This is a solicitation for a construction project to replace two gantry cranes at Chief Joseph Dam in Bridgeport, Washington. Work includes designing, fabricating, delivering, installing, testing and certifying a new 50-ton intake gantry crane and modifying overhead power conductors. It also includes designing, fabricating, delivering, installing, testing and certifying a new 18-ton tailrace gantry crane and installing a new wall-mounted conductor system. The contractor must remove the existing intake and tailrace cranes. The expected magnitude of construction is between $10 million and $25 million. Proposals are due to the U.S. Army Corps of Engineers Engineering District in Seattle by the date specified in the solicitation. The place of performance is Chief Joseph Dam Highway 17 and Pearl Hill Road in Bridgeport, Washington.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912DW21R0033 - Amendment 0003.pdf | ||
| W912DW21R0033 Amendment 0001.pdf | ||
| PPQ.docx | DOCX document | |
| Site Visit Photo File Descriptions.docx | DOCX document | |
| Tailrace Reference Drawings.pdf | ||
| Intake Reference Drawings.pdf | ||
| FY21 CJD Intake Gantry and Tailrace Crane Specifications.pdf | ||
| CJD Intake and Tailrace Crane Plans 10-21-20.pdf | ||
| W912DW21R0033 - Solicitation.pdf | ||
| Virtual Site Visit Photos.zip | ZIP file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912DW21R0033
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Amendment 0002
(Please see continuation sheet)
1. CONTRACT ID CODE PAGE OF PAGES
1 9
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 22-Jan-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912DW21R0033
X 9B. DATED (SEE ITEM 11)
10-Dec-2020
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
22-Jan-2021
CODE
USA ENGINEER DISTRICT, SEATTLE
ATTN: CENWS-CT
4735 EAST MARGINAL WAY SOUTH, BLDG. 1202
SEATTLE WA 98134-2388
W912DW 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0002
1. This amendment provides for the following changes:
a. Section 00 21 00 para. 11 “Subcontracting Plan” is revised
b. Section 01 78 00 is revised.
2. The attached revised sections are to be replaced in their entirety. All portions of the revised sections shall apply whether or not changes have been indicated.
3. NOTICE: Offerors must acknowledge receipt of this amendment by number and date on offer.
Attch:
Section 00 21 00 para. 11 “Subcontracting Plan” (revised) Section 01 78 00 (revised)
SECTION 00 21 00 - INSTRUCTIONS
The following have been modified:
INSTRUCTIONS TO OFFERORS
INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFEROR
1. General Description of Work
2. Disclosure of the Magnitude of the Seed Project
3. Copies of Solicitation Documents and Amendments
4. Offeror’s Questions and Comments
5. Small Business Size Standard / NAICS Code:
6. Proposal Expenses and Pre-Award Costs
7. Pre-Proposal Site Visit
8. Accuracy in Proposals
9. Proposal Submittals
10. Bid Guarantee
11. Subcontracting Plan
12. Solicitation Provisions
1. General Description of Work:
Contract Title: Chief Joseph Dam Intake and Tailrace Crane Replacement, Bridgeport, WA.
The 50-Ton Intake Gantry Crane at Chief Joseph Dam, designed in 1952 and constructed and placed in service in 1953, has exceeded its 50-year design life. Rehabilitation was most recently completed in 2000. The crane’s primary purpose is to isolate the generating units by placing and removing the stoplogs to or from the upstream intake along the powerhouse deck to allow, in conjunction with the tailrace crane, a generating unit to be completely unwatered for maintenance or for emergency repairs. This crane is a required element without which the maintenance necessary for safe, reliable, and optimum energy generation from the 27 generators in the powerhouse cannot be conducted. The intake crane also is used to remove debris, and to remove barges from the fore bay for maintenance.
The 18-ton Tailrace Gantry Crane at Chief Joseph Dam, also designed in 1952 and placed in service in 1954, has exceeded its 50-year design life. Rehabilitation was most recently completed in 2006. The crane’s primary purpose is to place or remove the 23- and 25-ton top and bottom stoplogs, respectively, to or from the downstream tailrace along the tailrace bridge deck to allow, in conjunction with the upstream intake crane, a generating unit to be completely dewatered for maintenance or for emergency repairs. This crane allows the maintenance required for safe and reliable energy generation from the 27 generators in the powerhouse.
2. Disclosure of the Magnitude of Construction:
In accordance with DFARS 236.204(ii) “Disclosure of the Magnitude of Construction Projects,” the magnitude of the project is estimated between $10,000,000 and $25,000,000.
3. Copies of Solicitation Documents and Amendments:
Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the U.S. Government’s Contract Opportunities website at: https://Beta.SAM.gov under Solicitation Number W912DW21R0033. A list of interested vendors (potential offerors and subcontractors) is available on the web site (registration required) with the solicitation announcement.
NOTE: Beta.SAM.gov is the new official U.S. Government website for Contract Opportunities.
It shall be the contractor’s responsibility to check the websites for any amendments. The Offeror shall submit in the proposal all requested information specified in this solicitation. There will be no public opening of the proposals received as a result of this solicitation.
4. Offeror’s Questions and Comments:
Bidder Inquiry
I. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet.
a. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and then click continue.
b. From this page you may view all bidder inquiries or add inquiry.
c. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
d. The Solicitation Number is: W912DW21R0033
e. The Bidder Inquiry Key is: Q5FPHK-Q6K8CZ
II. The Bidder Inquiry System will be unavailable for new inquires 3 business days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
III. Offerors are requested to review the specification in its entirety, review the Bidder
Inquiry System for answers to questions prior to submission of a new inquiry.
IV. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
V. Offers will NOT be publicly opened. Information concerning the status of the evaluation and/or award will NOT be available after receipt of proposals.
5. Small Business Size Standard / NAICS Code:
See Section 00 45 00, Provision 52.204-8 for the NAICS code and small business size standard.
6. Proposal Expenses and Pre-Award Costs:
This Request for Proposals (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.
7. Pre-Proposal Site Visit:
A pre-proposal Offeror conference and site visit WILL NOT be conducted due to the COVID19 national emergency.
All Department of Defense travel is restricted due to the COVID19 national emergency. A bidder site visit cannot be supported until the travel restrictions are lifted. In lieu of a site visit, you are invited to download selected photographs highlighting areas provided to the successful Offeror for storage, staging, and disposal presented in a following document that will be provided withing several days of the release of this RFP. Comments and questions may be submitted Using ProjNet as instructed on page 10 (https://www.projnet.org)
8. Accuracy in Proposals:
Proposals must set forth full, accurate, and complete information as required by this RFP (including attachments). The penalty for making false statements is prescribed in 18 U.S.C.
1001.
9. Proposal Submittals
In strict compliance with guidance relating to the current situation with COVID-19 and social distancing, the only authorized transmission method for proposals in response to this solicitation is electronically via EMAIL Proposals must be submitted to the following email address:
alex.r.marcinkiewicz@usace.army.mil
10. Bid Guarantee:
The Standard Form (SF) 24, dated 08/2016, shall be used for the submission of your bid bond and can be obtained from https://www.gsa.gov/reference/forms#SF. Submit the bid bond via email with your proposal.
Submit an electronic bid bond with your proposal. Bid Bonds (SF24) must be accompanied by a Power of Attorney containing an original or electronic signature from the surety, which must be affixed to the Power of Attorney after the Power of Attorney has been generated. Computer generated and signed Powers of Attorney will be accepted if accompanied by a certification from a current officer of the surety attesting to its authenticity and continuing validity.
NOTE: Digital scans, or photographed or otherwise reproduced images, of ink signatures are not considered acceptable "electronic signatures." If a required submitted document does not contain electronic signatures, you must submit original hard-copy documents.
11. Subcontracting Plan
Submission Requirements (NOTE: This Requirement only applies to the otherwise successful Offeror if it is other than a Small Business.
If the Offeror proposing on this solicitation is a large business concern, in accordance with the definition as identified in FAR Clause 52.219-1, “SMALL BUSINESS PROGRAM REPRESENTATION”, upon notification that it is the apparent successful Offeror, the firm must submit a small business subcontracting plan in accordance with FAR Clause 52.219-9 SMALL BUSINESS SUBCONTRACTING PLAN (Jan 2002) The goals established for small business, small disadvantaged business, woman-owned business, HUBZone business, Service disabled veteran-owned small business participation are:
Goals. The U.S. Army Corps of Engineers considers the following goals reasonable and achievable for the performance of the resultant contract:
Small Business – 33%
HUBZone Small Business – 3%
Service-Disabled Veteran-Owned Small Business – 3%
Veteran-Owned Small Business – 2%
Small Disadvantaged Business – 5%
Women-Owned Small Business – 5%
1) 10% of total contract dollars will be placed with all small business concerns. For the purpose of this subcontracting plan, Small Disadvantaged Business (SDB), Women-owned Small Business (WOSB), HUBZone Small Business, Veteran-owned Small Business, and Service Disabled Veteran-owned Small Business concerns are subsets of small business concerns.
2) 1% of total contract dollars will be placed with small disadvantaged business concerns or Historically Black Colleges and Universities or Minority Institutions. To be considered a small disadvantaged business concern, business must be certified by the Small Business Administration in addition to meeting the definition under FAR Clause 52.219-8(3).
3) 1% of total contract dollars will be placed with small women-owned business concerns. Women-owned business concerns may meet the definition of a small disadvantaged business. If so, it will also be considered a subset of a small disadvantaged business concern.
4) 1% of total contract dollars will be placed with HUBZone small business concerns.
To be considered a HUBZone small business concern, business must be certified by the U.S. Small Business Administration in addition to meeting the definition under FAR Clause 52.219-8(3).
5) 1% of total contract dollars will be placed with Service Disabled Veteran-owned small business concerns.
6) 2% of total contract dollars will be placed with Veteran-owned small business concerns.
The Small Business Subcontracting Plan shall be thorough, complete, and in accordance with AFARS Appendix DD and FAR Clause 52.219-9, as it will be incorporated into the contract upon award of the contract to the Offeror, if acceptable and upon final approval of the Contracting Officer. The Plan shall include a description of the types of services the firm proposes to subcontract with small business (SB), small disadvantaged business (SDB), woman-owned small business (WOSB), HUBZone business, and service-disabled veteran-owned small business (SDVOSB), along with the proposed percentages of their participation, to demonstrate a plan to meet the subcontracting goals that will apply to these contracts. If practical, the Offeror shall provide specific information on proposed subcontracted effort for this project.
12. Solicitation Provisions
See the applicable Provisions for this Solicitation in Section 00 21 00 and Section 00 45 00.
(End of Summary of Changes)
CJD Intake Gantry and Tailrace Cranes 20008 Chief Joseph Dam, Bridgeport, WA
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 78 00
CLOSEOUT SUBMITTALS
05/19
PART 1 GENERAL
1.1 REFERENCES
1.2 DEFINITIONS
1.2.1 As-Built Drawings
1.2.2 Record Drawings
1.2.3 Record Model
1.2.4 Advanced Modeling
1.2.5 USACE CAD/BIM Technology Center
1.3 SOURCE DRAWING FILES
1.3.1 Terms and Conditions
1.4 RECORD DRAWINGS
1.4.1 Variation with Contract Drawings
1.4.2 Data Loss, Corruption, and Error
1.4.3 Modeling Completeness and Quality
1.5 SUBMITTALS
1.6 SPARE PARTS DATA
1.7 QUALITY CONTROL
1.8 WARRANTY MANAGEMENT
1.8.1 Warranty Management Plan
1.8.2 Performance Bond
1.8.3 Pre-Warranty Conference
1.8.4 Contractor's Response to Construction Warranty Service
Requirements
1.8.5 Warranty Tags
PART 2 PRODUCTS
2.1 RECORD DRAWINGS
2.1.1 Additional Drawings
2.1.1.1 Sheet Numbers and File Names
2.2 ADVANCED MODELING PACKAGE
2.3 CERTIFICATION OF EPA DESIGNATED ITEMS
2.4 CERTIFICATION OF USDA DESIGNATED ITEMS
2.5 PDF AS-BUILT FILES
2.6 REDLINES AND MARKUPS
2.7 GEO-DATA-BASE FILES
2.8 AS-BUILT OR ADVANCED MODELING RE-SUBMISSION REQUIREMENTS
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
3.1.1 Markup Guidelines
3.1.2 As-Built Drawings Content
3.2 RECORD DRAWING FILES
3.2.1 Rename the CAD Drawing files
SECTION 01 78 00 Page 1
W912DW21R0033 R0001
3.3 RECORD DRAWINGS
3.3.1 Final Record Drawing Package
3.4 FINAL APPROVED SHOP DRAWINGS
3.5 CONSTRUCTION CONTRACT SPECIFICATIONS
3.6 AS-BUILT RECORD OF EQUIPMENT AND MATERIALS
3.7 OPERATION AND MAINTENANCE MANUALS
3.8 CLEANUP
-- End of Section Table of Contents --
SECTION 01 78 00 Page 2
SECTION 01 78 00
CLOSEOUT SUBMITTALS
05/19
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-1-2909 (2012) Geospatial Data and Systems
ERDC/ITL TR-12-1 (2015) A/E/C Graphics Standard, Release 2.0
ERDC/ITL TR-12-6 (2015) A/E/C CAD Standard - Release 6.0
1.2 DEFINITIONS
1.2.1 As-Built Drawings
As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents. These deviations and additions may result from coordination required by, but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site and red-lined PDF files . These files serve as the basis for the creation of the record drawings.
1.2.2 Record Drawings
The record drawings are the final compilation of actual conditions reflected in the as-built drawings.
Produce the record drawings from the Record Model(s) and do not include annotations indicating revisions.
1.2.3 Record Model
A model reflecting approved changes during construction including red-lines, requests for information (RFI's), and contract modifications.
Include updated construction phase facility/site data for components.
1.2.4 Advanced Modeling
A subset of geospatial technologies as defined in EM 1110-1-2909 to include Building Information Modeling (BIM), Civil Information Modeling (CIM), Geographic Information Systems (GIS), and Computer-Aided Design (CAD). Advanced modeling is comprised of models and drawings that form a
SECTION 01 78 00 Page 3 digital representation of the project, or part thereof, that are comprised of model elements with facility data.
1.2.5 USACE CAD/BIM Technology Center
The USACE CAD/BIM Technology Center hosts all standard content for USACE.
This content can be accessed through the CAD/BIM Technology Center website, https://cadbimcenter.erdc.dren.mil/ .
1.3 SOURCE DRAWING FILES
Request the full set of electronic drawings, in the source format, for Record Drawing preparation, after award and at least 30 days prior to required use.
1.3.1 Terms and Conditions
Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.
These electronic CAD drawing files are not construction documents.
Differences may exist between the CAD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CAD files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic source drawing files for use in producing construction drawings and data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).
1.4 RECORD DRAWINGS
The Government will provide an optical disc (CD or DVD) at the preconstruction conference that contains one set of "as-designed" electronic CAD files in the specified software and format revised to reflect all amendments and the final contract PDF drawings. The CAD files are provided to enable preparation of as-built or as-constructed drawings. If discrepancies exist between the CAD files and the contract PDF drawings, correct the CAD files to show the contract PDF drawings.
SECTION 01 78 00 Page 4
1.4.1 Variation with Contract Drawings
The electronic files provided are not part of the contract documents. If there is any discrepancy between the electronic files and the contract drawings, the contract drawings govern. The Government has no responsibility to modify any GFM due to changes in the design that occur after award.
Evaluate the content and quality of the GFM upon receipt. If major discrepancies or omissions occur in the GFM, notify the Contracting Officer and indicate the nature of such variations.
1.4.2 Data Loss, Corruption, and Error
Transfer of GFM files may result in corrupted files resulting in data loss and errors. Use of GFM files at own risk. Verify data integrity upon receipt and request a replacement if necessary. Make any adjustment in file structure, format, or software version as needed to make GFM compatible with computer systems and/or software to meet the requirements of the contract.
1.4.3 Modeling Completeness and Quality
The Government makes no guarantee that the GFM provide the level of completeness or quality as required by the contract. Further, the Government makes no guarantee that identified variations will be corrected upon notification.
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-03 Product Data
Warranty Management Plan
Warranty Tags
Spare Parts Data
SD-08 Manufacturer's Instructions
Posted Instructions
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals; G
SD-11 Closeout Submittals
As-Built Drawings; G
Record Drawings; G
SECTION 01 78 00 Page 5
Record Model; G
As-Built Record of Equipment and Materials
Final Approved Shop Drawings; G
Construction Contract Specifications; G
Certification of EPA Designated Items; G
Certification Of USDA Designated Items; G
Interim DD FORM 1354; G
Checklist for DD FORM 1354; G
High Performance and Sustainable Building (HPSB) Checklist; G
1.6 SPARE PARTS DATA
Submit two copies of the Spare Parts Data list.
a. Indicate manufacturer's name, part number, and stock level required for test and balance, pre-commissioning, maintenance and repair activities. List those items that may be standard to the normal maintenance of the system.
b. At acceptance of commissioning, ensure the required stock level is supplied as indicated in subparagraph a for maintenance and repair activities through the facilities warranty period. Provision of spare parts does not relieve the Contractor of responsibilities listed under the contract guarantee provisions.
1.7 QUALITY CONTROL
Additions and corrections to the contract drawings must be equal in quality and detail to that of the originals. Line colors, line weights, lettering, layering conventions, and symbols must conform to
ERDC/ITL TR-12-6 .
1.8 WARRANTY MANAGEMENT
1.8.1 Warranty Management Plan
Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction. At least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan narrative must contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesmen, or of engineering background, not necessarily familiar with this contract. The term "status" as indicated below must include due date and whether item has been submitted or was accomplished. Submit warranty information, made available during the construction phase, to the Contracting Officer for approval prior to each monthly pay estimate.
Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period must begin
SECTION 01 78 00 Page 6 on the date of project acceptance and continue for the full product warranty period. Conduct a joint 4 month and 9 month warranty inspection, measured from time of acceptance; with the Contractor, Contracting Officer and the Customer Representative. The warranty management plan must include, but is not limited to, the following:
a. Roles and responsibilities of personnel associated with the warranty process, including points of contact and telephone numbers within the organizations of the Contractors, subcontractors, manufacturers or suppliers involved.
b. For each warranty, the name, address, telephone number, and e-mail of each of the guarantor's representatives nearest to the project location.
c. A list and status of delivery of Certificates of Warranty for extended warranty items, including roofs, HVAC balancing, pumps, motors, transformers, and for commissioned systems, such as fire protection and alarm systems, sprinkler systems, and lightning protection systems.
d. As-Built Record of Equipment and Materials list for each warranted equipment, item, feature of construction or system indicating:
(1) Name of item.
(2) Model and serial numbers.
(3) Location where installed.
(4) Name and phone numbers of manufacturers or suppliers.
(5) Names, addresses and telephone numbers of sources of spare parts.
(6) Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have warranties longer than one year must be indicated with separate warranty expiration dates.
(7) Cross-reference to warranty certificates as applicable.
(8) Starting point and duration of warranty period.
(9) Summary of maintenance procedures required to continue the warranty in force.
(10) Cross-reference to specific pertinent Operation and Maintenance manuals.
(11) Organization, names and phone numbers of persons to call for warranty service.
(12) Typical response time and repair time expected for various warranted equipment.
e. The plans for attendance at the 4 and 9 month post-construction warranty inspections conducted by the Government.
f. Procedure and status of tagging of equipment covered by warranties longer than one year.
g. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty or safety reasons.
1.8.2 Performance Bond
The Performance Bond must remain effective throughout the construction and warranty period.
a. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will
SECTION 01 78 00 Page 7 have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
b. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the Contractor's expense, the Contracting Officer will have the right to recoup expenses from the bonding company.
c. Following oral or written notification of required construction warranty repair work, respond in a timely manner. Written verification will follow oral instructions. Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.
1.8.3 Pre-Warranty Conference
Prior to contract completion, and at a time designated by the Contracting Officer, meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. At this meeting, establish and review communication procedures for Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty In connection with these requirements and at the time of the Contractor's quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contact must be located within the local service area of the warranted construction, be continuously available, and be responsive to Government inquiry on warranty work action and status. This requirement does not relieve the Contractor of any of its responsibilities in connection with other portions of this provision.
1.8.4 Contractor's Response to Construction Warranty Service Requirements
Following oral or written notification by the Contracting Officer, respond to construction warranty service requirements in accordance with the "Construction Warranty Service Priority List" and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed. If the Contractor does not perform the construction warranty within the timeframe specified, the Government will perform the work and back charge the construction warranty payment item established.
a. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.
b. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.
c. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.
d. The "Construction Warranty Service Priority List" is as follows:
SECTION 01 78 00 Page 8
Code 1-Life Safety Systems
(1) Fire suppression systems.
(2) Fire alarm system(s) in place in the building.
Code 1-Air Conditioning Systems
(1) Recreational support.
(2) Air conditioning leak in part of building, if causing damage.
(3) Air conditioning system not cooling properly.
Code 1-Doors
(1) Overhead doors not operational, causing a security, fire, or safety problem.
(2) Interior, exterior personnel doors or hardware, not functioning properly, causing a security, fire, or safety problem.
Code 3-Doors
(1) Overhead doors not operational.
(2) Interior/exterior personnel doors or hardware not functioning properly.
Code 1-Electrical
(1) Power failure (entire area or any building operational after 1600 hours).
(2) Security lights
(3) Smoke detectors
Code 2-Electrical
(1) Power failure (no power to a room or part of building).
(2) Receptacle and lights (in a room or part of building).
Code 3-Electrical Street lights.
Code 1-Gas
(1) Leaks and breaks.
(2) No gas to family housing unit or cantonment area.
Code 1-Heat
(1) Area power failure affecting heat.
(2) Heater in unit not working.
Code 2-Kitchen Equipment
(1) Dishwasher not operating properly.
(2) All other equipment hampering preparation of a meal.
Code 1-Plumbing
(1) Hot water heater failure.
(2) Leaking water supply pipes.
Code 2-Plumbing
(1) Flush valves not operating properly.
(2) Fixture drain, supply line to commode, or any water pipe leaking.
(3) Commode leaking at base.
Code 3 -Plumbing Leaky faucets.
Code 3-Interior
SECTION 01 78 00 Page 9
(1) Floors damaged.
(2) Paint chipping or peeling.
(3) Casework.
Code 1-Roof Leaks Temporary repairs will be made where major damage to property is occurring.
Code 2-Roof Leaks Where major damage to property is not occurring, check for location of leak during rain and complete repairs on a Code 2 basis.
Code 2-Water (Exterior) No water to facility.
Code 2-Water (Hot) No hot water in portion of building listed.
Code 3-All other work not listed above.
1.8.5 Warranty Tags
At the time of installation, tag each warranted item with a durable, oil and water resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating.
Also, submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature must remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Inspector's signature
Construction Contractor
Address
Telephone number
Warranty contact
Address
SECTION 01 78 00 Page 10
Telephone number
Warranty response time priority code
WARNING - PROJECT PERSONNEL TO PERFORM ONLY OPERATIONAL MAINTENANCE DURING THE
WARRANTY PERIOD.
PART 2 PRODUCTS
2.1 RECORD DRAWINGS
Prepare the CAD drawing files in AutoCAD Release 20 1320MicroStation V8 format compatible with a Windows 7 operating system.
2.1.1 Additional Drawings
If additional drawings are required, prepare them using the specified electronic file format applying ERDC/ITL TR-12-6 and ERDC/ITL TR-12-1 .
The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.
2.1.1.1 Sheet Numbers and File Names
If a sheet needs to be added between two sequential sheets, append a Supplemental Drawing Designator in accordance with ERDC/ITL TR-12-6 Adding a drawing sheet, and ERDC/ITL TR-12-1 Adding or deleting drawing sheets and index sheet procedures.
2.2 ADVANCED MODELING PACKAGE
For each Advanced Modeling Package submittal for both the Interim Record Model Package and the Final Record Model Package, submit in accordance with ERDC/ITL TR-12-6 and also provide the following items:
a. Advanced Modeling PxP: Provide an electronic copy of the most current approved version of the project Advanced Modeling PxP.
b. Electronic Files: Provide an electronic list (.txt file or similar), of all submitted electronic files including a description, directory, and file name for each file submitted. Identify which files have been produced from the Model and Facility Data. For all sheet files, include a list of the sheet titles and sheet numbers.
c. Advanced Modeling Submittal Checklist: Complete the USACE BIM/CIM Advanced Modeling Submittal Checklist and include with each submittal. Download the Checklist from the USACE CAD/BIM Technology Center website.
d. Advanced Modeling Files: Provide all native Advanced Modeling files associated with the production of the contract drawings and associated as-modeled drawings. Update and maintain in compliance with the Advanced Modeling formatting, content requirement, and standards in , in order to yield a complete and coordinated document package.
e. Quality Control (QC) Reports: Provide electronic PDFs of all QC reports and checklist utilized to ensure full compliance with the
SECTION 01 78 00 Page 11
W912DW21R0033 R0001
g3endnp9 Rectangle g3endnp9 Line contract requirements and standards.
f. CAD Exports of BIM-Generated Sheets and Drawings: Provide supplemental 2D CAD exports from the project BIM model as needed to demonstrate compliance with contract requirements. Export all contract drawings sheets to the CAD format(s) defined in Section 01 33 16.00 10 DESIGN
DATA(DESIGN AFTER AWARD).
2.3 CERTIFICATION OF EPA DESIGNATED ITEMS
Submit the Certification of EPA Designated Items as required by FAR 52.223-9 Estimate of Percentage of Recovered Material Content for EPA Designated Items and FAR 52-223-17 Affirmative Procurement of EPA designated items in Service and Construction Contracts. Include on the certification form the following information: project name, project number, Contractor name, license number, Contractor address, and certification. The certification will read as follows and be signed and dated by the Contractor. "I hereby certify the information provided herein is accurate and that the requisition/procurement of all materials listed on this form comply with current EPA standards for recycled/recovered materials content. The following exemptions may apply to the non-procurement of recycled/recovered content materials:
a. The product does not meet appropriate performance standards;
b. The product is not available within a reasonable time frame;
c. The product is not available competitively (from two or more sources);
d. The product is only available at an unreasonable price (compared with a comparable non-recycled content product)."
Record each product used in the project that has a requirement or option of containing recycled content in accordance with SECTION 01 33 29 SUSTAINABILITY REPORTING, noting total price, total value of post-industrial recycled content, total value of post-consumer recycled content, exemptions (a, b, c, or d, as indicated), and comments. Recycled content values may be determined by weight or volume percent, but must be consistent throughout.
2.4 CERTIFICATION OF USDA DESIGNATED ITEMS
Submit the Certification of USDA Designated Items as required by FAR 52-223-1 Bio-based Product Certifications and FAR 52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts. Include on the certification form the following information:
project name, project number, Contractor name, license number, Contractor address, and certification. The certification will read as follows and be signed and dated by the Contractor. "I hereby certify the information provided herein is accurate and that the requisition/procurement of all materials listed on this form comply with current USDA standards for biobased materials content. The following exemptions may apply to the non-procurement of biobased content materials:
a. The product does not meet appropriate performance standards;
b. The product is not available within a reasonable time frame;
c. The product is not available competitively (from two or more sources);
SECTION 01 78 00 Page 12
d. The product is only available at an unreasonable price (compared with a comparable bio-based content product)."
Record each product used in the project that has a requirement or option of containing biobased content in accordance with SECTION 01 33 29 SUSTAINABILITY REPORTING, noting total price, total value of post-industrial recycled content, total value of post-consumer recycled content, total value of biobased content, exemptions (a, b, c, or d, as indicated), and comments. Biobased content values may be determined by weight or volume percent, but must be consistent throughout.
2.5 PDF AS-BUILT FILES
Provide electronic PDF "plots" of all contract drawings sheets associated with the as-built drawing submittal. Compile and organize the PDF set to match the contract drawings. Bookmark and label the pages of the PDF file in accordance with Section 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD).
2.6 REDLINES AND MARKUPS
Provide PDFs of the current working redlines and/or markups complying with the as-builts drawing and markup requirements contained in this specification.
2.7 GEO-DATA-BASE FILES
Provide a SDSFIE/FGDC GeoReferenced personal GeoDataBase. For all information outside of the building walls, provide a personal GeoDataBase in .mdb format using the latest version of Spatial Data Standard for Facilities, Infrastructure, and Environment (SDSFIE) as the database structure. Provide a shell database to define the projection and database structure.
For all drawings within and including the exterior walls, utilize the advanced modeling formats described and referenced herein. Provide a short GeoDataBase read-me file explaining the deliverable. The read-me file will include a description of the software used to create the data, projection, and include the attribute tables used.
2.8 AS-BUILT OR ADVANCED MODELING RE-SUBMISSION REQUIREMENTS
If elements of an as-built submittal or advanced modeling package are rejected, provide the following for each re-submission, in addition to any information required in Section 01 33 00 SUBMITTAL PROCEDURES:
a. Re-submit all components required under paragraph As-Builts or Advanced Modeling Package, including a new Advanced Modeling Submittal Checklist and updated content in response to Government comments.
b. Provide a copy of all Government review comments.
c. Provide a disposition/response to each Government review comment for a back-check of the re-submission deliverable.
SECTION 01 78 00 Page 13
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
Provide and maintain two black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as-builts throughout construction as red-lined hard copies on site and red-lined PDF files.
Submit As-Built Drawings 30 days prior to Beneficial Occupancy Date (BOD).
3.1.1 Markup Guidelines
Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing.
Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:
a. Use base colors of red, green, and blue. Color code for changes as follows:
(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.
(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders.
(3) Additions (Green) - Added items, lettering in notes and leaders.
b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.
c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.
d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.
e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.
f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.
g. For deletions, cross out all features, data and captions that relate to that revision.
h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.
i. Indicate one of the following when attaching a print or sketch to a markup print:
1) Add an entire drawing to contract drawings
2) Change the contract drawing to show
SECTION 01 78 00 Page 14
3) Provided for reference only to further detail the initial design.
j. Incorporate all shop and fabrication drawings into the markup drawings.
3.1.2 As-Built Drawings Content
Revise As-Built Drawings and red-lined PDF files in accordance with ERDC/ITL TR-12-1 and ERDC/ITL TR-12-6 . Keep these working as-built markup drawings current on a weekly basis and at least one set available on the jobsite at all times. Changes from the contract drawings which are made during construction or additional information which might be uncovered in the course of construction must be accurately and neatly recorded as they occur by means of details and notes. Submit the working as-built markup drawings for approval prior to submission of each monthly pay estimate.
For failure to maintain the working and final record drawings as specified herein, the Contracting Officer will withhold 10 percent of the monthly progress payment until approval of updated drawings. Show on the as-built drawings, but not limited to, the following information:
a. The actual location, kinds and sizes of all sub-surface utility lines. In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, show by offset dimensions to two permanently fixed surface features the end of each run including each change in direction on the record drawings. Locate valves, splice boxes and similar appurtenances by dimensioning along the utility run from a reference point. Also record the average depth below the surface of each run.
b. The location and dimensions of any changes within the building structure.
c. Layout and schematic drawings of electrical circuits and piping.
d. Correct grade, elevations, cross section, or alignment of roads, earthwork, structures or utilities if any changes were made from contract plans.
e. Changes in details of design or additional information obtained from working drawings specified to be prepared or furnished by the Contractor; including but not limited to shop drawings, fabrication, erection, installation plans and placing details, pipe sizes, insulation material, dimensions of equipment, and foundations.
f. The topography, invert elevations and grades of drainage installed or affected as part of the project construction.
g. Changes or Revisions which result from the final inspection.
h. Where contract drawings or specifications present options, show only the option selected for construction on the working as-built markup drawings.
i. If borrow material for this project is from sources on Government property, or if Government property is used as a spoil area, furnish a contour map of the final borrow pit/spoil area elevations.
j. Systems designed or enhanced by the Contractor, such as HVAC controls, SECTION 01 78 00 Page 15 fire alarm, fire sprinkler, and irrigation systems.
k. Changes in location of equipment and architectural features.
l. Modifications.
m. Actual location of anchors, construction and control joints, etc., in concrete.
n. Unusual or uncharted obstructions that are encountered in the contract work area during construction.
o. Location, extent, thickness, and size of stone protection particularly where it will be normally submerged by water.
3.2 RECORD DRAWING FILES
If additional drawings are required, prepare them using the specified electronic file format applying ERDC/ITL TR-12-6 and ERDC/ITL TR-12-1 .
The title block and drawing border to be used for any new final record drawings must be identical to that used on the contract drawings.
Accomplish additions and corrections to the contract drawings using CAD files. Provide all program files and hardware necessary to prepare final PDF record drawings. The Contracting Officer will review final PDF record drawings for accuracy and return them to the Contractor for required corrections, changes, additions, and deletions.
3.2.1 Rename the CAD Drawing files
Rename the CAD Drawing files using the contract number as the Project Code field,(e.g., W91238-15-C-10A-102. DWGDGN) as instructed in the Pre-Construction conference. Use only those renamed files for the Marked-up changes. Make all changes on the layer/level as the original item.
a. For AutoCAD files (DWG), enter all as-built delta changes and notations on the AS-BUILT layer. MicroStation files (DGN), enter all as-built delta changes and notations on:
- Level #63
- Level/Layer Name contains: ANNO-REVS
- Level/Layer Description: Revisions
b. When final revisions have been completed, show the wording "RECORD DRAWING AS-BUILTS" followed by the name of the Contractor in letters at least 3/16 inch high on the cover sheet drawing. Date RECORD DRAWING AS-BUILTS" drawing revisions in the revision block.
c. Within 10 days after Government approval of all of the working record drawings for a phase of work, prepare the final CAD record drawings for that phase of work and submit PDF drawing files and two sets of prints for review and approval. The Government will promptly return one set of prints annotated with any necessary corrections. Within 7 days revise the CAD files accordingly at no additional cost and submit one set of final prints for the completed phase of work to the Government. Within 10 days of substantial completion of all phases of work, submit the final record drawing package for the entire project.
Submit one set of electronic CAD files, and one set of the approved working record PDF files on three optical discs with two sets of
SECTION 01 78 00 Page 16 prints. The CAD files must be complete in all details and identical in form and function to the CAD drawing files supplied by the Government. Prepare AutoCAD files for transmittal using e-Transmit.
Prepare MicroStation files for transmittal using the Packager (Archive). Make any transactions or adjustments necessary to accomplish this. The Government reserves the right to reject any drawing files it deems incompatible with the customer's CAD system.
Paper prints, drawing files and storage media submitted will become the property of the Government upon final approval.