W912DW25Q0035 Amendment 0004_PSTW Debris signed.pdf

PDF 529 KB Posted

Attached to
W912DW25Q0035 FY25 PSTW Collected Debris Removal
Solicitation number
W912DW25Q0035
Issued by

About this file

This document is a Standard Form 30 (SF-30) Amendment of Solicitation/Modification of Contract for a U.S. Army Corps of Engineers contract (W912DW25Q0035). The amendment, dated 05-Aug-2025, updates the Bid Schedule to include a Contract Line Item Number (CLIN) structure for a debris removal project at the Hiram M. Chittenden Locks in Seattle, Washington.

The updated Bid Schedule includes base items and optional items for various tasks: local barge movement, offload and handling, solid waste debris disposal, recyclable debris disposal, liquid waste debris disposal, and leveling the dock area. The base items include 6 jobs/tasks with quantities ranging from 1 to 400 units (tons or gallons). Optional items provide additional quantities for similar tasks. The contract performance period is from 30-Aug-2025 to 30-Sep-2026, with inspection and acceptance to be conducted at the Hiram M. Chittenden Locks. The required response date/time was changed from 08-Aug-2025 10:00 AM to 12-Aug-2025 02:00 PM.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to update the Bid Schedule to include the CLIN structure.

See the continuation page

1. CONTRACT ID CODE PAGE OF PAGES

1 13

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 05-Aug-2025

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912DW25Q0035

X 9B. DATED (SEE ITEM 11)

09-Jul-2025

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

05-Aug-2025

CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

Shemekia McMillan shemekia.r.mcmillan@usace.army.mil

W912DW25Q0035

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

UPDATED BID SCHEDULE

Bid Schedule

ITEM

NO.

DESCRIPTION QTY UNIT UNIT

PRICE

AMOUNT

0001 Task 2 Local Barge Moved at LWSC 6 JOB $ $

0002 Task 3 Offload and Handling 400 TON $ $

0003 Task 4 Solid Waste Debris Disposal 200 TON $ $

0004 Task 5 Recyclable Debris Disposal 200 TON $ $

0005 Task 6 Liquid Waste Debris Disposal 150 GAL $ $

0006 Task 7 Level Dock Area 1 JOB $ $

TOTAL ESTIMATED AMOUNT BASE ITEMS $

OPTIONAL ITEMS

1001 Offload and Handling – Task 1 200 Ton $ $ 1002 Offload and Handling- Task 1 200 Ton $ $ 1003 Offload and Handling- Task 1 200 Ton $ $ 1004 Offload and Handling- Task 1 200 Ton $ $ 1005 Solid waste Debris Disposal- Task 2 200 Ton $ $ 1006 Solid waste Debris Disposal- Task 2 200 Ton $ $ 3001 Recyclable Debris Disposal- Task 3 200 Ton $ $ 3002 Recyclable Debris Disposal- Task 3 200 Ton $ $ 4001 Four in layer of crushed rock spread evenly- Task 5 1 Job $ $

TOTAL ESTIMATED AMOUNT OPTION ITEMS $

TOTAL ESTIMATED AMOUNT BASE & OPTION ITEMS $

Note 1: Quantities are ESTIMATED except where shown as “TON”.

Note: 2: Option Item No. 1001 is additional task Task 3 Offload and Handling (described as 0002) Note 3: Option Item No. 1002, Option Item No 1003, and Option Item No 1004 are additional Task 3 Offload and Handling (described as 0002) Note 4: Option Item No. 1005 and Option Item No 1006 are additional Task 4 Solid Waste Debris Disposal (described as 0003) Note 5: Option Item No. 3001 and Option Item No 3002 are additional Task 5 Recyclable Debris Disposal (described as 0004) Note 6 Option Item No. 4001, are additional Task 7, Level Dock Area (described as 0005) Note 7: Bids shall not be submitted for quantities less than those specified for each line item.

Note 8: Offerors must insert a price on all numbered items of the Bid Schedule. Prices are on a unit basis. Failure to include pricing for all quantities of all line items will result in rejection of the bid as non-responsive.

Note 9: The contract price will be evaluated based on the total price of all options exercised the maximum number of times, added to the total price of the base items.

DEFINITIONS FOR CONTRACT LINE ITEM (CLIN) SCHEDULE

TON = Net Ton (2,000 LB) GAL = US Gallon

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 08-Aug-2025 10:00 AM to 12-Aug-

2025 02:00 PM.

SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

The barges are stored at the LWSC project site at the Ballard Locks East Wing Waiting Wall and will need to be moved to the quay wall offload area and back to the waiting wall once cleared of debris. The movement of the barges will consist of up to 6 movements total, unless more moves are determined by the COR to be required. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, applicable licenses and permits, and other items and non-personal services necessary to perform PSTW Debris Removal at the Hiram M. Chittenden Locks for Navigation Section as defined in this PWS.

To:

Task 2 (Basic Services) Local Barge Moved to LWSC-The barges are stored at the LWSC project site at the Ballard Locks East Wing Waiting Wall and will need to be moved to the quay wall offload area and back to the waiting wall once cleared of debris. The movement of the barges will consist of up to 6 movements total, unless more moves are determined by the COR to be required. The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, applicable licenses and permits, and other items and non-personal services necessary to perform PSTW Debris Removal at the Hiram M. Chittenden Locks for Navigation Section as defined in this PWS.

CLIN 0002

Off-load all collected debris from barges onto quay/dock area. Contractor shall follow all applicable regulations, publications, manuals, and local policies and procedures. Barges shall be swept clean at completion of debris removal event.

Task 3 Offload and HandlingOff-load all collected debris from barges onto quay/dock area. Contractor shall follow all applicable regulations, publications, manuals, and local policies and procedures. Barges shall be swept clean at completion of debris removal event.

CLIN 0003

Dispose of solid waste debris at proper waste disposal site. Provide tonnage weight tickets as part of invoice.

Task 4-Solid Waste Debris Disposal-Dispose of solid waste debris at proper waste disposal site. Provide tonnage weight tickets as part of invoice.

CLIN 0004

Dispose debris at proper recycle sites and/or coordinate drop off/pick up of habitat restoration logs to non-profit/governmental agencies. Location of habitat restoration logs disposition shall be coordinated with government representative. Provide tonnage weight tickets as part of invoice for recyclables and tonnage weight tickets for habitat restoration logs either by industry standard truck scale or through coordination with government representative and non-profit/governmental agencies if they have an available scale or weight ticket capability.

Task 5-Recyclable Debris Disposal-Dispose debris at proper recycle sites and/or coordinate drop off/pick up of habitat restoration logs to non-profit/governmental agencies. Location of habitat restoration logs disposition shall be coordinated with government representative. Provide tonnage weight tickets as part of invoice for recyclables and tonnage weight tickets for habitat restoration logs either by industry standard truck scale or through coordination with government representative and non-profit/governmental agencies if they have an available scale or weight ticket capability.

CLIN 0005

Dispose of liquid waste at proper waste disposal site or recycle. Provide tonnage weight tickets as part of invoice.

Provide volume in gallons for liquids disposal.

Task 6 Liquid Waste Debris Disposal- Dispose of liquid waste at proper waste disposal site or recycle. Provide tonnage weight tickets as part of invoice. Provide volume in gallons for liquids disposal.

CLIN 0006

At the completion of the debris disposal event, ensure quay/dock area is leveled and a new four (4) inch layer of crushed rock is spread evenly over the area to create a new leveled surface. The crushed rock shall be clean, crushed rock meeting the requirements of WSDOT Standard Specification 9-03.9(1). Required testing results will be provided as part of the QCP. Material must be approved by the government representative prior to placement. This area is immediately adjacent to the offload barge location and approximately 6,800 square feet.

Task 7 Level Dock Area-At the completion of the debris disposal event, ensure quay/dock area is leveled and a new four (4) inch layer of crushed rock is spread evenly over the area to create a new leveled surface. The crushed rock shall be clean, crushed rock meeting the requirements of WSDOT Standard Specification 9-03.9(1). Required testing results will be provided as part of the QCP. Material must be approved by the government representative prior to placement. This area is immediately adjacent to the offload barge location and approximately 6,800 square feet.

CLIN 1001

The CLIN description has changed from Optional: Local Barge Moved at LWSC to to Optional: Offload and Handling.

Optional: Local Barge Moved to LWSC to Ouail Area. As described in PWS.

Optional: Offload and Handling-Task 1- As described in PWS. 200 ton

CLIN 2001

The CLIN description has changed from Optional: Offload and Handling to Offload and Handling- Task 1.

INFO: Offload and Handling: As described in PWS.

Informational Purposes only--OPTIONAL-Offload and Handling- Task 1

SUBCLIN 2001AA

200 tons

OPTIONAL-Offload and Handling- Task 1-200 tons

The option status has changed from No Status to Option.

SUBCLIN 2001AB

OPTIONAL-Offload and Handling- Task 1-200 tons

SUBCLIN 2001AC

OPTIONAL- Offload and Handling- Task 1-200 tons

CLIN 3001

Solid Waste Debris Disposal: As described in PWS.

Informational Purposes Only-Solid Waste Debris Disposal: As described in PWS.

SUBCLIN 3001AA

OPTIONAL-Solid waste Debris Disposal- Task 2-200 tons

SUBCLIN 3001AB

OPTIONAL-Solid waste Debris Disposal- Task 2-200 tons

CLIN 4001

INFO: Recyclable Debris Disposal: As described in PWS.

INFO Purposes Only: Recyclable Debris Disposal: As described in PWS.

SUBCLIN 4001AA

OPTIONAL Recyclable Debris Disposal- Task 3-200 tons

SUBCLIN 4001AB

OPTIONAL Recyclable Debris Disposal- Task 3-200 tons

CLIN 5001

Four in layer of crushed rock spread evenly: As described in PWS.

OPTIONAL-Four in layer of crushed rock spread evenly- Task 5: As described in PWS.

SUBCLIN 2001AD is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

2001AD 200 Net Ton

(2,000

LB).

OPTION Optional: Offload and Handling

FFP

OPTIONAL- Offload and Handling- Task 1-200 tons NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.

FOB: Destination

PSC CD: S205

NET AMT

DELIVERIES AND PERFORMANCE

The following Delivery Schedule for CLIN 1001 has been deleted:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

POP 30-AUG-2025 TO

30-SEP-2026

N/A US ARMY CORPS OF ENGINEERS,

SEATTLE DIST

DARRELL D. HUTCHENS

4735 E. MARGINAL WAY SOUTH

SEATTLE WA 98134-2385

206-316-3877 FOB: Destination

W68MD9

INSPECTION AND ACCEPTANCE

The Acceptance/Inspection Schedule for CLIN 0001 has been changed from:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

The Acceptance/Inspection Schedule for CLIN 0002 has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for CLIN 0003 has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for CLIN 0004 has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for CLIN 0005 has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for CLIN 0006 has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for CLIN 1001 has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

N/A HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 2001AA has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 2001AB has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 2001AC has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The following Acceptance/Inspection Schedule was added for SUBCLIN 2001AD:

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 3001AA has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 3001AB has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 4001AA has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

The Acceptance/Inspection Schedule for SUBCLIN 4001AB has been changed from:

US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

SEATTLE WA 98134-2388

Government US ARMY CORPS OF

ENGINEERS

SEATTLE DISTRICT

4735 E. MARIGINAL WAY S.

HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

SEATTLE WA 98107-4299

Government HIRAM M. CHITTENDEN LOCKS

3015 NW 54TH ST

(End of Summary of Changes)

2025-08-05T14:45:56-0700
MCMILLAN.SHEMEKIA.ROSHELLE.1064845159

File details come from the government source that posted it. Updated .