Master Schedule for relocation
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish Predecessors
1 U.S. ARMY MEDICAL MATERIEL CENTER - Europe (USAMMCE) 1118 days Mon 11/24/14 Fri 12/15/17
2 PROJECT MILESTONES 1118 days Mon 11/24/14 Fri 12/15/17 3 IO&T Contract Award 0 days Fri 1/23/15 Fri 1/23/15 4 IO&T Notice-to-Proceed 0 days Fri 1/23/15 Fri 1/23/15 3SS 5 Design-build contract NTP 0 days Mon 11/24/14 Mon 11/24/14 6 Beneficial Occupancy Date-First building [BOD] - Bldg. 2222 0 days Tue 10/24/17 Tue 10/24/17 7 End of construction 0 days Fri 4/21/17 Fri 4/21/17 8 Ribbon Cutting Ceremony 0 days Fri 9/8/17 Fri 9/8/17 9 OFB - All Buildings Open for Business 0 days Mon 8/28/17 Mon 8/28/17
10 Task Order Complete (Closeout) 0 days Sun 12/17/17 Sun 12/17/17 11 INITIAL CONTRACT OBLIGATIONS 38 days Sun 2/1/15 Wed 3/11/15 12 Telephonic Kick Off Meeting 0 days Tue 2/3/15 Tue 2/3/15 3FS+10 days 13 IO Kick Off Partnering Meeting/Site 1 day Wed 3/11/15 Wed 3/11/15 14 Obtain CAC cards 0 days Mon 2/23/15 Mon 2/23/15 3FS+7.1 days 15 IO PM designated in writing 0 days Sun 2/1/15 Sun 2/1/15 3FS+10 days 16 Communication Chain Diagram 0 days Sun 2/1/15 Sun 2/1/15 3FS+10 days 17 PM mobilized to site (Not later than) 0 days Sun 3/8/15 Sun 3/8/15 3FS+45 days 18 Project Net account setup 0 days Sun 3/8/15 Sun 3/8/15 3FS+45 days
20 COMPREHENSIVE PROJECT MANAGEMENT 988 days Tue 2/10/15 Tue 10/24/17 21 Develop initial Project Management Plan 50 days Thu 2/26/15 Thu 4/16/15 12,3FF+60 days 22 Develop initial IMS 50 days Thu 2/26/15 Thu 4/16/15 12,3FF+60 days 23 Quarterly Site Visits 250 days Mon 2/22/16 Fri 10/28/16 24 PM and TP Site Visit 5 days Mon 2/22/16 Fri 2/26/16 25 PM and TP Site Visit 5 days Mon 6/27/16 Fri 7/1/16 26 PM and TP Site Visit 5 days Mon 10/24/16 Fri 10/28/16 27 Transition Meetings - Monthly 915 days Fri 4/24/15 Tue 10/24/17 59 Integrated Master Schedule Updates - Monthly 911 days Tue 4/7/15 Tue 10/3/17 91 Project Meetings Weekly 988 days Tue 2/10/15 Tue 10/24/17
234 Progress Reports-Weekly 960 days Mon 3/9/15 Mon 10/23/17
374 IO&T 638 days Tue 2/3/15 Tue 11/1/16 375 IO Submittal #1/35% 161 days Tue 2/3/15 Mon 7/13/15 376 Obtain New Buildings floor plans 30 days Tue 2/3/15 Wed 3/4/15 12 377 Perform detailed Equipment Inventory 14 days Mon 3/9/15 Sun 3/22/15 12FF+45 days 378 Compare Property Book for Reuse Equipment verification 30 days Mon 3/9/15 Tue 4/7/15 377SS 379 Division/User Interview Meetings 14 days Mon 4/27/15 Sun 5/10/15 378,377 380 Standardization Meeting 2 days Mon 5/11/15 Tue 5/12/15 379 381 Review/Validate floor plans(Generate RFI if required) 30 days Mon 3/23/15 Tue 4/21/15 377 382 Compare Equipment Lists to Drawings (Generate ECP, if required) 14 days Wed 4/22/15 Tue 5/5/15 381 383 Validate requirements list for new equipment 30 days Mon 5/11/15 Tue 6/9/15 382,379 384 Develop reconfiguration of existing and new furniture layouts 55 days Wed 4/22/15 Mon 6/15/15 381 385 IO-Submittal #1 - Due 0 days Mon 6/15/15 Mon 6/15/15 384FF 386 #1 Submittal Government Review 10 days Tue 6/16/15 Thu 6/25/15 385 387 Government Comments Due 0 days Thu 6/25/15 Thu 6/25/15 386FF 388 #1 Submittal WPS Response to Gov't Review 5 days Fri 6/26/15 Tue 6/30/15 386 389 WPS Answer Dr Checks 0 days Tue 6/30/15 Tue 6/30/15 388FF 390 Review Conference 5 days Thu 7/9/15 Mon 7/13/15 388 391 IO Submittal #2/65% 71 days Tue 7/14/15 Tue 9/22/15 392 Rework CIL with Gov. Comment, Resubmit final CIL 45 days Sat 7/18/15 Mon 8/31/15 393 Develop and Prepare Artwork Package 30 days Sat 7/18/15 Sun 8/16/15 392SS 394 Develop ConOps, each Dept. 45 days Sat 7/18/15 Mon 8/31/15 392SS 395 Division/User Interview Meetings 11 days Tue 7/14/15 Fri 7/24/15 390SS 396 Standardization Meeting 0 days Mon 7/27/15 Mon 7/27/15 395 397 Create draft Building/Room relocation schedule (staff) 25 days Tue 7/14/15 Fri 8/7/15 390 398 Create draft From/To List (equipment) 25 days Tue 7/14/15 Fri 8/7/15 390 399 Develop draft Move Plan 27 days Sat 8/8/15 Thu 9/3/15 398,397 400 IO - Submittal #2 - Due 0 days Thu 9/3/15 Thu 9/3/15 399FF,394,393 401 #2 Submittal Government Review 11 days Fri 9/4/15 Mon 9/14/15 400 402 Government Comments Due 0 days Mon 9/14/15 Mon 9/14/15 401FF 403 #2 Submittal WPS Response to Gov't Review 5 days Tue 9/15/15 Sat 9/19/15 402SS 404 WPS Answer Dr Checks 0 days Sat 9/19/15 Sat 9/19/15 403FF 405 Review Conference 1 day Tue 9/22/15 Tue 9/22/15 404FS+2 days 406 IO Submittal #3/95% 87 days Wed 9/23/15 Fri 12/18/15 407 Identify Long Lead & Mission Critical Items to acquire 15 days Mon 9/28/15 Mon 10/12/15 408 Develop Disposal Plan of old equipment and furniture 30 days Mon 9/28/15 Tue 10/27/15 407SS 409 Develop a sourcing and procurement plan 30 days Mon 9/28/15 Tue 10/27/15 407SS 410 Finalize Building/Room relocation schedule (staff) 20 days Wed 9/23/15 Mon 10/12/15 405 411 Finalize From/To List (equipment) 24 days Wed 9/23/15 Fri 10/16/15 405 412 Division/User Interview Meetings 12 days Mon 9/28/15 Fri 10/9/15 407SS 413 Standardization Meeting 0 days Mon 10/12/15 Mon 10/12/15 412
IO&T Contract Award
1/23
11/24
10/24
4/21
9/8
8/28
12/17
2/3
Obtain CAC cards
IO PM designated in writing
Communication Chain Diagram
PM mobilized to site (Not later than)
Project Net account setup
COMPREHENSIVE PROJECT MANAGEMENT
376 Obtain New Buildings floor plans
377 Perform detailed Equipment Inventory
378 Compare Property Book for Reuse Equipment verification
379 Division/User Interview Meetings
381 Review/Validate floor plans(Generate RFI if required)
382 Compare Equipment Lists to Drawings (Generate ECP, if required)
383 Validate requirements list for new equipment
384 Develop reconfiguration of existing and new furniture layouts
6/15
386 #1 Submittal Government Review
6/25
388 #1 Submittal WPS Response to Gov't Review
6/30
390 Review Conference
392 Rework CIL with Gov. Comment, Resubmit final CIL
393 Develop and Prepare Artwork Package
394 Develop ConOps, each Dept.
395 Division/User Interview Meetings
7/27
397 Create draft Building/Room relocation schedule (staff)
398 Create draft From/To List (equipment)
399 Develop draft Move Plan
9/3
401 #2 Submittal Government Review
9/14
403 #2 Submittal WPS Response to Gov't Review
9/19
405 Review Conference
407 Identify Long Lead & Mission Critical Items to acquire
408 Develop Disposal Plan of old equipment and furniture
409 Develop a sourcing and procurement plan
410 Finalize Building/Room relocation schedule (staff)
411 Finalize From/To List (equipment)
412 Division/User Interview Meetings
10/12
B M E B M E B M E B M E B April March February January December November October
USAMMCE - KAD - 9 March 2017
KAD Task Order Schedule (TOS) Page 1
414 Develop Equipment Training Schedule 15 days Wed 10/28/15 Wed 11/11/15 409 415 Finalize Public Relations Plan 15 days Tue 10/13/15 Tue 10/27/15 410 416 Finalize detailed Move Plan 24 days Sun 10/18/15 Tue 11/10/15 410,411 417 Finalize ConOps, each Dept. 23 days Tue 10/13/15 Wed 11/4/15 410 418 Develop Day in the Life scenarios 9 days Thu 11/5/15 Fri 11/13/15 417 419 IO - Submittal #3 - Due 0 days Fri 11/20/15 Fri 11/20/15 416,417,410,411,418 420 #3 Submittal Government Review 11 days Fri 11/20/15 Mon 11/30/15 419 421 Gov't Comments Due 1 day Sun 11/29/15 Mon 11/30/15 420FF 422 #3 Submittal WPS Response to Gov't Review 7 days Sat 12/5/15 Fri 12/11/15 423 WPS Answer Dr Checks 0 days Fri 12/11/15 Fri 12/11/15 422FF 424 Review Conference 5 days Mon 12/14/15 Fri 12/18/15 423SS 425 IO&C Submittal 100% 10 days Mon 2/29/16 Wed 3/9/16 426 IO-Corrected Final Submittal- DUE 0 days Fri 3/25/16 Fri 3/25/16 427 IO-Negotiations 5 days Fri 3/25/16 Tue 3/29/16 426 428 IO-C Award 0 days Tue 11/1/16 Tue 11/1/16
430 IO&C 912 days Thu 6/18/15 Fri 12/15/17 431 Source Material & Equipment 250 days Tue 1/26/16 Sat 10/1/16 432 PROCUREMENT 775 days Thu 6/18/15 Mon 7/31/17 433 Equipment Procurement 674 days Thu 6/18/15 Fri 4/21/17 434 Conveyor System 510 days Thu 6/25/15 Tue 11/15/16 435 Option 1002 & 1003 Award – Conveyor System and Racking Bldg. 2369 1 day Thu 6/25/15 Thu 6/25/15 436 Conveyor System and Racking Purchase Order Issued 255 days Tue 3/1/16 Thu 11/10/16 435FS+249 days 437 Manufacturing and Delivery 231 days Tue 3/15/16 Mon 10/31/16 436SS+14 days 438 Stock Selectors PO Issued 1 day Tue 11/15/16 Tue 11/15/16 439 HAZMAT Container 477 days Mon 12/28/15 Mon 4/17/17 440 Award Option 1007-HAZMAT Containers 2239 1 day Mon 12/28/15 Mon 12/28/15 441 HAZMAT Container Purchase Order Issued 1 day Mon 2/1/16 Mon 2/1/16 440FS+32 days 442 Manufacturing and Delivery 245 days Tue 8/16/16 Mon 4/17/17 441FS+165 days 443 Contingency Shelving & Walk Lift System 388 days Wed 9/23/15 Fri 10/14/16 444 Award Option 1009 - Contingency Shelving & Walk Lift System 2264 1 day Wed 9/23/15 Wed 9/23/15 445 Contingency Shelving & Walk Lift System Purchase Order Issued 1 day Thu 3/31/16 Thu 3/31/16 444SS 446 Manufacturing and Delivery 120 days Fri 6/17/16 Fri 10/14/16 445FS+122 days 447 Furniture / Procurement 144 days Thu 11/10/16 Mon 4/3/17 448 Award Option 1,4,5,6,8,10,11 & 12 30 days Thu 11/10/16 Fri 12/9/16 449 Furniture Purchase Order Issued 116 days Tue 11/15/16 Fri 3/10/17 448SS 450 Manufacturing and Delivery 60 days Tue 1/10/17 Fri 3/10/17 449FF 451 Miscellaneous Purchase Orders Issued 60 days Mon 1/2/17 Thu 3/2/17 452 Track Deliveries 228 days Tue 11/15/16 Fri 6/30/17 453 Receive Furniture / Equipment Deliveries at KAD 89 days Mon 4/3/17 Fri 6/30/17 452FF 454 Coordinate Furniture/Equipment Installation 120 days Mon 4/3/17 Mon 7/31/17 455 TRANSITION PREPARATION 610 days Tue 3/1/16 Tue 10/31/17 456 Turn In Excess Equipment 504 days Wed 6/15/16 Tue 10/31/17 457 Develop MOAs with KAD facilities 458 days Tue 3/1/16 Thu 6/1/17 456SS+60 days 458 Refine DITL Scenarios 308 days Tue 3/1/16 Mon 1/2/17 457SS 459 Update Employee PDs where required for position changes 182 days Tue 11/1/16 Mon 5/1/17 458SS+245 days 460 Update Personnel Employee Contracts with new duty location 338 days Tue 3/1/16 Wed 2/1/17 457SS 461 Update/Renew all Service and Maintenance Contracts 121 days Thu 12/1/16 Fri 3/31/17 460SS+275 days 462 Update DPW Housekeeping/Cleaning Contract (two locations during transition) 152 days Thu 12/1/16 Mon 5/1/17 461SS 463 Conduct ROC Drills 5 days Mon 2/27/17 Fri 3/3/17 467FS+9 days 464 Personnel CAC Card Access 427 days Tue 3/1/16 Mon 5/1/17 457SS 465 Conveyor Work Instructions 0 days Tue 5/9/17 Tue 5/9/17 464FS+7 days 466 Conduct Building Orientations 12 days Mon 6/5/17 Fri 6/16/17 465FS+27 days 467 Conduct Emergency codes rehearsals (Run with Orientation) 12 days Mon 6/5/17 Fri 6/16/17 466SS 468 Conduct Day in the Life Scenarios 5 days Mon 7/24/17 Fri 7/28/17 463FS+23 days 469 Switch Receiving Location to KAD 5 days Fri 7/28/17 Tue 8/1/17 468FF 470 INSTALLATION SERVICES 244 days Thu 12/15/16 Tue 8/15/17 471 Furniture 61 days Mon 4/3/17 Fri 6/2/17 472 Install Furniture at KAD and Kleber 61 days Mon 4/3/17 Fri 6/2/17 473 Install furniture in 2219 2 days Mon 4/3/17 Tue 4/4/17 474 Government Accepts/Signs DD250 for furniture in 2219 3 days Wed 4/5/17 Fri 4/7/17 473 475 Install furniture in 2264 1 day Mon 4/10/17 Mon 4/10/17 473FS+5 days 476 Government Accepts/Signs DD250 for furniture in 2264 3 days Tue 4/11/17 Thu 4/13/17 475 477 Install furniture in 2222 1 day Mon 4/17/17 Mon 4/17/17 475FS+6 days 478 Government Accepts/Signs DD250 for furniture in 2222 3 days Tue 4/18/17 Thu 4/20/17 477 479 Install furniture in 2213 2 days Mon 4/24/17 Tue 4/25/17 477FS+6 days 480 Government Accepts/Signs DD250 for furniture in 2213 3 days Wed 4/26/17 Fri 4/28/17 479 481 Install furniture in 2238 1 day Mon 5/1/17 Mon 5/1/17 479FS+5 days 482 Government Accepts/Signs DD250 for furniture in 2238 3 days Tue 5/2/17 Thu 5/4/17 481 483 Install furniture in 2369 8 days Mon 5/8/17 Mon 5/15/17 481FS+6 days 484 Government Accepts/Signs DD250 for furniture in 2369 3 days Tue 5/16/17 Thu 5/18/17 483 485 Install furniture in 2276 1 day Thu 5/18/17 Thu 5/18/17 483FS+2 days
414 Develop Equipment Training Schedule
415 Finalize Public Relations Plan
416 Finalize detailed Move Plan
417 Finalize ConOps, each Dept.
418 Develop Day in the Life scenarios
11/20
420 #3 Submittal Government Review
421 Gov't Comments Due
422 #3 Submittal WPS Response to Gov't Review
12/11
424 Review Conference
3/25
427 IO-Negotiations
11/1
431 Source Material & Equipment
452 Track Deliveries
453 Receive Furniture / Equipment Deliveries at KAD
454 Coordinate Furniture/Equipment Installation
5/9
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 2
486 Government Accepts/Signs DD250 for furniture in 2276 4 days Fri 5/19/17 Mon 5/22/17 485 487 Install ADVON training furniture in training area in 3201 2 days Mon 4/3/17 Tue 4/4/17 488 Install furniture in 3201 10 days Mon 5/22/17 Wed 5/31/17 485FS+3 days 489 Government Accepts/Signs DD250 for furniture in 3201 2 days Thu 6/1/17 Fri 6/2/17 488 490 New Equipment Installation 244 days Thu 12/15/16 Tue 8/15/17 491 IT Equipment Installation 60 days Mon 5/1/17 Thu 6/29/17 497 Conduct Warehouse Operations 150 days Wed 3/1/17 Fri 7/28/17 498 Receive New Equipment at KAD 154 days Wed 3/15/17 Tue 8/15/17 499 Equipment Installation 244 days Thu 12/15/16 Tue 8/15/17 500 Install equipment for building 2213 9 days Thu 6/22/17 Fri 6/30/17 501 Install Slurry System 4 days Tue 6/27/17 Fri 6/30/17 502 Training on Slurry System 1 day Tue 6/27/17 Tue 6/27/17 503 Government Accepts/Signs DD250 for Slurry System in Bldg 2213 3 days Wed 6/28/17 Fri 6/30/17 502 504 Install Miscellaneous Equipment 6 days Thu 6/22/17 Tue 6/27/17 505 Government Accepts/Signs DD250 for Miscellaneous Equipment in Bldg 2213 3 days Wed 6/28/17 Fri 6/30/17 504 506 Install Equipment in building 2219 10 days Mon 5/1/17 Wed 5/10/17 500FS-30 days 507 Install Miscellaneous Equipment 5 days Mon 5/1/17 Fri 5/5/17 508 Provide Training on New Equipment 5 days Mon 5/1/17 Fri 5/5/17 507SS 509 Government Accepts/Signs DD250 for Equipment in Bldg 2219 3 days Mon 5/8/17 Wed 5/10/17 508FS+2 days 510 Install Equipment in building 2222 17 days Mon 6/5/17 Wed 6/21/17 511 Install Miscellaneous Equipment 10 days Mon 6/5/17 Wed 6/14/17 512 Government Accepts/Signs DD250 for Equipment in Bldg 2222 2 days Tue 6/20/17 Wed 6/21/17 511 513 Install Equipment in building 2238 2 days Mon 8/7/17 Tue 8/8/17 514 Install Pushcart 2 days Mon 8/7/17 Tue 8/8/17 515 Government Accepts/Signs DD250 for Equipment in Bldg 2238 1 day Tue 8/8/17 Tue 8/8/17 516 Install Equipment for building 2239 95 days Mon 4/17/17 Thu 7/20/17 517 Install HAZMAT Container System 22 days Mon 3/27/17 Mon 4/17/17 518 Install of HAZMAT Container 8 days Mon 3/27/17 Mon 4/3/17 519 3rd Party (GC) Utility Hook up 5 days Tue 4/4/17 Mon 4/10/17 518 520 Government Accepts/Signs DD250 for HAZMAT Container System in Bldg 2239 3 days Thu 4/13/17 Mon 4/17/17 521 521 Conduct Orientation & Training on HAZMAT Container System 2 days Wed 5/17/17 Thu 5/18/17 519 522 Install Miscellaneous Equipment 8 days Mon 7/10/17 Mon 7/17/17 523 Government Accepts/Signs DD250 for Miscellaneous Equipment in Bldg 2239 3 days Tue 7/18/17 Thu 7/20/17 522 524 Install equipment for building 2264 159 days Mon 1/9/17 Fri 6/16/17 525 Install Contingency Shelving & Walk Lift System 159 days Mon 1/9/17 Fri 6/16/17 526 Basstech Access to Bldg / Install Begins 1 day Mon 1/9/17 Mon 1/9/17 527 Shelf Assembly 40 days Mon 1/9/17 Fri 2/17/17 528 Walklift System Training 10 days Fri 3/31/17 Thu 4/13/17 529 Government Accepts/Signs DD250 for Contingency Shelving & Walk Lift System in
Bldg 2264 0 days Tue 4/25/17 Tue 4/25/17
530 Running In Period & Completion 14 days Wed 4/26/17 Tue 5/9/17 531 Install Miscellaneous Equipment 5 days Mon 6/5/17 Fri 6/9/17 532 Government Accepts/Signs DD250 for Miscellaneous Equipment in Bldg 2264 3 days Mon 6/12/17 Wed 6/14/17 531FS+2 days 533 Install Equipment for building 2369 244 days Thu 12/15/16 Tue 8/15/17 534 Install Conveyor and Racking System 244 days Thu 12/15/16 Tue 8/15/17 535 Basstech Access to Bldg for Material Staging 0 days Mon 1/9/17 Mon 1/9/17 536 Basstech Begins Installation 0 days Mon 1/16/17 Mon 1/16/17 537 Shelving Assembly 28 days Wed 1/25/17 Tue 2/21/17 538 BSO User Training for Conveyer System 30 days Tue 6/27/17 Wed 7/26/17 539 Bins Deliveries 58 days Wed 3/8/17 Thu 5/4/17 540 Labelling & Positioning 58 days Mon 3/13/17 Tue 5/9/17 541 Mock Warehouse Test (Day in the Life) 5 days Thu 7/20/17 Mon 7/24/17 542 Government Accepts/Signs DD250 for Conveyor and Racking System in Bldg 2369 0 days Tue 7/18/17 Tue 7/18/17 541 543 Delivery & Install of Conveyor System Complete 0 days Tue 7/18/17 Tue 7/18/17 544 Control System 212 days Mon 1/16/17 Tue 8/15/17 545 Development and Testing 54 days Mon 1/16/17 Fri 3/10/17 546 Provide TEWLS Data to Basstech for Location 0 days Fri 3/31/17 Fri 3/31/17 547 Control System Start-Up 84 days Wed 4/26/17 Tue 7/18/17 548 Sprinkler System 29 days Wed 4/19/17 Wed 5/17/17 549 Sprinkler Assembly 29 days Wed 4/19/17 Wed 5/17/17 550 Sprinkler Certification 8 days Wed 7/12/17 Wed 7/19/17 551 Checking Period 28 days Wed 7/5/17 Tue 8/1/17 552 Testing by USAMMCE 28 days Wed 7/5/17 Tue 8/1/17 553 System Acceptance 29 days Tue 7/18/17 Tue 8/15/17 554 System Acceptance and Handover 0 days Tue 7/18/17 Tue 7/18/17 555 Running In Period 28 days Wed 7/19/17 Tue 8/15/17 556 Final Delivery 0 days Tue 8/15/17 Tue 8/15/17 557 Install Banding Machine 18 days Mon 6/19/17 Thu 7/6/17 558 Banding Machine Training 2 days Wed 7/5/17 Thu 7/6/17 559 Government Accepts/Signs DD250 for Banding Machine in Bldg 2369 2 days Wed 7/5/17 Thu 7/6/17 560 Install Sweeper Machine 18 days Mon 6/19/17 Thu 7/6/17 561 Sweeper Machine Training 2 days Wed 7/5/17 Thu 7/6/17 562 Government Accepts/Signs DD250 for Sweeper Machine in Bldg 2369 2 days Wed 7/5/17 Thu 7/6/17
497 Conduct Warehouse Operations
4/25
1/9
1/16
7/18
7/18
3/31
7/18
8/15
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 3
563 Delivery & Install of MHE 24 days Mon 6/19/17 Wed 7/12/17 564 MHE Training 10 days Wed 6/28/17 Fri 7/7/17 565 Government Accepts/Signs DD250 for MHE in Bldg 2369 3 days Mon 7/10/17 Wed 7/12/17 564FS+2 days 566 Install Miscellaneous Equipment 48 days Wed 6/21/17 Mon 8/7/17 567 Government Accepts/Signs DD250 for Miscellaneous Equipment in Bldg 2369 3 days Mon 8/7/17 Wed 8/9/17 566 568 Input DMLSS Documentation 44 days Mon 6/19/17 Tue 8/1/17 569 Turn Over Equipment Reference Manuals 4 days Tue 8/1/17 Fri 8/4/17 570 Initiate Warranties on New Equipment 4 days Tue 8/1/17 Fri 8/4/17 571 RELOCATION SERVICES 731 days Tue 12/15/15 Thu 12/14/17 572 Building 2213 BOD 0 days Fri 1/13/17 Fri 1/13/17 573 Building 2213 Optical Activities Division OAD (from building 4108) 29 days Wed 5/31/17 Wed 6/28/17 574 Complete relocation risk assessment 3 days Fri 5/26/17 Tue 5/30/17 575 Conduct pre-Move Seminar and Issue Moving Supplies / Guides 1 day Wed 5/31/17 Wed 5/31/17 576 Pack, Box, Protect, all Reuse Equipment and TI items as required, Records etc. 7 days Tue 6/13/17 Mon 6/19/17 575FS+6 days 577 Transition & relocate all Reuse Equip to new space 7 days Tue 6/13/17 Mon 6/19/17 576SS 578 Unpack, Place FF & E, & IT Equipment, TI as required. 7 days Tue 6/13/17 Mon 6/19/17 577SS 579 Move Inventory/Transfer Custody 15 days Mon 6/12/17 Mon 6/26/17 580 USAMMCE Equipment Move and Installed by GC 5 days Mon 6/19/17 Fri 6/23/17 581 Pack, Box and Move Office Files and Personnel 7 days Tue 6/20/17 Mon 6/26/17 582 IMD Computer Configuration and Connection 1 day Mon 6/26/17 Mon 6/26/17 581 583 Update DMLSS 1 day Tue 6/27/17 Tue 6/27/17 584 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building
1 day Tue 6/27/17 Tue 6/27/17 582
585 OFB 0 days Wed 6/28/17 Wed 6/28/17 584 586 Building 2219 BOD 1 day Thu 1/12/17 Thu 1/12/17 587 Building 2219 336 days Tue 9/20/16 Mon 8/21/17 588 Information Management Division ADVON (from building 4108, 4123, & 4133) 233 days Tue 9/20/16 Wed 5/10/17 589 GC Move and Install of I3MP Cabinet & Server Racks from bldg 4133 2 days Tue 9/20/16 Wed 9/21/16 586FS+7 days 590 Complete relocation risk assessment DD 2977 (for both IMD ADVON & IMD) 3 days Wed 4/26/17 Fri 4/28/17 591 Conduct pre-Move Seminar and Issue Moving Supply / Guides 1 day Mon 5/1/17 Mon 5/1/17 595FS-8 days 592 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Thu 5/4/17 Fri 5/5/17 591FS+3 days 593 Transition & relocate all Reuse Equip and IT Items to new space 2 days Thu 5/4/17 Fri 5/5/17 592SS 594 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Thu 5/4/17 Fri 5/5/17 595 Pack, Box and Move Office Files and Personnel 1 day Mon 5/8/17 Mon 5/8/17 507 596 IMD Computer Configuration and Connection 1 day Mon 5/8/17 Mon 5/8/17 595SS 597 Update DMLSS 1 day Mon 5/8/17 Mon 5/8/17 598 OFB 0 days Tue 5/9/17 Tue 5/9/17 596 599 Information Management Division Main IMD (from building 4108 & 4133) 12 days Mon 7/31/17 Fri 8/11/17 600 Conduct pre-Move Seminar 1 day Mon 7/31/17 Mon 7/31/17 604FS-11 days 601 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 8/7/17 Tue 8/8/17 600FS+6 days 602 Transition & relocate all Reuse Equip and IT Items to new space 2 days Mon 8/7/17 Tue 8/8/17 601SS 603 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 8/7/17 Tue 8/8/17 602SS 604 Pack, Box and Move Office Files and Personnel 1 day Wed 8/9/17 Wed 8/9/17 566FS+2 days 605 IMD Computer Configuration and Connection 1 day Wed 8/9/17 Wed 8/9/17 602SS 606 Update DMLSS 1 day Wed 8/9/17 Wed 8/9/17 607 OFB 0 days Thu 8/10/17 Thu 8/10/17 604 608 Assemblage Management Branch (from building 4141) 19 days Wed 8/2/17 Mon 8/21/17 609 Complete relocation risk assessment DD 2977 3 days Wed 8/2/17 Fri 8/4/17 610 Conduct pre-Move Seminar 1 day Mon 8/7/17 Mon 8/7/17 600FS+6 days 611 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 8/14/17 Tue 8/15/17 610FS+6 days 612 Transition & relocate all Reuse Equip and IT Items to new space 5 days Mon 8/14/17 Fri 8/18/17 611SS 613 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 8/14/17 Tue 8/15/17 612SS 614 Move Inventory/Transfer Custody 3 days Mon 8/14/17 Wed 8/16/17 613SS 615 USAMMCE Equipment Move and Installed by GC 3 days Mon 8/14/17 Wed 8/16/17 614SS 616 Pack, Box, and Protect all Transitioning Staff Professional Items 1 day Wed 8/16/17 Wed 8/16/17 615FS-1 day 617 Pack, Box and Move Office Files and Personnel 1 day Wed 8/16/17 Wed 8/16/17 616SS 618 IMD Computer Configuration and Connection 1 day Thu 8/17/17 Thu 8/17/17 617 619 Update DMLSS 1 day Fri 8/18/17 Fri 8/18/17 620 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building 2219 1 day Fri 8/18/17 Fri 8/18/17 618
621 OFB 0 days Mon 8/21/17 Mon 8/21/17 620 622 Building 2222 BOD 0 days Wed 1/25/17 Wed 1/25/17 623 Building 2222 Clinical Engineering (CED) ADVON 233 days Tue 9/20/16 Wed 5/10/17 624 Complete relocation risk assessment DD 2977 (for CED ADVON & CED) 3 days Wed 4/26/17 Fri 4/28/17 625 Conduct pre-Move Seminar and Issue Moving Supply / Guides 1 day Tue 5/2/17 Tue 5/2/17 626 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Thu 5/4/17 Fri 5/5/17 627 Transition & relocate all Reuse Equip and IT Items to new space 2 days Thu 5/4/17 Fri 5/5/17 628 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Thu 5/4/17 Fri 5/5/17 629 Pack, Box and Move Office Files and Personnel 1 day Mon 5/8/17 Mon 5/8/17 630 IMD Computer Configuration and Connection 1 day Mon 5/8/17 Mon 5/8/17 631 Update DMLSS 1 day Mon 5/8/17 Mon 5/8/17 632 OFB 0 days Tue 5/9/17 Tue 5/9/17 633 Building 2222 Clinical Engineering Division CED (from building 4136) 15 days Mon 6/6/16 Mon 6/20/16 634 Conduct pre-Move Seminar 1 day Wed 5/31/17 Wed 5/31/17
1/13
575 Conduct pre-Move Seminar and Issue Moving Supplies / Guides
577 Transition & relocate all Reuse Equip to new space
579 Move Inventory/Transfer Custody
6/28
591 Conduct pre-Move Seminar and Issue Moving Supply / Guides
593 Transition & relocate all Reuse Equip and IT Items to new space
596 IMD Computer Configuration and Connection
5/9
600 Conduct pre-Move Seminar
602 Transition & relocate all Reuse Equip and IT Items to new space
605 IMD Computer Configuration and Connection
8/10
610 Conduct pre-Move Seminar
612 Transition & relocate all Reuse Equip and IT Items to new space
614 Move Inventory/Transfer Custody
615 USAMMCE Equipment Move and Installed by GC
618 IMD Computer Configuration and Connection
8/21
1/25
5/9
634 Conduct pre-Move Seminar
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 4
635 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 4 days Mon 6/12/17 Thu 6/15/17 636 Transition & relocate all Reuse Equip and IT Items to new space 5 days Mon 6/12/17 Fri 6/16/17 635SS 637 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 6/12/17 Tue 6/13/17 636SS 638 Move Inventory/Transfer Custody (MEDSTEP/ORF) 2 days Mon 6/12/17 Tue 6/13/17 637SS 639 Pack, Box and Move Office Files and Personnel 2 days Tue 6/13/17 Wed 6/14/17 640 IMD Computer Configuration and Connection 1 day Tue 6/14/16 Tue 6/14/16 641 Update DMLSS 1 day Mon 6/20/16 Mon 6/20/16 642 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building
1 day Tue 6/21/16 Tue 6/21/16
643 OFB 0 days Tue 6/21/16 Tue 6/21/16 644 Building 2238 BOD 0 days Tue 12/15/15 Tue 12/15/15 645 Building 2238 HAZMAT Packing (from building 4172) 14 days Fri 7/7/17 Thu 7/20/17 646 Complete relocation risk assessment DD 2977 3 days Tue 7/4/17 Thu 7/6/17 647 Conduct pre-Move Seminar 1 day Fri 7/7/17 Fri 7/7/17 523FS-14 days 648 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Wed 7/26/17 Thu 7/27/17 647SS+7 days 649 Transition & relocate all Reuse Equip and IT Items to new space 3 days Wed 7/26/17 Fri 7/28/17 648SS 650 Unpack, Place FF & E, & IT Equipment, TI as required. 3 days Wed 7/26/17 Fri 7/28/17 649SS 651 Move Inventory/Transfer Custody 3 days Wed 7/26/17 Fri 7/28/17 650SS 652 Pack, Box and Move Office Files and Personnel 3 days Wed 7/26/17 Fri 7/28/17 653 IMD Computer Configuration and Connection 2 days Fri 7/28/17 Sat 7/29/17 654 Update DMLSS 1 day Mon 7/31/17 Mon 7/31/17 655 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building
1 day Mon 7/31/17 Mon 7/31/17 653
656 OFB 0 days Mon 7/31/17 Mon 7/31/17 655 657 Building 2239 BOD 0 days Fri 4/7/17 Fri 4/7/17 658 Building 2239 HAZMAT Storage (from building 4170 & 4129) 7 days Fri 7/7/17 Mon 7/17/17 659 Complete relocation risk assessment DD 2977 3 days Tue 7/4/17 Thu 7/6/17 660 Conduct pre-Move Seminar 1 day Fri 7/7/17 Fri 7/7/17 523FS-14 days 661 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building
1 day Fri 7/14/17 Fri 7/14/17
662 OFB 0 days Mon 7/17/17 Mon 7/17/17 661 663 Building 2264 BOD 0 days Wed 1/18/17 Wed 1/18/17 664 Building 2264 78 days Tue 5/16/17 Tue 8/1/17 665 Logistics Division MAIN (from buildings 4190,4133,4016,4022,4025,4122,4136, & 4172) 12 days Mon 7/17/17 Fri 7/28/17 666 Conduct pre-Move Seminar 1 day Mon 7/17/17 Mon 7/17/17 671FS-10 days 667 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 7/17/17 Tue 7/18/17 666FS+6 days 668 Transition & relocate all Reuse Equip and IT Items to new space 2 days Mon 7/17/17 Tue 7/18/17 667SS 669 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 7/17/17 Tue 7/18/17 668SS 670 Move Inventory/Transfer Custody 7 days Fri 7/21/17 Thu 7/27/17 669SS 671 Pack, Box and Move Office Files and Personnel 1 day Wed 7/26/17 Wed 7/26/17 542SS+1 day 672 IMD Computer Configuration and Connection 1 day Wed 7/26/17 Wed 7/26/17 673 Update DMLSS 1 day Thu 7/27/17 Thu 7/27/17 674 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens o KAD for building
1 day Thu 7/27/17 Thu 7/27/17
675 OFB 1 day Mon 7/31/17 Mon 7/31/17 674 676 D&T Contingency (from buildings 4120, 4123, 4136, 4171, & 4172) 12 days Tue 5/30/17 Wed 6/14/17 677 Complete relocation risk assessment DD 2977 2 days Tue 5/30/17 Wed 5/31/17 678 Conduct Pre-Move Seminar 1 day Wed 5/31/17 Wed 5/31/17 531SS 679 Move Inventory/Transfer Custody 4 days Tue 6/6/17 Fri 6/9/17 682SS-3 days 680 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 6/12/17 Tue 6/13/17 678FS+6 days 681 Transition & relocate all Reuse Equip and IT Items to new space 2 days Mon 6/12/17 Tue 6/13/17 680SS 682 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 6/12/17 Tue 6/13/17 681SS 683 GC Move & Install of Generator from building 4120 9 days Tue 5/16/17 Wed 5/24/17 682SS 684 IMD Computer Configuration and Connection 1 day Tue 6/13/17 Tue 6/13/17 683FS+1 day 685 Update DMLSS 1 day Tue 6/13/17 Tue 6/13/17 686 OFB 0 days Wed 6/14/17 Wed 6/14/17 684SS 687 Building 2276 BOD 0 days Mon 10/24/16 Mon 10/24/16 688 Building 2276 Works Council (from building 4102) 14 days Thu 7/20/17 Thu 8/3/17 689 Complete relocation risk assessment DD 2977 3 days Thu 7/20/17 Mon 7/24/17 690 Conduct Pre-Move Seminar 1 day Tue 7/25/17 Tue 7/25/17 694FS-8 days 691 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 7/31/17 Tue 8/1/17 690FS+5 days 692 Transition & relocate all Reuse Equip and IT Items to new space 1 day Mon 7/31/17 Mon 7/31/17 691SS 693 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 7/31/17 Tue 8/1/17 692SS 694 Pack, Box and Move Office Files and Personnel 1 day Tue 8/1/17 Tue 8/1/17 541 695 IMD Computer Configuration and Connection 1 day Tue 8/1/17 Tue 8/1/17 694SS 696 Update DMLSS 1 day Tue 8/1/17 Tue 8/1/17 697 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building
1 day Wed 8/2/17 Wed 8/2/17 695
698 OFB 0 days Thu 8/3/17 Thu 8/3/17 697 699 Building 2369 BOD 0 days Tue 2/28/17 Tue 2/28/17 700 Building 2369 64 days Mon 6/26/17 Mon 8/28/17 701 D&T ADVON (from buildings 4171, 4136, & 4196) 26 days Mon 7/24/17 Fri 8/18/17 702 Complete relocation risk assessment DD 2977 3 days Wed 6/21/17 Fri 6/23/17 703 GC Move & Install of 2nd Generator and 2nd UPS from bldg 4196 5 days Mon 6/26/17 Fri 6/30/17 704 Conduct pre-Move Seminar 1 day Thu 7/20/17 Thu 7/20/17 541FS-12 days 705 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Thu 7/27/17 Fri 7/28/17 704FS+6 days 706 Transition & relocate all Reuse Equip and IT Items to new space 2 days Thu 7/27/17 Fri 7/28/17 705FS-2 days
636 Transition & relocate all Reuse Equip and IT Items to new space
638 Move Inventory/Transfer Custody (MEDSTEP/ORF)
640 IMD Computer Configuration and Connection
6/21
12/15
647 Conduct pre-Move Seminar
649 Transition & relocate all Reuse Equip and IT Items to new space
651 Move Inventory/Transfer Custody
653 IMD Computer Configuration and Connection
7/31
4/7
7/17
1/18
668 Transition & relocate all Reuse Equip and IT Items to new space
670 Move Inventory/Transfer Custody
672 IMD Computer Configuration and Connection
6/14
10/24
8/3
2/28
704 Conduct pre-Move Seminar
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 5
707 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Thu 7/27/17 Fri 7/28/17 706SS 708 Move Inventory/Transfer Custody 2 days Thu 7/27/17 Fri 7/28/17 707SS 709 Pack, Box and Move Office Files and Personnel 1 day Mon 7/31/17 Mon 7/31/17 704FS+10 days 710 IMD Computer Configuration and Connection 1 day Tue 8/1/17 Tue 8/1/17 709 711 Life Safety Training/Rehearsal 1 day Wed 8/2/17 Wed 8/2/17 710 712 Close Reefer / Freezer / Hazmat for Packing 3 days Wed 7/26/17 Fri 7/28/17 714FS-5 days 713 Pack and Move Receiving to KAD 12 days Mon 7/24/17 Fri 8/4/17 714 Start Receiving Operations 0 days Mon 8/7/17 Mon 8/7/17 713SS 715 Vault Certification and Acceptance (Security) 1 day Mon 7/31/17 Mon 7/31/17 716 Pack and Move Vault & Cage 3 days Wed 7/26/17 Fri 7/28/17 714FS+3 days 717 Vault and Cage Operational 0 days Mon 7/31/17 Mon 7/31/17 714FS+7 days 718 Prepack Bulk for moveto KAD 5 days Fri 8/11/17 Tue 8/15/17 714FS+9 days 719 Move Bulk to KAD 5 days Fri 8/11/17 Tue 8/15/17 714FS+12 days 720 Pack and Move Turn-in Section 2 days Mon 8/14/17 Tue 8/15/17 714FS+7 days 721 GC Move & Install of 2nd Generator and 2nd UPS from bldg 4196 1 day Wed 8/16/17 Wed 8/16/17 722 Stock Bulk in KAD 3 days Wed 8/16/17 Fri 8/18/17 714FS+14 days 723 Update DMLSS 1 day Fri 8/18/17 Fri 8/18/17 724 Bulk Operational in KAD 1 day Fri 8/18/17 Fri 8/18/17 714FS+15 days 725 D&T Main [from building 4171, 4136, 4129, 4170, 4172, 4140 (TI), 4141 (AM), & 4143] 27 days Tue 8/1/17 Mon 8/28/17 726 Complete relocation risk assessment DD 2977 3 days Tue 8/1/17 Thu 8/3/17 727 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 728 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 4 days Fri 8/18/17 Mon 8/21/17 727FS+13 days 729 Transition & relocate all Reuse Equip and IT Items to new space 8 days Fri 8/18/17 Fri 8/25/17 728SS 730 Unpack, Place FF & E, & IT Equipment, TI as required. 4 days Fri 8/18/17 Mon 8/21/17 728SS 731 Move Inventory/Transfer Custody (BIN) 7 days Fri 8/18/17 Thu 8/24/17 728SS 732 GC Move & Install 5 days Mon 8/21/17 Fri 8/25/17 731FS-4 days 733 Pack, Box and Move Office Files and Personnel 5 days Mon 8/21/17 Fri 8/25/17 734 IMD Computer Configuration and Connection 3 days Tue 8/22/17 Thu 8/24/17 733SS+1 day 735 Update DMLSS 1 day Thu 8/24/17 Thu 8/24/17 736 Gov't Accepts/Signs DD250 for Equipment Relocated from Pirmasens to KAD for building 2369 1 day Fri 8/25/17 Fri 8/25/17 734
737 OFB 0 days Mon 8/28/17 Mon 8/28/17 736 738 MMD (from building 4108) 14 days Fri 8/4/17 Thu 8/17/17 739 Complete relocation risk assessment DD 2977 3 days Tue 8/1/17 Thu 8/3/17 740 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 741 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 8/14/17 Tue 8/15/17 742 Transition & relocate all Reuse Equip and IT Items to new space 2 days Mon 8/14/17 Tue 8/15/17 741SS 743 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 8/14/17 Tue 8/15/17 741SS 744 Pack, Box and Move Office Files and Personnel 1 day Tue 8/15/17 Tue 8/15/17 745 IMD Computer Configuration and Connection 1 day Tue 8/15/17 Tue 8/15/17 744FS-1 day 746 Update DMLSS 1 day Tue 8/15/17 Tue 8/15/17 747 OFB 0 days Fri 8/18/17 Fri 8/18/17 745 748 CSD (from building 4108) 5 days Fri 8/4/17 Tue 8/8/17 749 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 750 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 1 day Fri 8/4/17 Fri 8/4/17 749FS+6 days 751 Transition & relocate all Reuse Equip and IT Items to new space 1 day Fri 8/4/17 Fri 8/4/17 750SS 752 Unpack, Place FF & E, & IT Equipment, TI as required. 1 day Fri 8/4/17 Fri 8/4/17 750SS 753 Pack, Box and Move Office Files and Personnel 1 day Fri 8/4/17 Fri 8/4/17 752FS-1 day 754 IMD Computer Configuration and Connection 1 day Mon 8/7/17 Mon 8/7/17 753FS-2 days 755 Update DMLSS 1 day Mon 8/7/17 Mon 8/7/17 756 OFB 1 day Tue 8/8/17 Tue 8/8/17 754 757 Safety Office (from building 4108) 7 days Fri 8/4/17 Mon 8/14/17 758 Complete relocation risk assessment DD 2977 3 days Tue 8/1/17 Thu 8/3/17 759 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 760 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 1 day Fri 8/11/17 Fri 8/11/17 759FS+6 days 761 Transition & relocate all Reuse Equip and IT Items to new space 1 day Fri 8/11/17 Fri 8/11/17 760SS 762 Unpack, Place FF & E, & IT Equipment, TI as required. 1 day Fri 8/11/17 Fri 8/11/17 760SS 763 Pack, Box and Move Office Files and Personnel 1 day Fri 8/11/17 Fri 8/11/17 764 IMD Computer Configuration and Connection 1 day Fri 8/11/17 Fri 8/11/17 765 Update DMLSS 1 day Fri 8/11/17 Fri 8/11/17 766 OFB 0 days Mon 8/14/17 Mon 8/14/17 764SS 767 HHD [(SDNCO)from buildings 4108 & 4102] 12 days Fri 8/4/17 Tue 8/15/17 768 Complete relocation risk assessment DD 2977 3 days Tue 8/1/17 Thu 8/3/17 769 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 770 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Wed 8/9/17 Thu 8/10/17 769FS+6 days 771 Transition & relocate all Reuse Equip and IT Items to new space 1 day Fri 8/11/17 Fri 8/11/17 770SS 772 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Fri 8/11/17 Mon 8/14/17 770SS 773 Pack, Box and Move Office Files and Personnel 1 day Mon 8/14/17 Mon 8/14/17 770SS 774 IMD Computer Configuration and Connection 1 day Mon 8/14/17 Mon 8/14/17 773SS 775 Update DMLSS 1 day Mon 8/14/17 Mon 8/14/17 776 OFB 0 days Tue 8/15/17 Tue 8/15/17 774 777 Building 3201 BOD 0 days Thu 12/14/17 Thu 12/14/17 778 Building 3201 – Kleber Admin Building 27 days Thu 7/20/17 Tue 8/15/17
709 Pack, Box and Move Office Files and Personnel
710 IMD Computer Configuration and Connection
8/7
715 Vault Certification and Acceptance (Security)
7/31
727 Conduct pre-Move Seminar
729 Transition & relocate all Reuse Equip and IT Items to new space
731 Move Inventory/Transfer Custody (BIN)
734 IMD Computer Configuration and Connection
8/28
740 Conduct pre-Move Seminar
742 Transition & relocate all Reuse Equip and IT Items to new space
745 IMD Computer Configuration and Connection
8/18
749 Conduct pre-Move Seminar
751 Transition & relocate all Reuse Equip and IT Items to new space
754 IMD Computer Configuration and Connection
759 Conduct pre-Move Seminar
761 Transition & relocate all Reuse Equip and IT Items to new space
763 Pack, Box and Move Office Files and Personnel
764 IMD Computer Configuration and Connection
8/14
769 Conduct pre-Move Seminar
771 Transition & relocate all Reuse Equip and IT Items to new space
774 IMD Computer Configuration and Connection
8/15
12/14
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 6
779 Business Support Office BSO (from building 4155) 8 days Thu 7/20/17 Mon 7/31/17 780 Complete relocation risk assessment DD 2977 3 days Mon 7/17/17 Wed 7/19/17 781 Conduct pre-Move Seminar 1 day Thu 7/20/17 Thu 7/20/17 785FS-9 days 782 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Thu 7/27/17 Fri 7/28/17 781FS+6 days 783 Transition & relocate all Reuse Equip and IT Items to new space 2 days Thu 7/27/17 Fri 7/28/17 782SS 784 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Thu 7/27/17 Fri 7/28/17 783SS 785 Pack, Box and Move Office Files and Personnel 2 days Thu 7/27/17 Fri 7/28/17 786 IMD Computer Configuration and Connection 1 day Fri 7/28/17 Fri 7/28/17 787 Update DMLSS 1 day Fri 7/28/17 Fri 7/28/17 788 OFB 0 days Mon 7/31/17 Mon 7/31/17 786 789 Resource Management Division RMD (from building 4108) 12 days Thu 7/20/17 Mon 7/31/17 790 Complete relocation risk assessment DD 2977 3 days Mon 7/17/17 Wed 7/19/17 791 Conduct pre-Move Seminar 1 day Thu 7/20/17 Thu 7/20/17 795FS-9 days 792 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Thu 7/27/17 Fri 7/28/17 791FS+6 days 793 Transition & relocate all Reuse Equip and IT Items to new space 2 days Thu 7/27/17 Fri 7/28/17 792SS 794 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Thu 7/27/17 Fri 7/28/17 793SS 795 Pack, Box and Move Office Files and Personnel 2 days Thu 7/27/17 Fri 7/28/17 542FS+10 days 796 IMD Computer Configuration and Connection 2 days Fri 7/28/17 Mon 7/31/17 795SS+1 day 797 Update DMLSS 1 day Fri 7/28/17 Fri 7/28/17 798 Gov't Accepts/Signs DD250 for Equipment Relocated from Permasens to KAD for building 3201 1 day Fri 7/28/17 Fri 7/28/17 796
799 OFB 0 days Mon 7/31/17 Mon 7/31/17 798 800 HHD/Ops Office (from buildings 4108,4102, & 4155) 18 days Mon 7/17/17 Wed 8/9/17 801 Complete relocation risk assessment DD 2977 16 days Mon 7/17/17 Tue 8/1/17 802 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 803 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 2 days Mon 8/7/17 Tue 8/8/17 802FS+5 days 804 Transition & relocate all Reuse Equip and IT Items to new space 2 days Mon 8/7/17 Tue 8/8/17 803SS 805 Unpack, Place FF & E, & IT Equipment, TI as required. 2 days Mon 8/7/17 Tue 8/8/17 804SS 806 Pack, Box and Move Office Files and Personnel 1 day Tue 8/8/17 Tue 8/8/17 807 IMD Computer Configuration and Connection 1 day Tue 8/8/17 Tue 8/8/17 808 Update DMLSS 1 day Tue 8/8/17 Tue 8/8/17 809 OFB 0 days Wed 8/9/17 Wed 8/9/17 807 810 Security (from buidlings 4108 & 4107) 8 days Fri 8/4/17 Fri 8/11/17 811 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 812 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 1 day Thu 8/10/17 Thu 8/10/17 811FS+6 days 813 Transition & relocate all Reuse Equip and IT Items to new space 1 day Thu 8/10/17 Thu 8/10/17 812SS 814 Unpack, Place FF & E, & IT Equipment, TI as required. 1 day Thu 8/10/17 Thu 8/10/17 813SS 815 Pack, Box and Move Office Files and Personnel 1 day Thu 8/10/17 Thu 8/10/17 816 IMD Computer Configuration and Connection 1 day Thu 8/10/17 Thu 8/10/17 817 Update DMLSS 1 day Thu 8/10/17 Thu 8/10/17 818 OFB 0 days Fri 8/11/17 Fri 8/11/17 816SS 819 USAMMCE Command (from building 4108) 8 days Fri 8/4/17 Fri 8/11/17 820 Complete relocation risk assessment DD 2977 3 days Tue 8/1/17 Thu 8/3/17 821 Conduct pre-Move Seminar 1 day Fri 8/4/17 Fri 8/4/17 542 822 Pack, Box, Protect, all IT items Reuse Equipment and TI items as required, Records etc. 1 day Thu 8/10/17 Thu 8/10/17 821FS+6 days 823 Transition & relocate all Reuse Equip and IT Items to new space 1 day Thu 8/10/17 Thu 8/10/17 822SS 824 Unpack, Place FF & E, & IT Equipment, TI as required. 1 day Thu 8/10/17 Thu 8/10/17 823SS 825 Pack, Box and Move Office Files and Personnel 1 day Fri 8/11/17 Fri 8/11/17 826 IMD Computer Configuration and Connection 1 day Fri 8/11/17 Fri 8/11/17 825SS 827 Update DMLSS 1 day Fri 8/11/17 Fri 8/11/17 828 OFB 0 days Fri 8/11/17 Fri 8/11/17 826 829 Clean Up Husterhoeh Kaserne 140 days Wed 6/14/17 Tue 10/31/17 830 Receive and Maintain Dumpters According to Schedule 142 days Mon 6/12/17 Tue 10/31/17 639SS-1 day 831 Remove excess from CED building 4136 5 days Thu 6/15/17 Mon 6/19/17 639 832 Remove excess from Contingency buildings 4171 & 4136 4 days Fri 6/16/17 Mon 6/19/17 831SS+1 day 833 Remove excess from OAD building 4108 5 days Thu 6/29/17 Mon 7/3/17 581SS 834 Remove excess from HAZMAT Packing building 4172 3 days Tue 7/4/17 Thu 7/6/17 833 835 Remove excess from HAZMAT Storage building 4170 3 days Tue 7/18/17 Thu 7/20/17 836 Remove excess from Works Council building 4102 1 day Mon 7/31/17 Mon 7/31/17 694FS-2 days 837 Remove excess from BSO building 4155 3 days Tue 8/1/17 Thu 8/3/17 785FS+1 day 838 Remove excess from IMD building 4108 & 4123 2 days Thu 8/10/17 Fri 8/11/17 604SS 839 Remove excess from RMD building 4108 1 day Tue 8/15/17 Tue 8/15/17 795SS+1 day 840 Remove excess from USAMMCE HQs, RMD, HHD/OPS, & Secuity, buildings 4108 &4102 3 days Tue 8/15/17 Thu 8/17/17 839SS 841 Remove Excess from LOG buildings 4016,4022,4025,4029,4122,4123,4133,4136,4148,4190 10 days Tue 8/15/17 Thu 8/24/17 840SS 842 Remove excess from MMD, CSD, Safety, Security & SDNCO, building 4108 5 days Thu 8/17/17 Mon 8/21/17 744 843 Remove excess from Assemblage Management buildings 4141 &4172 2 days Thu 8/17/17 Fri 8/18/17 617 844 Remove excess from D&T buildings 4136,4140,4170,4171, and 4172 7 days Wed 8/23/17 Tue 8/29/17 733SS+2 days 845 Remove excess from Gym building 4101 2 days Thu 8/24/17 Fri 8/25/17 844SS+1 day 846 Remove excess from building 4015 Smoking Hood 1 day Mon 8/28/17 Mon 8/28/17 845 847 Remove excess from 4112, Reviewing Stand/Running Track 1 day Tue 8/29/17 Tue 8/29/17 846 848 Remove excess from 4168, Overflow 1 day Wed 8/30/17 Wed 8/30/17 847 849 Remove excess from Guard/Security building 4107 1 day Wed 8/30/17 Wed 8/30/17 848SS 850 Clean all Buildings 91 days Tue 8/1/17 Mon 10/30/17
781 Conduct pre-Move Seminar
783 Transition & relocate all Reuse Equip and IT Items to new space
786 IMD Computer Configuration and Connection
7/31
791 Conduct pre-Move Seminar
793 Transition & relocate all Reuse Equip and IT Items to new space
796 IMD Computer Configuration and Connection
7/31
802 Conduct pre-Move Seminar
804 Transition & relocate all Reuse Equip and IT Items to new space
807 IMD Computer Configuration and Connection
8/9
811 Conduct pre-Move Seminar
813 Transition & relocate all Reuse Equip and IT Items to new space
816 IMD Computer Configuration and Connection
8/11
821 Conduct pre-Move Seminar
823 Transition & relocate all Reuse Equip and IT Items to new space
826 IMD Computer Configuration and Connection
8/11
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 7
851 Turn in Husterhoeh Buildings 63 days Wed 8/30/17 Tue 10/31/17 850SS+29 days 852 Excess Turn In 853 Turn in RTCH 2 days Mon 12/12/16 Tue 12/13/16 854 Furniture 123 days Fri 6/30/17 Mon 10/30/17 855 Advertise to Local Agencies 14 days Fri 6/30/17 Thu 7/13/17 856 Assemble and Stage Furniture for Processing 14 days Fri 7/14/17 Thu 7/27/17 857 Schedule the Furniture Excess Turn In 1 day Mon 8/28/17 Mon 8/28/17 855 858 Assemble Furniture onto Pallets 14 days Tue 8/29/17 Fri 9/15/17 859 Deliver Furniture to Excess Turn In 31 days Mon 9/18/17 Mon 10/30/17 860 Medical 106 days Thu 6/1/17 Thu 9/14/17 861 Advertise to Local Agencies / TRIMED 47 days Thu 6/1/17 Mon 7/17/17 862 Assemble and Stage Medical Equipment for Processing 14 days Tue 8/15/17 Mon 8/28/17 861FS+30 days 863 Schedule Medical Equipment for Excess Turn In 1 day Wed 8/23/17 Wed 8/23/17 862SS+8 days 864 TI and Condition Code Medical Equipment 7 days Fri 8/25/17 Thu 8/31/17 862SS+10 days 865 Assemble Medical Equipment onto Pallets 11 days Fri 8/25/17 Mon 9/4/17 864SS 866 Deliver Medical Equipment to Excess Turn In 10 days Tue 9/5/17 Thu 9/14/17 865 867 Non-medical 136 days Wed 6/14/17 Fri 10/27/17 868 Assemble and Stage Non-medical Equipment for Processing 78 days Wed 6/14/17 Wed 8/30/17 869 Advertise to Local Agencies 15 days Mon 8/14/17 Mon 8/28/17 868FS-17 days 870 Schedule Non-medical for Excess Turn In 1 day Mon 8/28/17 Mon 8/28/17 869FS-1 day 871 Assemble Non-medical Equipment onto Pallets 30 days Tue 8/29/17 Wed 9/27/17 870 872 Deliver Non-medical Equipment to Excess Turn In 59 days Wed 8/30/17 Fri 10/27/17 871SS+1 day 873 Ribbon Cutting Ceremony 192 days Wed 3/1/17 Fri 9/8/17 874 USAMMCE coordinates VIPs and invite list 125 days Wed 3/1/17 Mon 7/3/17 875 Advance email notifications 125 days Wed 3/1/17 Mon 7/3/17 876 USAMMCE Submits ceremony requirements (guest speaker, flyer, and ceremony agenda) 125 days Wed 3/1/17 Mon 7/3/17 877 Notify support commands 30 days Thu 6/15/17 Fri 7/14/17 878 Develop ceremony wayfinding 30 days Thu 6/15/17 Fri 7/14/17 879 Place order for ceremony equipment / Logistics support (tents, chairs, tables, etc) 30 days Thu 6/15/17 Fri 7/14/17 880 Commence Ribbon Cutting Ceremony 1 day Fri 9/8/17 Fri 9/8/17 8SS
881 CLOSEOUT
882 Finalize and submit any remaining documentation 8 days Mon 9/11/17 Mon 9/18/17 883 Compile all Documents in Electronic/Hardcopy 8 days Tue 9/19/17 Tue 9/26/17 882 884 Facilitate Project Files/History Transfer 7 days Wed 9/27/17 Tue 10/3/17 883 885 Provide Lessons Learned Documentation 0 days Wed 11/15/17 Wed 11/15/17 884FS+40 days 886 Closeout Complete 0 days Sun 12/17/17 Sun 12/17/17 10SS
9/8
882 Finalize and submit any remaining documentation
883 Compile all Documents in Electronic/Hardcopy
884 Facilitate Project Files/History Transfer
11/15
12/17
B M E B M E B M E B M E B April March February January December November October
KAD Task Order Schedule (TOS) Page 8