RFP W912DW20R0017 Fuel Hydrant System Repair.pdf

PDF 17 MB Posted

Attached to
FY20 Repair of Fuel Hydrant System, Spots 25-28 at Fairchild Air Force Base, Spokane, WA.
Solicitation number
W912DW-20-R-0017
Issued by

About this file

This solicitation is for repair work on a fuel hydrant system at Fairchild Air Force Base in Spokane, Washington. The Department of the Army Corps of Engineers Engineering District Seattle is seeking bids to repair fuel hydrant spots 25 through 28. The solicitation package includes the RFP document, a drawing of the project site, and a specification document outlining the repair work. Bids are due by April 2, 2020 and the contract is to be awarded by May 15, 2020. The repair work involves assessing and replacing components of the hydrant system as needed, including piping, valves, and associated hardware. The contractor will be responsible for providing all labor, equipment, and materials to complete the repairs in accordance with the specification documents.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. W912DW20R0017

Seattle District

FY20 Repair of Fuel Hydrant System, Spots 25-28 at Fairchild Air Force Base, Spokane, WA

Construction Solicitation and Specifications

July 2020

Request for Proposals (RFP) W912DW20R0017 "Repair of Fuel Hydrant System Spots 25-28 at Fairchild Air Force Base, Spokane, WA.”

This project w ill be procured on an Unrestricted Basis.

Per DFARS 236.204(ii), Disclosure of the magnitude of construction projects is estimated betw een $10,000,000 and $25,000,000. NAICS Code 236220, Size determination $39,500,000.00

Funds are not currently available for this acquisition. No contract aw ard w ill be made until appropriated funds are made available from w hich payment for contract purposes can be made.

Technical inquiries and questions relating to the proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://projnet.org/projnet. Please see Section 00 21 16, Bidder Inquiry for further instructions.

NOTE: See Block 13.A - The government w ill only accept electronic copies of submission. See instruction of submission under section 00 21 16 Para 1.11 "Proposal Submittals"

HYUN TOWNSLEY 206-316-4381

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

09-Jul-2020

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________730 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________52.211-10

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

X YES NO

13.

A.

local time ______________02 Sep 2020 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.

B. An offer guarantee X is, is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______120 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

USA ENGINEER DISTRICT, SEATTLE

ATTN: CENWS-CT

4735 EAST MARGINAL WAY SOUTH, BLDG. 1202

SEATTLE WA 98134-2388

W912DW

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

ADDITIONAL SOLICITATION REQUIREMENTS:

Sealed offers in original and (See Block 10)_ copies to perform the w ork required are due at the place specif ied in Item 8 by1_0_:_0_0 _A__M (__hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

206-764-6817FAX:TEL: TEL: FAX:

W912DW20R0017 90

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

Section 00 01 10 - Table of Contents

TABLE OF CONTENTS

SECTION TITLE

Cover Page

SF 1442 –Solicitation, Offer, and Award

00 01 10 Table of Contents

00 10 00 Solicitation, Caution to Offeror, Corporate Certificate, and Price Schedule

00 21 00 Contract Provisions

00 21 16 Instructions to Proposers

00 22 16 Evaluation Factors for Award

00 45 00 Representations and Certifications

00 72 00 General Conditions - Contract Clauses

00 73 00 Supplementary Conditions

Subcontracting Plan (Sample)

Davis-Bacon General Wage Determination

End of Table of Contents

Section 00 10 00 - Solicitation

CAUTION TO OFFERORS

! ! ! C A U T I O N TO O F F E R O R ! ! !

1. BUSINESS HOURS: For the Seattle District Corps of Engineers are from 7:30 A.M. to

4:00 P.M., Monday through Friday.

2. AVAILABILITY OF FUNDS: Funds are not currently available for this acquisition.

No contract award will be made until appropriated funds are made available from which payment for contract purposes can be made.

BEFORE SIGNING AND ELECTRONICALLY SUBMITTING THIS OFFER,

PLEASE TAKE NOTE OF THE FOLLOWING, AS FAILURE TO PERFORM ANY

ONE OF THESE ACTIONS MAY CAUSE YOUR OFFER TO BE REJECTED

3. AMENDMENTS: Have you acknowledged receipt of ALL amendments?

4. AMENDED SECTIONS: If any of the amendments furnished amended sections, the amended sections must be used in submitting your offer.

5. MISTAKE IN OFFER: Have you reviewed your offer price for possible errors in calculation or work left out?

6. OFFER ACCEPTANCE PERIOD: The minimum offer acceptance period is specified in block 13D of SF1442. Please ensure that you allow at least the stated number of calendar days for the Government to accept your offer.

7. SYSTEM FOR AWARD MANAGEMENT: Contractors are required, before receipt of contract award, to ensure that their firm is registered in the government web site entitled

System for Award Management (SAM) and that all information required is current and up to date. https://www.sam.gov/SAM/

8. IMPORTANT NOTE FOR OTHER THAN U.S. SMALL BUSINESSES ONLY:

Small Business Subcontracting Plan is required. Please see paragraph 8.0 of Section 00 22 16 for submittal requirements. No award will be made to an Offeror until an approved subcontracting plan is in place. The Government will evaluate the subcontracting plan in accordance with AFARS Appendix DD (http://farsite.hill.af.mil/vmafara.htm) and with the requirements of FAR Clause 52.219-9 and DEVIATION 2018-O0018. The subcontracting plan must contain the mandatory requirements outlined in FAR 19.704 and the dollar amount for each socioeconomic category. The final approved subcontracting plan shall become a material part of the contract.

NOTE: A sample Subcontracting Plan format which can be used as a guide, is attached to

Section 00 73 00. Use of this format is not mandatory and does not guarantee acceptance.

The subcontracting plan must contain the mandatory plan requirements outlined in FAR

19.704.

http://www.sam.gov/SAM/ http://farsite.hill.af.mil/vmafara.htm)

CORPORATE CERTIFICATE

IF THE CONTRACTOR IS A CORPORATION OR PARTNERSHIP, THE APPLICABLE PORTION OF THE

FORM LISTED BELOW MUST BE COMPLETED. IN THE ALTERNATIVE, OTHER EVIDENCE MUST BE

SUBMITTED TO SUBSTANTIATE THE AUTHORITY OF THE PERSON SIGNING THE CONTRACT. IF A

CORPORATION, THE SAME OFFICER SHALL NOT EXECUTE BOTH THE CONTRACT AND THE

CERTIFICATE.

CORPORATE CERTIFICATE

I, , certify that I am the

Secretary of the Corporation named as Contractor herein; that , who signed this contract on behalf of the Contractor was then o f said corporation; that said contract was duly signed for and on behalf of said corporation by authority of its governing body and is within the scope of its corporate powers.

(CORPORATE

(Secretary) SEAL)

AUTHORITYTOBIND

PARTNERSHIP

This is to certify that the names and signatures of all partners are listed below and that the person signing the contract has authority actually to bind the partnership pursuant to its partnership agreements. Each of the partners individually has full authority to enter into and execute contractual instruments on behalf of said partnership with the United States of America, except as follows: (state "none" or describe limitations, if any)

This authority shall remain in full force and effect until such time as the revocation of authority by any cause whatsoever has been furnished in writing to, and acknowledged by, the Contracting Officer.

(Names and Signatures of all Partners)

NAME SIGNATURE

PRICE SHEDULE

PRICE SCHEDULE

CLIN

Description of Item Quantity Unit Unit

Amount

Fueling System

Detection Systems

All work for leak detection system

1 JOB N/A $

TOTAL ALL OPTIONAL ITEMS 0008 - 0008 $

TOTAL ALL ITEMS 0001 - 0008 $

Item # Price

BASE ITEMS

All work for repairs to airfield paving

0001 systems at aircraft parking spots 25-28 1

JOB

N/A

All Work for repairs to Hydrant

All work for repairs to Intrusion

All work for removal and replacement of

0004 Petroleum Contaminated Soil (PCS)

3,100

TON

All work for O&M manuals as specified in

Section 01 78 23 OPERATIONS AND

MAINTENANCE MANUALS from 1 preparation to final approval.

JOB N/A $15,000

All work for As-Built drawings as specified in Section 01 78 00

CLOSEOUT SUBMITTALS from 1 preparation to final approval.

$30,000

All work for DD 1354 as specified in

Section 01 78 00 CLOSEOUT

$15,000

SUBMITTALS from preparation to final approval

TOTAL ALL BASE ITEMS 0001 - 0007 $

OPTIONAL ITEMS

NOTES:

1. 100% Design project cannot be altered, changed, or re-designed in any way. No alternate proposals will be accepted.

2. To better facilitate the receipt and proposal process, all revisions to proposals are to be submitted on copies of the latest Price Schedule as published in the solicitation or the latest amendment thereto. On lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

3. Offerors must insert a price on Line Item #0001, #0002, #0003, #0004 and #0008 of the Price

Schedule. Failure to do so will result in the offer being unacceptable.

4. The dollar amount established in Contract Line Item #0005, #0006, and #0007 shall not be revised by the Offerors.

5. CLIN 0004 is a unit-priced item with estimated quantities and is subject to FAR 52.211-18.

Variation in Estimated Quantities.

6. Award of optional items will be made in accordance with FAR 52.217-7 “OPTION FOR

INCREASED QUANTITY”.

7. General Note, Definitions of Units:

TON: Ton – 2000 lbs.

JOB: Job – Full and complete work

Section 00 21 00 - Instructions

CLAUSES INCORPORATED BY REFERENCE

52.204-7 Alt I System for Award Management-- Alternate I OCT 2018

52.204-16 Commercial and Government Entity Code Reporting JUL 2016

52.215-1 Instructions to Offerors--Competitive Acquisition JAN 2017

52.222-5 Construction Wage Rate Requirements--Secondary Site of the MAY 2014 Work

52.222-38 Compliance With Veterans' Employment Reporting FEB 2016 Requirements

52.246-12 Inspection of Construction AUG 1996

252.204-7008 Compliance With Safeguarding Covered Defense Information OCT 2016 Controls

252.215-7011 Requirements for Submission of Proposals to the JAN 2018 Administrative Contracting Officer and Contract Auditor.

252.219-7000 Advancing Small Business Growth SEP 2016 252.236-7008 Contract Prices-Bidding Schedules DEC 1991

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm Fixed Price contract resulting from this solicitation.

(End of provision)

52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL

EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)

(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance

Requirements for Construction clause of this solicitation.

(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:

Goals for minority participation for each trade

Goals for female participation for each trade

6.2%

6.9%

These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract

Compliance Programs office.

(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from

Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.

(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract

Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --

(1) Name, address, and telephone number of the subcontractor;

(2) Employer's identification number of the subcontractor;

(3) Estimated dollar amount of the subcontract;

(4) Estimated starting and completion dates of the subcontract; and

(5) Geographical area in which the subcontract is to be performed.

(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Fairchild Air

Force Base, Spokane, Washington

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000.00 whichever is less.-

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (email address below) by obtaining written and dated acknowledgment of receipt from:

Roger D. Williams, Jr. Chief, Contracting Division

US Army Corps of Engineers –Seattle District

Email: Roger.D.Williams@usace.army.mil

(b) The electronic copy of any protest shall be received via email designated above within one day of filing a protest with the GAO.

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for – please see Section 00 21 16, Paragraph 1.9 for instruction on registration and the specific date, time and location.

52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Alterations, if necessary, will be via amendment mailto:Roger.D.Williams@usace.army.mil http://www.acquisition.gov/

Section 00 21 16 - Instructions to Proposers

SECTION 00 21 16 - INSTRUCTIONS TO PROPOSERS

SECTION TABLE OF CONTENTS

1. GENERAL INFORMATION

1.1 GENERAL DESCRIPTION OF WORK

1.2. DISCLOSURE OF MAGNITUDE

1.3. SUBJECT TO AVAILABILITY OF FUNDS

1.4. GOVERNMENT SECURITYREQUIREMENTS

1.5. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

1.6. OFFEROR'S QUESTIONS AND COMMENTS

1.7. SMALL BUSINESS SIZE STANDARD/NAICS CODE

1.8. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

1.9. SITE VISIT

1.10. ACCURACY IN PROPOSALS

1.11. PROPOSAL SUBMITTALS

1.12. PROPOSAL FORMAT

1.13. BID GUARANTEE

1.14. JOINT VENTURE PROPOSAL REQUIREMENTS

1.15. SUBCONTRACTING PLAN

INSTRUCTION TO PROPOSERS

1.0 GENERAL INFORMATION

1.1. GENERAL DESCRIPTION OF WORK

The U.S. Army Corps of Engineers (USACE), Seattle District (NWS) intends to procure services to repair

Type III hydrant fuel, airfield pavement and intrusion detection systems serving aircraft parking spots 25 through 28 to make them serviceable for parking and fueling KC-135 and other large airframe aircraft. This project will replace 18” carbon steel piping with 12” lined carbon steel piping from the pumphouse to Spot

28 and create a looped system, reconstruct all pavements for KC-135 parking spots 25-28, extend the intrusion detection system to serve these parking spots, and properly dispose of and replace any contaminated soils disturbed. The project will be 100% design complete prior to solicitation.

1.2. DISCLOSURE OF MAGNITUDE

Proposed project will be a Firm Fixed-Price construction project. In accordance with DFARS 236.204

Disclosure of the magnitude of construction projects, the order of magnitude for this project is estimated to be in the range of $10,000,000.00 to $25,000,000.00. 100 percent payment and performance bonds will be required.

1.3. SUBJECT TO AVAILABILITY OF FUNDS

FAR Clause 52.232-18 “Availability of Funds,” (APR 1984) Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the

Contracting Officer.

1.4. GOVERNMENT SECURITY REQUIREMENTS

The Offeror(s) must ensure that ALL mail sent to the Seattle District, U.S. Army Corps of Engineers

(NWS), either pre-contract or post-contract award, has a return mailing address on the outside of the envelope, package, box, etc. ANY MAIL addressed to the U.S. Army Corps of Engineers, including but not limited to proposals, revised proposals, bonds, correspondence, etc., may be REJECTED by the US Army

Corps of Engineers mail room facility located in Building 1202, at 4735 East Marginal Way South, Seattle, WA 98134 if it does not contain a return mailing address.

1.5. COPIES OF SOLICITATION DOCUMENTS AND AMENDMENTS

Copies of the solicitation and amendments are available by INTERNET ACCESS ONLY. All solicitation documents will be posted to the Federal Business Opportunities website at https://beta.sam.gov under RFP number W912DW-20-R- 0017.

It shall be the contractor’s responsibility to check the websites for any amendments. There will be no public opening of the proposals received as a result of this solicitation.

A list of interested vendors (potential offerors and subcontractors) is available on the federal business opportunities web site (registration required) with the solicitation announcement.

1.6. OFFEROR'S QUESTIONS AND COMMENTS

Administrative questions and/or comments relative to these documents should be submitted via e-mail to:

Contract Specialist Hyun J Townsley Phone: 206-764-3781

Email: Hyun.Townsley@usace.army.mil

Contracting Officer Michael M. Miyagi Phone: 206-764-3266

Email: Michael.m.miyagi@usace.army.mil

1.6.1. Bidder Inquiry

1.6.1.1. Technical inquiries and questions relating to proposal procedures or bonds are to be submitted via Bidder Inquiry in ProjNet at http://www.projnet.org/projnet

1.6.1.1.1. To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into the system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency

USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.

1.6.1.1.2. From this page you may view all bidder inquiries or add inquiry.

1.6.1.1.3. Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.

1.6.1.1.4. The Solicitation Number is: W912DW-20-R-0017

1.6.1.1.5. The Bidder Inquiry Key is: YPCYQM-749UQX

1.6.1.2. The Bidder Inquiry System will be unavailable for new inquiries three (3) business days prior to proposal submission in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.

1.6.1.3. Offerors are requested to review the solicitation in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.

1.6.1.4. The call center operates weekdays from 8AM to 5PM U.S. Central Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.

1.6.1.5. There will be no publicly available information until after proposals are received, evaluated and an award is made.

1.7. SMALL BUSINESS SIZE STANDARD/NAICS CODE

See Section 00 45 00, FAR Provision, 52.204-8 for the small business size standard/NAICS Code.

1.8. PROPOSAL EXPENSES AND PRE-CONTRACT COSTS

This Request for Proposal (RFP) does not commit the Government to pay, as a direct charge, any costs incurred in the preparation and submission of a proposal.

1.9. SITE VISIT

Bidders wishing to visit the site shall contact Mr. Nathan Watko at 509-244- 5571 extension 1222 no later than 1500 hours (3:00 PM) PDT on 22 July 2020 to register by providing their full names, social security numbers, and date of birth so that a background check can be completed prior to the site visit. Bidders who have registered by the deadline above shall assemble at the Visitor Center parking lot at the Main Gate entrance of Fairchild Air Force Base at 8:00 am on 4 August 2020 to obtain 1 day access pass to the base.

Bidders who fail to register by the deadline will not be permitted attend the site visit.

mailto:Hyun.Townsley@usace.army.mil mailto:Michael.m.miyagi@usace.army.mil http://www.projnet.org/projnet

Individuals will need to have current, valid identification as specified in specification section 01 14 00, Work Restrictions, of this solicitation. Anyone wishing to drive on base must have a current vehicle registration and proof of insurance with them. Background checks will be conducted and anyone with an open warrant, foreign nationals without adequate documentation, and anyone in possession of federally controlled substances (esp. marijuana) are likely to be detained. Procedures are available at:

http://www.fairchild.af.mil/Home/VVCC.aspx. Tour at the construction site will depart the main gate promptly at 10:00 am on 4 August 2020.

Due to COVID-19, social distancing will be strictly observed and the gathering will remain outdoors.

Guidelines are as follows:

- Each offeror will be limited to four representatives, including all subs and partners, for site visit.

- All participants will remain at their vehicle until Government representatives form small sub-groups of less than 10 persons per sub-group to walk through the project site.

-Attendance for each sub-group will be recorded by the Government rep for each group through verbal communication.

-Social distancing (6 foot distance) will be strictly observed.

- All participants are required to wear face coverings, per Washington Statewide Face Covering Order effective

June 26, 2020. More information:

https://www.coronavirus.wa.gov/information-for/you-and-your-family/face-masks-or-cloth-face-covering

1.10. ACCURACY IN PROPOSALS

Proposals must set forth full, accurate, and complete information as required by this RFP, (including attachments). The penalty for making false statements is prescribed in 18 U.S.C. 1001.

1.11. PROPOSAL SUBMITTALS

In strict compliance with guidance relating to the current situation with COVID-19 and social distancing, the only authorized transmission method for proposals in response to this solicitation is electronically via

SAFE online submission. NO OTHER TRANSMISSION METHODS (E-MAIL, FACSIMILE, REGULAR MAIL, HAND CARRIED, ETC.) WILL BE ACCEPTED.

The Offeror’s proposal must be received by the Government by the date/time specified in the solicitation.

Offerors shall electronically transmit their proposals using the following link:

https://safe.apps.mil/

Please send proposals using the link above to Contract Specialist Hyun Townsley at

Hyun.Townsley@usace.army.mil AND to Contracting Officer Michael

M. Miyagi at Michael.m.miyagi@usace.army.mil.

1.11.1 Instructions for Submitting Electronic Proposals

In an effort to reduce paperwork and cost, all proposals shall be submitted electronically through the SAFE site. Submission shall be in Adobe PDF format. Submit no more than five (5) PDF files. Total file size cannot exceed 8GB package, and each package cannot contain more than 25 files (DoD SAFE’s published limit). Files may be compressed and/or combined into ZIP files using compression utility software such as

WinZip or PKZip to reduce file size and facilitate transmission.

1.11.2 Request for Upload Code

Email Contract Specialist Hyun Townsley at Hyun.Townsley@usace.army.mil AND to Contracting Officer

Michael M. Miyagi at Michael.m.miyagi@usace.army.mil no later than five (5) working days prior to the proposal due date to receive a request code. Include “W912DW20R0017 SAFE Proposal Drop-Off Request

…” in the subject. Include the name and email address of the sender, and the name of the offeror in the http://www.fairchild.af.mil/Home/VVCC.aspx http://www.fairchild.af.mil/Home/VVCC.aspx mailto:Hyun.Townsley@usace.army.mil mailto:Michael.m.miyagi@usace.army.mil mailto:Hyun.Townsley@usace.army.mil body of the email.

The request code will allow a one-time file upload via the SAFE site. Offerors that fail to email for request a code five (5) working days before proposal submission date may not be able to receive a request code in time to upload their submission.

You will receive an email from NoReplyTo@mail.mil with the subject line similar to "[DoD SAFE]

W912DW20RTEST Proposal Drop-off Invite”. The body of the email will contain a hyperlink, with the drop-off key embedded, for your use in uploading your proposal. The body of the email may also contain additional instructions from the Contracting Specialist in a note beneath the hyperlink. The drop-off key will be valid for 14 calendar days.

1.11.3 Instructions for Upload of Proposal

1.11.3.1 Follow the hyperlink in the email. This will take you to the DoD SAFE drop off page. The page will be pre-populated with the Name and email you provided, the name and email of the recipient, and the note with additional instructions from the Contracting Specialist.

1.11.3.2 Add Contract Specialist Hyun Townsley at Hyun.Townsley@usace.army.mil and Contracting

Officer Michael Miyagi at Michael.m.miyagi@usace.army.mil as recipients. The Proposer must enter the e-mail address for both the Contracting Officer and Specialist. The Proposer can enter an additional email address if desired. After entering the e-mail address, click the ADD button to add the person(s) e-mail to the “Recipients List” of your response. When your proposal is submitted, a notification will be sent to the recipients you added.

NOTE: Do NOT send the SAFE site packages to group e-mail accounts.

1.11.3.3 Accept the default checkbox settings. Add the files that contain your offer. Files for upload will be listed beneath the “Click to Add Files or Drag Them Here” button. Enter a description for each file.

Ensure your proposal is complete and all files are listed; this is a one-time drop-off key. Click on “Drop-off Files” when all files are listed.

1.11.3.4 When the upload is complete, DoD SAFE will present a screen listing the files uploaded and transmit an email to the recipient(s) to inform them that your proposal has been uploaded.

1.11.4 Receipt of Submissions

The Government will consider proposal submission timely if it is completely uploaded into the SAFE website and the acknowledgement email sent by the date and time proposals are due. It is the Offeror’s responsibility to allow sufficient time for upload. It can take several minutes or even hours in some cases.

The government will not be responsible for submissions delivered to any location or to anyone other than those designated to receive proposals. Offerors are responsible for ensuring that proposals are submitted so as to reach the designated recipient. Offerors are responsible for allowing sufficient time for the proposal to be received in accordance with the instructions provided.

1.12. PROPOSAL FORMAT

1.12.1 File format. Proposals shall be submitted in PDF format, suitable for reading using Adobe Acrobat in a Windows 10 operating system. PDF files may be combined and compressed using compression utility software such as WinZip or PKZip.

1.12.2 File Organization. Volumes I and II shall be submitted in different files. Each Volume shall be organized as specified below. PDFs shall be indexed and bookmarked to facilitate navigation.

1.12.3 File Names shall clearly state the RFP Number, Volume Number and Offeror Name. If applicable, mailto:NoReplyTo@mail.mil file names may include the Tab, Example Project Number, and similar relevant information.

1.12.4 Formatting. Pagination shall be in 8 ½” x 11” format, using at least ½” margins and 10 point or larger font size.

1.12.4.1 The prime or joint venture’s name, address, a signature of the official that can bind the firm and a telephone number shall appear in the lower left corner of the title page of any document/volume to be evaluated.

1.12.4.2 Volume number, section and date submitted shall appear in the bottom right corner of each page

(along with the revision number for the amended page, if necessary). (Volume II as defined in Section 00

22 16).

1.12.5 Volume I

The Offeror’s Technical Proposal shall include the following sections, in the general format specified below:

Table of Contents for Volume I – (Listing of all sections of the technical proposal)

Tab A/Factor A – Relevant Experience, Attachment 1.

Tab B/Factor B –Past Performance, Attachment 4.

1.12.6 Volume II

The Offeror’s Price Proposal shall include the following, in the general format specified below:

SF 1442 and Bid Schedule, Section 00 11 00 (filled out in its entirety)

Bid Guarantee

Pre-Award Information found at back of Section 00 45 00 (filled out in its entirety)

Section 00 45 00 Representations and Certifications

Subcontracting Plan see section 00 22 16, paragraph 8.0, subcontracting plan.

NOTE: Offeror’s Price Proposal is due AT THE SAME TIME as Technical Proposal.

1.13 BID GUARANTEE

In accordance with FAR 52.228-1 in Section 00 21 16 Instructions to Proposers, the Offeror is required to submit a bid guarantee along with its proposal. The bid guarantee shall be included in Volume II of the proposal. Any proposal received without a bid guarantee will be rejected and is ineligible for review by the

Government. The amount of the Bid Guarantee shall be twenty (20) percent of the Offeror’s proposed price or $3,000,000.00, whichever is less.

1.14. JOINT VENTURE PROPOSAL REQUIREMENTS

When proposing as a joint venture, all members of the joint venture shall sign the SF 1442 and the bid bond unless a written agreement by the joint venture is furnished with the proposal designating one firm with the authority to bind the other member(s) of the joint venture. In addition, a copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirements may eliminate the proposal from further consideration. If this is an 8(a) or HubZone joint venture, the offeror shall ensure that it complies with the applicable requirements of 13 CFR Part 124 and 13 CFR Part 126, respectively.

1.15. SUBCONTRACTING PLAN/ SUBCONTRACTING GOALS REGARDING THE UTILIZATION

OF SMALL BUSINESS CONCERNS

(a) Application. This clause applies to all offerors that are other than Small Businesses submitting proposals.

(b) Federal Acquisition Regulations (FAR). Attention is directed to the following FAR and

DFARS provisions contained in this solicitation:

52.219-8, Utilization of Small Business Concerns (Alternate I)

52.219-9, Small Business Sub Contracting Plan (Alternate I) (applies only to Large Business)

52.219-16, Liquidated Damages – Small Business Subcontracting Plan (applies only to Large Business)

252.226-7001, Utilization of Indian Organizations, Indian-Owned Economic Enterprises, an Native

Hawaiian Small Business Concerns

(c) Goals. The U.S. Army Corps of Engineers considers the following goals reasonable and achievable for the performance of the resultant contract:

Small Business – 53.1%

HUBZone Small Business – 3.5%

Service-Disabled Veteran-Owned Small Business – 10.6%

Small Disadvantaged Business/8(a) – 23.6%

Women-Owned Small Business – 4.3%

Note: Sample SUBCONTRACTING PLAN FORMAT PROVIDED IN SECTION 00 73 00(If applicable)

END OF SECTION 00 21 16

Section 00 22 16 - Evaluation Factors for Award

EVALUATION FACTORS FOR AWARD

1.0 BASIS OF AWARD

Award of this Contract will be made to the technically acceptable responsible Offeror submitting the lowest priced offer (based on the total of all line items on the Bid Schedule) – Lowest Priced Technically Acceptable Offer

(LPTA). This acquisition will result in the award of a firm-fixed price, construction contract.

The technical evaluation of each proposal will be solely on the basis of Technical Evaluation Factors found in this section. The Government will evaluate each proposal on a technically acceptable/unacceptable basis only with respect to the technical evaluation factors (criteria) described herein. Award will be to the Offeror who presents the technically acceptable proposal with the overall total lowest price. It is the intent of the Government to award off initial offers without discussions.

2.0 PROPOSAL EVALUATION

2.1 Technical Evaluation

Acceptability will be based on all factors receiving an acceptable rating. The proposal will be evaluated according to the Criteria for Non-Price Evaluation Factors of this section.

Proposals will receive either an ACCEPTABLE or an UNACCEPTABLE rating for each of the evaluation factors.

Find the description of these ratings in Table 1.

TABLE 1: TECHNICAL ACCEPTABLE/UNACCEPTABLE RATINGS

Rating: Description

Acceptable Proposal clearly meets the minimum requirements of the solicitation.

Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.

2.2 Pricing Evaluation

The Government will evaluate offers for award purposes by adding the total price for all line items, including optional items, identified on the Contract Line Item Schedule (Price-Schedule), Section 00 11 00 of this Solicitation.

3.0 EVALUATION PROCESS

The evaluation process consists of three parts:

Proposal Compliance Review. This is an initial review to ensure that all required forms and certifications are complete and that a complete proposal is received. An initial review of each of the proposals will be conducted to check for apparent errors, omissions and areas that require clarification. The purpose of this preliminary review session is to eliminate minor irregularities or apparent clerical mistakes. This preliminary evaluation will ensure that each proposal contains the Price Volume II and the correct number of copies.

Technical Review. Relevant Experience and Past Performance. Relevant Experience and

Past Performance will be evaluated according to the Criteria for Non-Price Evaluation

Factors found in this section.

Price Evaluation. The Government will evaluate price for fairness and reasonableness through the use of price analysis. Price will also be verified for unbalancing of line items.

3.1 Definitions

Clarification is a limited exchange with an Offeror for the sole purpose of eliminating minor irregularities, informalities, or apparent clerical mistakes in the proposal or to address adverse past performance not previously addressed with the Offeror. Clarifications do not give an Offeror the opportunity to revise of modify its proposal and are used, as necessary, when not opening discussions.

Communications are a limited exchange with an Offeror used to assist in determinations of the competitive range. Communications are limited to enhancing Government understanding of proposals and addressing adverse past performance information not previously addressed if said information is the determining factor preventing an Offeror from being included in the competitive range. Such communications shall not be used to cure proposal deficiencies or material omissions, or otherwise revise the proposal.

Discussions offer the opportunity to resolve deficiencies or weaknesses in the proposals, based on the requirement and the evaluations factors set forth in the solicitation. If the Contracting Officer determines it is necessary to open discussions, they must discuss with all Offerors in the competitive range. Offerors have the opportunity to revise their proposals at the conclusion of discussions.

A Project is a temporary endeavor undertaken to create a unique result. Submit only projects that demonstrate Relevant Experience required under Factor A and Past Performance required under

Factor B. Submit projects performed under C-type contracts or task orders; do not submit base or umbrella IDIQ contracts as projects.

Year is defined as 365 consecutive days.

4.0 EVALUATION CRITERIA

4.1 Criteria for Non-Price Evaluation Factors

Proposals shall concisely, accurately, and completely provide the information required for each of the following non-price evaluation factors. NOTE: Absence of complete information will be deemed as if no support information was provided for that factor. Proposals that do not meet the minimum requirements of all of the non-price evaluation factors shall be determined to be UNACCEPTABLE and are not eligible for award consideration. NO assumptions may be made by the Government. Your proposal must CLEARLY demonstrate the requisite technical experience and qualifications to receive an ACCEPTABLE rating for each of the following criteria:

TABLE 2: EVALUATION

FACTORS

LOCATION DESCRIPTION

FACTOR A VOLUME 1, TAB A RELEVANT EXPERIENCE

FACTOR B VOLUME 1, TAB B PAST PERFORMANCE

5.0 FACTOR A – RELEVANT EXPERIENCE

5.1 Definitions for Factor A (Definitions for the purposes of this factor)

Relevant is defined as having a logical connection with the requirements in this request for technical proposals; that is, featuring work that is similar in complexity, magnitude, and scope to the current requirement. To be acceptable, there must be an explanation of how the provided project information is relevant to the proposed work

Complexity means new construction or major repair with many varied elements of work or sequencing of the work required for construction or major repair of hydrant fueling systems and aircraft parking spots within the controlled flight line area of active U.S. Department of Defense airfields serving large airframe, fixed-wing aircraft.

Magnitude means a total project contract value –greater than $5,000,000.

Scope means containing many of the elements of work and of physical size of construction of

DoD Type III hydrant fueling pits, and piping and/or construction of Portland cement and asphalt concrete airfield pavements.

Similar means not necessarily identical but showing a resemblance in qualities or characteristics of the proposed project.

Experience - knowledge and skill obtained by performing or managing work.

5.2 Submission Requirements for Factor A

5.2.1 Submit a minimum of three and a maximum of six (3-6) project examples to clearly demonstrate the relevant experience required. Submit Attachment 1, Offeror’s Relevant Experience Matrix and use Attachment 2, Offeror Experience Form, for each project. Submit only those projects for which the Offeror was the Prime

Contractor or part of a Joint Venture, except as specified below. If more than six (6) projects are submitted, only the first six will be evaluated, in the order they are presented in the proposal.

5.2.1.1 For purposes of evaluating construction experience as a Prime Contractor, the Offeror and prime contractor are defined as the contractor identified in Block 14 of SF1442. If a Joint Venture is identified in Block 14 of the SF

1442, then a signed Joint Venture Agreement must be submitted with the proposal and the Joint Venture shall be registered as such in the System for Award Management (SAM) before this proposal response date established in this solicitation.

5.2.1.2 The Offeror may demonstrate prime contractor experience if it served on the example project as one of the partners in a Joint Venture executing that project; if an Offeror is claiming prior project experience as a partner in a

Joint Venture, then the signed Joint Venture Agreement applicable to that example project must also be submitted.

5.2.1.3 Projects performed by contractors other than the Offeror (such as teaming partners) will not be evaluated as construction experience by a prime contractor unless (1) those other contractors are part of a Joint Venture for this solicitation as demonstrated by a signed Joint Venture Agreement or (2) those other contractors are proposed as key subcontractors and commitment is demonstrated with a completed Attachment 3, Letter of Commitment of Key

Sub-Contractor. Prior experience as a subcontractor is not considered relevant when evaluating the experience of the

Offeror as a prime contractor.

5.2.1.4 The Government will also consider prime contractor experience of the Offeror’s parent/subsidiary/affiliate firm as experience attributable to the Offeror for evaluation purposes if the proposal establishes that the parent/subsidiary/affiliate firm will have a significant involvement in performance of this contract and describe the resources of the parent/subsidiary/affiliate firm that will be utilized on project that is the subject of this procurement.

If submitting a parent/subsidiary/affiliate firm’s project for experience, it is the Offeror’s responsibility to effectively demonstrate and describe how the parent/subsidiary/affiliate firms’ resources (such as workforce, management, facilities, or other resources) will significantly contribute to the execution of the project which is the subject of this procurement; failure to effectively demonstrate and describe the planned contribution of the parent/subsidiary/affiliate firm’s involvement in the subject project of this procurement will cause the past experience of the parent/subsidiary/affiliate firms to be considered not relevant for evaluation purposes in this procurement.

5.2.2 Submit projects that are 100% construction complete, accepted by the client and have been completed within six (6) years of the issue date of this RFP. Each project cited should have a construction dollar value greater than $5 Million.

5.2.3 Describe each project with enough detail to ensure that the Government can meaningfully assess the recency and relevancy of the projects submitted. Limit the length of each Attachment 1, Offeror Experience Form to four (4) pages.

5.2.4 Each project example shall demonstrate relevant experience to the proposed acquisition. In addition, Offerors should clearly explain how the information provided is relevant to the proposed acquisition.

5.2.5 Project examples shall demonstrate the following experience:

5.2.5.1 At least three (3) project examples shall demonstrate experience with construction (or repair), and commissioning of pressurized hydrant fueling systems designed in accordance with UFC 3-460-01 “Design:

Petroleum Fuel Facilities” and Standard Design AW 078-24-28, “DOD Pressurized Hydrant Fueling System

Type III” (DoD Type III Hydrant Fueling Systems) to support concurrent fueling and/or defueling of multiple large airframe aircraft.

5.2.5.2 At least one (1) project example shall demonstrate experience with installation of 12” diameter lined carbon steel fuel circulation piping for DoD Type III Hydrant Fueling Systems.

5.2.5.3 At least one (1) project example shall demonstrate experience with construction of hydrant fuels system hydrants, low point drains and high point vents for DoD Type III Hydrant Fueling Systems.

5.2.5.4 At least one (1) project example shall demonstrate experience with installation of impressed current cathodic protection systems for DoD Type III Hydrant Fueling Systems.

5.2.5.5 At least two (2) project examples shall demonstrate experience with the construction of airfield pavements to support large airframe military aircraft (e.g., KC-135 or C-17).

5.2.5.6 At least one (1) project example shall demonstrate experience with construction of Portland cement airfield pavements in sections similar to those required under this solicitation.

5.2.5.7 At least one (1) project example shall demonstrate experience with construction of asphalt concrete airfield pavements in sections similar to those required under this solicitation.

5.2.5.8 At least one (1) project example shall demonstrate experience with removal and disposal of petroleum contaminated soils.

5.2.5.9 At least one (1) project example shall demonstrate experience with installation or repair of buried line sensor intrusion detection systems for military airfields.

5.3 Evaluation Method for Factor A

5.3.1 The proposal will be evaluated to determine whether it meets the requirements of this Factor A. If any of the required information is not provided in the Offeror’s proposal, the Offeror will be evaluated as “Unacceptable.”

The Government may check any or all cited references to verify that the supplied information demonstrates compliance with the relevance…