This document is a presentation for an Ediz Hook Beach Nourishment Industry Day (Virtual) hosted by the US Army Corps of Engineers Seattle District Navigation Section. The project involves beach nourishment for erosion control at Ediz Hook, with construction scheduled between 16 July 2026 and 30 September 2026. Key project details include procuring and placing 6 to 12-inch rounded cobbles along the seaward side of an existing revetment, with a total fill material volume of up to 40,000 tons. The project will extend approximately 2,000 feet, working from an access point towards the southwest, and all work will be conducted from land with minimal in-water activities.

The solicitation (Solicitation #: W912DW26B0001) is being considered as an Invitation for Bid, likely targeted at small businesses. The project has completed environmental documentation, with plans and specifications in progress, and an anticipated contract award in December 2025 or January 2026. The US Army Corps of Engineers is seeking industry feedback on general project considerations, bid schedule (with a large portion potentially classified as option items), and solicitation type. Interested parties are encouraged to engage early, understand small business involvement, and utilize resources like SAM.gov and FPDS for subcontracting opportunities.

View the file

Other files

File Type Posted
IndustryDay_Follow-up.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EDIZ HOOK BEACH

NOURISHMENT INDUSTRY

DAY (VIRTUAL)

Seattle District Navigation Section Solicitation #: W912DW26B0001

• Remain muted

• Raise hand if you have a comment or question

MEETING ETIQUETTE

PROJECT HISTORY

• Ediz Hook Erosion Control Project -- federally authorized in 1974.

• Construction of the USACE armor stone revetment was completed in 1978.

• Typical beach nourishment schedule is every 5 years.

• Beach nourishment last occurred in 2016.

BEACH NOURISHMENT - PROJECT OVERVIEW

• Purpose is to provide erosion protection by placing beach nourishment fill material along the toe of the seaward side of the armor stone revetment.

• The construction in-water work window for this project is limited to 16 July 2026 thru 30 Sept 2026.

• All work, including cleanup of the premises, must be complete by 15 Oct 2026.

• All work will be from land.

Access/staging area

Sta. 174+00

Sta. 145+00

Beach Nourishment Extent

Note: All locations shown are approximate.

PROJECT DETAILS - CONTINUED

• Procure and place 6 to 12” rounded cobbles to a height of 12 ft MLLW on seaward side of revetment.

• Start at access point and work towards southwest.

• Place up to 40,000 tons of fill material.

• Pre- and post-construction surveys will be required.

Typical Cross Section:

PROJECT DETAILS - CONTINUED

• Temporarily remove and stockpile armor stone to access the seaward side.

• Return the armor stone to the revetment upon completion of beach nourishment.

• In-water work must be avoided or minimized to the maximum extent practicable.

• Continuous water quality monitoring for turbidity will be required.

EDIZ HOOK – STATUS

• Environmental documents are complete.

• Plans and Specifications are in progress

• Anticipated award of December 2025/January 2026

• Construction would be in FY26, during the in-water work window for this project: 16 July 2026 – 30 Sept 2026.

We want your feedback on the following items:

1. General: Any concerns and considerations regarding the project.

2. Bid Schedule: A large amount of the work may be classified as Option Items.

3. Type of Solicitation: Considering soliciting as Invitation For Bid, likely as small business.

EDIZ HOOK BEACH NOURISHMENT – FEED BACK

ITEMS

General Advice

• Get engaged, EARLY o Understand anticipated SB involvement (if applicable)

• Small Business Commitment Document

• Subcontracting Plan – USACE goals are based on historical data, market info o Utilize SAM.gov and FPDS for subcontracting opportunities

• Build relationships, NOW o SBA SubNet – https://subnet.sba.gov/client/dsp_Landing.cfm o FPDS - https://www.fpds.gov/fpdsng_cms/index.php/en/ o Request agency info on recent awards with a subcontracting plan o Request assistance to source SBs (utilize your APEX Accelerators)

• Understand other than small contractor responsibilities under FAR 52.219-9 o Good Faith Efforts (FAR 19.705-7) o eSRS reporting requirements

USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS

https://subnet.sba.gov/client/dsp_Landing.cfm https://www.fpds.gov/fpdsng_cms/index.php/en/

USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS

Enshané Nomoto Small Business Professional Enshane.Nomoto@usace.army.mil (best initial contact method)

Tel: 206-316-3990

General Email: cenws-sb@usace.army.mil USACE NWS SB Homepage:

https://www.nws.usace.army.mil/Business-With-Us/Small-Business/ mailto:Enshane.Nomoto@u mailto:Enshane.Nomoto@uace.army.mil https://www.nws.usace.army.mil/Business-With-Us/Small-Business/

QUESTIONS?

Further Questions should be emailed to the contracting team:

Contracting Officer:

Robert Gonzalez Robert.L.Gonzalez@usace.army.mil

Contracting Specialist:

Mckenna Rain Mckenna.T.Rain@usace.army.mil

Ediz Hook Beach Nourishment Industry Day (Virtual)
Meeting Etiquette
Project History
Beach Nourishment - Project overview
Project Details - Continued
Project Details - Continued
Ediz hook – StatuS
Ediz Hook Beach nourishment – feed back items
USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS
USACE NWS OFFICE OF SMALL BUSINESS PROGRAMS
Questions?