This document is a Standard Form 30 (SF-30) Amendment to Solicitation/Modification of Contract for a U.S. Army Corps of Engineers contract (W912DW25Q8004) related to crane rental services at Mud Mountain Dam. The amendment provides responses to three key questions about the crane rental, clarifying that the project involves two distinct mobilizations for stoplog installation and removal, with each mobilization lasting approximately 6-8 hours on-site.
The contract requires a Liebherr LTR1060 or similar telescopic crawler crane capable of lifting 100,000 lbs at 40' radius for two separate picks: one in July 2025 to install three tunnel entrance stoplogs, and another in October 2025 to remove the same stoplogs. The project specifies precise weight details for the stoplogs (bottom: 80,000 lbs, middle: 72,000 lbs, top: 52,000 lbs) and includes challenging logistical requirements such as traversing steep dam access roads and using a specific pneumatic cylinder pin release mechanism for lifting.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Answ er questions received from solicitation.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 16-Jun-2025
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW25Q8004
X 9B. DATED (SEE ITEM 11)
03-Jun-2025
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
16-Jun-2025
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912DW25Q8004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
RESPONSES TO QUESTIONS
Q: Could you please confirm that the crane rental is not continuous between July 1 and October 17, but rather involves two distinct mobilizations and demobilizations—one for each pick?
A: Correct, this involves two distinct mobilizations and demobilizations for each pick.
Q: If known, could you advise approximately how long the crane will be in use during each mobilization?
A: Duration on site depends upon equipment type, assembly, traversing the switchbacks to the pick site, etc.
Previous picks ranged from 6-8 hours on-site.
Q: In the SOW 2025 it calls out a max weight of “104,00lbs (beam + largest stop log)”. Further down the page it specifically calls out a Liebherr LTR1060 or similar Telescopic Crawler capable of lifting 100,000lbs at 40’. We need to know if 104,000lbs is the max load + safety factor or if a gross capacity of 100k at 40’ is all that is required. Could you please advise which is required - 104,000# + safety factor OR if 100,000# lift capacity at 40' radius is all that is required?
A: Project confirmed that each stoplog weighs approximately 60,000-70,000 pounds, and the beam weighs approximately 10,000 pounds.
(End of Summary of Changes)