MSEC- Building 606 - Amendment 1 - RFIs - 20 Aug 25.pdf

PDF 161 KB Posted

Attached to
Repair Bldg. 606, General Instruction Building, Math and System Engineering Center (MSEC) USMA at West Point, NY
Solicitation number
W912DS25RA002
Issued by

About this file

This document is an Amendment (0001) for a construction repair project at West Point, NY, specifically for Building 606, the General Instruction Building in the Math and System Engineering Center (MSEC). The solicitation (W912DS23R0009) includes key updates regarding past performance evaluation criteria, including extending the acceptable project timeframe from seven to ten years and confirming that non-federal projects will be weighted equally to federal projects. A site walk-through is scheduled for 04 September at 1000 AM EST, with participants meeting on Thayer Road east of Building 606.

The amendment addresses several bidder inquiries, including clarifications on project relevancy attributes (which are weighted equally), maintaining page limits for Factors 2 and 3 at fifteen pages each, and confirming that no escalation will be used to determine project magnitude. Potential bidders are advised that RFIs may be submitted until 15 September at 5:00 PM EST, and that the solicitation documents provide sufficient information for bidding. No changes were made to drawings or specifications in this amendment.

View the file

Other files

File Type Posted
23 30 00_AM 9.pdf PDF
I-113_AM 6.pdf PDF
I-100.4_AM 6.pdf PDF
A-206_AM 6.pdf PDF
A-314_AM 6.pdf PDF
A-313_AM 6.pdf PDF
A-312_AM 6.pdf PDF
MP-104_AM 6.pdf PDF
S-312_AM 6.pdf PDF
S-115_AM 6.pdf PDF
S-105_AM 6.pdf PDF
05 51 33_AM 6.pdf PDF
33 61 13.13_AM 6.pdf PDF
I-108_AM 6.pdf PDF
I-105_AM 6.pdf PDF
I-100.3_AM 6.pdf PDF
I-100.2_AM 6.pdf PDF
AD-101_AM 6.pdf PDF
A-304_AM 6.pdf PDF
A-315_AM 6.pdf PDF
A-503_AM 6.pdf PDF
Lead Inspection Report Summary.pdf PDF
SF24-23a.pdf_safe AM 5.pdf PDF
Solicitation Amendment W912DS25RA0020005 SF 30.pdf PDF
Appendix G_AM 5.pdf PDF
A-124_AM 4.pdf PDF
A-602_AM 4.pdf PDF
A-564_AM 4.pdf PDF
E-601 - DIAGRAMS - ONE-LINE_AM3.pdf PDF
Criteria and Factors for Evaluation_Basis of Award_Evaluation Criteria_Rating System_AM 3 revised.pdf PDF
M-303_AM3.pdf PDF
E-512 - DETAILS - ELECTRICAL_AM3.pdf PDF
MSEC- Building 606 - Amendment 3 - RFIs - 16 Sep 25.pdf PDF
Solicitation Amendment W912DS25RA0020003 SF 30.pdf PDF
Site Walk through sign in sheet_04Sept25.pdf PDF
S-318.pdf PDF
S-112.pdf PDF
A-406.pdf PDF
A-122.pdf PDF
A-120.pdf PDF
Solicitation Amendment W912DS25RA0020002 SF 30.pdf PDF
A-319.pdf PDF
Solicitation Amendment W912DS25RA0020001 SF 30.pdf PDF
Solicitation - W912DS25RA002.pdf PDF
JA-004-25 Best Cylinders MSEC - 31 Jan 25 signedJF sDL -_Redacted.pdf PDF
JA-008-25 IDS MSEC - 31 Jan 25 signedJF sDL_Redacted.pdf PDF
JA-006-25 CAC MSEC - 31 Jan 25 signedJF sDL -_Redacted.pdf PDF
W912DS19C0034 PN 94078 Repair Building 606 Revised RTA Drawings - Volume 3.pdf PDF
W912DS19C0034 PN 94078 Repair building 606 REV.RTA Specification Manual Volume 2.pdf PDF
JA-007-25 Monaco Fire Alarm MSEC - 31 Jan 25 signedJF sDL_Redacted.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT TITLE: REPAIR BLDG. 606, GENERAL INSTRUCTION BUILDING,

MATH AND SYSTEM ENGINEERING CENTER (MSEC).

PROJECT LOCATION: WEST POINT, NY

W912DS23R0009

AMENDMENT 0001 for REPAIR BLDG. 606, GENERAL INSTRUCTION BUILDING, MATH AND

SYSTEM ENGINEERING CENTER (MSEC).

TO OFFERORS

A site walk through is scheduled for 04 September at 1000 AM EST. Meet on Thayer Road east of Building 606. Allow enough time to obtain a visitor’s pass, if necessary, at South Post.

Instructions for are posted on https://www.westpoint.edu/gateway-for-visitors#all.

The following changes shall be made to the drawings and specifications.

DRAWINGS:

1. The following DRAWINGS have been REVISED and REISSUED:

None

2. The following DRAWINGS have been REVISED but NOT REISSUED:

3. The following DRAWINGS have been ADDED:

4. The following DRAWINGS have been DELETED:

SPECIFICATIONS:

1. The following SPECIFICATION SECTIONS have been ADDED and are provided in their entirety herein:

2. The following SPECIFICATIONS SECTIONS have been DELETED in their entirety:

3. The following SPECIFICATIONS SECTIONS have been REVISED and REISSUED:

4. The following SPECIFICATIONS have been REVISED but NOT REISSUED:

PROPOSER’S QUESTIONS AND GOVERNMENT REPLY

Questions that may be of general interest to all Offerors and/or the Government and that are not readily answered by the proceeding changes will appear below. These questions may have been paraphrased or altered to represent several questions regarding the same subject and/or simply revised to clarify and simplify the question(s).

Questions and answers are issued to the Offerors “for information only” and do not revise the solicitation, plans or specifications.

BIDDER INQUIRY#1:

Past Performance Timeframe Extension - The evaluation states: “All the submitted projects shall be recent construction experience, which means that completion should be no more than seven (7) years preceding the date of issuance of this solicitation.” To provide the government with the most accurate representation of our firm’s expertise and capabilities—while also meeting the intent of the solicitation requirements—we respectfully request that the allowable experience window be expanded from seven (7) years to ten (10) years preceding the date of issuance of the solicitation.

RESPONSE#1:

VOLUME 1 – FACTOR 1 – PAST PERFORMANCE Revise Para. “Also include performance recognition documents received within the last seven (7) years from the date of issuance of the solicitation such as award fee determinations, customer letters of commendation, and any other forms of performance recognition” TO “Also include performance recognition documents received within the last ten (10) years from the date of issuance of the solicitation such as award fee determinations, customer letters of commendation, and any other forms of performance recognition.”

AND

4.3.2 RELEVANT PAST PERFORMANCE Revise Para. “All the submitted projects shall be recent construction experience which means that completion should be no more than seven (7) years preceding the date of issuance of this solicitation.” TO “All the submitted projects shall be recent construction experience which means that completion should be no more than ten (10) years preceding the date of issuance of this solicitation.”

BIDDER INQUIRY#2:

Federal vs. Non-Federal Project Preference - The evaluation criteria allow for both federal and commercial (non-federal) projects under Factor 1 – Past Performance. Please confirm whether federal projects will be weighted more favorably than non-federal projects during the evaluation, even when commercial projects meet the stated relevancy requirements.

RESPONSE#2:

Non-federal projects will be weighted the same as federal projects, although as per the selection criteria “additional consideration” may be given for “[p]rojects showing past experience working with USACE..”

BIDDER INQUIRY#3:

Prioritization of Relevancy Elements - Section 4.3.2 lists several attributes that may contribute to project relevancy under Factor 1 (e.g., historic preservation, structural reinforcement, USACE experience). Please clarify whether if any specific elements are considered of higher priority or will carry greater evaluation weight than the others listed for this project.

RESPONSE#3:

Factor 1 project relevancy attributes are all weighted equally.

BIDDER INQUIRY#4:

Page Limit Increase for Factors 2 and 3 - The solicitation sets page limits for Factors 2 and 3 at fifteen (15) pages each. These sections are critical for demonstrating our firm’s understanding of the project and our unique execution plan. Given that this is a one-step procurement with limited opportunity for collaboration with USACE and West Point leadership, we respectfully request that the page limits for Factors 2 and 3 be increased from a maximum of fifteen (15) pages to a maximum of twenty (20) pages each.

RESPONSE#4:

The solicitation sets page limits for Factors 2 and 3 at fifteen (15) pages each. This limit remains unchanged.

BIDDER INQUIRY#5:

Existing Building Information - To support accurate planning and risk assessment, please confirm whether any existing documentation for Building 606—such as as-builts, previous construction records, surveys, or assessments—is available for offeror review.

RESPONSE#5:

The solicitation documents include sufficient information for bid.

BIDDER INQUIRY#6:

Looking through the documents for this project I did not see a date to submit any RFI’s, please advise so I can add it to my calendar.

RESPONSE#6:

RFIs may be submitted now. The current suspense for all RFIs is 15 September 25 5:00 PM EST.

BIDDER INQUIRY#7:

Please confirm escalation will be allowed for the past performance projects that were completed years ago and please provide the allowed escalation percentages per year if allowed.

RESPONSE#7:

As per the solicitation “Similar magnitude is defined as projects greater than $75,000,000.” Escalation will NOT be used to determine the magnitude of each project.