled to all property to be dismantled or demolished that is not specifically designated otherwise by the Government/owner in this contract and/or any subsequent task order. The entitlement shall vest in the Contractor immediately upon issuing the notice to proceed (NTP) with the work.
3.2 Government-Furnished Records and Documents
The Government shall furnish site-specific information, which may include environmental surveys, hazardous material surveys, drawings, and installation policies and procedures affecting the work. The documents may include items such as local procedures for disposal of C&D materials, site limitations for working hours, travel routes, a list of Government retained property and Service Contract Act determinations. All such items, when and where available shall be provided with the respective task order RFP.
3.3 Government-Furnished Landfill / Borrow Pit
The Contractor may be granted access to and use of the on-site installation landfill for disposal of various demolition and abatement debris. Availability for selected debris categories shall be provided in the respective task order. The Contractor may also be granted use of an on-site installation borrow pit for deposit of, or access to, suitable backfill materials, as the project dictates. Information concerning the use of a borrow pit shall be provided with the respective task order PWS.
3.4 Government-Furnished Utilities
The Installation shall provide to the Contractor use of such utilities as are available at the site.
However, determination of the existence and location of such utilities is the responsibility of the Contractor and the Installation is under no obligation to provide utilities if none are available on site. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the task order . Unless otherwise provided in the task order specifications, when utilities are available they shall be furnished without charge. The Contractor, at its expense and in a workmanlike manner satisfactory to the Government, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used. Prior to final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.
4.0 CONTRACTOR-FURNISHED ITEMS and SERVICES
The contractor is required to furnish all services, materials, and equipment needed to perform the requirements of this contract, except for those items specifically enumerated in Section 3. The burden of determining exactly what items and services are required to perform this contract according to all its terms is the responsibility of the contractor.
The Contractor shall provide a full range of commercial demolition services to include, but not limited to, the specific work tasks stated in Section 5, that follows. Additional detailed demolition-related services may be required, per individual task order. The objective of this contract is to remove excess existing U.S. Army and other Federal facilities using proven commercial means, methods, techniques, and best practices. Specific project details and special conditions shall be delineated in individual task orders awarded under this contract. Contractors can generally anticipate task order projects to consist of some form of ACM abatement and hazardous material removal, demolition, and site restoration.
The Contractor shall perform all…
This is the start of the file's text. The full file is on GovTribe.