SOLICITATION_W912DY-16-R-0077_MEGA-RESTRICTED.pdf

PDF 879 KB Posted

Attached to
Multiple Environmental Government Acquisition (MEGA)-Restricted Federal contract opportunity
Solicitation number
W912DY-16-R-0077
Issued by
Department of the Army Corps of Engineers Engineering Support Center Huntsville

About this file

This is a solicitation for a Multiple Award Task Order Contract (MATOC) to provide environmental remediation and munitions response services to the U.S. Army Corps of Engineers Engineering Support Center Huntsville. Services include munitions and explosives of concern investigations and removal, hazardous waste cleanup, and other compliance activities. The period of performance is a three-year base period with one two-year option. The total contract capacity is $400 million to be shared among five awardees. Task orders will be issued on a competitive basis using fair opportunity procedures. Pricing for task orders may be firm-fixed-price or cost-plus-fixed-fee. Proposals are due by 2:00 PM local time on November 30, 2017. Award is anticipated for restricted competition among small businesses.

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Environmental Government Acquisition (MEGA)-Restricted, newest first.
File Type Posted
W912DY-16-R-0077_AMD_0005_conformed.pdf PDF
W912DY-16-R-0077_AMD_0005.pdf PDF
amendment_0004_conformed_copy.pdf PDF
projnet_12.21.2017.pdf PDF
amendment_0004.pdf PDF
Exhibit_5_-_1of3.pdf PDF
EXHIBIT_5_-_2of3.pdf PDF
EXHIBIT_6_-_Key_Subs_and_Personnel.doc DOC document
EXHIBIT_2_-_PRS.doc DOC document
ATTACHMENT_I_-_Sample_Task_Order_Pricing_WorkSheets_HNC_Rev_10_Aug_2017.xls XLS spreadsheet
EXHIBIT_5_-_3of3.pdf PDF
EXHIBIT_1_-_HNC_DIDs_.pdf PDF
projnet_responses_final.pdf PDF
ATTACHMENT_C_-_Sample_Task_Order_27Nov2017.docx DOCX document
ATTACHMENT_A_-_Past_Performance_Questionnaire.doc DOC document
ATTACHMENT_E_-_Letter_of_Commitment_for_Key_Personnel.doc DOC document
EXHIBIT_3_-_QASP.docx DOCX document
ATTACHMENT_F_-_Letter_of_Commitment_of_Key_Subcontractor.doc DOC document
W912DY16R0077_amendment_0003.pdf PDF
Amendment_-_ATTACHMENT_H_-_Schedule_B_worksheet-HNC.XLS XLS spreadsheet
ATTACHMENT_B_-_EXPERIENCE_PP_REFERENCE.doc DOC document
EXHIBIT_4_-_Profit-Fee_Calculation_Worksheet.doc DOC document
W912DY16R0077_Amendment_0003_conformed_copy.pdf PDF
ATTACHMENT_G_-_Sample_Task_Order_Wage_Det.docx DOCX document
ATTACHMENT_D_-_Key_Personnel_Resume.doc DOC document
W912DY16R0077_amendment_0002_conformed_copy.pdf PDF
W912DY16R0077_amendment_0002.pdf PDF
W912DY16R00770001.pdf PDF
W912DY16R0077_conformed_solicitation.pdf PDF
ATTACHMENT_C_-_Sample_Task_Order_Rev3Aug2017.pdf PDF
EXHIBIT_5_-_2of3.pdf PDF
ATTACHMENT_H_-_Schedule_B_worksheet-HNC.xls XLS spreadsheet
Exhibit_5_-_1of3.pdf PDF
EXHIBIT_5_-_3of3.pdf PDF
EXHIBIT_1_-_HNC_DIDs_.pdf PDF
ATTACHMENT_I_-_Sample_Task_Order_Pricing_WorkSheets_HNC_Rev_10_Aug_2017.xls XLS spreadsheet
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CODE

(Hour)

PAGE(S)

until 02:00 PM local time 30 Nov 2017

X

A X B X C X D

EX

X

G F 134 - 144

145 - 166 X H 167 - 177

Lashonda.Smith@uasce.army.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 177

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

W912DY 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 2 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and

See Instructions to Offerors conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

LASHONDA SMITH 256-895-7795

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

1 - 3 4 - 10

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT X

PACKAGING AND MARKING

11 - 62

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 66 - 70 X

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 71 - 75 X M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

76 - 105

PART II - CONTRACT CLAUSES

US ARMY ENGINEERING & SUPPORT CENTER

HUNTSVILLE ENGINEERING & SUPPORT CENTER

P.O. BOX 1600

HUNTSVILLE AL 35807-4301

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

106 - 133

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

18 Sep 2017

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

W912DY-16-R-0077

Section A - Solicitation/Contract Form

EXECUTIVE SUMMARY

ALL ADMINISTRATION AND FUTURE TASK ORDERS UNDER THIS MATOC WILL BE

ISSUED BY THE U.S. ARMY CORPS OF ENGINEERS, HUNTSVILLE CENTER (CEHNC).

1. The objective of this multiple-award Indefinite Delivery Indefinite Quantity (IDIQ) contract is to procure the services of Small Business firms to perform Military Munitions Response Program (MMRP) responses involving conventional munitions; Environmental Compliance and Remediation Services (ECRS); and Other Munitions-Related Services (OMRS), as necessary to enable lands and waters to be safely and efficiently used for their intended purpose.

2. A target multiple-award IDIQ contract pool consisting of a total of five (5) contractors is planned to result from this acquisition, however the government reserves the right to award more, less, or none at all. All services procured under this IDIQ will use a performance-based work statement at the task order level. The manner in which the requirements are to be accomplished will not be dictated to the IDIQ awardees.

3. The capacity for the multiple-award IDIQ contract pool is $400 Million. The total capacity amount will be shared among all awardees in the multiple-award pool. The IDIQ awardees will only compete among the other awardees in the pool for task order awards.

4. Task orders will be awarded against the basic IDIQ contracts using the fair opportunity procedures discussed in FAR 16.5 in addition to the competitive source selection procedures identified in Section 803 of Public Law 107-107 implemented in DFARS 216.505-70 and Public Law 110-181, Section 843. Each order exceeding $3,500.00 will be awarded on a competitive basis in accordance with FAR 16.505 and DFARS 216.505-70 (c), unless an exception described in FAR 16.505(b)(2) or DFARS 216.505-70(b)(1) applies. Task orders may be Firm-Fixed Price (FFP) or Cost Plus Fixed Fee (CPFF). Based on recent procurement experience, it is anticipated that approximately 85% of the task order efforts will be CPFF for work of an indefinite nature or to support an urgent need. Individual task orders may also contain a combination of FFP and CPFF; e.g., planning and characterization may be FFP while fieldwork may be CPFF.

5. The ordering period shall commence upon the date of award and may continue for a period of five years. This consists of a three-year base period with one (1), two-year option period; if the option is exercised. Labor rates may be escalated at the beginning of the option period (but See FAR 52.222-43 (b) for limitations) as provided in the schedule; however, the labor rates in effect at the time a task order is awarded will remain in effect through completion of the task order, unless modified due to an increase in the Department of Labor wage rates in accordance with FAR 52.222-43, FAR 52.222-44, and Chapter 7 of Engineer Pamphlet 1180-1-1.

6. The Government reserves the right to make staggered awards. Later awarded contracts will have an initial period of performance that will be less than the full three-year base period in duration and will end on the same date as all other contractors which receive a basic IDIQ award.

The option period will be the same for all awardees, if exercised. If determined to be in the Government’s interest to hold discussions, discussions may be held with Offerors remaining in the competitive range after initial awards have been made to some Offerors.

7. When Request for Proposals (RFPs) for task order requirements are issued, offerors must provide sufficient detail with regard to labor categories and hours, material, and travel to allow an evaluation of the proposed cost. Travel costs shall not exceed the amounts allowed under the Joint Travel Regulation. Profit/fee is not allowable on travel costs.

8. For CPFF orders, all hours for direct labor shall be supported by individual daily job cards or time records signed by the individual thereof.

9. CEHNC is the Procurement Contracting Office and no other agency can make changes to the Base Contract. Other USACE offices, upon authorization from CEHNC, may issue task orders.

CEHNC may also transfer task orders to other USACE offices for administration. Only a warranted Contracting Officer (either PCO or ACO) acting within their delegated limits has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.

10. The minimum guaranteed order for each awardee shall be $3,000.00 for the base period only.

11. THE FOLLOWING ELEMENTS OF [Name of Offeror] PROPOSAL SUBMITTED IN

RESPONSE TO SOLICITATION W912DY-16-R-0077 ARE HEREBY INCORPORATED

INTO THIS CONTRACT.

A. The rates proposed by the contractor in Attachment H are binding cost elements.

These rates shall be maximum allowable rates for task orders issued during the ordering period of this contract. Thus the rates proposed on a task order may be less than those proposed in the contractor’s Attachment H of the IDIQ contract, but may not exceed the maximum rates included in the basic IDIQ contract award unless the applicable wage determination is higher than the contractor base rate in the contract. The Government may extend the ordering period in accordance with terms in FAR Clause 52.217-8, Option to Extend Services. The evaluated rates in effect during the base period or option period will remain in effect during any extension executed under the stated clause; not to exceed six months.

B. Technical Exhibit 6, “Key Subcontractors and Key Personnel”.

C. [Name of Offeror] subcontracting plan dated xx/xx/xxxx [date], and approved by the Contracting Officer on xx/xx/xxxx [date], is hereby incorporated into this contract.

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES MAX

QUANTITY

UNIT UNIT PRICE MAX AMOUNT

0001 UNDEFINED Job FFP Environmental Remediation Svcs

FFP

This CLIN is for Firm Fixed Priced Task Orders or for Firm Fixed Price Tasks within a Task Order. The contractor shall perform environmental remediation and other related functions as required by Section C and applicable task order specifications. The individual task order Performance Work Statement will clearly indicate the specific requirements of the task(s) awarded. The contractor shall furnish the required labor, general management, quality management, administration, travel, supervision, quality control, supplies, materials, equipment (not otherwise furnished as Government Furnished Materials), transportation, and documents/permits necessary to deliver services and any associated deliverables within schedule and in accordance with contract terms and conditions, reference documents, specific contract and task order requirements, and contract clauses.

The Contractor shall be responsible for obtaining all required documents/permits required for travel and performance of work.

FOB: Destination

MAX

NET AMT

UNIT UNIT PRICE MAX AMOUNT

0002 UNDEFINED Job CPFF Environmental Remediation Svcs

CPFF

This CLIN is for Cost Plus Fixed Fee Task Orders or for Cost Plus Fixed Fee Tasks within a Task Order. The contractor shall perform environmental remediation and other related functions as required by Section C and applicable task order specifications. The individual task order Performance Work Statement will clearly indicate the specific requirements of the task(s) awarded. The contractor shall furnish the required labor, general management, quality management, administration, travel, supervision, quality control, supplies, materials, equipment (not otherwise furnished as Government Furnished Materials), transportation, and documents/permits necessary to deliver services and any associated deliverables within schedule and in accordance with contract terms and conditions, reference documents, specific contract and task order requirements, and contract clauses. The Contractor shall be responsible for obtaining all required documents/permits required for travel and performance of work.

In accordance with FAR 15.404-4(c)(4)(i)(C), the fixed fee shall not exceed 10%.

MAX COST

FIXED FEE

TOTAL MAX COST + FEE

UNIT UNIT PRICE MAX AMOUNT

0003 UNDEFINED Job Contractor Manpower Reporting

FFP

This CLIN is used for the pricing of the collection and reporting of Contractor Manpower Reporting data as described in Section C. Reporting period will be the period of performance not to exceed twelve months ending 30 September of each Government Fiscal Year and must be reported by 31 October of each calendar year.

UNIT UNIT PRICE MAX AMOUNT

0004 UNDEFINED Each Minimum Guarantee

FFP

The Government limits the minimum guarantee to extend only to the base contract period of performance for this IDIQ contract and only in the amount of $3000.00. Funding for this minimum guarantee will be obligated against this contract line item at the time of the base contract award. (NOTE: This is a minimum ordering amount; not a minimum payment.) Should the Government fail to award task order(s) with an aggregate value meeting or exceeding the minimum guarantee of $3000.00 within the period of performance of the base contract, then, ONLY after submittal of proof of contract damages from the contractor, the Government may pay the contractor up to $3000.00. Following the agency’s payment of an amount meeting/exceeding the minimum guarantee under a task order award during the base period, the agency will de-obligate funding for the minimum guarantee.

UNIT UNIT PRICE MAX AMOUNT

1001 UNDEFINED Job OPTION FFP Environmental Remediation Svcs

FFP

This CLIN is for Firm Fixed Priced Task Orders or for Firm Fixed Price Tasks within a Task Order. The contractor shall perform environmental remediation and other related functions as required by Section C and applicable task order specifications. The individual task order Performance Work Statement will clearly indicate the specific requirements of the task(s) awarded. The contractor shall furnish the required labor, general management, quality management, administration, travel, supervision, quality control, supplies, materials, equipment (not otherwise furnished as Government Furnished Materials), transportation, and documents/permits necessary to deliver services and any associated deliverables within schedule and in accordance with contract terms and conditions, reference documents, specific contract and task order requirements, and contract clauses.

The Contractor shall be responsible for obtaining all required documents/permits required for travel and performance of work.

UNIT UNIT PRICE MAX AMOUNT

1002 UNDEFINED Job OPTION CPFF Environmental Remediation Svcs

CPFF

This CLIN is for Cost Plus Fixed Fee Task Orders or for Cost Plus Fixed Fee Tasks within a Task Order. The contractor shall perform environmental remediation and other related functions as required by Section C and applicable task order specifications. The individual task order Performance Work Statement will clearly indicate the specific requirements of the task(s) awarded. The contractor shall furnish the required labor, general management, quality management, administration, travel, supervision, quality control, supplies, materials, equipment (not otherwise furnished as Government Furnished Materials), transportation, and documents/permits necessary to deliver services and any associated deliverables within schedule and in accordance with contract terms and conditions, reference documents, specific contract and task order requirements, and contract clauses. The Contractor shall be responsible for obtaining all required documents/permits required for travel and performance of work.

In accordance with FAR 15.404-4(c)(4)(i)(C), the fixed fee shall not exceed 10%.

MAX COST

FIXED FEE

TOTAL MAX COST + FEE

UNIT UNIT PRICE MAX AMOUNT

1003 UNDEFINED Job OPTION Contractor Manpower Reporting

FFP

This CLIN is used for the pricing of the collection and reporting of Contractor Manpower Reporting data as described in Section C. Reporting period will be the period of performance not to exceed twelve months ending 30 September of each Government Fiscal Year and must be reported by 31 October of each calendar year.

UNIT UNIT PRICE MAX AMOUNT

1004 UNDEFINED Job

OPTION 6 - MONTH OPTION PERIOD

FFP

The Government may extend the ordering period in accordance with terms in FAR Clause 52.217-8, Option to Extend Services. The evaluated rates in effect during the last option year will remain in effect during any extension executed under the stated clause; not to exceed six months.

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

$3,000.00 $400,000,000.00

DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND ORDER VALUE

The minimum quantity and order value for each Delivery/Task Order issued shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for each Delivery/Task Order issued shall not exceed the maximum quantity and order value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

3,000.00 $3,000.00 400,000,000.00 $400,000,000.00

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

Section C - Descriptions and Specifications

PERFORMANCE WORK STATEMENT

MILITARY MUNITIONS RESPONSE; ENVIRONMENTAL COMPLIANCE AND

REMEDIATION SERVICES; AND OTHER MUNITIONS RELATED SERVICES

10 August 2017

1.0 OBJECTIVE.

1.1 The objective of this Multiple Award Task Order Contract (MATOC) is to procure the services of Small Business firms to perform Military Munitions Response Program (MMRP) responses involving conventional munitions; Environmental Compliance and Remediation Services (ECRS); and Other Munitions-Related Services (OMRS), as necessary to enable lands and waters to be safely and efficiently used for their intended purpose.

1.2 This work may occur at sites located throughout the United States, including Alaska and Hawaii, the U.S. territories, outlying areas as defined by FAR 2.101, and Territorial waters. The services provided under this contract will be used in support of various Department of Defense Commands and Installations and other federal agencies, where sponsored by an appropriate U.S.

Government agency.

1.3 The shall safely locate; identify; recover, evaluate; assess; package; transport; manage; and make final disposition, as required, of Munitions and Explosives of Concern (MEC), and Hazardous, Toxic and Radioactive Waste (HTRW) at various currently and formerly used defense sites, property adjoining currently and formerly used defense sites, other federally controlled/owned sites, as well as sites in foreign jurisdictions. Work performed under this contract may include project planning; assessments; inspections; surveys; investigations;

studies, engineering evaluations; cost analyses; remedial or removal actions; spill response;

sampling and analysis; engineering containment and filtration; recovery; storage; transportation;

and disposal, as required, of MEC to include MC, HTRW; monitoring; data management;

training; permitting; public involvement; and logistical; medical; and security support. In addition, for OMRS the work may also include anomaly avoidance, construction support, range clearance. Work efforts may consist of robotic technology where feasible and practical.

1.4 Specific services and task activities are listed in Paragraph 3. The description of work stated herein provides a general understanding of the Contractor functions to be performed; individual Task Orders will contain the specific performance-based requirements.

2.0 GENERAL.

2.1 The Contractor shall perform Environmental Compliance and Remediation Services to protect human health and the environment from risks associated with HTRW, MC, and other adverse environmental conditions, as well as MMRP/OMRS services to protect human health and the environment from hazards associated with military munitions. For the purposes of this contract the term “HTRW response” represents any and all work required under environmental compliance and remediation. The terms "Munitions or MC Response", "MEC, or MC operations", "Munitions Response activities", and "Munitions Response Sites (MRS)" generally apply to work performed under the Military Munitions Response Program (MMRP). The terms "other munitions related services (OMRS)", “other munitions related operations", "other munitions related activities", and "other munitions related sites" generally apply to non-MMRP work involving munitions. Specific services and task activities are listed in Paragraph 3.

2.2 Permits and Licenses. The Contractor shall obtain the permits and licenses necessary to conduct work required by this Contract including, but not necessarily limited to, environmental permits, building permits, well permits where required by regulation, licensed drillers, licenses to purchase explosives, and Department of Transportation (DOT) requirements for the transport of MEC, MC, and HTRW on public highways. The Contractor shall comply with all applicable Federal, State, and local laws and regulations, including TB 700-2, when transporting MEC and/or MPPEH.

2.3 Applicable Laws and Regulations. The Contractor shall perform this work in accordance with all applicable laws and regulations. The Contractor shall be responsible for acquiring the latest version of applicable regulatory or agency guidance, including but not limited to the referenced documents cited in this Solicitation and/or subsequent Task Orders issued after award of the Contract, unless otherwise specified.

2.4 Publications and References. All work under this contract shall be in accordance with the applicable publications and references in this Section C.

2.5 Data Ownership and Data Rights. All reports and data whatsoever, including all electronic data and software, generated under this contract will be determined by negotiation IAW the DFARS. When submitting proposals, offerors shall identify IAW DFARS 252.227-7017 to the extent known all technical data or software that will be delivered with restrictions on its use, release, or disclosure.

2.6 Safety and Health Program. The Contractor shall develop and implement a written Safety and Health Program in accordance with guidelines specified in EM 385-1-1. The Contractor shall ensure that its Subcontractors, suppliers, and support personnel follow all safety and health provisions established in the approved Accident Prevention Plan (APP) for the site. A Site Safety and Health Plan (SSHP) shall be included in the APP as an Attachment. No work shall be undertaken at any project site by a Contractor without an approved APP/SSHP work plan.

The Government reserves the right to stop work under this contract for any violations at no additional cost to the Government. The Government will verify that the Contractor has implemented corrective action before allowing continued performance under the contract.

2.6.1 Medical Surveillance. An ongoing medical surveillance program meeting the requirements of 29 CFR 1910.120 shall be developed for personnel performing onsite activities.

2.6.2 Personal Protective Equipment. A written Personal Protective Equipment (PPE) program is required IAW 29CFR1910.120 (g) (5), 29 CFR 1926.65(g)(5); as well as the respiratory protection requirements of 29 CFR 1910.134 and EM 385-1-1. When working with radioactive material, the respiratory protection requirements of 10 CFR 20 must be met. All employees working within a radiologically restricted area shall receive appropriate dosimetry monitoring for radiation exposure in accordance with EM 385-1-1.

2.7 Munitions with Unknown Liquid Filler. During conventional MEC or other munitions related operations, if the Contractor identifies or suspects an unknown liquid filled munition, the Contractor shall immediately withdraw upwind from the work area and contact the responsible Contracting Officer and the appropriate point of contact in their Work Plan (WP)/Accident Prevention Plan (APP). The Contractor shall secure the area and provide two personnel located upwind of the suspect unknown liquid filled munition to secure the site until relieved by the Department of the Army emergency response personnel. Additional support may be required by the emergency response personnel, e.g. construction of blast mitigation controls.

2.8 Improved Conventional Munitions. (ICM). Prior to entering areas/ranges contaminated with Improved Conventional Munitions (ICMs) or submunitions, a Department of the Army (DA) a Deviation Approval and Risk Acceptance Document (DARAD) in accordance with DA Pam 385-30 must be conducted by the Contractor and approved by the affected installation or for FUDS properties, the executing Corps district. If an ICM or submunitions is found at a site not previously known to contain ICMs or submunitions, work will cease the Contractor will contact the responsible Contracting Officer and the appropriate point of contact in their Work Plan (WP)/Accident Prevention Plan (APP). The Contractor shall secure the area and provide two personnel to secure the site until relieved by the Department of the Army emergency response personnel. Additional support may be required by the emergency response personnel, e.g., construction of blast mitigation controls.

2.9 HTRW at MMRP/OMRS. During Munitions Responses or other munitions related operations, the Contractor may encounter HTRW material containers, landfills, Open Burning/Open Detonation (OB/OD) areas, ground spills, contaminated surface water, or contaminated groundwater. If suspected HTRW of unknown origin and nature is encountered, the Contractor shall immediately stop work in the affected area, and notify the responsible KO and the appropriate point of contact in their WP/APP. The Contractor shall take necessary actions to protect the safety of its workforce, the public, and the environment in close consultation with the Contracting Officer.

2.10 HTRW. Work performed at HTRW locations will generally follow the CERCLA process.

However, some projects may follow the RCRA Corrective Action process for active installations. If disposal is required per the Task Order, the Contractor shall ensure that all hazardous waste is properly transported to and disposed of at a permitted Treatment Storage and Disposal Facility (TSDF) in compliance with all applicable International, Federal, State, and local requirements.

2.11 Laboratory Capabilities.

2.11.1 Laboratories must demonstrate compliance with the DoD Quality Systems Manual (DoD QSM) (latest version) through accreditation by the DoD Environmental Laboratory Accreditation Program (DoD ELAP) for all project-required parameters. A list of laboratories accredited under DoD ELAP can be found at the DoD ELAP Denix web site at http://www.denix.osd.mil/edqw/Accreditation/AccreditedLabs.cfm. The laboratory used shall have experience handling media potentially contaminated with munitions constituents and shall be identified early in the project planning (at the proposal stage). For additional details on laboratory requirements, see DID HNC-005.02.

2.11.2 Any laboratory performing chemical analysis must provide its DoD ELAP accreditation certificate and supporting documentation to the applicable Military Munitions Design Center (MM DC) in order to be approved by that MM DC. If the laboratory fails to meet project-specific requirements, the KO or Contracting Officer’s Representative (COR) may require the Contractor to stop using this laboratory and obtain analytical services from another qualified laboratory that can meet project-specific requirements. The contract laboratory may not subcontract analytical services to another laboratory without the approval of the Contracting Officer. The subcontracted laboratory must meet all requirements for the contract laboratory.

2.11.3 Geotechnical Testing Laboratories. Geotechnical testing shall be conducted in accordance with the requirements of ER 1110-1-8157, Geotechnical Data Quality Management for Hazardous Waste Remedial Activities, to include laboratory requirements specified in ASTM D- 3740. The laboratory shall have experience performing physical testing of materials potentially contaminated with HTRW or MC. The types of laboratory services anticipated under this contract include, but are not limited to, mechanical analysis (sieve analysis), hydrometer analysis, Atterberg Limits, soils classifications, permeability, standard and modified proctor tests and relative density tests.

2.11.4 Task Order proposals shall identify the primary laboratory and secondary laboratory (ies) to be used for geotechnical laboratories and laboratories performing chemical analysis.

2.12 Security. When work is performed at a military installation, the Contractor shall comply with all security requirements of that installation. In accordance with Engineering Regulation, ER 380-1-18 (http://www.publications.usace.army.mil/), Section 4, foreign nationals who work on USACE contracts or task orders shall be approved by the HQUSACE Foreign Disclosure Officer or higher before beginning work on the contract/task order. This regulation includes Subcontractor employees. The Contractor shall submit to the Contracting office the names of all foreign nationals proposed for performance under this contract/task order, along with documentation to verify that he/she was legally admitted into the United States and has authority to work in the U.S. Additional security requirements may apply such as those required to fulfill OPORD 2013-74 (Integrating Antiterrorism (AT) and Operations Security (OPSEC) into the USACE Acquisition Process)

2.13 Performance-Based Milestones/Objectives: The Government defines Performance Based Milestones/Objectives as the desired outcome(s) that have been defined in the Performance Work Statement in clear, simple, concise, results-oriented, measurable and legally enforceable terms. The Government defines the completion of a Performance Based Milestone/Objective as:

an outcome that has been 100% completed and approved and accepted by the approval authority under the Task Order/Contract. Simply meeting the Milestone/Objective, (i.e., submittal of a document for review) is not the same as completion of the Milestone/Objective. Only upon the completion, approval, and acceptance will the Government pay for that Milestone/Objective.

2.14 A Performance Work Statement (PWS) for a Task Order will to every extent possible:

– Define desired results/outcomes.

– Define what level of performance is expected (and ensure it is meaningful, measurable and fair) and use performance standards and Quality Assurance Surveillance Plans

(QASP).

– Provide all information known about the site(s), or where it can be located and accessed by the Contractor.

– Define incentives and disincentives.

– Define the terms using clear and concise language avoiding vague or broad statements.

3.0 SPECIFIC SERVICES.

3.1 Task Orders. Task Orders issued under this Contract may be Firm-Fixed Price and/or Cost- Reimbursable incorporating the Service Contract Labor Standards (formally known as the Service Contract Act) and/or the Construction Wage Rate Requirements (formally known as the Davis Bacon Act) Wage Determinations, as applicable, depending on the type of work being performed in each individual Task Order. For each Task Order under this contract, the Government will provide a specific Scope of Work (SOW) or PWS describing at a minimum the work required to be performed, performance metrics, schedule requirements, types and numbers of submittals, and places for review. The Contractor shall, upon award of a Task Order, supply all personnel, tools, equipment, communications, transportation, materials and supervision (except as otherwise noted) to integrate, manage, and execute all specified aspects of the Task Order. If Government Furnished Property (GFP) will be provided to or if property is acquired under a Cost-Reimbursable CLIN to/by the Contractor for use on individual task orders, and it is approved to do so IAW FAR 45.102 and DFARS PGI 245.103-70, the Contractor shall control, maintain, care for, and use Government Property in its possession or control from the time of receipt until properly relieved of responsibility IAW FAR and DFARS clauses outlined in the Contractors Property Management Control Plan.

3.2 Site Visit.

3.2.1 Pre-proposal. A site visit may be authorized by the KO to assist in the preparation of the Contractor’s proposal. Cost for this site visit will be at the Contractor’s own expense. The Government strongly encourages, but does not require, the Contractor to prepare an Abbreviated Accident Prevention Plan (AAPP) to ensure extra safety precautions are taken to avoid an accident. No intrusive activities shall be conducted during the site visit and site access restrictions may apply.

3.2.2 Post Task Order award. A site visit may be authorized by the KO to assist in the preparation of the initial Work Plan (WP) for field activities. Cost for this site visit will be covered under the Task Order. The Contractor shall prepare an (AAPP) and submit it to the responsible KO for acceptance before the site visit. The format of the AAPP shall comply with current USACE guidance. The Contractor will not conduct any intrusive activities during the site visit.

3.3 Work Plan. The Contractor shall prepare and submit, for KO acceptance, a WP/UFP-QAPP in accordance with DD Form 1423, EM 385-1-97, EM 200-1-15, DID HNC-001.02, or other guidance as specified by the KO, describing how the required effort will be accomplished. The Contractor may not mobilize to the site or begin working until the KO has accepted the WP and issued a Notice to Proceed (NTP). MEC-related operations may not begin until applicable explosives safety plans (e.g. Explosive Safety Submission (ESS), Explosive Siting Plan (ESP) have been approved.

3.4 Task Activities. Typical activities under Task Orders to this contract may include, but are not limited to:

3.4.1Administrative and Permanent Record Files. Establish and maintain Administrative and Permanent Record files for projects in formats required in the project Task Order.

3.4.2 Air Monitoring. Conduct on-site work area and site perimeter air monitoring for protecting workers, visitors, public, and the environment.

3.4.3 Anomaly Avoidance. Provide support to field operations as necessary to avoid buried anomalies and surface munitions.

3.4.4 Anomaly Investigation. Excavate and evaluate target anomalies to determine their identity, size, composition, depth, location and condition.

3.4.5 Antiterrorism Compliance. The Contractor shall ensure contracts comply with Integrating Antiterrorism (AT) and Operations Security (OPSEC) provisions of the FAR, DFARS, and USACE specific contracting policy guidance.

3.4.6 Blast-Effects Engineering Analysis. Perform complex engineering analyses of the effects of the overpressure, heat, fragmentation, and related factors resulting from detonations and implement effective mitigation measures.

3.4.7 Building Demolition. Conduct building demolitions incidental to building remediation and disposal.

3.4.8 Chemical Sampling and Analysis. Perform chemical sampling and analyses (both on-site and off-site) for MC, HTRW, and other target compound list chemicals as required.

3.4.9 Community Relations. Perform community relations actions to include but not limited to:

restoration and advisory board support, public meeting support, community restoration planning, and other stakeholder forums that facilitate public involvement; perform educational awareness training; establish and maintain Administrative Records, prepare Community Relations Plans for various response, service and support activities. Surveys may include CWA and BWA contaminated facilities to determine remediation required for facility decommissioning

3.4.10 Conduct hazardous building materials surveys. Conduct surveys for hazardous building materials to include but not limited to lead, asbestos and PBCs, analyze surveys to develop operation and maintenance report or remediation reports. Perform abatement with personnel certified in abatement when certification is required.

3.4.11 Construct/deploy and maintain waste incinerators. Construct/deploy and maintain short term waste incinerators for compliance/remediation response.

3.4.12 Construction Support. Provide support at construction sites to ensure safety of construction personnel to include but not limited to clearing anomalies prior to intrusive construction operations, visual surveillance and reconnaissance, performing demolition operations, etc.

3.4.13 Cost Analysis. Perform cost analyses for various responses, service and support activities.

3.4.14 Cost Engineering Support. Develop cost-to-complete estimates that support the environmental liability reporting for the Army Formerly Used Defense Sites (FUDS) program, the Army Installation Restoration Program and other USACE customers. Provide ancillary services such as review of cost estimating products, maintenance of the unit price book, review of Remedial Action Cost Engineering and Requirements (RACER) cost models and assemblies, and other related tasks.

3.4.15 Dig and Haul. Properly recover, treat, store, transport, and dispose of contaminated environmental media including dewatering design as needed.

3.4.16 Engineering Evaluations. Perform engineering evaluations for various responses, service and support activities.

3.4.17 Engineering Support or Design. Provide engineering support or design for various responses, service and support activities.

3.4.18 Environmental Assessment. Perform environmental assessments to assess potential impacts of and alternatives to federal action.

3.4.19 Environmental Impact Statement. Prepare Environmental Impact Statements to assess the potential impacts of and alternatives to federal actions.

3.4.20 Environmental Master Planning. Develop Environmental Master Plans for various responses, service and support activities.

3.4.21 Environmental Permits. Prepare or support the preparation of permits for operations.

3.4.22 Environmental Restoration. Environmental Restoration to include but not limited to:

chemical treatment, neutralization, incineration, stabilization, fixation or encapsulation, bioremediation, extraction of water or soil gas.

3.4.23 Evacuations. Perform necessary coordination with property owners to evacuate the public from areas within exclusion zones during various responses, service and support activities as required.

3.4.24 Explosive Ordnance Support. Perform Explosive Ordnance operations to include but not limited to range maintenance and emergency response.

3.4.25 Field Reconnaissance. Verify or substantiate past usage of specific areas as well as presence of MEC, MC or HTRW by conducting field reconnaissance.

3.4.26 Feasibility Studies. Perform feasibility studies for various responses, service and support activities.

3.4.27 Geologic and Hydrogeologic Support. Provide geological and hydrogeological support, including but not limited to: the design, oversight, and installation of soil/rock borings, monitoring wells and/or extraction wells; the proper development and sampling of such wells;

the analysis and interpretation of collected samples; the analysis of ground water flow; borehole or trench logging and sampling for geotechnical and chemical analysis; and the oversight and logging for the abandonment of wells.

3.4.28 Geographic Information System. Develop Geographic Information System (GIS) databases; create and manage a computerized GIS for various responses, service and support activities.

3.4.29 Geophysical Surveys and Mapping. Perform digital and analog geophysical surveys using instruments capable of detecting, locating, and identifying underground features for various response, service and support activities.

3.4.30 Groundwater Wells. Perform design, drilling, installation and development of groundwater monitoring wells, production wells, extraction wells, piezometers or other instrumentation.

3.4.31 Historical Data Analysis. Conduct witness interviews, collect and analyze historical information such as photographs, records, data, and documents to identify past use of a site.

3.4.32 Hydrogeological Studies. Conduct hydrogeological field-testing and perform analyses and data interpretation. This may include aquifer testing by pumping or slug test methods.

3.4.33 Implement Green and Sustainable Remediation (GSR) Practices: The Contractor shall include process of considering, incorporating, documenting, and evaluating the benefits of green and sustainable remediation (GSR) practices Pursuant to the Department of Defense (DoD) Memorandum “Consideration of Green and Sustainable Remediation Practices in the Defense

Environmental Restoration Program” (DoD, 2009), GSR employs strategies throughout the remedial process that:

• Use natural resources and energy efficiently;

• Reduce negative impacts on the environment;

• Minimize or eliminate pollution at its source;

• Protect and benefit the community at large; and

• Reduce waste to the greatest extent possible.

3.4.33 Innovative Technology. Investigate, develop, demonstrate, validate, and apply emerging technology tools, techniques, methodologies, and equipment for various responses, service and support activities.

3.4.34 Institutional Analysis. Identify and evaluate the local regulatory, demographic, and related factors that may affect, or be affected by the use and management of real property potentially containing or contaminated with HTRW, MEC, MC or other munitions.

3.4.35 Instructional Support. Provide instruction, training, and/or develop training materials and training aids, for various responses, services, and support activities otherwise within scope of this contract.

3.4.36 Landfill Liners and Covers. Design, construct, install and/or monitor temporary and permanent liners and covers for landfills.

3.4.37 Logistical, Medical and Engineering Management. Provide logistical (e.g., food services, lodging, transportation, and other necessary equipment and supplies), medical and other services to sustain field operations for various response, service and support activities.

3.4.38 Long Term Management (LTM). Perform LTM activities to include 5-Year reviews.

3.4.39 MEC-related operations or other munitions related operations. Provide the necessary personnel and equipment for any operation with the purpose of intentional physical contact with MEC, MC, or other munitions. The procedures used during Munitions Response actions and other munitions related operations shall comply with those contained in Engineering Manual 385-1-97, the accepted WP, and approved explosives safety plans (ESS, ESP, CSS, CSP, IHFSP). If burning/detonating operations cannot be conducted on-site, the Contractor shall pack and transport all MEC and/or MPPEH to an approved storage or disposal area. If MEC or other munitions are encountered that cannot be moved due to its condition and the location prevents disposal in place, then the project’s USACE OE Safety Specialist or Range Control shall be notified.

3.4.40 Monitoring (Short and Long term). Monitor environmental treatment processes for various responses, service and support activities. These activities may include sampling and analysis of treatment process influent, effluent, and residuals; soil; air emissions; ground water;

or other environmental media. Conduct studies to optimize the monitoring programs.

3.4.41 Operation and Maintenance (Short and Long term). Prepare operations and maintenance plans for on-going treatment operations/equipment. Operate and maintain environmental treatment processes for HTRW remediation, or Munitions Demilitarization projects.

3.4.42 Optimization of Remediation Systems. Provide independent and expert evaluation of remediation activities, treatment systems, monitoring programs to improve effectiveness, accelerate cleanup, and reduce future costs of remediation.

3.4.43 Potentially Responsible Party (PRP) Support. Provide technical review and assistance for PRP claims resolution for various responses, service and support activities.

3.4.44 Programmatic Studies and Documentation. Prepare programmatic studies, documentation, and technical guidance in support of USACE's management activities in support of various responses, service and support activities.

3.4.45 Range Clearance/Maintenance. Provide support at operational ranges as necessary to remove military munitions, munitions debris, and other range-related debris.

3.4.46 Remote Sensing. Collect and/or analyze remote sensing data (e.g., aerial and satellite imagery, hyperspectral data, LIDAR, or other stand-off sensors) to determine physical characteristics and/or current and past use of a site.

3.4.47 Risk Assessment. Perform quantitative and/or qualitative risk assessments and/or impact analyses and/or hazard assessment to support various response, service and support activities.

3.4.48 Remedial Investigations. Perform remedial investigations to support various response, service and support activities.

3.4.49 Remedial and Removal Response Actions. Perform short-term, long-term, and permanent actions as necessary to achieve clean-up of media contaminated with materials including but not limited to ordnance scrap, ordnance firing systems, UXO, MEC, MC, HTRW, or other environmental contamination. Response actions may include sorting, sampling and analysis, decontamination, neutralization, recycling, consolidation, disposal, and removal of drums, tanks, structural and other materials.

3.4.50 Site Inspections. Perform site inspections for various responses, service and support activities.

3.4.51 Site Security. Provide site security to include but not limited to security plans, fencing, barriers, signage, intrusion detection systems, or guard service as required for various response, service and support activities. At a minimum, the Contractor shall maintain all areas to minimize the risk of injury or accident and prevent unauthorized access. When working at BRAC or active installations, there may be additional installation-specific security requirements that shall be followed.

3.4.52 Support Facilities. Install and operate support facilities (e.g., site project office, command post, decontamination facilities, roads, and utilities) and establish exclusion, contamination reduction, and support zones. The site project office shall include space for one or more Government representatives. The Contractor shall locate staging and demolition areas, subject to Government approval.

3.4.53 Surveying. Provide location surveys along with conventional and global positioning system (GPS) mapping to support various responses, service and support activities.

3.4.54 Technical Project Planning. Participate in and facilitate meetings with DoD personnel, regulatory agencies, restoration advisory boards, and other stakeholders to determine appropriate approaches to project implementation.

3.4.55 Treatability Studies. Perform laboratory, bench-scale, and field trials of approaches to optimize clean-up of contaminated media.

3.4.56 Waste Collection and Control. Provide process control (i.e. waste management from point of origin to controlled final disposition) for various waste streams to include but not limited to:

lithium batteries, asbestos, waste oils, DFAC oils, antifreeze, hydrocarbon contaminated soils, and sewage sludge via standardized safe disposal practices, environmental laws, and regulations.

3.4.57 Water Treatment Plants/Pump and Treat. Design, permit, construct, upgrade, maintain, and/or operate facilities to remove contaminants from groundwater or surface water.

3.5 Environmental and Munitions Center of Expertise (EM-CX) Support. Provide technical support to EM-CX staff technical disciplines such as environmental chemists, analytical chemists, health physicists, industrial hygienists, environmental risk assessors, geologists, geotechnical engineers, environmental engineers, process engineers, cost engineers, project managers, and other related disciplines. Support may include but is not limited to developing guidance (e.g. checklists, example reports and correspondence etc.) conduct desk audits, on-site laboratory inspections, conducting optimization studies, etc.

3.6 Other DoD and Federal Agencies Support. Provide MMRP, OMRS, and HTRW investigations, evaluations and response assistance on an as-needed basis to other DoD and Federal Agencies. Perform other MMRP, OMRS, and HTRW related work for foreign governments/agencies, where appropriately sponsored by DoD or other Federal Agency.

4.0 CONTRACT MANAGEMENT AND DELIVERABLES.

4.1 Program Management. The Contractor shall submit a Monthly Status Report each month for the duration of the task order in accordance with DD Form 1423 and DID HNC 009.01

4.2 Project Management. The Contractor shall execute each task under the direction of a Project Manager (PM), meeting the qualification requirements of paragraph 5.4.5.

4.3 Quality Management. The Contractor is responsible for the control of product quality and for offering to the Government for acceptance only those products/services that conform to the contractual requirements. Quality Assurance Projects Plans shall be prepared in accordance with

EM 200-1-15.

4.4 Presentations and Meetings. The frequency and locations of presentations and meetings will be identified in each Task Order.